You are on page 1of 267

DAFTAR KESEPAKATAN HARGA SATUAN BAHAN / MATERIAL DAN UPAH SEMESTER 2

DINAS BINA MARGA, DINAS PENGELOLAAN SUMBER DAYA AIR & PERTAMBANGAN
DAN DINAS CIPTA KARYA & TATA RUANG
KABUPATEN CIREBON
TAHUN ANGGARAN 2014

NO URAIAN BAHAN/MATERIAL SAT. HARGA KET


KESEPAKATAN
A. BAHAN :
I. BATU
1 Abu Batu m3 172,500.00
2 Atras ( tanah urug ) m3 125,000.00
3 Base course A m3 175,000.00
4 Base course B m3 165,800.00
5 Batu apung kg 4,300.00
6 Batu belah 10/15 cm m3 135,000.00
7 Batu belah 15/20 cm m3 135,000.00
8 Batu pecah mesin 0.5-1 cm m3 180,000.00
9 Batu pecah mesin 1-2 cm m3 180,000.00
10 Batu pecah mesin 2-3 cm m3 180,000.00
11 Batu tempel Palimanan 10 X 20 bh 1,500.00
12 Batu tempel kapur tekstur tidak rata bh 2,000.00
13 Kapur bakar m3 70,000.00
14 Kapur Sirih kg 2,000.00
15 Kerikil m3 65,000.00

II. PASIR
1 Pasir beton m3 150,000.00
2 Pasir aspal m3 150,000.00
3 Pasir pasang m3 143,000.00
4 Pasir urug m3 110,000.00
5 Sirtu m3 110,000.00
6 Sirtu tersaring m3 115,000.00
7 Tanah urug pilhan m3 125,000.00
8 Tanah urug biasa m3 100,000.00
III. BESI / PIPA / KAWAT
1 Besi WF/Besi Profil kg 11,250.00
2 Besi strip kg 11,250.00
3 Besi beton kg 11,000.00
4 Besi stainless dia. 0,5" m' 38,000.00
5 Besi stainless dia. 1" m' 60,000.00
6 Besi stainless dia. 1,5" m' 75,000.00
7 Besi stainless dia. 2" m' 80,000.00
8 Besi stainless dia. 2,5" m' 125,000.00
9 Besi stainless dia. 3" m' 152,000.00
10 Besi galvanis dia. 0.5" m' 25,000.00
11 Besi galvanis dia. 1" m' 27,000.00
12 Besi galvanis dia. 1.5" m' 45,000.00
13 Besi galvanis dia. 2" m' 57,000.00
14 Besi galvanis dia. 2.5" m' 80,500.00
15 Besi galvanis dia. 3" m' 96,000.00
16 Besi biasa dia. 2" btg 250,000.00
17 Besi biasa dia. 3" btg 310,000.00
18 Dop besi Ø 3 " bh 60,000.00
19 Kawat beton / Kawat tali kg 18,000.00
20 Kawat bronjong dia. 4 mm kg 20,000.00
21 Kawat galvanis dia. 4 mm kg 20,000.00
22 Kawat galvanis dia. 6 mm kg 24,000.00
23 Kawat duri m' 20,000.00
24 Pipa besi galvanis 2" btg 324,000.00
25 Pipa besi galvanis 3" btg/6m' 600,000.00
26 Pipa PVC Ø 2" S-12,5 ( 8 - 10 bar ) m' 26,300.00
27 Pipa PVC Ø 3" S-12,5 ( 8 - 10 bar ) m' 53,600.00
28 Pipa PVC / paralon 2 inch btg 50,600.00
29 Pipa PVC / paralon 3 inch btg 75,000.00
30 Pipa Reducer PVC Ø 3"-4" bh 5,800.00
31 Pipa Knee/bend PVC Ø 3" bh 5,800.00
32 Plat baja tebal 5 mm - 20 mm kg 12,650.00
33 Ram kawat harmonika m2 23,200.00
34 Socket besi O 3 " bh 45,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN

IV. PABRIKAN / TOKO


1 Alumunium foil m2 9,000.00
2 Alumunium pelapis pintu KM lbr 130,000.00
3 Asbes gelombang 1500 x 1050 x 4 mm lbr 35,000.00
4 Asbes gelombang 1800 x 920 x 4 mm lbr 42,500.00
5 Asbes gelombang 2100 x 1050 x 4 mm lbr 57,000.00
6 Asbes gelombang 2400 x 1050 x 4 mm lbr 65,000.00
7 Asbes gelombang 2700 x 1050 x 4 mm lbr 75,000.00
8 Asbes gelombang 3000 x 1050 x 4 mm lbr 85,000.00
9 Bak mandi keramik volume 0,3 m3 bh 185,000.00
10 Bak mandi fiber 120 L bh 220,000.00
11 Batu apung kg 4,300.00
12 Baut 3/4 " bh 3,000.00
13 Baut 5/8 " bh 3,800.00
14 Baut 1/2 " bh 6,000.00
15 Baut 1/2 " panjang 30 cm bh 8,550.00
16 Baut lawa-lawa bh 9,900.00
17 Beading penurunan ( PC ) gypsum m' 10,000.00
18 Beading horison gypsum m' 10,000.00
19 Cat Menie kg 20,000.00
20 Cat genteng kg 48,000.00
21 Cat penutup kayu kg 49,000.00
22 Cat penutup tembok kg 23,000.00
23 Cat penutup besi kg 45,000.00
24 Cat Sinkromat kg 80,000.00
25 Closet duduk ( mono block ) porselen merk INA bh 1,237,000.00
26 Closet duduk ( siram ) porselen merk INA bh 545,000.00
27 Closet jongkok porselen merk INA/KIA bh 140,000.00
28 Dempul kayu kg 18,000.00
29 Dinding keramik uk. 10 x 20 cm bh 950.00
30 Dinding keramik uk. 20 x 20 cm bh 1,850.00
31 Dinding keramik uk. 20 x 25 cm bh 2,200.00
32 Dinding keramik uk. 30 x 30 cm bh 3,300.00
33 Door closer bh 158,125.00
34 Daun pintu alumunium lengkap warna natural/coklat dop bh 900,000.00
35 Daun pintu alumunium lengkap warna coklat kilap bh 1,300,000.00
36 Daun jendela alumunium lengkap warna natural/coklat dop bh 350,000.00
37 Daun jendela alumunium lengkap warna coklat kilap bh 400,000.00
38 Elastomer 30x30x5 bh 550,000.00
39 Engsel jendela set 12,000.00
40 Engsel pintu set 15,000.00
41 Engsel meubeler bh 3,800.00
42 Eternit tebal 4 mm uk. 1 m x 1 m lbr 6,800.00
43 Eternit tebal 4 mm uk. 1 m x 0,5 m lbr 3,400.00
44 Flincote ltr 22,000.00
45 Glass beat kg 20,000.00
46 Glass Block bh 17,500.00
47 Gas elpiji kg 8,800.00
48 Grendel pintu / jendela bh 5,500.00
49 Gypsum board lbr 50,000.00
50 GRC tebal 4 mm lbr 53,000.00
51 Hampelas lbr 4,000.00
52 Kaca nako tebal 5 mm berikut teralis bh 11,400.00
53 Kaca polos tebal 3 mm m2 63,250.00
54 Kaca polos tebal 5 mm m2 75,000.00
55 Kait angin bh 9,500.00
56 Kunci gembok bh 17,000.00
57 Kunci pintu ukuran besar bh 125,000.00
58 Kunci pintu ukuran sedang bh 85,000.00
59 Kunci dan daun pintu dari fiber bh 350,000.00
60 Kusen Alumunium 3" warna natural m' 55,000.00
61 Kusen Alumunium 3" warna coklat dop m' 60,000.00
62 Kusen Alumunium 3" warna coklat kilap m' 75,000.00
63 Kusen Alumunium 4" warna natural m' 60,000.00
64 Kusen Alumunium 4" warna coklat dop m' 65,000.00
65 Kusen Alumunium 4" warna coklat kilap m' 85,000.00
66 Langko - langko kuda - kuda bh 18,000.00
67 Lantai granit 40 x 40 cm ex. Essenza bh 43,500.00
68 Lantai granit 40 x 40 cm ex. Granito bh 42,000.00
69 Lantai granit 60 x 60 cm ex. Granito bh 46,800.00
70 Lantai keramik uk. 10 x 20 cm bh 950.00
71 Lantai keramik uk. 20 x 20 cm bh 1,650.00
72 Lantai keramik uk. 30 x 30 cm bh 3,650.00
73 Lantai keramik uk. 40 x 40 cm ( putih polos ) bh 6,900.00
74 Lantai terakota 20 x 5 cm bh 4,400.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
75 Lem kayu ltr 30,000.00
76 Lemkra/zat addictive kg 15,000.00
77 Lemkra Just Do It kg 4,500.00
78 Lemkra FS Nat kg 15,850.00
79 List kayu B.3 ( lebar sisi 3 cm ) m' 4,400.00
80 List kayu B.4 ( lebar sisi 4 cm ) m' 4,800.00
81 List keliling gypsum lebar 7 cm m' 6,250.00
82 List keliling gypsum lebar 10 cm m' 7,250.00
83 List keliling gypsum lebar 12 cm m' 8,750.00
84 List drop m' 8,900.00
85 Melamin / folywood lbr 88,500.00
86 Mozaik uk. 20 x 20 cm bh 1,900.00
87 Multiplex tebal 15 mm m2 272,000.00
88 Paku biasa 1/2" - 1" kg 15,000.00
89 Paku biasa 2" - 5" kg 12,500.00
90 Paku pancing 60 x 230 bh 825.00
91 Paku sekrup 3" - 5 " bh 400.00
92 Paku ulir bh 150.00
93 Plamir kayu / kualitas 1 kg 17,500.00
94 Plamir tembok kg 25,000.00
95 Plester Mutiara kg 8,700.00
96 Polycarbonate m2 115,000.00
97 Plywood lbr 92,250.00
98 Portland Cement ( PC ) zak 61,000.00
99 Rubber joint 25x10x5 bh 175,000.00
100 Roster / batu kerawang bh 2,600.00
101 Semen portland kg 1,220.00
102 Semen warna kg 11,000.00
103 Seng BJLS 30 L. 90 cm m2 32,500.00
104 Seng gelombang 3' - 6 " BJLS 30 lbr 42,000.00
105 Sirlak kg 19,500.00
106 Spirtus ltr 11,000.00
107 Skim Coat kg 4,400.00
108 Taekwood 4 mm 1200 x 2400 mm lbr 90,000.00
109 Taekwood 4 mm 900 x 2400 mm lbr 75,000.00
110 Ter kayu kg 14,500.00
111 Thermoplastic Glass beat kg 23,000.00
112 Tiner / minyak cat ltr 9,200.00
113 Triplek 3 mm lbr 45,000.00
114 Triplek 4 mm lbr 55,000.00
115 Triplek 6 mm lbr 75,000.00
116 Triplek 9 mm lbr 95,000.00
117 Triplek 12 mm lbr 200,000.00
118 TG 302 kg 46,500.00
119 Ubin abu2 kepala basah 20 x 20 cm bh 2,000.00
120 Ubin abu2 kepala basah 30 x 30 cm bh 2,500.00
121 Ubin wafel ukuran 20 x 20 cm bh 2,000.00
122 Ubin warna 20 x 20 cm bh 2,300.00
123 Ubin warna 30 x 30 cm bh 2,900.00
124 Washtafel bh 686,000.00
125 Woodplank bh 59,500.00
126 Zincalume m2 70,000.00
127 Rangka plafon memakai Hollow dengan penutup GRC tebal 4 mm + pengecatan m2 88,200.00
128 Rangka atap baja ringan
a. Atap Baja Ringan memakai Genteng Keramik/Plentong ( jarak reng 22-28 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 165,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 210,000.00
b. Atap Baja Ringan Genteng Metal/Spandek ( jarak reng 37,5-90 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 155,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 162,500.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 160,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 180,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
129 Pintu Air Sorong
- Pintu Air Sorong Baja B = 0.40-0.60 ( 1 drat stang tanpa roda gigi ) Unit 8,497,000.00
- Pintu Air Sorong Baja B = 0.70-0.80 ( 1 drat stang tanpa roda gigi ) Unit 9,639,000.00
- Pintu Air Sorong Baja B = 0.90-1.00 ( 1 drat stang tanpa roda gigi ) Unit 13,500,000.00
- Pintu Air Sorong Baja B = 0.70-1.00 ( 1 drat stang + roda gigi ) Unit 11,414,000.00
- Pintu Air Sorong Baja B = 1.00-1.10 ( 2 drat stang + roda gigi ) Unit 25,366,000.00
- Pintu Air Sorong Baja B = 1.50-1.80 ( 2 drat stang + roda gigi ) Unit 38,049,000.00
- Pintu Air Sorong Baja B = 2.00-2.50 ( 2 drat stang + roda gigi ) Unit 50,732,000.00
130 Gigi Payung / Jantung Besar bh 1,250,000.00
131 Gigi Payung / Jantung Sedang bh 1,100,000.00
132 Gigi Piring Besar bh 2,930,000.00
133 Gigi Piring Sedang bh 1,903,000.00
134 Blok Laher bh 1,750,000.00
135 Bron mur drat 5 " bh 3,250,000.00
136 Bron mur drat 3 " bh 2,150,000.00
137 Drat stang 2" x 100 bh 2,500,000.00
138 Drat stang 3/4" x 100 bh 1,750,000.00
139 Drat stang 1,5" x 100 bh 1,550,000.00
140 Dudukan as horisontal bh 1,850,000.00
141 As Horisontal bh 1,850,000.00
142 Karet sel 8 x 3 cm bh 1,500,000.00
143 As Pemutar bh 750,000.00
144 Laher/Bearing bh 350,000.00
145 Engkel Kemudi Sedang bh 450,000.00
146 Daun Pintu B.50, H.50 bh 1,000,000.00
147 Pintu Klep B=0,5 m unit 1,750,000.00
148 Pintu Klep B=1,0 m unit 3,000,000.00
149 Pintu Klep B=1,5 m unit 4,500,000.00

