➢ Site visit last Feb 18, 2022 with Meralco representative ➢ July 2022 - 4th week (old) ➢ June 20, 2022 (old) may extend depends on site production ▪ June 21, 2022 - Tabang Substation 34.5kV ▪ 1st~2nd wk. of July 2022 tentative (new)
SITE ACTIVITY
• Erection of concrete post (done)
• Installation of new electrical cable: ongoing (started on June 2, 2022) • Target completion: July 11 to 16, 2022 Bored pile Progress as of June-30-2022 • 2403/2415 piles (99.50%) • Remaining: 12 piles(include Embankment area)