You are on page 1of 14

CONSTRUCTION CONTRACT

KNOW ALL MEN BY THESE PRESENTS:

This Construction Contract (“Contract”) made and entered into this ___ day of
January 2017 by and between:

______________________________, Filipino, married/single, of


legal age, and currently residing at
________________________________________________________________
hereinafter referred to as the “OWNER”.

and

CONSTRUCTION, INC., a Corporation duly organized and


existing by virtue of the laws of the Republic of the Philippines,
with office address at ________________________, Quezon City,
represented herein by its President, MR. _______________, by
virtue of the Board resolution hereto attached as ANNEX “A”,
and hereinafter referred to as the “CONTRACTOR”

Collectively known as the “PARTIES.”

WITNESSETH: That

WHEREAS The OWNER is the absolute and registered owner of a parcel of land
located at __________________________________________________________________________ and
more particularly described under TCT No. _______________________ (hereinafter called the
“Property”).

WHEREAS, the OWNER is looking for a reputable and qualified building contractor for
construction works to be built on the Property (hereinafter called the “Project”).

WHEREAS, the CONTRACTOR represents and warrants itself as an experienced,


competent and duly licensed professional building contractor.

WHEREAS the PARTIES have agreed that the CONTRACTOR shall undertake the
construction of the Project.

NOW THEREFORE, for and in consideration of the foregoing premises and the terms
and conditions hereinafter set forth, the parties hereto have agreed as follows:

ARTICLE I
CONTRACT DOCUMENTS
1.1 The following documents shall form and be interpreted and construed as part of this
Contract, viz.;

a. General and Special Conditions of the Contract;


b. Scope of Works;
c. Drawings and Plans;
d. Technical Specifications;
e. Project Cost Proposals (Bill of Quantities (BOQ), Detailed/Breakdown of
Estimates, Summary of Bids);
f. Other Contract documents that may be required by existing laws, the
___________________________________ (the “Homeowner’s Association”).

1.2 Any and all deficiencies that can be found in this Contract which are intended to be
covered by it, but are not expressly stated herein, shall be supplied by any of the
aforesaid Contract Documents.

1.3 In case of doubt or conflict between and among the provisions of this Contract, and/or
between and among the above Contract Documents and this Contract, the
CONTRACTOR shall refer the same in writing to the OWNER for clarification and
guidance. The clarification or determination made by the OWNER for clarification and
guidance. The clarification or determination made by the OWNER shall be binding and
conclusive upon the parties.

1.4 The parties herein may, in writing, agree to any revision, alteration, or addition to the
terms and conditions of this Contract, provided the same shall not be in violation of any
law, rule or regulation governing contracts of infrastructure of government.

ARTICLE II
SCOPE OF WORKS AND RESPONSIBILITIES OF THE CONTRACTOR

2.1 The CONTRACTOR shall provide the labor, supervision, materials, supplies,
equipment, services, facilities, project management, tools, consumables and all other
necessary items in order to complete the Project in accordance with the Contract
Documents. The scope of the Work and responsibilities of the CONTRACTOR include,
but are not limited to, the following:

a. Mobilization/demobilization of equipment, labor, materials and temporary


facilities at the Project site;
b. Application, liaison and payment of all necessary building permits both from the
subdivision and the municipality;
c. Application, liaison and payment of utilities connection, excluding payment for
meter deposits;
d. Construction and completion of the Works in full compliance with all Philippine
laws, Philippine building construction standards, codes, regulations, ordinances,
and rules and regulations imposed by the Homeowner’s Association that are
applicable to the Project.

2
e. The CONTRACTOR shall ensure that the Project site is kept clean, safe &
hygienic at all times and that its workers comply with any rules and regulations
imposed on the Project Site.

2.2 The CONTRACTOR hereby warrants and guarantees that all the materials to be
supplied by it under this Contract are new, free from defects and shall fully comply in
every respect with the specifications, approved samples and other requirements of the
contract plan and other related Contract Documents. The CONTRACTOR shall make no
substitution for materials required to be furnish by it under the Contract unless no such
stock is available from the market and an approved equal is readily available. The
CONTRACTOR warrants that the materials to be supplied by it are free and clear of all
liens and encumbrances.

2.3 The CONTRACTOR shall employ sufficient number of men to carry out the various
phases of work diligently and efficiently in order to complete the PROJECT in
accordance with the agreed Work Program.