V. ASPAL
1 Aspal kemasan kg 10,785.00
2 Aspal curah kg 9,930.00

VI. MINYAK
1 Premium liter 4,500.00
2 Premium (non subsidi) liter 9,950.00
3 Solar liter 4,500.00
4 Solar (non subsidi) liter 8,500.00
5 Minyak tanah liter 9,000.00
6 Olie SAE 20, 40, 60, 80 dan 120 liter 35,000.00
7 Pelumas bekisting liter 10,000.00
8 Stempet kg 25,000.00

VII.CETAKAN
1 Bata merah bh 600.00
2 Bata berongga bh 2,250.00
3 Genteng glazuur turbo ex Jatiwangi bh 2,500.00
4 Genteng nok/bubung diglazuur ex Jatiwangi bh 3,500.00
5 Genteng nok/bubung press mesin ex Jatiwangi bh 2,200.00
6 Genteng nok/bubung press tangan ex Jatiwangi bh 2,000.00
7 Genteng nok/bubung morando diglazuur bh 4,500.00
8 Genteng nok/bubung morando bh 4,000.00
9 Genteng press diglazuur ex Jatiwangi bh 2,000.00
10 Genteng press mesin ex Jatiwangi bh 1,900.00
11 Genteng press tangan ex Jatiwangi bh 1,400.00
12 Genteng Type Viktoria bh 9,000.00
13 Genteng nok/bubung Type Viktoria bh 12,500.00
14 Genteng nok/bubung ujung Type Viktoria bh 20,000.00
15 Genteng nok/bubung ujung pertigaan Type Viktoria bh 25,000.00
16 Genteng beton bh 5,000.00
17 Genteng metal m2 75,000.00
18 Gorong-gorong buis beton dia. 100 cm bh/0,5 m' 120,000.00
19 Gorong-gorong buis beton dia. 80 cm bh/0,5 m' 100,000.00
20 Gorong-gorong buis beton dia. 60 cm bh/m' 70,000.00
21 Gorong-gorong buis beton dia. 40 cm bh/m' 60,000.00
22 Gorong-gorong buis beton dia. 30 cm bh/m' 50,000.00
23 Gorong-gorong buis beton dia. 20 cm bh/m' 40,000.00
24 Gravel dia. 60 cm bh 38,000.00
25 Gravel dia. 40 cm bh 35,000.00
26 Gravel dia. 20 cm bh 20,000.00
27 Nok steel gelombang 1050 x 5 mm m' 23,000.00
28 Nok steel gelombang 920 x 5 mm m' 22,500.00
29 Nok / bubung genteng beton bh 6,000.00
30 Paving Block K.175 Segi Enam bh 1,500.00
31 Paving Block K.175 Persegi bh 2,000.00
32 Paving Block K.125 Segi Enam bh 1,250.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
33 Paving Block K.125 Persegi bh 1,600.00
34 Digital printing m2 25,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
VIII. KAYU
1 Bambu Ø6 - Ø8 / 6 m btg 14,000.00
2 Kayu deplank 8/20 - 4 m (Jati Jateng) m3 8,000,000.00
3 Kayu deplank 8/20 - 4 m (Balau) m3 7,500,000.00
4 Kayu deplank 8/20 - 4 m (Borneo) m3 4,500,000.00
5 Kayu dolken O 8 - 10 /4 m btg 57,000.00
6 Kayu dolken O 12 - 15 /4 m btg 60,000.00
7 Kayu dolken O 5 /3 m btg 35,000.00
8 Kayu hutan/kayu perancah acuan m3 4,255,000.00
9 Kayu kamper m3 8,200,000.00
10 Kayu kaso 5/7 meranti m3 5,000,000.00
11 Kayu kaso 5/7 meranti btg 79,000.00
12 Kayu kruing m3 7,274,000.00
13 Kayu lanan m3 6,546,000.00
14 Kayu meranti m3 5,000,000.00
15 Kayu jati Jabar m3 7,500,000.00
16 Kayu Balau m3 7,500,000.00
17 Kayu Borneo m3 4,500,000.00
18 Kayu bakar m3 90,000.00
19 Reng kayu borneo ukuran 2/3 cm btg 54,000.00
20 Tali Ijuk kg 9,000.00

B. UPAH
1 Mandor /hari 70,000.00
2 Kepala tukang /hari 65,000.00
3 Tukang kayu / besi /hari 60,000.00
4 Tukang batu /hari 60,000.00
5 Pembantu tukang /hari 50,000.00
6 Operator terlatih /hari 60,000.00
7 Operator kurang terlatih /hari 55,000.00
8 Pembantu operator /hari 50,000.00
9 Supir truk /hari 55,000.00
10 Pembantu supir /hari 50,000.00
11 Buruh lapangan terlatih /hari 55,000.00
12 Buruh lapangan kurang terlatih /hari 50,000.00
13 Buruh lapangan tak terlatih / pekerja /hari 50,000.00

DINAS BINA MARGA DINAS PENGELOLAAN SUMBER DAYA AIR


KABUPATEN CIREBON DINAS CIPTA KARYA DAN TATA RUANG DAN PERTAMBANGAN KAB.CIREBON
KABUPATEN CIREBON Kepala Seksi Perencanaan Teknik
Kepala Seksi Desain Teknik
Jalan dan Jembatan Kepala Seksi Bangunan Gedung

SUPARMAN,S.Sos, ST Ir. DAWUD


NIP. 19721230 199901 1 001 YEDI ADHI PRIATNA, BAE, S.Sos NIP. 19640525 199303 1 007
NIP. 19660815 199803 1 004
Kepala Bidang Bina Teknik Kepala Bidang Bina Teknik
Kepala Bidang Bangunan Gedung, Perumahan dan
Permukiman

RACHMAT S, BE AGUNG GUMILANG, SS., M.si


NIP. 19571008 198709 1 001 Ir. FELLYANTO TAMZIL, MM NIP. 19711224 199803 1 004
NIP. 19620428 199003 1 006
Kepala Dinas Bina Marga Kepala Dinas Pengelolaan Sumber Daya Air
Kabupaten Cirebon Kepala Dinas Cipta Karya dan Tata Ruang dan Pertambangan Kabupaten Cirebon
Kabupaten Cirebon

Ir. AVIP SUHERDIAN, MT DEDI NURUL SUDJUDI A


NIP. 19640827 199303 1 006 Ir. H. ARIEF BUDI PRAYITNO NIP. 19590721 198303 1 009
NIP. 19620428 199003 1 006
DAFTAR KESEPAKATAN HARGA SATUAN BAHAN / MATERIAL DAN UPAH
DINAS BINA MARGA, DINAS PENGELOLAAN SUMBER DAYA AIR & PERTAMBANGAN
DAN DINAS CIPTA KARYA & TATA RUANG
KABUPATEN CIREBON
TAHUN ANGGARAN 2014

NO URAIAN BAHAN/MATERIAL SAT. HARGA KET


KESEPAKATAN
A. BAHAN :
I. BATU
1 Abu Batu m3 172,500.00
2 Agregat kasar m3 203,000.00
3 Agregat halus m3 203,000.00
4 Atras ( tanah urug ) m3 125,000.00
5 Base course A m3 175,000.00
6 Base course B m3 165,800.00
7 Batu apung kg 4,300.00
8 Batu belah 10/15 cm m3 153,000.00
9 Batu belah 15/20 cm m3 153,000.00
10 Batu pecah mesin 0.5-1 cm m3 180,000.00
11 Batu pecah mesin 1-2 cm m3 180,000.00
12 Batu pecah mesin 2-3 cm m3 190,000.00
13 Batu tempel Palimanan 10 X 20 bh 1,500.00
14 Batu tempel kapur tekstur tidak rata bh 2,000.00
15 Chipping m3 203,000.00
16 Filler kg 90.00
17 Kapur bakar m3 70,000.00
18 Kapur Sirih kg 2,000.00
19 Kerikil m3 65,000.00

