Professional Documents
Culture Documents
MS Project
MS Project
Introduction
PERT ANALYSIS Analyzing Resource Distribution
Introduction to Microsoft Project
Working with PERT Entry sheet Understanding resource usage and
Understanding Project
Setting
management task usage views
PERT weights
User interface Contouring resource assignments
Determining Expected duration
Lifecycle, Project Phases Assigning overtime work
for task
General management skills Preparing schedule Resource graph analysis
Certifications Study of over allocation of
DAY –7
DAY – 2 resources
Exercise -1
NEW PROJECT Different methods to identify over
DAY – 8
Creating new project allocated resources
Work Breakdown Structure
Project justification DAY – 12
Customizing WBS Code
Project selection criteria Resolving over allocation
Outlining task list – Summary
Project selection methods Understanding Resource leveling
and Subtasks
Project manager Indenting and Out denting techniques
Project charter Outline numbers for tasks Concepts of stretching, crunching
DAY – 3 Recurring tasks and splitting
Calendar DAY – 9 Automatic and Manual methods of
Introduction to base calendars Constraints resource leveling
Defining new calendars Working with constraints
DAY - 13
Editing project working time Resolving conflicts caused by
Exercise -2
Setting project calendar constraints
Setting deadline dates DAY – 14
Working with timescale
DAY – 10 Viewing the project
DAY – 4
Resource Planning Using split views
Tasks
Entering Manpower resources Sorting information
Entering Tasks
Entering Material resources Grouping information
Estimating task duration
Entering Construction Filtering information
Entering task duration
equipment resources Using Auto filters
Milestones
Activity duration Using Zoom
Organising tasks into Phases
Cost estimating DAY – 15
DAY – 5
Resource notes Optimising project plan
Task management
Effort driven scheduling Reviewing schedule
Linking tasks
Assigning resources Filtering tasks and Resources
Editing task links
Assigning additional resources Including fixed cost values
Unlinking tasks
Assigning Material resources Estimating cost for task/project
Creating recurring tasks
Saving Baseline plan
Using taks info. Dialogue box
Task notes
Moving and copying tasks
Inserting and deleting task
DAY -16 DAY – 20
TRACKING PROGRESS
Porject status update
Tracking progress
Saving baseline plan
Updating actual performance
Updating entire project
(work and cost)
Updating task actual values
Updating individual task
Update completion percentage
Updating entire project
Actual wor & actual cost
Displaying progress line
progress lines DAY –21
Comparative study of baseline Exercise -3
and actual (Tracking Gantt chart) DAY – 22
Analyzing variance and revising
Status check
the schedule
Viewing project statistics
DAY – 17 Project costs
NEW PROJECT Project critical path
Creating new project Variation in task duration
Project justification Variation in cost
Project selection criteria Identifying tasks with lags
DAY –26 to 30
Project work