6mm THK x 4' x 8' HARDIFLEX LOUVERS (ROOF VENT) WELDED MESH, 25mm
DOUBLE WALL W/ 50 x 75mm x APERTURE
0.5mm THK METAL STUDS SP
@ 400mm VERTICAL
TOP OF KING POST
(EL +9.50m)
2500
TOP OF ROOF BEAM
(EL +7.00m)
3000
TOP OF CORR
6000
G.I. SHT. WALL
2700
TOP OF PEDESTAL/
CHB WALL
(EL +1.00m)
1000
FFL
(EL 0.00m)
NGL
GA. 24 CORR G.I. SHEET CONCRETE (EL -0.20m)
200
WALLING BAGUIO GREEN ON PEDESTAL
2''x 4" CEE PURLINS
HORIZONTAL STUDS
5 4 3 2 1
WELDED MESH, 25mm LOUVERS (ROOF VENT) 6mm THK x 4' x 8' HARDIFLEX
APERTURE DOUBLE WALL W/ 50 x 75mm x
EMERGENCY 0.5mm THK METAL STUDS SP
EXIT FIRE DOOR @ 400mm VERTICAL
TOP OF KING POST
(EL +9.50m)
2500
1200
CILING LINE
(EL +5.80m)
3000
3000
TOP OF CORR
6000
TOP OF PEDESTAL/
CHB WALL
2800
(EL +1.00m)
1000
FFL FFL
(EL 0.00m) (EL 0.00m)
200
NGL NGL
(EL -0.20m) CONCRETE GA. 24 CORR G.I. SHEET FIRE EXIT (EL -0.20m)
CHB # 6 WALL SMOOTH
200
PROJECT TITLE : SIGNATORY SIGNATURE DATE RECOMMENDING APPROVAL: DATE SHEET CONTENTS: DRAWING NO:
APPROVED BY:
PREPARED BY:
ENGR. J.G. AGBAYANI ECS - 1618 - MN - 5
CONSTRUCTION OF MINE CW SUPERVISOR LEFT SIDE ELEVATION
FABRICATION SHOP BUILDING CHECKED BY: LORENZ EMMANUEL I. ALMAZAR RIGHT SIDE ELEVATION
ENGR. P.C. DAMASCO MINE-DIVISION MANAGER
SCALE: SHEET NO:
CW DEP'T. MNGR