II. PASIR
1 Pasir beton m3 178,000.00
2 Pasir aspal m3 150,000.00
3 Pasir pasang m3 145,000.00
4 Pasir urug m3 140,000.00
5 Sirtu m3 140,000.00
6 Sirtu tersaring m3 145,000.00
7 Tanah urug pilhan m3 125,000.00
8 Tanah urug biasa m3 100,000.00
III. BESI / PIPA / KAWAT
1 Besi WF/Besi Profil kg 12,500.00
2 Besi strip kg 12,500.00
3 Besi beton kg 11,000.00
4 Besi stainless dia. 0,5" m' 38,000.00
5 Besi stainless dia. 1" m' 60,000.00
6 Besi stainless dia. 1,5" m' 75,000.00
7 Besi stainless dia. 2" m' 80,000.00
8 Besi stainless dia. 2,5" m' 125,000.00
9 Besi stainless dia. 3" m' 152,000.00
10 Besi galvanis dia. 0.5" m' 25,000.00
11 Besi galvanis dia. 1" m' 27,000.00
12 Besi galvanis dia. 1.5" m' 45,000.00
13 Besi galvanis dia. 2" m' 57,000.00
14 Besi galvanis dia. 2.5" m' 80,500.00
15 Besi galvanis dia. 3" m' 96,000.00
16 Besi biasa dia. 2" btg 250,000.00
17 Besi biasa dia. 3" btg 310,000.00
18 Dop besi Ø 3 " bh 60,000.00
19 Kawat beton / Kawat tali kg 18,000.00
20 Kawat bronjong dia. 4 mm kg 20,000.00
21 Kawat galvanis dia. 4 mm kg 20,000.00
22 Kawat galvanis dia. 6 mm kg 24,000.00
23 Kawat duri m' 14,000.00
24 Pipa besi galvanis 2" btg 324,000.00
25 Pipa besi galvanis 3" btg/6m' 500,000.00
26 Pipa PVC Ø 2" S-12,5 ( 8 - 10 bar ) m' 26,300.00
27 Pipa PVC Ø 3" S-12,5 ( 8 - 10 bar ) m' 53,600.00
28 Pipa PVC / paralon 2 inch btg 65,000.00
29 Pipa PVC / paralon 3 inch btg 90,000.00
30 Pipa Reducer PVC Ø 3"-4" bh 6,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
31 Pipa Knee/bend PVC Ø 3" bh 6,000.00
32 Plat baja tebal 5 mm - 20 mm kg 12,650.00
33 Ram kawat harmonika m2 23,000.00
34 Socket besi O 3 " bh 45,000.00
35 Toren Penguin 250 lt bh 525,000.00
36 Toren 500 lt bh 860,000.00
37 Toren 1000 lt bh 1,450,000.00

IV. PABRIKAN / TOKO


1 Alumunium foil m2 9,000.00
2 Alumunium pelapis pintu KM Tebal 0.2 lbr 35,000.00
3 Alumunium pelapis pintu KM Tebal 0.3 lbr 50,000.00
4 Alumunium pelapis pintu KM Tebal 0.4 lbr 70,000.00
5 Asbes gelombang 1500 x 1050 x 4 mm lbr 42,500.00
6 Asbes gelombang 1800 x 920 x 4 mm lbr 32,000.00
7 Asbes gelombang 2100 x 1050 x 4 mm lbr 57,000.00
8 Asbes gelombang 2400 x 1050 x 4 mm lbr 65,000.00
9 Asbes gelombang 2700 x 1050 x 4 mm lbr 75,000.00
10 Asbes gelombang 3000 x 1050 x 4 mm lbr 85,000.00
11 Ampelas lbr 3,000.00
12 Bak mandi keramik volume 0,3 m3 bh 185,000.00
13 Bak mandi fiber 120 L bh 220,000.00
14 Batu apung kg 4,300.00
15 Baut 3/4 " bh 8,500.00
16 Baut 5/8 " bh 3,800.00
17 Baut 1/2 " bh 6,000.00
18 Baut 1/2 " panjang 30 cm bh 8,550.00
19 Beading penurunan ( PC ) gypsum m' 10,000.00
20 Beading horison gypsum m' 10,000.00
21 Cat Menie kg 20,000.00
22 Cat genteng Matex kg 48,000.00
23 Cat genteng maxilite kg 50,000.00
24 Cat penutup kayu Bee brand kg 49,000.00
25 Cat penutup kayu Vim kg 25,000.00
26 Cat penutup kayu Ftalit kg 46,000.00
27 Cat penutup kayu Avian kg 48,000.00
28 Cat penutup tembok Vinilex kg 23,000.00
29 Cat penutup tembok Metrolit kg 23,000.00
30 Cat penutup tembok catylac kg 18,600.00
31 Cat penutup tembok Q Luc kg 10,000.00
32 Cat penutup tembok Property kg 9,500.00
33 Cat penutup besi kg 45,000.00
34 Cat Sinkromat kg 80,000.00
35 Closet duduk ( mono block ) porselen merk INA bh 1,237,000.00
36 Closet duduk ( siram ) porselen merk INA bh 545,000.00
37 Closet jongkok porselen merk INA/KIA bh 140,000.00
38 Closet jongkok porselen merk Avena bh 100,000.00
39 Dempul kayu kg 18,500.00
40 Dinding keramik uk. 10 x 20 cm bh 1,000.00
41 Dinding keramik uk. 20 x 20 cm bh 2,000.00
42 Dinding keramik uk. 20 x 25 cm bh 2,200.00
43 Dinding keramik uk. 30 x 30 cm bh 4,500.00
44 Door closer bh 160,000.00
45 Daun pintu alumunium lengkap warna natural/coklat dop bh 900,000.00
46 Daun pintu alumunium lengkap warna coklat kilap bh 1,300,000.00
47 Daun jendela alumunium lengkap warna natural/coklat dop bh 350,000.00
48 Daun jendela alumunium lengkap warna coklat kilap bh 400,000.00
49 Elastomer 30x30x5 bh 550,000.00
50 Engsel jendela set 12,000.00
51 Engsel pintu set 19,000.00
52 Engsel meubeler bh 3,800.00
53 Eternit tebal 4 mm uk. 1 m x 1 m lbr 6,900.00
54 Eternit tebal 4 mm uk. 1 m x 0,5 m lbr 3,450.00
55 Flincote ltr 22,000.00
56 Loster Jati bh 25,000.00
57 Glass beat kg 20,000.00
58 Glass Block bh 17,500.00
59 Gas elpiji kg 8,800.00
60 Grendel pintu / jendela bh 5,500.00
61 Gypsum board lbr 52,500.00
62 GRC tebal 4 mm lbr 52,500.00
63 Fiber Gelombang 180 x80 lbr 40,000.00
64 Kaca nako tebal 5 mm berikut teralis bh 11,400.00
65 Kaca polos tebal 3 mm m2 63,250.00
66 Kaca polos tebal 5 mm m2 75,000.00
67 Kaca polos tebal 5 mm ryben m2 80,000.00
68 Kait angin bh 7,500.00
69 Kran air Onda bh 12,000.00
70 Kunci gembok bh 20,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
71 Kunci pintu ukuran besar bh 125,000.00
72 Kunci pintu ukuran sedang bh 85,000.00
73 Kunci dan daun pintu dari fiber bh 350,000.00
74 Kusen Alumunium 3" warna natural m' 60,000.00
75 Kusen Alumunium 3" warna coklat dop m' 65,000.00
76 Kusen Alumunium 3" warna coklat kilap m' 70,000.00
77 Kusen Alumunium 4" warna natural m' 65,000.00
78 Kusen Alumunium 4" warna coklat dop m' 70,000.00
79 Kusen Alumunium 4" warna coklat kilap m' 75,000.00
80 Kusen Alumunium 3" YKK m' 100,000.00
81 Kusen Alumunium 4" YKK m' 1,300,000.00
82 Langko - langko kuda - kuda bh 18,000.00
83 Lantai granit 60 x 60 cm ex. Granito corak bh 57,600.00
84 Lantai granit 60 x 60 cm ex. Granito polos bh 84,600.00
85 Lantai granit 40 x 40 cm ex. Essenza bh 43,500.00
86 Lantai granit 40 x 40 cm ex. Granito bh 42,000.00
87 Lantai granit 60 x 60 cm ex. Granito bh 46,800.00
88 Lantai keramik uk. 10 x 20 cm bh 1,000.00
89 Lantai keramik uk. 20 x 20 cm bh 2,000.00
90 Lantai keramik uk. 30 x 30 cm bh 2,200.00
91 Lantai keramik uk. 40 x 40 cm ( putih polos ) bh 4,500.00
92 Lantai terakota 20 x 5 cm bh 4,400.00
93 Lem kayu ltr 30,000.00
94 Lemkra/zat addictive kg 15,000.00
95 Lemkra Just Do It kg 4,500.00
96 Lemkra FS Nat kg 15,850.00
97 List kayu B.3 ( lebar sisi 3 cm ) m' 4,400.00
98 List kayu B.4 ( lebar sisi 4 cm ) m' 4,800.00
99 List keliling gypsum lebar 7 cm m' 14,000.00
100 List keliling gypsum lebar 10 cm m' 16,000.00
101 List keliling gypsum lebar 12 cm m' 18,000.00
102 List drop m' 8,900.00
103 Melamin / folywood lbr 88,500.00
104 Mozaik uk. 20 x 20 cm bh 1,900.00
105 Multiplex tebal 12 mm lbr 175,000.00
106 Multiplex tebal 15 mm lbr 275,000.00
107 Paku biasa 1/2" - 1" kg 16,000.00
108 Paku biasa 2" - 5" kg 13,000.00
109 Paku pancing 60 x 230 bh 825.00
110 Paku sekrup 3" - 5 " bh 400.00
111 Paku ulir bh 150.00
112 Plamir kayu / kualitas 1 kg 18,500.00
113 Plamir tembok kg 20,000.00
114 Plester Mutiara kg 8,000.00
115 Pintu kamer mandi fiber polos Daimaru bh 175,000.00
116 Pintu kamer mandi fiber Kaca Daimaru bh 245,000.00
117 Pintu kamer mandi Almunium Kettler bh 700,000.00
118 Polycarbonate m2 115,000.00
119 Plywood lbr 92,250.00
120 Portland Cement ( PC ) tiga roda zak 63,000.00
121 Portland Cement ( PC ) holcim zak 62,500.00
122 Portland Cement ( PC ) gresik zak 61,000.00
123 Rubber joint 25x10x5 bh 175,000.00
124 Roster / batu kerawang bh 4,000.00
125 Semen portland kg 1,260.00
126 Semen warna kg 6,000.00
127 Seng BJLS 30 L. 90 cm m2 38,000.00
128 Seng gelombang 3' - 6 " BJLS 30 lbr 42,000.00
129 Sirlak kg 19,500.00
130 Spirtus ltr 9,000.00
131 Skim Coat kg 4,400.00
132 Taekwood 4 mm 1200 x 2400 mm lbr 80,000.00
133 Taekwood 4 mm 900 x 2400 mm lbr 65,000.00
134 Ter kayu kg 14,500.00
135 Thermoplastic Glass beat kg 23,000.00
136 Tiner / minyak cat ltr 6,000.00
137 Triplek 3 mm lbr 45,000.00
138 Triplek 4 mm lbr 55,000.00
139 Triplek 6 mm lbr 75,000.00
140 Triplek 9 mm lbr 102,500.00
141 Triplek 12 mm lbr 200,000.00
142 Tempat cuci piring Beleza bh 400,000.00
143 Tempat cuci piring Benoti bh 175,000.00
144 Tempat cuci piring Royal bh 160,000.00
145 TG 302 kg 43,600.00
146 Washtafel bh 686,000.00
147 Woodplank corak 4 m lbr 60,000.00
148 Woodplank polos 2 m lbr 32,500.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
149 Ubin abu2 kepala basah 20 x 20 cm bh 2,000.00
150 Ubin abu2 kepala basah 30 x 30 cm bh 2,500.00
151 Ubin wafel ukuran 20 x 20 cm bh 2,000.00
152 Ubin warna 20 x 20 cm bh 2,300.00
153 Ubin warna 30 x 30 cm bh 2,900.00
154 Washtafel bh 686,000.00
155 Woodplank corak 4 m lbr 60,000.00
156 Woodplank polos 2 m lbr 32,500.00
157 Zincalume m2 75,000.00
158 Rangka plafon memakai Hollow dengan penutup GRC tebal 4 mm + pengec m2 88,200.00
159 Rangka atap baja ringan
a. Atap Baja Ringan memakai Genteng Keramik/Plentong ( jarak reng 22-28 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 165,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 210,000.00
b. Atap Baja Ringan Genteng Metal/Spandek ( jarak reng 37,5-90 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 155,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 162,500.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 160,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 180,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00