2.4 The CONTRACTOR shall be responsible for the storage and safekeeping of its materials.
Any damages, losses and pilferages to these materials shall be for its sole account.

2.5 It is mutually understood and agreed that the CONTRACTOR is an independent


Contractor not an employee of the OWNER. Neither shall the personnel, Workmen or
sub-Contractors of the CONTRACTOR be deemed employees of the OWNER. Hence,
the OWNER shall not in any way be liable or responsible for any personal injury or
damages including death sustained or caused by any of the employees of the
CONTRACTOR and/or its sub-Contractors during the lawful performance of their
duties. The CONTRACTOR shall at all times be directly responsible and liable for the
enforcement of and compliance with all existing laws, rules and regulations particularly
in respect of any and all claims brought by its personnel for the enforcement of the
provisions of the Labor Code of the Philippines and other related laws. The
CONTRACTOR hereby holds the OWNER free and harmless from all such claims and
liabilities.

2.6 The CONTRACTOR has the right to introduce sub-contractors, specifically Construction
Inc., as the lead Contractor, in constructing and finishing the said project.

2.7 The CONTRACTOR shall secure the construction building permits, application fees,
licenses and taxes, if necessary, for the execution/completion of the Project including the
final certificate of occupancy, which shall be paid for by the CONTRACTOR. The
CONTRACTOR shall also comply with all laws, rules and regulations promulgated by
the government of the Republic of the Philippines or any of its instrumentalities
applicable to this PROJECT as well as regulations imposed by the Homeowner’s
Association, and shall be personally and solely responsible for any violation of the same.
Should the OWNER request to make alteration not in line with the approved building
plan, OWNER shall be responsible for the approval of such alteration and shall hold
CONTRACTOR free and harmless against any government regulatory inspection or any
other warranty arising from the said alteration.

3
2.8 The CONTRACTOR shall hold the OWNER, its Officers, agents and employees, free and
harmless against any claim, losses, damages, or injuries of whatever kind or nature that
may be filed or claimed against the OWNER by any third person, firm or entity arising
out of or in connection with the construction undertaken by the CONTRACTOR under
this Contract, or by the negligence of the CONTRACTOR, its agents, servants and
employees during the construction period.

2.9 After the completion but before the acceptance of the work and final settlement is made
between the parties, the CONTRACTOR shall forthwith remove all the surplus
materials, scaffoldings, apparatus, machinery, tools and equipment not part of the
Project, furnished or supplied by it and shall remove all debris and leave the work free
and clean of all obstruction and hindrances.

2.10 All provisions with respect to warranties contained in this Contract are cumulative and
all alternatives are in addition to such warranties as may be provided by law or
contained in the other provisions of this Contract.

ARTICLE III
RIGHTS AND OBLIGATIONS OF THE OWNER

3.1 Pay the Contractor the Contract Amount punctually as stated in Articles IV and V of this
Contract.

3.2 Prompt approval of plan, documents, and material samples necessary for the progress of
the Project as requested by the Contractor.

3.3 Timely delivery of owner-supplied materials (OSM) (if any) necessary for the progress
of the Works.

3.4 The OWNER and/or its representatives may, without invalidating this Contract or the
Contract Documents, at any time during the progress of the work by its written
specifications to the CONTRACTOR, cause alterations in the original plans and
specifications by way of addition, deletion or otherwise deviations therefrom, and the
work shall be executed by the CONTRACTOR. In which case, any additional
costs/expenses that can be incurred by reason of such alterations, over and above the
original contract price, shall be borne by the OWNER. Any reduction in costs / expenses
by reason of any alterations or deletions shall be subtracted from the Contract Price. The
OWNER shall be responsible for any additional permits for such alterations in
accordance with Article 2.7 hereof.

3.5 The OWNER shall inform the CONTRACTOR of any pending litigation involving the
former, which might adversely tend to affect or affect the PROJECT, and/or the relations
and obligations of each party to one another. Upon notification by the OWNER thereof,
the CONTRACTOR shall acknowledge the notice by executing a document duly
notarized stating that it has been informed thereof.

3.6 The OWNER shall hold CONTRACTOR free from any liability arising from the
negligence of the former.

4
3.7 The OWNER shall provide for the application fee and all other incidental expenses for
the installation of the water and electricity at site. The same utilities shall be provided to
the CONTRACTOR all the time, provided that utilization cost thereof shall be borne by
the CONTRACTOR.

