Obstruction for Bored piling as of June-30-2022

RED FONT: UPDATE AVAILABLE

• PR7-19 : Meralco Substation


PR7-19 EMPLOYER SCOPE
Meralco substation (12 piles)
• Temporary relocation plan Submitted Sep-21-2021

• Relocation plan: approved by NSTren Sep-27-2021

• Target start: after final design plan

• New Schematic Design: already submitted by MERALCO


➢ Ongoing revision considering SMCC comments
➢ Temporary relocation between,
▪ PR7-18 & 19
▪ PR7-19 & 20
▪ PR7-20 & 21

• Target completion of temporary relocation:


➢ Site visit last Feb 18, 2022 with Meralco
representative
➢ July 2022 - 4th week (old)
➢ June 20, 2022 (old) may extend depends on
site production
▪ June 21, 2022 - Tabang Substation 34.5kV
▪ 1st~2nd wk. of July 2022 tentative (new)

SITE ACTIVITY

• Erection of concrete post (done)


• Installation of new electrical cable:
ongoing (started on June 2, 2022)
• Target completion: July 11 to 16,
2022
Bored pile Progress as of June-30-2022
• 2403/2415 piles (99.50%)
• Remaining: 12 piles(include Embankment area)

Obstructed pile
• SMCC scope: 0 piles
• Employer scope: 12 piles
• SCIC: 0 piles
• Total: 12 piles
• 12/12 = 100%