IE 401

Recitation #10
Lot Sizing

Net requirements for a particular component over five periods are (45, 75, 105, 12, 50).
The holding cost is $2 per unit and the fixed ordering cost is $200.

Part a. Determine the lot sizes using Silver-Meal heuristic.

Part b. Determine the lot sizes using Part Period Balancing heuristic.

Part c. Determine the optimal lot sizes using Wagner-Whitin algorithm.