3.8 Unless specifically stated in this Article III, the Contractor shall be responsible for all
items, actions and payments that are necessary for the completion and Final Acceptance
of the Work.

ARTICLE IV
CONTRACT PRICE

4.1 The OWNER shall pay the CONTRACTOR, in consideration for the satisfactory
performance and accomplishment of all the obligations herein specified which the
CONTRACTOR agrees to undertake, perform and accomplish, the total amount of
_______________________________________ for this Project for the
______________________ inclusive of all applicable government fees and taxes,
excluding refundable deposits and application fee on utilities. Completion of the
project shall be ten (10) months or three hundred (300) working days from the actual
commencement of the project OR the release of the Building Permit, whichever is later.

ARTICLE V
TERMS OF PAYMENT

5.1 The OWNER in its interest to have the PROJECT started and completed on time
stipulates to give the CONTRACTOR an advance payment 5% Down payment, or the
sum of ___________________________________, upon the execution of this Contract;

a. 20% Additional Payment shall be paid by the OWNER to the CONTRACTOR,


or the sum of ______________________________ at least three (3) days prior to
mobilization;

b. 35% Additional Payment shall be paid by the OWNER to the CONTRACTOR,


or the sum of ____________________ before concreting of the Second Floor Slab;

c. 15% Additional Payment shall be paid by the OWNER to the CONTRACTOR,


or the sum of ___________________ before the installation of the roof;

d. 15% Additional Payment shall be paid by the OWNER to the CONTRACTOR,


or the sum of _____________________ before the installation of the windows;

e. Final 10% shall be paid by the OWNER to the CONTRACTOR, or the amount of
_________________ upon the turnover and acceptance of the project by the
OWNER.

5
5.2 It is hereby agreed that, whenever by reason of the causes mentioned in Paragraph 3.02
of Article III hereof and Paragraph 9.02 or Article 9 of this Contract it becomes legally
and/or physically impossible for either of the parties to perform their respective
obligations, any of the parties may legally demand rescind this Contract, and the
OWNER to indemnify the actual damages due to the CONTRACTOR based on the
above payment scheme.

5.3 The CONTRACTOR shall submit its billing based on the above stated accomplishment
to the OWNER and the OWNER shall pay the CONTRACTOR within five (5) working
days upon receipt of said billings from the CONTRACTOR together with the latter’s
appropriate recommendation.

5.4 Failure on the part of the OWNER to pay the CONTRACTOR billings within fifteen
(15) calendar days due to causes imputable to the OWNER shall entitle the
CONTRACTOR to suspend work on the PROJECT.

5.5 Should the OWNER require the CONTRACTOR to perform any additional work, the
cost of additional work shall be added to the amount stated in Article IV hereof
(CONTRACT PRICE) and the computation of the cost shall be based on the unit price
scheduled.

5.6 Under no circumstances shall the CONTRACTOR be entitled to payment for any extra
work or change of work without the written order of the OWNER to perform such
work. Any work done without such expressed order shall be for the sole account of the
CONTRACTOR.

5.7 In case of extra-ordinary inflation, or extraordinary Circumstance, that would have


resulted to an extra ordinary increase in the materials and labor cost, the PARTIES shall
amend the contract price to reflect such extra- ordinary inflation. Failure of the
PARTIES to sign a new contract can result to work stoppage without fault to the
CONTRACTOR.

5.8 Any payment due to the CONTRACTOR may be offset against liquidated damages
due to the OWNER under this Contract.

PERFORMANCE BOND

5.9 The OWNER may at his own discretion procure a Performance Bond coterminous
with the date of final acceptance of the PROJECT by the OWNER. The Performance

6
Bond may be in forms of Surety bond callable upon demand issued by any reputable
surety or insurance company.

5.10 If the PROJECT cannot be completed within the period prescribed under Section 4.1 to
the satisfaction of the OWNER for final acceptance, the CONTRACTOR shall post a
substitute Performance Bond or effect an extension of the original Performance Bond
to cover the period of extension until final acceptance of the PROJECT is made.

5.11 The CONTRACTOR shall post the substitute Performance Bond immediately upon
determination by the OWNER of the inability of the CONTRACTOR to complete the
PROJECT for final acceptance. This determination shall be made by the OWNER
within ten (10) working days immediately preceding the expiration date of the
Performance Bond.

