You are on page 1of 1

PROJECT PROJECT NO.

CONTRACTOR CONTRACT NO.


ARCHITECT DATE

REQUEST FOR INFORMATION NO.


FROM: (Name, Co.) TO: (Name, Co.)

FROM CONTRACTOR:
Subject:
Question:

Suggestion:

Estimated Cost (if known): ($000.00 or N/A)


REPLY TO CONTRACTOR DATE ANSWERED:

Per the Contract General Conditions, the Contractor shall not proceed with additive or deductive Work which has change order
implications as a result of this RFI without prior written approval from the Trustees.

Copies to:
• Project Manager/Construction Inspector
• Architect
• Construction Administrator
• Contractor