Reporting date : Reported by :

SCHEDULE AND PROGRESS REPORT


Period : September 2022

Project Name : New Plant AHM Deltamas Cikarang Location : Plant Assembling

September PROGRESS (%)


PHOTO REMARKS
NO DESCRIPTION mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri
(if any)
PLAN ACTUAL
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 Bobok Tiang Pancang : Plan

As Y / 17-21 18 : Progress &

As J1 / 17-21 7 New Plan


As P1 / 17-21 7

As 17 / Y- B1 39

As Y / 21-25 12

As J1 / 21-25 8

As P1 / 21-25 10

As Y / 25-29 12

As J1 / 25-29 8

As P1 / 25-29 10

As Y / 29 - 33 12

As J1 / 29 - 33 8

As P1 / 29 - 33 10

As Y / 33 - 37 12

As J1 / 33 - 37 8

As P1 / 33 - 37 10

As Y / 37 - 42 12

As J1 / 37 - 42 8

As P1 / 37 - 42 10

As Y / 42 - 52 15 15 15

As J1 / 45 - 52 15 15 15

As Y / 53 - 59 15 15 15

As J1 / 53 - 59 15 15 15

32 39 30 30 30 30 30 30 30 30 30 30 30