160 Pintu Air Sorong


- Pintu Air Sorong Baja B = 0.40-0.60 ( 1 drat stang tanpa roda gigi ) Unit 8,497,000.00
- Pintu Air Sorong Baja B = 0.70-0.80 ( 1 drat stang tanpa roda gigi ) Unit 9,639,000.00
- Pintu Air Sorong Baja B = 0.90-1.00 ( 1 drat stang tanpa roda gigi ) Unit 13,500,000.00
- Pintu Air Sorong Baja B = 0.70-1.00 ( 1 drat stang + roda gigi ) Unit 11,414,000.00
- Pintu Air Sorong Baja B = 1.00-1.10 ( 2 drat stang + roda gigi ) Unit 25,366,000.00
- Pintu Air Sorong Baja B = 1.50-1.80 ( 2 drat stang + roda gigi ) Unit 38,049,000.00
- Pintu Air Sorong Baja B = 2.00-2.50 ( 2 drat stang + roda gigi ) Unit 50,732,000.00
161 Gigi Payung / Jantung Besar bh 1,250,000.00
162 Gigi Payung / Jantung Sedang bh 1,100,000.00
163 Gigi Piring Besar bh 2,930,000.00
164 Gigi Piring Sedang bh 1,903,000.00
165 Blok Laher bh 1,750,000.00
166 Bron mur drat 5 " bh 3,250,000.00
167 Bron mur drat 3 " bh 2,150,000.00
168 Drat stang 2" x 100 bh 2,500,000.00
169 Drat stang 3/4" x 100 bh 1,750,000.00
170 Drat stang 1,5" x 100 bh 1,550,000.00
171 Dudukan as horisontal bh 1,850,000.00
172 As Horisontal bh 1,850,000.00
173 Karet sel 8 x 3 cm bh 1,500,000.00
174 As Pemutar bh 750,000.00
175 Laher/Bearing bh 350,000.00
176 Engkel Kemudi Sedang bh 450,000.00
177 Daun Pintu B.50, H.50 bh 1,000,000.00
178 Pintu Klep B=0,5 m unit 1,750,000.00
179 Pintu Klep B=1,0 m unit 3,000,000.00
180 Pintu Klep B=1,5 m unit 4,500,000.00

V. ASPAL
1 Aspal kemasan kg 11,300.00
2 Aspal curah kg 11,100.00

VI. MINYAK
1 Premium liter 6,500.00
2 Premium (non subsidi) liter 9,600.00
3 Solar liter 6,500.00
4 Solar (non subsidi) liter 10,400.00
5 Minyak tanah liter 10,300.00
6 Olie SAE 20, 40, 60, 80 dan 120 liter 35,000.00
7 Pelumas bekisting liter 10,000.00
8 Stempet kg 25,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
VII.CETAKAN
1 Bata merah bh 650.00
2 Bata berongga bh 2,400.00
3 Batako bh 3,200.00
4 Genteng glazuur turbo ex Jatiwangi bh 2,500.00
5 Genteng nok/bubung diglazuur ex Jatiwangi bh 3,500.00
6 Genteng nok/bubung press mesin ex Jatiwangi bh 2,200.00
7 Genteng nok/bubung press tangan ex Jatiwangi bh 2,000.00
8 Genteng nok/bubung morando diglazuur bh 4,500.00
9 Genteng morando bh 3,500.00
10 Genteng nok/bubung morando bh 4,000.00
11 Genteng press diglazuur ex Jatiwangi bh 2,500.00
12 Genteng press mesin ex Jatiwangi bh 1,900.00
13 Genteng press tangan ex Jatiwangi bh 1,400.00
14 Genteng Type Viktoria bh 9,000.00
15 Genteng nok/bubung Type Viktoria bh 12,500.00
16 Genteng nok/bubung ujung Type Viktoria bh 20,000.00
17 Genteng nok/bubung ujung pertigaan Type Viktoria bh 25,000.00
18 Genteng beton bh 5,000.00
19 Genteng metal 70 x 80 cm lbr 48,000.00
20 Gorong-gorong buis beton dia. 100 cm bh/0,5 m' 120,000.00
21 Gorong-gorong buis beton dia. 80 cm bh/0,5 m' 100,000.00
22 Gorong-gorong buis beton dia. 60 cm bh/m' 80,000.00
23 Gorong-gorong buis beton dia. 40 cm bh/m' 60,000.00
24 Gorong-gorong buis beton dia. 30 cm bh/m' 50,000.00
25 Gorong-gorong buis beton dia. 20 cm bh/m' 40,000.00
26 Gravel dia. 60 cm bh 40,000.00
27 Gravel dia. 40 cm bh 35,000.00
28 Gravel dia. 20 cm bh 25,000.00
29 Nok steel gelombang 1050 x 5 mm m' 29,000.00
30 Nok steel gelombang 920 x 5 mm m' 22,500.00
31 Nok / bubung genteng beton bh 6,000.00
32 Paving Block K.175 Segi Enam Netural tebal 8 cm m2 62,000.00
33 Paving Block K.175 Segi Enam motif tebal 8 cm m2 64,000.00
34 Paving Block K.175 Segi Enam warna tebal 8 cm m2 69,000.00
35 Paving Block K.175 Segi Enam Netural tebal 7 cm m2 55,000.00
36 Paving Block K.175 Segi Enam motif tebal 7 cm m2 58,000.00
37 Paving Block K.175 Segi Enam warna tebal 7 cm m2 64,000.00
38 Paving Block K.175 Segi Enam Netural tebal 6 cm m2 50,000.00
39 Paving Block K.175 Segi Enam motif tebal 6 cm m2 53,000.00
40 Paving Block K.175 Segi Enam warna tebal 6 cm m2 57,000.00
41 Paving Block K.125 Segi Enam Netural tebal 6 cm bh 43,000.00
42 Paving Block K.125 Segi Enam warna tebal 6 cm bh 47,000.00
43 Digital printing m2 25,000.00
VIII. KAYU
1 Bambu Ø6 - Ø8 / 6 m btg 17,000.00
2 Kayu deplank 8/20 - 4 m (Jati Jateng) m3 8,000,000.00
3 Kayu deplank 8/20 - 4 m (Balau) m3 9,500,000.00
4 Kayu deplank 8/20 - 4 m (Borneo) m3 5,000,000.00
5 Kayu dolken O 8 - 10 /4 m btg 60,000.00
6 Kayu dolken O 12 - 15 /4 m btg 68,000.00
7 Kayu dolken O 5 /3 m btg 12,500.00
8 Kayu hutan/kayu perancah acuan m3 4,255,000.00
9 Kayu kamper m3 8,200,000.00
10 Kayu kaso 5/7 meranti m3 6,000,000.00
11 Kayu kaso 5/7 meranti btg 79,000.00
12 Kayu kruing m3 7,274,000.00
13 Kayu lanan m3 6,546,000.00
14 Kayu meranti m3 6,000,000.00
15 Kayu jati Jabar m3 8,200,000.00
16 Kayu Balau m3 9,500,000.00
17 Kayu Borneo m3 5,000,000.00
18 Kayu bakar m3 90,000.00
19 Reng kayu borneo ukuran 2/3 cm btg 54,000.00
20 Tali Ijuk kg 9,000.00
NO URAIAN BAHAN/MATERIAL SAT. HARGA KET
KESEPAKATAN
B. UPAH
1 Mandor /hari 85,000.00
2 Kepala tukang /hari 75,000.00
3 Tukang kayu / besi /hari 70,000.00
4 Tukang batu /hari 70,000.00
5 Pembantu tukang /hari 55,000.00
6 Operator terlatih /hari 100,000.00
7 Operator kurang terlatih /hari 55,000.00
8 Pembantu operator /hari 50,000.00
9 Supir truk /hari 55,000.00
10 Pembantu supir /hari 50,000.00
11 Mekanik /hari 55,000.00
12 Pembantu mekanik /hari 50,000.00
13 Buruh lapangan terlatih /hari 55,000.00
14 Buruh lapangan kurang terlatih /hari 50,000.00
15 Buruh lapangan tak terlatih / pekerja /hari 55,000.00

DINAS BINA MARGA DINAS CIPTA KARYA DAN TATA RUANG DINAS PENGELOLAAN SUMBER DAYA AIR
KABUPATEN CIREBON KABUPATEN CIREBON DAN PERTAMBANGAN KAB.CIREBON
Kepala Seksi Perencanaan Teknik
Kepala Seksi Desain Teknik Kepala Seksi Bangunan Gedung
Jalan dan Jembatan

SUPARMAN,S.Sos, ST YEDI ADHI PRIATNA, BAE, S.Sos Ir. DAWUD


NIP. 19721230 199901 1 001 NIP. 19660815 199803 1 004 NIP. 19640525 199303 1 007

Kepala Bidang Bina Teknik Kepala Bidang Bangunan Gedung, Perumahan dan Kepala Bidang Bina Teknik
Permukiman

RACHMAT S, BE Ir. FELLYANTO TAMZIL, MM AGUNG GUMILANG, SS., M.si


NIP. 19571008 198709 1 001 NIP. 19620428 199003 1 006 NIP. 19711224 199803 1 004

Kepala Dinas Bina Marga Kepala Dinas Cipta Karya dan Tata Ruang Kepala Dinas Pengelolaan Sumber Daya Air
Kabupaten Cirebon Kabupaten Cirebon dan Pertambangan Kabupaten Cirebon

