POWER CORPORATION
Technical Operation and Engineering Department
DAILY ACTIVITIES
Date: August 14, 2022
Technical Operations
I. Meter Readers (7:00am -5:00pm)
Work Description Location Remarks
Meter Reading
Statement of Account
(SOA Deliveries)
II. Line Crew (8:00am - 5:00pm)
Crew A (3 manpower)
Work Description Work Order No. Location Remarks
8:00AM - 4:00PM
Inspection of substation and recording of Substation (Taño Rd,
operational data . Manghinao Proper)
Regular OT - 3 manpower
Routinary Activity:
4:00PM - 12:00PM
Inspection of substation and recording of Substation (Taño Rd,
operational data . Manghinao Proper)
Crew D (2 manpower)
Routinary Activity:
12:00AM - 8:00AM
Inspection of substation and recording of Substation (Taño Rd,
operational data . Manghinao Proper)
Regular OT - 3 manpower
Routinary Activity:
(5pm - 10pm)
Today To Date
0 17,725
TOTAL CUSTOMER TO DATE:
New Connection
A. Residential B. Commercial
Total
Today To Date Today To Date
0 8,907 0 1,289 9,872
Total Consumer 23,929 Total Consumer 2,263 25,872