SEMI DETAILED LESSON PLAN IN PERT/CPM


I. Objectives

At the end of the lesson, the students should be able to:

a. Know the definition of PERT/CPM


b. Basic steps in PERT/CPM
c. Know the calculation in getting the Critical Path

II. Subject matter


Topic: Introduction and applications of PERT/CPM

III. Materials
Laptop and Projector

IV. Procedure
a. Preparation
Greet the students and ask them to listen during the discussion and
explain some rules when the instructor is discussing.

b. Lesson proper
 Make a recall discussion about network analysis
 Give a detail example in making network Analysis
 Introduction to PERT/CPM
 Discussion in Finding the Critical path
 Summary in PERT/CPM procedure
 Benefits of PERT/CPM
 Applications of PERT/CPM

V. Assessment
 Drawing of PERT/CPM Network
 Finding the Earliest Start and Earliest Finish
 Finding the latest Start and latest Finish
 Finding the Critical Path

VI. Assignment
Identify some activities that you will do at home and apply the PERT/CPM

PREPARED BY: BENJAMIN RUBIN