Ir. AVIP SUHERDIAN, MT Ir. H. ARIEF BUDI PRAYITNO DEDI NURUL SUDJUDI A
NIP. 19640827 199303 1 006 NIP. 19620428 199003 1 006 NIP. 19590721 198303 1 009
DAFTAR KESEPAKATAN HARGA SATUAN BAHAN / MATERIAL DAN UPAH
DINAS BINA MARGA, DINAS PENGELOLAAN SUMBER DAYA AIR & PERTAMBANGAN
DAN DINAS CIPTA KARYA & TATA RUANG
KABUPATEN CIREBON
HARGA TERTINGGI TAHUN ANGGARAN 2015

kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
A. BAHAN :
I. BATU
1 Abu Batu m3 185,850.00 204,400.00
2 Atras ( tanah urug ) m3 125,000.00 137,500.00
3 Base course A m3
4 Base course B m3
5 Batu apung kg 4,300.00 4,700.00
6 Batu belah 10/15 cm m3 175,000.00 192,500.00
7 Batu belah 15/20 cm (Krakal) m3 175,000.00 192,500.00
8 Batu pecah mesin 0.5-1 cm m3 200,000.00 220,000.00
9 Batu pecah mesin 1-2 cm m3 200,000.00 220,000.00
10 Batu pecah mesin 2-3 cm m3 200,000.00 220,000.00
11 Batu pecah mesin 3-5 cm 182,000.00 200,200.00
12 Batu tempel Palimanan 10 X 20 bh 1,500.00 1,650.00
13 Batu tempel kapur tekstur tidak rata bh 2,000.00 2,200.00
14 Chipping m3 245,300.00 269,800.00
15 Filler kg 100.00 100.00
16 Kapur bakar m3 70,000.00 77,000.00
17 Kapur Sirih kg 2,000.00 2,200.00
18 Kerikil m3 65,000.00 71,500.00

II. PASIR
1 Pasir beton m3 179,000.00 196,900.00
2 Pasir aspal m3 175,000.00 192,500.00
3 Pasir pasang m3 162,000.00 178,200.00
4 Pasir urug m3 150,000.00 165,000.00
5 Sirtu m3 145,000.00 159,500.00
6 Sirtu tersaring m3 147,000.00 161,700.00
7 Tanah urug pilhan m3 125,000.00 137,500.00
8 Tanah urug biasa m3 100,000.00 110,000.00
Tanah merah m3 112,500.00 123,750.00
III. BESI / PIPA / KAWAT
1 Besi WF/Besi Profil kg 13,750.00 15,125.00
2 Besi strip kg 13,750.00 15,125.00
3 Besi beton kg 13,000.00 14,300.00
4 Besi stainless dia. 0,5" m' 38,000.00 41,800.00
5 Besi stainless dia. 1" m' 60,000.00 66,000.00
6 Besi stainless dia. 1,5" m' 75,000.00 82,500.00
7 Besi stainless dia. 2" m' 80,000.00 88,000.00
8 Besi stainless dia. 2,5" m' 125,000.00 137,500.00
9 Besi stainless dia. 3" m' 152,000.00 167,200.00
10 Besi galvanis dia. 0.5" m' 25,000.00 27,500.00
11 Besi galvanis dia. 1" m' 27,000.00 29,700.00
12 Besi galvanis dia. 1.5" m' 45,000.00 49,500.00
13 Besi galvanis dia. 2" m' 57,000.00 62,700.00
14 Besi galvanis dia. 2.5" m' 80,500.00 88,550.00
15 Besi galvanis dia. 3" m' 84,000.00 92,400.00
16 Besi biasa dia. 2" btg 250,000.00 275,000.00
17 Besi biasa dia. 3" btg 310,000.00 341,000.00
18 Dop besi Ø 3 " bh 60,000.00 66,000.00
19 Kawat beton / Kawat tali kg 18,000.00 19,800.00
20 Kawat bronjong pabrikan dia. 3 mm (uk 2x1x0.5) unit 388,080.00 426,888.00
21 Kawat bronjong dia. 4 mm kg 20,000.00 22,000.00
22 Kawat galvanis dia. 4 mm kg 20,000.00 22,000.00
23 Kawat galvanis dia. 6 mm kg 24,000.00 26,400.00
24 Kawat duri m' 14,000.00 15,400.00
25 Pipa besi galvanis 2" btg/6m' 324,000.00 356,400.00
26 Pipa besi galvanis 3" btg/6m' 500,000.00 550,000.00
27 Pipa PVC Ø 2" S-12,5 ( 8 - 10 bar ) m' 26,300.00 28,900.00
28 Pipa PVC Ø 3" S-12,5 ( 8 - 10 bar ) m' 53,600.00 58,900.00
29 Pipa PVC / paralon 2 inch btg 69,000.00 75,900.00
30 Pipa PVC / paralon 3 inch btg 90,000.00 99,000.00
31 Pipa Reducer PVC Ø 3"-4" bh 6,000.00 6,600.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
32 Pipa Knee/bend PVC Ø 3" bh 6,000.00 6,600.00
33 Plat baja tebal 5 mm - 20 mm kg 13,000.00 14,300.00
34 Ram kawat harmonika m2 25,000.00 27,500.00
35 Socket besi O 3 " bh 45,000.00 49,500.00
36 Toren Penguin 250 lt bh 525,000.00 577,500.00
37 Toren 500 lt bh 860,000.00 946,000.00
38 Toren 1000 lt bh 1,450,000.00 1,595,000.00
39 Sling Ø 32 mm m 300,000.00 330,000.00
40 Sling Ø 16 mm m 175,000.00 192,500.00
41 Klem sling Ø 32 mm set 250,000.00 275,000.00
42 Warfel / jarum keras Ø 32 mm bh 200,000.00 220,000.00
43 Causen sling Ø 32 mm bh 85,000.00 93,500.00
44 Klem kokat sling Ø 32 mm bh 210,000.00 231,000.00
45 Segel sling Ø 32 mm bh 250,000.00 275,000.00
46 Warfel sling Ø 16 mm bh 135,000.00 148,500.00
47 Segel sling Ø 16 mm bh 140,000.00 154,000.00
48 Klem kokat sling Ø 16 mm bh 35,000.00 38,500.00
49 Causen sling Ø 16 mm bh 50,000.00 55,000.00
50 Jarum keras Ø 16 mm bh 75,000.00 82,500.00