5.12 The OWNER shall be responsible in acquiring an additional performance security to


cover any cumulative increase of more than ten percent (10%) over the original value
of the contract as a result of amendments to order or change orders, extra work orders
and supplemental contracts, made by the OWNER.

5.13 In case of work suspension not due to the fault of the CONTRACTOR, the OWNER
shall be liable to the CONTRACTOR for the demobilization and remobilization of all
equipment at the amount of ONE HUNDRED THOUSAND PESOS (Php100,000.00).

ARTICLE VI
CONTRACTOR’S GUARANTEE OF WORK

6.1 Aside from the warranties imposed by law, the CONTRACTOR further agrees to
guarantee its work against qualitative defects, poor workmanship and the like for a
period of one (1) year reckoned from the date of final acceptance of the PROJECT,
during which time, in cases of defects, failure and poor workmanship of any parts of
the PROJECT due to normal use, the CONTRACTOR shall make good such defects
and/or failures at no expenses to the OWNER such defects includes:

a. Paintings
b. Lightings (Electrical only, bulbs not included)
c. Tiles / Tiling, except those due to the fault of the OWNER
d. Waterproofing

6.2 The CONTRACTOR further agrees to guarantee its work against qualitative defects,
poor workmanship and the like for a period of two (2) year reckoned from the date of
final acceptance of the PROJECT, during which time, in cases of defects, failure and
poor workmanship of any parts of the PROJECT due to normal use, the
CONTRACTOR shall make good such defects and/or failures at no expenses to the
OWNER such defects includes:

7
a. Roofing
b. Piping, with regard to leaks thereof;
c. Cabinets, with regard to its workmanship and durability, excluding
ordinary wear and tear and fault or negligence of the OWNER;
d. Ceilings, except those damages that are man-made, intentional or by force
majeure;
e. Flooring
f. Locksets
g. Door Hinges;
h. Walling
i. Windows, except those damages that are man-made, intentional or by
force majeure;
j. Electrical wirings

ARTICLE VII
OPTION TO COMPLETE WORK OR TAKEOVER

7.1 If at any time during the progress of the work, the CONTRACTOR should fail, refuse
or neglect to supply and provide the required tools, materials, supplies, equipment,
facilities and labor-workmen or should abandon or fail to continue with the Project, the
OWNER may at its option, take over the work and complete the same or engage the
service of another CONTRACTOR to do the same all at the expense and for the
account of the CONTRACTOR. In any case, the CONTRACTOR shall also be liable to
the OWNER of all damages incurred by the latter.

ARTICLE VIII
OWNER’S RIGHT TO TERMINATE/SUSPEND CONTRACT

8.1 TERMINATION WITH CAUSE. The OWNER may immediately terminate this
Contract, without prior notice to the CONTRACTOR, upon the occurrence of any of the
following cases:

a. If the CONTRACTOR is adjudged bankrupt or insolvent;


b. If the CONTRACTOR makes a general assignment of this assets for the benefit
of his creditors;
c. If a trustee or receiver is appointed for the CONTRACTOR or for any of the
CONTRACTOR’s property; or
d. If the CONTRACTOR files a petition for suspension of payments, or to
reorganize under the bankrupt or similar laws.

8.2 OTHER GROUNDS FOR TERMINATION WITH CAUSE. The OWNER may terminate
this Contract upon the occurrence of any of the following:

8
a. The CONTRACTOR repeatedly fails to supply, based on the construction
schedule, the sufficient number of skilled workmen or suitable materials or
equipment;
b. The CONTRACTOR repeatedly fails to make without just cause prompt
payments to Sub-Contractor for labor, materials or equipment, and completion of
the Work is being delayed;
c. The CONTRACTOR disregards the Laws or lawful order of any public body
having jurisdiction as well as regulations imposed by the Homeowner’s
Association.

The OWNER may, after giving the CONTRACTOR 15 day written notice, terminate
the services of the CONTRACTOR, exclude the CONTRACTOR from the site and take
possession of the Work and all the CONTRACTOR tools, appliances, construction
equipment and machinery at the site, including those stored elsewhere for which the
OWNER has paid the CONTRACTOR, and finish the work as the OWNER may deem
expedient. In such case, the CONTRACTOR shall not be entitled to receive any further
payment until the work is finished.

8.3 TERMINATION WITHOUT CAUSE. Upon 15 days written notice to the


CONTRACTOR, the OWNER, without prejudice to any other right or remedy, may
elect to abandon the work and terminate based on the payment scheduled stipulated
in the Contract. In such case, the CONTRACTOR shall be paid for all work executed
based on the payment scheme stated in 5.01 and any expenses sustained plus
reasonable termination expenses.

