Converting Planned Orders to Production Orders

Converting Planned Orders to Production Orders

Explanation Screenshot

Would you like to know more


about how a production
planner converts a planned
order to a production order?

If so, follow this interactive


tutorial.

1. To open the app, select


the Check Material
Coverage tile.

2. In the Material field, enter


FG126 and press Enter.

1
Converting Planned Orders to Production Orders

Explanation Screenshot

3. To select a plant, open


the list.

4. Select 1710.

5. The Shortage Definition


has been selected as MRP
Standard for you.

Choose OK.

6. The stock/requirements
list is shown for the material.

To see the planned order for


the semi-finished good
material, choose PldOrd
407.

2
Converting Planned Orders to Production Orders

Explanation Screenshot

The planned order details


display.

7. Choose Close.

8. Choose Edit.

9. Select Convert.

3
Converting Planned Orders to Production Orders

Explanation Screenshot

10. Check the quantity and


end date.

Choose OK.

The planned order has been


processed and converted
into a production order.

11. Similarly, you can create


a production order for the
material SG124. This has
been done for you.

To return to the launchpad,


choose SAP.

You have succesfully


converted a planned order to
a production order.

This concludes the


interactive tutorial.