List of Activities

Proj 478 Mr. Vipin


TASK DESCRIPTION DURATION PAYMENTS STATUS
Paid - 350000, Bal - 93000 to be
Column (Ground floor) 4 383000+60000 = 443000 paid before ground floor roof
concrete.
Roof Slab (Ground floor) 18
To be paid at the completion of
Column (First floor) 6 255000
ground floor slab
Roof Slab (First floor) 20
To be paid at the completion of
Column (Second floor) 6 255000
first floor slab
Roof Slab (Second floor) 22
To be paid at the completion of
Brickwork 12 255000
second floor slab
To be paid at the completion of
Electrical wall chasing 3 255000
brickwork
Ceiling Plastering 6
Wall Plastering 12
To be paid at the completion of
Putty work 4 255000
wall plastering
Floor tiling 8
Toilet tiling 3
Window fixing 1
Window Grills 2
To be paid at the completion of
Second Coat putty 6 255000
Flooring
Primer work 3
First coat painting 4
Electrical Switch fixing 2
Plumbing fittings 2
Door fixing 2
Final coat painting 6
Before keys and document
Keys Handover 1 135500
handover