Create Project Plan

▪ Specify project name and start (or finish) date.

▪ Identify and define project tasks. , Define duration for each project task.

Task 1 : Information Gathering

Task 2 : Design
Task 3 : Customer Coding

Task 4 : Vendor Coding


Task 5 : Admin Coding

Task 6 : Testing
Task 7 : Deployment

▪ Define milestones in the plan


▪ Define dependency between tasks
Dependency between Information gathering and design

Dependency between design and Customer coding, Vendor Coding, and Admin Coding
Dependency between coding and testing

Dependency between testing and deployment


▪ Define project calendar.

▪ Define project resources and specify resource type


Project manager : RAM
Shyam : Developer

Sita: Developer
Geeta: Tester

▪ Assign resources against each task and baseline the project plan

Ram : Deployment and Information Gathering


Shyam : Coding Customer and Deployment

Sita: Coding Vendor and Admin


Geeta: Testing

Baseline