8.4 The OWNER shall have the authority to suspend the work wholly or partly by written
order for such, period as may be deemed necessary, due to force majeure or any
fortuitous events or for failure on the part of the CONTRACTOR to correct bad
conditions which are unsafe for workers or for the general public, to carry out valid
orders given by the OWNER or to perform any provisions of the contract, or due to
adjustment of plans to suit field conditions as found necessary during construction.
The CONTRACTOR shall immediately comply with such order to suspend the work
wholly or partially.

8.5 The CONTRACTOR or its duly authorized representatives shall have the right to
suspend work operation on any or all projects/activities along the critical path of
activities after fifteen (15) days from date of receipt of written notice from the
CONTRACTOR to the OWNER due to the following:

8.5.1 There exist right-of-way problems which prohibited the CONTRACTOR


from performing work in accordance with the approved construction
schedule.

8.5.2 Peace and order conditions make it extremely dangerous, if not impossible
to work.

8.5.3 Delay in the payment of CONTRACTOR’s claim for progress billing beyond
fifteen (15) calendar days from the time the CONTRACTOR’S claim has

9
been received by the OWNER’s authorized representatives and also that the
documents are complete, unless there are justifiable reasons therefore
which shall be communicated in writing to the CONTRACTOR.

8.5.4 In case of total suspension of activities along the critical path, which is not
due to any fault of the CONTRACTOR, the time elapsed between the
effective order of suspending operations and the other order to resume
work shall be allowed the CONTRACTOR by adjusting the contract time
accordingly and payment of labor fee and other penalties for the work
suspension, including mobilization fee.

ARTICLE IX
CONTRACT TIME, COMPLETION DATE & LIQUIDATED DAMAGES

9.1 The work to be performed by the CONTRACTOR under this Contract shall
commence within seven (7) calendar days upon signing of this Contract or upon
issuance of the Notice to Proceed AND the release of the Building Permit, and shall be
completed and delivered as defined in the Contract. Provided that the pre-
mobilization fee is likewise fully paid before any work commences. Work shall not
commence until the release of the Building Permit.

9.2 Any and all extensions of time in the completion of the Project shall be authorized or
granted by the OWNER upon written request of the CONTRACTOR, for any of the
following causes or reasons:

a. Force Majeure or unforeseen or unforeseeable events and circumstances;

b. Causes or events, which are beyond the control and without the fault or
negligence of the CONTRACTOR.

9.3 Should the amount of additional work of any kind or other special circumstances of
any kind whatsoever occur such as to fairly entitle the CONTRACTOR to an extension
the same may be considered, provided that, the OWNER is not bound to take into
account any claim for extension of the time unless the OWNER has, prior to the
expiration of the contract time and within sixty (60) calendar days after such work has
been commenced or after the circumstances leading to such claim have arisen,
delivered to the OWNER notice shall constitute a waiver by the CONTRACTOR of
any claim.

9.4 In case the CONTRACTOR encounters any justifiable cause or reason for delay, the
CONTRACTOR shall within ten (10) days from occurrence thereof submit to the
OWNER, a written request for time extension. Failure by the CONTRACTOR to
comply with this requirement shall result in outright denial by the OWNER of such
request:

ARTICLE X
INSURANCE

10
10.1 After execution of this Contract and prior to commencing construction work, a
COMPREHENSIVE/THIRD PARTY LIABILITY, ALL RISK INSURANCE shall be
secured by the CONTRACTOR covering the entire project more particularly the work
under this Contract or any property transferred to the CONTRACTOR by the
OWNER against any damage/loss or injury which may be caused thereto by the
CONTRACTOR or its personnel or any third party. The Insurance coverage shall be
through an insurance company acceptable to the OWNER. The CONTRACTOR shall
pay the premium of said insurance.

ARTICLE XI
PROJECT COMPLETION

11.1 When the Project reaches an accomplishment of ninety percent (90%) of the total
contract amount, the OWNER may create an inspectorate team to conduct preliminary
inspection and submit a punch-list to the CONTRACTOR in preparation for the final
turnover of the project. Said punch-list shall contain, among others, the remaining
works, work deficiencies for necessary correction, and the specific duration/time to
fully complete the project considering the approved remaining contract time. This,
however, shall not preclude the CONTRACTOR to claim for liquidated damages.

