Patricio Chacana
Plant Manager, Los Bronces
Content
• Process description
• Crusher Chutes
• SAG Changes
• Water Reclaiming System
• Tail Thickener
• Delivery
• Final Thoughts
Process Description
LB Process Flow Sheet
Mine
5
LB Slurry Transport System
Pipeline 1 Pipeline 2
Length 56 km Length 51.7 km
Diameter 24” Diameter 28”
% Solids 38 - 60 % Solids 38 - 60
Flow l/s 700 - 900 Flow l/s 950 – 1,280
tph 1,300 – 3,100 tph 3,300 – 4,500
Elevation (∆) 3,359 – 755m (2,604m) 6 Elevation (∆) 2,230 m
Las Tórtolas Plant – Flow Sheet
From Los Bronces
24” pipeline Rougher Flotation
Regrind
Cu thickener
Scavenger Flotation
Cleaner Flotation
Mo concentrate
Storage & dispatch Administration Building &
Bulk concentrate
thickener Personnel Facilities
Tailings thickener
From Los Bronces
28” pipeline Rougher Flotation Verti Mill Regrind
Cu thickener
Scavenger Flotation
Hyperbaric Filters
Confluencia – Las Tórtolas
87.000 tdp New Plant Reagents Area / Facilities
Cleaner Flotation
Mo concentrate
Storage & dispatch
Bulk concentrate
thickener
7
Tailings impoundment
WEST DAM
WATER RECOVERY
EAST DAM
MAIN DAM
8
Primary Crusher Chutes and
Diverters
Primary Crushing and Ore Transport System
CM3
10
Transfer Tower
Los Bronces
Stockpile
11
Chutes Modelling
12
Bedrocks Design
13
Bedrocks design
14
SAG Mill Changes
SAG LINERS MODIFICATION
15
10
0
3.000 3.250 3.500 3.750 4.000 4.250 4.500 4.750 5.000 5.250
Tonelaje Descarga, ton/hr
Delivery
LTIFR
28
Primary Crushers
Aug YTD
Crusher CP1 CP2 CP1 CP2
Availability,% 95,5 89,3 90,3 89,6
OT Crusher,% 75,5 77,7 74,7 81,4
Rock Breaker, % 10,3 16,5 9,1 15,0
LB CF LB CF
System OT % 58,1 75,4 57,9 75,4
TPH 3819 5369 3816 4990
• Budget 2013: 135.6 ktpd@70% OT & 8,070 tph
• August 2013: 150.4 ktpd@66.8% OT & 9,389 tph
• August YTD 2013: 143.3 ktpd@66.7 % OT & 8,960 tph
Crushers Downtime
250 100
200
Chancador 1 80
150 60
100 40
50 20
0 0
Cambio
Espera de Inchancabl Cambio Desechos Atollos Full Fallas
Preventiva Tronadura CM1 Chutes Limpieza
Mineral e Revest. Mina Chutes Stockpile Correas
(Febrero)
Hrs 197 174 164 120 101 90 69 69 43 41 37 33
Acum 13 25 37 45 52 58 63 67 70 73 76 78
200 100
Chancador 2 80
150
60
100
40
50 20
0 0
Cambio
Cambio de Espera de VDF (CM1A-
Preventiva Tronaduras Inchancable CVB003 Atollo Chute Otro
Revest. Mineral CM2A)
(Enero)
Hrs 170 170 113 79 71 58 53 49 42
Acum 16 32 43 51 58 63 68 73 77
(*) Solo considera el tiempo en que el chancador se detiene, es decir cuando la falta de mineral se prolonga por mas de 10 minutos.
Downtime Evolution
60
Chute Blockages 60 Waiting Ore
50
PCH1 PCH2 50
PCH1 PCH2
40
40
30 30
20 20
10 10
0 0
40
100 Chute Damage
80 Uncrushables 30 PCH1
PCH1 PCH2
60 20
40
10
20
0
0
31
Primary Crushers….
11000
10000
9000
8000
TPH
7000
6000
5000
4000
3000
40% 45% 50% 55% 60% 65% 70% 75% 80%
Operating Time (%)
136 ktpd Budget 2013 140 ktpd Budget 2014 148 ktpd 2011 2012 2013
32
KTPD
20
40
60
80
100
120
140
160
ene/10
mar/10
may/10
jul/10
sep/10
nov/10
ene/11
mar/11
Tratamiento Total
may/11
jul/11
sep/11
nov/11
Budget 2013 ene/12
Tratamiento Diario
(Balances Ene-10 a Jul-13 / Real Ago-13)
mar/12
may/12
jul/12
Ore Processed….
sep/12
Budget 2014
nov/12
ene/13
mar/13
may/13
jul/13
33
Confluencia Throughput
SAG, CF
140 100
120
80
100
80
60
60
40
40
20
0 20
Cambio de
Falta mineral Falla harnero MP
Revestimientos
Hrs 125 95 57 54,3
Acum 30 53 66 79
Confluencia SAG MTBF
OT YTD: 93%
SAG: Minutes / pieces
Finally…
• We survive…. Key factors:
• Previous preparation… never is enough!!
• Project / Operation / Contractors / Suppliers
Alliance
• Flexibility
• Simple is better!!
• Good information record
Final Message
"MEN WANTED FOR HAZARDOUS
JOURNEY. SMALL WAGES, BITTER COLD,
LONG MONTHS OF COMPLETE DARKNESS,
CONSTANT DANGER, SAFE RETURN
DOUBTFUL. HONOR AND RECOGNITION IN
CASE OF SUCCESS."
Ernest Shackleton, London Times, 1914
40
Thanks!!