You are on page 1of 1

SBR-ACEMC CP02_CO133

December 17, 2019

PROGETTA DEVELOPMENT AND CONSTRUCTION INC.


Unit 15, 3rd Floor Neth Square
Building 2 Addas Village 2
Molino 2, Molino Blvd.
Bacoor, Cavite

Attention : Engr. Gary Alviento


PDCI – Operations Manager

Thru : Ar. Rexell Reyes


PDCI - Construction Manager

Project : ACE Medical Center Palawan


Puerto Princesa, Palawan

Subject : SOLAR DECK - FOLLOW UP

Gentlemen:

Relative to our previously transmitted letter with reference number SBR-ACEMC-CP02-c0129 dated
December 2, 2019, we would like to inform your good office that we will proceed on the construction
of the remaining floors as per issued Construction Bulletin No. 11 until the revised plan is transmitted
to our office. As we do not receive any official documents regarding the mounting and/or embedment
for solar deck structure as of this writing.

For your perusal. Thank you.

Very Truly Yours,

ROBERT P. RODRIGUEZ
PROJECT MANAGER
SBR CENTER BUILDERS INC.