ARTICLE XII
FINAL CERTIFICATE OF COMPLETION

12.1 Upon receipt of written notice of the CONTRACTOR that the completed PROJECT
subject matter of this Contract is ready for final inspection and acceptance, the OWNER
shall promptly make such inspection. When the Parties determine that the said
PROJECT or works are acceptable under the terms of this Contract and that the same
has been duly performed, they shall promptly issue a Final Certificate of Completion
and Acceptance duly signed, stating that the PROJECT provided in this Contract has
been completed and is acceptable to them subject to the guarantee under Article 6
hereof and that the entire balance found to be due the CONTRACTOR and noted in
said Final Certificate of Completion is due and payable.

12.2 Before the issuance of the Final Certificate of Completion and Acceptance, the
CONTRACTOR shall submit to the OWNER the following:

a. Certificates of final inspection; and


b. Other documents that may be required and relevant to the occupancy of
the building.

12.3 Any claim submitted to the OWNER at any time by any party arising from this
Contract shall be sufficient reason for the OWNER to withhold any payment due the
CONTRACTOR.

11
12.4 It is hereby agreed that minor defects discovered in the final inspection must be
reported by the OWNER to the CONTRACTOR within sixty (60) days from the date of
Certificate of Final Acceptance. Otherwise, the Warranty shall be forfeited.

12.5 The issuance of a Certificate of Final Acceptance by the OWNER shall not relieve the
CONTRACTOR of any liability for any defect in the work, in accordance with Article
1723 of the New Civil Code and other related laws.

ARTICLE XIII
PERMANENT WATER, ELECTRICAL, AND TELECOMMUNICATIONS CONNECTIONS

13.1 The CONTRACTOR shall assist the OWNER in facilitating the release of applications,
permits, and all other necessary documents for the above-cited utilities of which
expenses to be shouldered by the OWNER.

ARTICLE XIV
ASSIGNMENT AND SUBCONTRACTING

14.1 The CONTRACTOR cannot assign, transfer, pledge, sub-contract, or otherwise dispose
of this Contract or any part or interest herein, except to CONSTRUCTION INC., which
will serve as the lead contractor, without the prior written approval of the OWNER.
Any such approval shall not relieve the CONTRACTOR from any liability or obligation
under law or this Contract, nor shall it create any contractual relation between the
assignee, transferee, sub-CONTRACTOR, pledgee, and the OWNER.

14.2 In case of Sub-Contracting, the CONTRACTOR shall submit, before Final Acceptance, a
sworn statement executed by the sub-CONTRACTOR attesting to the fact that the latter
has been fully paid by the CONTRACTOR for the materials furnished and the labor
performed under the sub-contract.

ARTICLE XV
MISCELLANEOUS

15.1 Any breach or violation by either party of the obligations and covenants under this
Contract shall entitle the aggrieved party to rescind or cancel this Contract, after
fifteen (15) days written notice to that effect. In addition, the party that breached or
violated this Contract agrees and obligates itself to pay for the actual damage incurred
by the other party.

15.2 Any failure of the OWNER to enforce her rights and privileges under this Contract
shall not be construed as a waiver or renunciation of such rights and privileges.

15.3 It is hereby agreed that any disputes arising out of or in connection with this Contract
shall be submitted to the Construction Industry Arbitration Commission (CIAC) for
arbitration.

12
15.4 This Contract shall be binding upon the respective assigns and successors-in- interest of
the parties hereto.

IN WITNESS WHEREOF, the parties to this Contract have on the day in the first above given,
hereunto set their hands and seals at the bottom of this page and on the left hand margin of all
other pages of this agreement

CONSTRUCTION, INC.
Contractor

_________________________ _________________________
Owner
President

13
ACKNOWLEDGEMENT

REPUBLIC OF THE PHILIPPINES }


CITY OF }

BEFORE ME, this _____ day of ____________________ in ___________________ personally


appeared:

Name Government ID Place / Date Issued


License #

known to me to be the same persons who executed the foregoing Construction Contract,
consisting of fourteen (14) pages including this page, wherein this Acknowledgment is written,
signed by the parties and their instrumental witnesses on each and every page thereof and
they acknowledged to me that the same is their free and voluntary act and deed.

WITNESS MY HAND AND SEAL this day of 2018 at City, Philippines.

Doc No
Page No
Book No
Series of 2018

14

You might also like