Professional Documents
Culture Documents
Lesson 6
Learning Objectives
2
Project Time Management
Processes
⚫ Activity definition: Identifying the specific
activities that the project team members
and stakeholders must perform to produce
the project deliverables.
⚫ Activity sequencing: Identifying and
documenting the relationships between
project activities.
⚫ Activity resource estimating: Estimating
how many resources a project team should
use to perform project activities.
3
Project Time Management
Processes
⚫ Activity duration estimating: Estimating
the number of work periods that are
needed to complete individual activities.
⚫ Schedule development: Analyzing activity
sequences, activity resource estimates,
and activity duration estimates to create the
project schedule.
⚫ Schedule control: Controlling and
managing changes to the project schedule.
4
1 Activity Definition
⚫ An activity or task is an element of work normally
found on the WBS that has an expected duration, a
cost, and resource requirements.
⚫ Project schedules grow out of the basic documents
that initiate a project.
◦ The project charter includes start and end dates
and budget information.
◦ The scope statement and WBS help define what
will be done.
⚫ Activity definition involves developing a more
detailed WBS and supporting explanations to
understand all the work to be done, so you can
develop realistic cost and duration estimates. 5
Activity Lists and Attributes
⚫ An activity list is a tabulation of activities to be
included on a project schedule. The list should
include:
◦ The activity name
◦ An activity identifier or number
◦ A brief description of the activity
⚫ Activity attributes provide more information about
each activity, such as predecessors, successors,
logical relationships, leads and lags, resource
requirements, constraints, imposed dates, and
assumptions related to the activity.
6
Milestones
⚫ A milestone is a significant event that
normally has no duration.
⚫ It
often takes several activities and a lot of
work to complete a milestone.
10
Common Areas of Error
(Cont.)
⚫ We“forget” all the tasks that need to
happen to produce this deliverable.
◦ E.g. We cannot just go and conduct user
training if we do not know what and who
we are training and we have no materials!
◦ Stand back – look at the big picture –
does it make sense?
11
Common Areas of Error
(Cont.)
⚫ Inall the different knowledge areas,
there are control processes. You need
to add in the activities that will be
undertaken to implement these control
processes
◦ E.g. Team meetings, status reports, risk
reviews, etc.
12
12
2. Activity Sequencing
⚫ Involves
reviewing activities and
determining dependencies.
⚫ A dependency or relationship
relates to the sequencing of project
activities or tasks.
15
Network for Product Upgrade Project
16
Leads and Lags
⚫ The most common type of logical dependency is
finish-to-start (FS)
⚫ Leads are helpful if a project needs to be completed
quickly
Finish-to-start – “the logical relationship where initiation of
work of the successor activity depends on completion of work
of the predecessor activity.” PMBOK® Guide
18
Start-to-Start Relationships
⚫ The graphics design could not start
until the design marketing campaign
started
19
Start-to-Finish Relationships
⚫ The least used relationship
⚫ Example – a project to replace an old
system where the new capability must
be started before the old one is
completely discontinued
Start-to-finish – “the logical relationship where completion of the
successor schedule activity is dependent on the initiation of the
predecessor schedule activity.” PMBOK® Guide
20
Task Dependency Types
21
3. Activity Resource
Estimating
⚫ Beforeestimating activity durations, you must
have a good idea of the quantity and type of
resources that will be assigned to each activity.
⚫ Considerimportant issues in estimating
resources:
◦ How difficult will it be to complete specific
activities on this project?
◦ What is the organization’s history in doing
similar activities?
◦ Are the required resources available?
22
4. Activity Duration Estimating
⚫ Duration includes the actual amount of
time worked on an activity plus the elapsed
time.
26
Gantt Chart (MS Project)
27
Gantt Chart (Excel)
28
Adding Milestones to Gantt
Charts
⚫ Many people like to focus on meeting
milestones, especially for large projects.
⚫ Milestones
emphasize important events or
accomplishments in projects.
29
Critical Path Method (CPM)
⚫ CPM is a network diagramming technique used to
predict total project duration.
⚫ A critical path for a project is the series of
activities that determines the earliest time by which
the project can be completed.
⚫ The critical path is the longest path through the
network diagram and has the least amount of slack
or float.
⚫ Slack or float is the amount of time an activity can
be delayed without delaying a succeeding activity
or the project finish date.
30
Critical Path
⚫ The critical path is the shortest time in
which the project can be done.
⚫ Any slip in one of those tasks means a slip
in the whole project.
⚫ By knowing which tasks are critical tasks
you can focus your attention on those tasks
as they are the most important.
⚫ You can the use the critical path analysis to
rearrange tasks to achieve the best
possible outcome.
31
Calculating the Critical Path
⚫ Develop a good network diagram.
33
More on the Critical Path
34
Using Critical Path Analysis to
Make Schedule Trade-offs
⚫ Free slack or free float is the amount
of time an activity can be delayed
without delaying the early start of any
immediately following activities.
⚫ Total slack or total float is the
amount of time an activity can be
delayed from its early start without
delaying the planned project finish
date.
35
Two-Pass Method
⚫ Used to determine the amount of slack each activity
has
⚫ Make two logical passes through the constructed
network
◦ The forward pass
◦ The backward pass
Forward pass – “the calculation of the early start and early finish dates
for the uncompleted portions of all network activities.” PMBOK® Guide
Backward pass – “the calculation of late finish dates and late start
dates for the uncompleted portions of all schedule activities.” PMBOK®
Guide
36
Two-Pass Example Schedule Set Up
38
Schedule Example Backward Pass
Complete
39
Using the Critical Path to Shorten a
Project Schedule
⚫ Three main techniques for shortening schedules:
41
Importance of Updating
Critical Path Data
⚫ Itis important to update project
schedule information to meet time
goals for a project.
43
PERT Time Estimate Example
44
PERT Considerations
⚫ Advantages
◦ Reinforces the degree of uncertainty that
exists in project schedules
◦ Calculations indicate that expected time is
actually longer than most likely time
⚫ Difficulties
◦ Takes more effort to create 3 estimates
◦ No guarantee how good the estimates are
◦ May underestimate the risk of a schedule
running long 45
6. Schedule Control
⚫ Perform reality checks on schedules.
⚫ Don’t
plan for everyone to work at 100
percent capacity all the time.
47
Reality Checks on Scheduling
⚫ Reviewthe draft schedule or estimated
completion date in the project charter.
⚫ Alert
top management well in advance if
there are schedule problems.
48
Summary