TASK DESCRIPTION DURATION PAYMENTS STATUS Paid - 350000, Bal - 93000 to be Column (Ground floor) 4 383000+60000 = 443000 paid before ground floor roof concrete. Roof Slab (Ground floor) 18 To be paid at the completion of Column (First floor) 6 255000 ground floor slab Roof Slab (First floor) 20 To be paid at the completion of Column (Second floor) 6 255000 first floor slab Roof Slab (Second floor) 22 To be paid at the completion of Brickwork 12 255000 second floor slab To be paid at the completion of Electrical wall chasing 3 255000 brickwork Ceiling Plastering 6 Wall Plastering 12 To be paid at the completion of Putty work 4 255000 wall plastering Floor tiling 8 Toilet tiling 3 Window fixing 1 Window Grills 2 To be paid at the completion of Second Coat putty 6 255000 Flooring Primer work 3 First coat painting 4 Electrical Switch fixing 2 Plumbing fittings 2 Door fixing 2 Final coat painting 6 Before keys and document Keys Handover 1 135500 handover