PROJECT MANAGER:Abhishek
TASK ID
MILESTONES & TASKS
NUMBER
1.1 Source packaging materials. This task will take 10 business days
Hire delivery drivers. This process will also take ten business days (March 15th to
1.2
March 26th).
Calculate the delivery fees. This task will also take 10 business days (March 29th to
1.3
April 9th).
2 Milestone 2: Select and install supply chain software and equipment
Supervise vendor setup of inventory management and fulfillment software. This
2.1
process will take three business days (April 12th to April 14th).
Supervise vendor installation of the fulfillment equipment from April 15th to April
2.2
16th (two business days).
Determine internal safety protocols for the equipment from April 19th to April 30th
2.3
(10 business days).
3 Milestone 3: Develop and launch an employee training program
3.1 Develop training sessions. This task will take 10 business days (May 3rd to May
14th).
3.2 Train employees to use the software and equipment. The training sessions will take
place over 10 business days (May 17th to May 28th).
3.3 Monitor employee progress and improve training processes. This process will last
for 10 business days (May 31st to June 11th).
COMPANY NAME:
CREATION DATE:
M T W R
1 2 3 4
3/15 3/26 10 0%
03/29 04/09 10 0%
equipment
Inventory Manager 4/12 4/14 3 0%
04/15 04/16 2 0%
4/19 4/30 10 0%
5/3 05/14 10 0%
05/17 5/28 10 0%
PHASE ONE
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7
APRIL
F M T W R F M T W R F M T W R F M T W R F M T W R F M
5 8 9 10 11 12 15 16 17 18 19 22 23 24 25 26 29 30 31 1 2 5 6 7 8 9 12
PHASE TWO
WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11
MAY
T W R F M T W R F M T W R F M T W R F M T W R F
13 14 15 16 19 20 21 22 23 26 27 28 29 30 3 4 5 6 7 10 11 12 13 14
PHASE THREE
WEEK 12 WEEK 13 WEEK 14 WEEK 15
JUNE
M T W R F M T W R F M T W R F M T W R F
17 18 19 20 21 24 25 26 27 28 31 1 2 3 4 7 8 9 10 11