Mechanical completion and commissioning Z-CR-007

Annex A Rev. 1, May 1996

Sheet No.
MC CHECK RECORD
<Project>
INSTRUMENT INSTALLATION AND
INSPECTION
(Rev. 1, May 1996)
Tag No. : MC Package No.
Description : Area :
PO No. : System : Comm.Package No.
Manufacturer : Subsystem :

INSTALLATION CHECK SUPPL. FABR. HOOK-UP Punchlist item No.


01 Check instrument against data sheet
02 Check CE marking
03 Check calibration certificate
04 Installation check
05 Leakage test
06 Flushing carried out

COMMENTS:

VERIFIED SUPPLIER FABRICATION HOOK-UP


Name
Sign
Date
Name
Sign
Date

NORSOK standard Page 15 of 26