LOM PANGAR PIPELINE MODIFICATION

WEEKLY HIGHLIGHTS
WEEK 15, Ending: Friday 11 April 2014
This Week Next Week Needs/Areas of Concern

HSE HSE

 Waste collection, segregation


 Management walk through of the and transportation from the site
ROW  Monitoring activities on the
 Waste collection, segregation and Right of Way
storage within the camp site.  Cleaning camp, segregating,
 Fibre Optic activities storage and transportation of
 Backfill at KP 481 wastes
 Loading and transportation  Backfilling at KP481/494
containers  General Housekeeping of KP
 Cathodic protection Activities 481/494
 Electrical Instrumentation activities  Construction of valve station at
at KP 509 KP 481

PROCUREMENT PROCUREMENT PROCUREMENT

abc abc abc

ENGINEERING ENGINEERING ENGINEERING

abc abc abc

QA/QC QA/QC QA/QC

abc abc abc

LOGISTIC LOGISTIC LOGISTIC

abc abc abc