IV. PABRIKAN / TOKO


1 Alumunium foil m2 9,000.00 9,900.00
2 Alumunium pelapis pintu KM Tebal 0.2 lbr 35,000.00 38,500.00
3 Alumunium pelapis pintu KM Tebal 0.3 lbr 50,000.00 55,000.00
4 Alumunium pelapis pintu KM Tebal 0.4 lbr 70,000.00 77,000.00
5 Asbes gelombang 1500 x 1050 x 4 mm lbr 42,500.00 46,750.00
6 Asbes gelombang 1800 x 920 x 4 mm lbr 32,000.00 35,200.00
7 Asbes gelombang 2100 x 1050 x 4 mm lbr 57,000.00 62,700.00
8 Asbes gelombang 2400 x 1050 x 4 mm lbr 65,000.00 71,500.00
9 Asbes gelombang 2700 x 1050 x 4 mm lbr 75,000.00 82,500.00
10 Asbes gelombang 3000 x 1050 x 4 mm lbr 85,000.00 93,500.00
11 Ampelas lbr 3,000.00 3,300.00
12 Bak mandi keramik volume 0,3 m3 bh 185,000.00 203,500.00
13 Bak mandi fiber 120 L bh 220,000.00 242,000.00
14 Batu apung kg 4,300.00 4,700.00
15 Baut 3/4 " bh 6,700.00 7,300.00
16 Baut 5/8 " bh 6,700.00 7,300.00
17 Baut 1/2 " bh 6,000.00 6,600.00
18 Baut 1/2 " panjang 30 cm bh 8,550.00 9,400.00
19 Baut lawa-lawa 12 cm 13,000.00 14,300.00
20 Beading penurunan ( PC ) gypsum m' 10,000.00 11,000.00
21 Beading horison gypsum m' 10,000.00 11,000.00
22 Cat Menie kg 25,000.00 27,500.00
23 Cat genteng Matex kg 48,000.00 52,800.00
24 Cat genteng maxilite kg 50,000.00 55,000.00
25 Cat penutup kayu Bee brand kg 49,000.00 53,900.00
26 Cat penutup kayu Vim kg 25,000.00 27,500.00
27 Cat penutup kayu Ftalit kg 46,000.00 50,600.00
28 Cat penutup kayu Avian kg 48,000.00 52,800.00
29 Cat penutup tembok Vinilex kg 25,000.00 27,500.00
30 Cat penutup tembok Metrolit kg 23,000.00 25,300.00
31 Cat penutup tembok catylac kg 18,600.00 20,400.00
32 Cat penutup tembok Q Luc kg 10,000.00 11,000.00
33 Cat penutup tembok Property kg 9,500.00 10,450.00
34 Cat penutup besi kg 52,000.00 57,200.00
35 Cat Sinkromat kg 90,000.00 99,000.00
36 Closet duduk ( mono block ) porselen merk INA bh 1,237,000.00 1,360,700.00
37 Closet duduk ( siram ) porselen merk INA bh 545,000.00 599,500.00
38 Closet jongkok porselen merk INA/KIA bh 140,000.00 154,000.00
39 Closet jongkok porselen merk Avena bh 100,000.00 110,000.00
40 Dempul kayu kg 18,500.00 20,350.00
41 Dinding keramik uk. 10 x 20 cm bh 1,000.00 1,100.00
42 Dinding keramik uk. 20 x 20 cm bh 2,000.00 2,200.00
43 Dinding keramik uk. 20 x 25 cm bh 2,200.00 2,400.00
44 Dinding keramik uk. 30 x 30 cm bh 4,500.00 4,950.00
45 Door closer bh 160,000.00 176,000.00
46 Daun pintu alumunium lengkap warna natural/coklat dop bh 900,000.00 990,000.00
47 Daun pintu alumunium lengkap warna coklat kilap bh 1,300,000.00 1,430,000.00
48 Daun jendela alumunium lengkap warna natural/coklat do bh 350,000.00 385,000.00
49 Daun jendela alumunium lengkap warna coklat kilap bh 400,000.00 440,000.00
50 Elastomer 30x30x5 bh 632,500.00 695,750.00
51 Engsel jendela set 12,000.00 13,200.00
52 Engsel pintu set 19,000.00 20,900.00
53 Engsel meubeler bh 3,800.00 4,200.00
54 Eternit tebal 4 mm uk. 1 m x 1 m lbr 6,900.00 7,600.00
55 Eternit tebal 4 mm uk. 1 m x 0,5 m lbr 3,450.00 3,800.00
56 Flincote ltr 22,000.00 24,200.00
57 Loster Jati bh 25,000.00 27,500.00
58 Glass beat kg 25,000.00 27,500.00
59 Glass Block bh 17,500.00 19,250.00
60 Gas elpiji kg 8,800.00 9,700.00
61 Grendel pintu / jendela bh 5,500.00 6,000.00
62 Gypsum board lbr 52,500.00 57,750.00
63 GRC tebal 4 mm lbr 52,500.00 57,750.00
64 Fiber Gelombang 180 x80 lbr 40,000.00 44,000.00
65 Kaca nako tebal 5 mm berikut teralis bh 11,400.00 12,500.00
66 Kaca polos tebal 3 mm m2 63,250.00 69,575.00
67 Kaca polos tebal 5 mm m2 75,000.00 82,500.00
68 Kaca polos tebal 5 mm ryben m2 80,000.00 88,000.00
69 Kait angin bh 7,500.00 8,250.00
70 Kran air Onda bh 12,000.00 13,200.00
71 Kunci gembok bh 20,000.00 22,000.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
72 Kunci pintu ukuran besar bh 125,000.00 137,500.00
73 Kunci pintu ukuran sedang bh 85,000.00 93,500.00
74 Kunci dan daun pintu dari fiber bh 350,000.00 385,000.00
75 Kusen Alumunium 3" warna natural m' 60,000.00 66,000.00
76 Kusen Alumunium 3" warna coklat dop m' 65,000.00 71,500.00
77 Kusen Alumunium 3" warna coklat kilap m' 70,000.00 77,000.00
78 Kusen Alumunium 4" warna natural m' 65,000.00 71,500.00
79 Kusen Alumunium 4" warna coklat dop m' 70,000.00 77,000.00
80 Kusen Alumunium 4" warna coklat kilap m' 75,000.00 82,500.00
81 Kusen Alumunium 3" YKK m' 100,000.00 110,000.00
82 Kusen Alumunium 4" YKK m' 1,300,000.00 1,430,000.00
83 Langko - langko kuda - kuda bh 18,000.00 19,800.00
84 Lantai granit 60 x 60 cm ex. Granito corak bh 57,600.00 63,400.00
85 Lantai granit 60 x 60 cm ex. Granito polos bh 84,600.00 93,000.00
86 Lantai granit 40 x 40 cm ex. Essenza bh 43,500.00 47,850.00
87 Lantai granit 40 x 40 cm ex. Granito bh 42,000.00 46,200.00
88 Lantai granit 60 x 60 cm ex. Granito bh 46,800.00 51,500.00
89 Lantai keramik uk. 10 x 20 cm bh 1,000.00 1,100.00
90 Lantai keramik uk. 20 x 20 cm bh 2,000.00 2,200.00
91 Lantai keramik uk. 30 x 30 cm bh 2,200.00 2,400.00
92 Lantai keramik uk. 40 x 40 cm ( putih polos ) bh 4,500.00 4,950.00
93 Lantai terakota 20 x 5 cm bh 4,400.00 4,800.00
94 Lem kayu ltr 30,000.00 33,000.00
95 Lemkra/zat addictive kg 15,000.00 16,500.00
96 Lemkra Just Do It kg 4,500.00 4,950.00
97 Lemkra FS Nat kg 15,850.00 17,400.00
98 List kayu B.3 ( lebar sisi 3 cm ) m' 4,400.00 4,800.00
99 List kayu B.4 ( lebar sisi 4 cm ) m' 4,800.00 5,300.00
100 List keliling gypsum lebar 7 cm m' 14,000.00 15,400.00
101 List keliling gypsum lebar 10 cm m' 16,000.00 17,600.00
102 List keliling gypsum lebar 12 cm m' 18,000.00 19,800.00
103 List drop m' 8,900.00 9,800.00
104 Melamin / folywood lbr 88,500.00 97,350.00
105 Mozaik uk. 20 x 20 cm bh 1,900.00 2,100.00
106 Multiplex tebal 12 mm lbr 175,000.00 192,500.00
107 Multiplex tebal 15 mm lbr 275,000.00 302,500.00
108 Paku biasa 1/2" - 1" kg 18,500.00 20,350.00
109 Paku biasa 2" - 5" kg 20,000.00 22,000.00
110 Paku pancing 60 x 230 bh 825.00 900.00
111 Paku sekrup 3" - 5 " bh 400.00 450.00
112 Paku ulir bh 150.00 200.00
113 Plamir kayu / kualitas 1 kg 20,000.00 22,000.00
114 Plamir tembok kg 23,000.00 25,300.00
115 Plester Mutiara kg 8,000.00 8,800.00
116 Pintu kamer mandi fiber polos Daimaru bh 175,000.00 192,500.00
117 Pintu kamer mandi fiber Kaca Daimaru bh 245,000.00 269,500.00
118 Pintu kamer mandi Almunium Kettler bh 700,000.00 770,000.00
119 Polycarbonate m2 115,000.00 126,500.00
120 Plywood lbr 92,250.00 101,475.00
121 Portland Cement ( PC ) tiga roda zak 68,000.00 68,000.00
122 Portland Cement ( PC ) holcim zak 67,000.00 67,000.00
123 Portland Cement ( PC ) gresik zak 66,000.00 66,000.00
124 Rubber joint 25x10x5 bh 192,500.00 211,750.00
125 Joint Sealent kg 42,900.00 47,200.00
126 Expansion Cap m2 7,600.00 8,400.00
127 Polytene 125 mikron kg 27,500.00 30,250.00
128 Curing Compound Ltr 4,400.00 4,850.00
129 Roster / batu kerawang bh 4,000.00 4,400.00
130 Semen portland kg 1,360.00 1,360.00
131 Semen warna kg 6,000.00 6,000.00
132 Seng BJLS 30 L. 90 cm m2 38,000.00 41,800.00
133 Seng gelombang 3' - 6 " BJLS 30 lbr 51,000.00 56,100.00
134 Sirlak kg 19,500.00 21,450.00
135 Spirtus ltr 9,000.00 9,900.00
136 Skim Coat kg 4,400.00 4,850.00
137 Taekwood 4 mm 1200 x 2400 mm lbr 80,000.00 88,000.00
138 Taekwood 4 mm 900 x 2400 mm lbr 65,000.00 71,500.00
139 Ter kayu kg 14,500.00 15,950.00
140 Thermoplastic Glass beat kg 25,000.00 27,500.00
141 Tiner / minyak cat ltr 11,500.00 12,650.00
142 Triplek 3 mm lbr 52,000.00 57,200.00
143 Triplek 4 mm lbr 55,000.00 60,500.00
144 Triplek 6 mm lbr 83,000.00 91,300.00
145 Triplek 9 mm lbr 102,500.00 112,750.00
146 Triplek 12 mm lbr 200,000.00 220,000.00
147 Tempat cuci piring Beleza bh 400,000.00 440,000.00
148 Tempat cuci piring Benoti bh 175,000.00 192,500.00
149 Tempat cuci piring Royal bh 160,000.00 176,000.00
150 TG 302 kg 43,600.00 47,950.00
151 Washtafel bh 686,000.00 754,600.00
152 Woodplank corak 4 m lbr 60,000.00 66,000.00
153 Woodplank polos 2 m lbr 32,500.00 35,750.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
154 Ubin abu2 kepala basah 20 x 20 cm bh 2,000.00 2,200.00
155 Ubin abu2 kepala basah 30 x 30 cm bh 2,500.00 2,750.00
156 Ubin wafel ukuran 20 x 20 cm bh 2,000.00 2,200.00
157 Ubin warna 20 x 20 cm bh 2,300.00 2,550.00
158 Ubin warna 30 x 30 cm bh 2,900.00 3,200.00
159 Washtafel bh 686,000.00 754,600.00
160 Woodplank corak 4 m lbr 60,000.00 66,000.00
161 Woodplank polos 2 m lbr 32,500.00 35,750.00
162 Zincalume m2 75,000.00 82,500.00
163 Rangka plafon memakai Hollow dengan penutup GRC teb m2 88,200.00 97,000.00
164 Rangka atap baja ringan
a. Atap Baja Ringan memakai Genteng Keramik/Plentong ( jarak reng 22-28 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumuni m2 165,000.00 181,500.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumuni m2 175,000.00 192,500.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumuniu m2 185,000.00 203,500.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alum m2 175,000.00 192,500.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alum m2 190,000.00 209,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumun m2 200,000.00 220,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumun m2 190,000.00 209,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumu m2 200,000.00 220,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumuni m2 210,000.00 231,000.00
b. Atap Baja Ringan Genteng Metal/Spandek ( jarak reng 37,5-90 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumuni m2 155,000.00 170,500.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumuni m2 162,500.00 178,750.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumuniu m2 170,000.00 187,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alum m2 160,000.00 176,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alum m2 175,000.00 192,500.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumun m2 185,000.00 203,500.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumun m2 170,000.00 187,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumu m2 180,000.00 198,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumuni m2 190,000.00 209,000.00

165 Pintu Air Sorong


- Pintu Air Sorong Baja B = 0.40-0.60 ( 1 drat stang tanpa Unit 8,497,000.00 9,346,700.00
- Pintu Air Sorong Baja B = 0.70-0.80 ( 1 drat stang tanpa Unit 9,639,000.00 10,602,900.00
- Pintu Air Sorong Baja B = 0.90-1.00 ( 1 drat stang tanpa Unit 13,500,000.00 14,850,000.00
- Pintu Air Sorong Baja B = 0.70-1.00 ( 1 drat stang + rod Unit 11,414,000.00 12,555,400.00
- Pintu Air Sorong Baja B = 1.00-1.10 ( 2 drat stang + rod Unit 25,366,000.00 27,902,600.00
- Pintu Air Sorong Baja B = 1.50-1.80 ( 2 drat stang + rod Unit 38,049,000.00 41,853,900.00
- Pintu Air Sorong Baja B = 2.00-2.50 ( 2 drat stang + rod Unit 50,732,000.00 55,805,200.00
166 Gigi Payung / Jantung Besar bh 1,250,000.00 1,375,000.00
167 Gigi Payung / Jantung Sedang bh 1,100,000.00 1,210,000.00
168 Gigi Piring Besar bh 2,930,000.00 3,223,000.00
169 Gigi Piring Sedang bh 1,903,000.00 2,093,300.00
170 Blok Laher bh 1,750,000.00 1,925,000.00
171 Bron mur drat 5 " bh 3,250,000.00 3,575,000.00
172 Bron mur drat 3 " bh 2,150,000.00 2,365,000.00
173 Drat stang 2" x 100 bh 2,500,000.00 2,750,000.00
174 Drat stang 3/4" x 100 bh 1,750,000.00 1,925,000.00
175 Drat stang 1,5" x 100 bh 1,550,000.00 1,705,000.00
176 Dudukan as horisontal bh 1,850,000.00 2,035,000.00
177 As Horisontal bh 1,850,000.00 2,035,000.00
178 Karet sel 8 x 3 cm bh 1,500,000.00 1,650,000.00
179 As Pemutar bh 750,000.00 825,000.00
180 Laher/Bearing bh 350,000.00 385,000.00
181 Engkel Kemudi Sedang bh 450,000.00 495,000.00
182 Daun Pintu B.50, H.50 bh 1,000,000.00 1,100,000.00
183 Pintu Klep B=0,5 m unit 1,750,000.00 1,925,000.00
184 Pintu Klep B=1,0 m unit 3,000,000.00 3,300,000.00
185 Pintu Klep B=1,5 m unit 4,500,000.00 4,950,000.00

