SUNNY PLACE TOWNHOUSE FINISHING

SCHEDULE
BUILDING DESCRIPTION START END

8 PAINTING-INTERIOR WALL
PAINTING-CEILING
14-Feb-22
14-Feb-22
28-Feb-22
28-Feb-22

5
CEILING WORKS-ORDINARY 14-Feb-22 28-Feb-22
CEILING WORKS-MR 14-Feb-22 28-Feb-22
PAINTING-INTERIOR WALL 14-Feb-22 19-Mar-22
PAINTING-CEILING 14-Feb-22 19-Mar-22

3
CEILING WORKS-ORDINARY 14-Feb-22 16-Mar-22
CEILING WORK-MR 14-Feb-22 16-Mar-22
PAINTING-INTERIOR WALL 6-Mar-22 9-Apr-22
PAINTING-CEILING 6-Mar-22 9-Apr-22

4
CEILING WORKS-ORDINARY 25-Mar-22 14-Apr-22
CEILING WORKS-MR 25-Mar-22 14-Apr-22
PAINTING-INTERIOR WALL 13-Mar-22 23-Apr-22
PAINTING-CEILING 29-Mar-22 23-Apr-22

1
CEILING WORKS-ORDINARY 8-Apr-22 21-Apr-22
CEILING WORKS-MR 8-Apr-22 21-Apr-22
PAINTING-INTERIOR WALL 2-Apr-22 7-May-22
PAINTING-CEILING 12-Apr-22 7-May-22

2
CEILING WORKS-ORDINARY 8-Apr-22 21-Apr-22
CEILING WORKS-MR 8-Apr-22 21-Apr-22
PAINTING-INTERIOR WALL 2-Apr-22 7-May-22
PAINTING-CEILING 12-Apr-22 7-May-22