SBR-ACEMC CP02_CO123

November 25, 2019

PROGETTA DEVELOPMENT AND CONSTRUCTION INC.


Unit 15, 3rd Floor Neth Square
Building 2 Addas Village 2
Molino 2, Molino Blvd.
Bacoor, Cavite

Attention : Engr. Gary Alviento


PDCI – Operations Manager

Thru : Ar. Rexell Reyes


PDCI - Construction Manager

Project : ACE Medical Center Palawan


Puerto Princesa, Palawan

Subject : REBAR – FAILED RETESTING RESULT

Gentlemen:

In relation to the recently conducted rebar testing dated November 25, 2019, we would like to inform
your good office that while we are waiting for your instruction or directive, we put on hold on all related
rebar works for the above stated project. With this, we will claim for the stand by charges accordingly.
Please see attached test result for your easy reference.

For your perusal. Thank you.

Very Truly Yours,

ROBERT RODRIGUEZ
PROJECT MANAGER, ACE Hospital Project
SBR CENTER BUILDERS INC.

Cc: Benedict Dy Tecklo – SBR President


Arnold John Anteojo – SBR COO
Eduardo Ladia – SBR VP for Finance