V. ASPAL
1 Aspal kemasan kg 12,100.00 12,100.00
2 Aspal curah kg 11,600.00 11,600.00
3 Aspal Emulsi ltr 10,500.00 10,500.00

VI. MINYAK
1 Premium liter 6,500.00 6,500.00
2 Premium (non subsidi) liter 11,400.00 11,400.00
3 Solar liter 5,500.00 5,500.00
4 Solar (non subsidi) liter 11,900.00 11,900.00
5 Minyak tanah liter 12,500.00 12,500.00
6 Olie SAE 20, 40, 60, 80 dan 120 liter 42,000.00 42,000.00
7 Pelumas bekisting liter 10,000.00 10,000.00
8 Stempet kg 25,000.00 25,000.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
VII.CETAKAN
1 Bata merah bh 800.00 900.00
2 Bata berongga bh 2,400.00 2,650.00
3 Batako bh 3,200.00 3,500.00
4 Genteng glazuur turbo ex Jatiwangi bh 3,500.00 3,850.00
5 Genteng nok/bubung diglazuur ex Jatiwangi bh 4,000.00 4,400.00
6 Genteng nok/bubung press mesin ex Jatiwangi bh 2,500.00 2,750.00
7 Genteng nok/bubung press tangan ex Jatiwangi bh 2,000.00 2,200.00
8 Genteng nok/bubung morando diglazuur bh 4,500.00 4,950.00
9 Genteng morando bh 3,500.00 3,850.00
10 Genteng nok/bubung morando bh 4,000.00 4,400.00
11 Genteng press diglazuur ex Jatiwangi bh 2,500.00 2,750.00
12 Genteng press mesin ex Jatiwangi bh 1,900.00 2,100.00
13 Genteng press tangan ex Jatiwangi bh 1,400.00 1,550.00
14 Genteng Type Viktoria bh 9,000.00 9,900.00
15 Genteng nok/bubung Type Viktoria bh 12,500.00 13,750.00
16 Genteng nok/bubung ujung Type Viktoria bh 20,000.00 22,000.00
17 Genteng nok/bubung ujung pertigaan Type Viktoria bh 25,000.00 27,500.00
18 Genteng beton bh 5,000.00 5,500.00
19 Genteng metal 70 x 80 cm lbr 48,000.00 52,800.00
20 Gorong-gorong buis beton dia. 100 cm bh/0,5 m' 150,000.00 165,000.00
21 Gorong-gorong buis beton dia. 80 cm bh/0,5 m' 130,000.00 143,000.00
22 Gorong-gorong buis beton dia. 60 cm bh/m' 140,000.00 154,000.00
23 Gorong-gorong buis beton dia. 40 cm bh/m' 100,000.00 110,000.00
24 Gorong-gorong buis beton dia. 30 cm bh/m' 80,000.00 88,000.00
25 Gorong-gorong buis beton dia. 20 cm bh/m' 60,000.00 66,000.00
26 Kansten Cetak 82,500.00 90,750.00
27 Gravel dia. 60 cm bh 75,000.00 82,500.00
28 Gravel dia. 40 cm bh 45,000.00 49,500.00
29 Gravel dia. 20 cm bh 35,000.00 38,500.00
30 Nok steel gelombang 1050 x 5 mm m' 29,000.00 31,900.00
31 Nok steel gelombang 920 x 5 mm m' 22,500.00 24,750.00
32 Nok / bubung genteng beton bh 6,000.00 6,600.00
33 Paving Block K.175 Segi Enam Netural tebal 8 cm m2 62,000.00 68,200.00
34 Paving Block K.175 Segi Enam motif tebal 8 cm m2 64,000.00 70,400.00
35 Paving Block K.175 Segi Enam warna tebal 8 cm m2 69,000.00 75,900.00
36 Paving Block K.175 Segi Enam Netural tebal 7 cm m2 55,000.00 60,500.00
37 Paving Block K.175 Segi Enam motif tebal 7 cm m2 58,000.00 63,800.00
38 Paving Block K.175 Segi Enam warna tebal 7 cm m2 64,000.00 70,400.00
39 Paving Block K.175 Segi Enam Netural tebal 6 cm m2 50,000.00 55,000.00
40 Paving Block K.175 Segi Enam motif tebal 6 cm m2 53,000.00 58,300.00
41 Paving Block K.175 Segi Enam warna tebal 6 cm m2 57,000.00 62,700.00
42 Paving Block K.125 Segi Enam Netural tebal 6 cm bh 43,000.00 47,300.00
43 Paving Block K.125 Segi Enam warna tebal 6 cm bh 47,000.00 51,700.00
44 Tiang pancang beton Pratekan m3 4,600,000.00 5,060,000.00
45 Digital printing m2 25,000.00 27,500.00
VIII. KAYU
1 Bambu Ø6 - Ø8 / 6 m btg 17,000.00 18,700.00
2 Kayu deplank 8/20 - 4 m (Jati Jateng) m3 9,800,000.00 10,780,000.00
3 Kayu deplank 8/20 - 4 m (Balau) m3 9,500,000.00 10,450,000.00
4 Kayu deplank 8/20 - 4 m (Borneo) m3 5,000,000.00 5,500,000.00
5 Kayu dolken O 8 - 10 /4 m btg 60,000.00 66,000.00
6 Kayu dolken O 12 - 15 /4 m btg 68,000.00 74,800.00
7 Kayu dolken O 5 /3 m btg 12,500.00 13,750.00
8 Kayu hutan/kayu perancah acuan m3 4,700,000.00 5,170,000.00
9 Kayu kamper m3 8,200,000.00 9,020,000.00
10 Kayu kaso 5/7 meranti m3 6,000,000.00 6,600,000.00
11 Kayu kaso 5/7 meranti btg 79,000.00 86,900.00
12 Kayu kruing m3 7,274,000.00 8,001,400.00
13 Kayu lanan m3 6,546,000.00 7,200,600.00
14 Kayu meranti m3 6,000,000.00 6,600,000.00
15 Kayu jati Jabar m3 8,200,000.00 9,020,000.00
16 Kayu Balau m3 9,500,000.00 10,450,000.00
17 Kayu Borneo m3 5,000,000.00 5,500,000.00
18 Kayu bakar m3 90,000.00 99,000.00
19 Reng kayu borneo ukuran 2/3 cm btg 54,000.00 59,400.00
20 Tali Ijuk kg 9,000.00 9,900.00
kesimpulan
NO URAIAN BAHAN/MATERIAL SAT. HARGA TERTINGGI 2015 HARGA TERTINGGI 2015 harga survay
HARGA DASAR + 10 % tertinggi
B. UPAH
1 Mandor /hari 85,000.00 85,000.00
2 Kepala tukang /hari 75,000.00 75,000.00
3 Tukang kayu / besi /hari 70,000.00 70,000.00
4 Tukang batu /hari 70,000.00 70,000.00
5 Pembantu tukang /hari 55,000.00 55,000.00
6 Operator terlatih /hari 100,000.00 100,000.00
7 Operator kurang terlatih /hari 55,000.00 55,000.00
8 Pembantu operator /hari 50,000.00 50,000.00
9 Supir truk /hari 55,000.00 55,000.00
10 Pembantu supir /hari 50,000.00 50,000.00
11 Mekanik /hari 55,000.00 55,000.00
12 Pembantu mekanik /hari 50,000.00 50,000.00
13 Buruh lapangan terlatih /hari 55,000.00 55,000.00
14 Buruh lapangan kurang terlatih /hari 50,000.00 50,000.00
15 Buruh lapangan tak terlatih / pekerja /hari 55,000.00 55,000.00

DINAS CIPTA KARYA DAN TATA


DINAS BINA MARGA RUANG DINAS PENGELOLAAN SUMBER DAYA AIR
KABUPATEN CIREBON KABUPATEN CIREBON DAN PERTAMBANGAN KAB.CIREBON
Kepala Seksi Perencanaan Teknik
Kepala Seksi Desain Teknik Kepala Seksi Bangunan Gedung
Jalan dan Jembatan

SUPARMAN,S.Sos, ST YEDI ADHI PRIATNA, BAE, S.Sos Ir. DAWUD


NIP. 19721230 199901 1 001 NIP. 19660815 199803 1 004 NIP. 19640525 199303 1 007

Kepala Bidang Bina Teknik Kepala Bidang Bangunan Gedung, Kepala Bidang Bina Teknik
Perumahan dan Permukiman

Ir. TETI MEIRAWATI Ir. FELLYANTO TAMZIL, MM AGUNG GUMILANG, SS., M.si
NIP. 19670502 199703 2 004 NIP. 19620428 199003 1 006 NIP. 19711224 199803 1 004

Kepala Dinas Bina Marga Kepala Dinas Cipta Karya dan Tata Kepala Dinas Pengelolaan Sumber Daya Air
Kabupaten Cirebon Ruang dan Pertambangan Kabupaten Cirebon
Kabupaten Cirebon

Ir. AVIP SUHERDIAN, MT DEDI NURUL SUDJUDI A


NIP. 19640827 199303 1 006 Ir. H. ARIEF BUDI PRAYITNO NIP. 19590721 198303 1 009
NIP. 19620428 199003 1 006
DAFTAR SATUAN ANALISA
DINAS PERUMAHAN KAWASAN PERMUKIMAN DAN PERTANAHAN
KABUPATEN CIREBON
TAHUN ANGGARAN 2018

HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


1 A. 2.2.1.1 (K3) Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter 463,749.00
2 A. 2.2.1.2 (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter 551,873.50
3 A. 2.2.1.3. (K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter 488,330.25
4 A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank 71,524.48
5 A. 2.2.1.5. (K3) Pembuatan 1 m2 kantor sementara lantai plesteran (direksikeet) 1,564,120.75
6 A. 2.2.1.6. (K3) Pembuatan 1 m2 rumah jaga (konstruksi kayu ) 1,731,555.00
7 A. 2.2.1.7. (K3) Pembuatan 1 m2 gudang semen dan peralatan 1,476,720.75
8 A. 2.2.1.8. (K3) Pembuatan 1 m2 bedeng pekerja 1,512,572.00
9 A. 2.2.1.9. (K3) Pembersihan 1 m2 lapangan dan perataan 15,525.00
10 A. 2.2.1.10. (K3) Pembuatan 1 m2 steger/perancah dari bambu 83,503.80
11 A. 2.2.1.11. Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm 241,028.50
12 A. 2.2.1.12. Pembuatan 1 m2 jalan sementara 159,710.85
13 A. 2.2.1.13. Pembongkaran 1 m3 beton bertulang 1,310,977.00
14 A. 2.2.1.14. Pembongkaran 1 m3 dinding tembok bata 655,488.50
15 A. 2.2.1.15. Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm 103,382.47
16 A.2.2.1.16. Pemasangan 1 m2 panel beton pracetak 5x50x240 cm untuk pagar 400,863.55
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
17 A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m 72,162.50
18 A.2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m 88,492.50
19 A.2.3.1.3. Menggali 1 m3 tanah biasa sedalam 3 m 105,075.50
20 A.2.3.1.4. Menggali 1 m3 tanah keras sedalam 1 m 96,048.00
21 A.2.3.1.5. Menggali 1 m3 tanah cadas sedalam 1 m 145,590.00
22 A.2.3.1.6. Menggali 1 m3 tanah lumpur sedalam 1 m 116,092.50
23 A.2.3.1.7. Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter 5,232.50
24 A.2.3.1.8. (K3) Pembuangan 1 m3 tanah sejauh 30 meter 31,625.00
25 A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah 52,325.00
26 A.2.3.1.10. (K3) Pemadatan tanah 1 m3 tanah ( per 20 cm) 52,325.00
27 A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug 268,019.00
28 A.2.3.1.12. Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7TL 350,071.50
29 A.2.3.1.13. Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan 98,497.50
30 A.2.3.1.14. Pengurugan 1 m3 sirtu padat 265,316.50
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
31 A.3.2.1.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP 994,469.98
32 A.3.2.1.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP 940,047.95
33 A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP 902,315.99
34 A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP 875,790.44
35 A.3.2.1.5. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 8PP 839,429.39
36 A.3.2.1.6. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 1KP : 2PP 648,541.35
37 A.3.2.1.7. Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3 KP : 10 PP 780,967.07
38 A.3.2.1.8. Pemasangan 1 m3 pondasi batu belah campuran ¼ SP : 1 KP : 4PP 754,890.71
39 A.3.2.1.9. (K3) Pemasangan 1 m3 batu kosong (anstamping) 522,848.19
40 A.3.2.1.10. Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah 2,994,481.55
41 A.3.2.1.11. Pemasangan 1 m3 pondasi sumuran, diameter 100 cm 956,813.80
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
42 A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 Mpa (sama dengan K 100), setara dengan beton rabat 984,980.75
43 A.4.1.1.2 Membuat 1 m3 beton mutu f’c = 9,8 Mpa (sama dengan K-125) 1,026,659.52
44 A.4.1.1.3 Membuat 1 m3 beton mutu f’c = 12,2 Mpa (sama denga K 150) 1,059,251.58
45 A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump (3-6) cm, w/c = 0,87 869,622.12
46 A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa, slump (120 ± 20) mm (sama dengan K 175) 1,097,876.89
47 A.4.1.1.6 Membuat 1 m3 beton mutu f’c = 16,9 Mpa (sama dengan K 220) 1,134,660.06
48 A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 19,3 Mpa (sama dengan K 225) 1,162,395.72
49 A.4.1.1.8. Membuat 1 m3 beton mutu f’c = 21,7 Mpa (sama dengan K 250) 1,180,483.52
50 A.4.1.1.9. Membuat 1 m3 beton mutu f’c = 24,0 Mpa (sama dengan K 325) 1,211,617.00
51 A.4.1.1.10. Membuat 1 m3 beton mutu f’c = 26,4 Mpa (sama dengan K 350) 1,221,252.94
52 A.4.1.1.11. Membuat 1 m3 beton mutu f’c = 28,8 Mpa (sama dengan K 375) 1,311,484.49
53 A.4.1.1.12. Membuat 1 m3 beton mutu f’c = 31,2 MPa, slump (120 ± 20) mm (sama dengan K 425) 1,324,127.46
Untuk pekerjaan beton pracetak yang bisa diangkat 24 jam diperlukan penambahan bahan
tambahan 2,021,889.96
54 A.4.1.1.13 Membuat 1 m3 beton kedap air dengan strorox – 100 1,312,040.75
55 A.4.1.1.14 Pemasangan 1 m’ PVC Waterstop lebar 150 mm 70,086.75

II - 19
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp
56 A.4.1.1.15 Pemasangan 1 m’ PVC Waterstop lebar 200 mm 162,771.00
57 A.4.1.1.16 Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm 151,811.50
58 A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir 176,266.25
59 A.4.1.1.18 Pemasangan 10 kg kabel prategang (prestressed) polos/strands 170,608.25
60 A.4.1.1.19 Pemasangan 10 kg jaring kawat baja (wiremesh) 117,107.57
61 A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting untuk pondasi 252,528.50
62 A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof 272,653.50
63 A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom 551,275.50
64 A.4.1.1.23 (K3) Pemasangan 1 m2 bekisting untuk balok 568,525.50
65 A.4.1.1.24 (K3) Pemasangan 1 m2 bekisting untuk lantai 838,775.50
66 A.4.1.1.25 (K3) Pemasangan 1 m2 bekisting untuk dinding 694,450.50
67 A.4.1.1.26 (K3) Pemasangan 1 m2 bekisting untuk tangga 510,450.50
68 A.4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton 175,783.25
69 A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 98,883.90
70 A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 123,968.85
A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
71 A.4.1.2.1. (K3) Pembuatan 1 m2 lahan produksi tebal 8 cm beton f’c 14,5 MPa, slump (120 ± 20) mm 87,846.71
72 A.4.1.2.2. (K3) Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c 14,5 MPa, slump (120 ± 20) mm 109,831.39
73 A.4.1.2.3. (K3) Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c 14,5 MPa, slump (120 ± 20) mm 131,706.82
74 A.4.1.2.4. (K3) Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c 14,5 MPa, slump (120 ± 20) mm 164,744.21
75 A.4.1.2.5. Pembuatan 1 m2 bekisting untuk pelat beton pracetak ( 5 kali pakai) 170,201.92
76 A.4.1.2.6 Pembuatan 1 m2 bekisting untuk balok beton pracetak (10-12 kali pakai) 57,243.19
77 A.4.1.2.7.
A.4.1.2.8. Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10-12 kali pakai) 51,751.94
78 Pemasangan dan membuka bekisting 1 buah komponen pelat beton pracetak 7,578.50
79 A.4.1.2.9. Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak 12,270.50
80 A.4.1.2.10. Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak 9,924.50
81 A.4.1.2.11. Penuangan/menebar beton 1 m3 komponen untuk pelat pracetak 62,008.00
82 A.4.1.2.12. Penuangan/menebar beton 1 m3 komponen untuk balok pracetak 63,750.25
83 A.4.1.2.13. Penuangan/menebar beton 1 m3 komponen kolom pracetak 57,356.25
84 A.4.1.2.14. Ereksi 1 buah komponen untuk pelat pracetak 785,441.26
85 A.4.1.2.15. Ereksi 1 buah komponen untuk balok pracetak 748,973.73
86 A.4.1.2.16. Ereksi 1 buah komponen untuk kolom pracetak 1,259,041.33
87 A.4.1.2.17. Langsir 1 buah komponen untuk pelat pracetak ( ± 20 m) 109,338.03
88 A.4.1.2.18. Langsir 1 buah komponen untuk balok pracetak ( ± 20 m) 109,338.03
89 A.4.1.2.19. Langsir 1 buah komponen untuk kolom pracetak ( ± 20 m) 109,338.03
90 A.4.1.2.20. Bahan 1 m3 grout campuran 3,426,425.00
91 A.4.1.2.21. Bahan 1 m3 grout (tidak campuran) 5,043,900.00
92 A.4.1.2.22. Upah 1 titik pekerjaan grout pada joint beton pracetak 55,821.00
93 A.4.1.2.23. Pemasangan 1 titik bekisting joint pracetak 144,137.55
94 A.4.1.2.24. Upah 1 titik joint dengan sling 49,461.50
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
95 A.4.2.1.1. Pemasangan 1 kg besi profil 31,708.38
96 A.4.2.1.2. Pemasangan 1 kg rangka kuda-kuda baja IWF 31,708.38
97 A.4.2.1.3. Pengerjaan 100 kg pekerjaan perakitan 135,475.75
98 A.4.2.1.4. Pembuatan 1 m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku 729,784.25
99 A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik 44,188.75
100 A.4.2.1.6. Pembuatan 1 m2 rangka jendela besi scuare tube 426,592.58
101 A.4.2.1.7. Pemasangan 1 m2 pintu rolling door besi 1,528,649.00
102 A.4.2.1.8. Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC 3,549,176.00
103 A.4.2.1.9. Pemasangan 1 m2 sunscreen alluminium 552,276.00
104 A.4.2.1.10. Pemasangan 1 m2 rolling door alluminium 685,400.00
105 A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium 151,365.88
106 A.4.2.1.12. Pemasangan 1 m2 pintu alluminium strip lebar 8 cm 2,254,752.68
107 A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium 646,164.88
108 A.4.2.1.14. Pemasangan 1 m2 venetions blinds dan vertical blinds 201,083.25
109 A.4.2.1.15. Pemasangan 1 m2 terali besi strip (2 x 3) mm 611,641.17
110 A.4.2.1.16. Pemasangan 1 m2 kawat nyamuk 431,064.97
111 A.4.2.1.17. Pemasangan 1 m2 jendela nako & tralis 373,152.00
112 A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm 173,736.25
113 A.4.2.1.19 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm 114,057.00
114 A.4.2.1.20. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, untuk partisi 209,571.21
115 A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, untuk plafon 253,990.92
116 A.4.2.1.22. (K3) Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75 219,598.08
117 A.4.2.1.22. (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75 236,452.08
A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
118 A. 4.4.1.1. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 2PP 302,371.80
119 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP 288,016.24
120 A. 4.4.1.3. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP 278,190.41
121 A. 4.4.1.4. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP 273,338.67
122 A. 4.4.1.5 Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 batu campuran 1SP : 6PP 272,163.37
123 A. 4.4.1.6 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP 253,767.91
124 A. 4.4.1.7 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP 146,199.73
125 A. 4.4.1.8 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP 139,304.10
126 A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP 135,400.66
127 A. 4.4.1.10 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :5PP 132,948.63
128 A. 4.4.1.11 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 6PP 131,715.37
129 A. 4.4.1.12 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :8PP 129,024.25
130 A. 4.4.1.13 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 3KP :10PP 127,011.75

II - 20
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp
131 A. 4.4.1.14 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :1PP 112,386.51
132 A. 4.4.1.15 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :2PP 114,448.92
133 A. 4.4.1.16 rob Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 3PP 101,400.01
134 A. 4.4.1.17 rob Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 4PP 105,243.72
135 A. 4.4.1.18 rob Pemasangan 1m2 dinding conblock HB15 campuran 1SP : 3PP 89,272.32
136 A. 4.4.1.19 rob Pemasangan 1 m2 dinding conblock HB15 campuran 1SP :4PP 89,306.45
137 A. 4.4.1.20 rob Pemasangan 1 m2 dinding conblock HB10 campuran 1SP :3PP 76,940.70
138 A. 4.4.1.21.rob Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 4PP 77,026.68
139 A. 4.4.1.22 Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1SP :3PP 151,082.98
140 A. 4.4.1.23 Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :4PP 151,082.98
141 A. 4.4.1.24.rob Pemasangan 1 m2 dinding bata berongga ekspose 5x11x23 campuran 1SP :3PP 244,777.82
142 A. 4.4.1.25 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai 279,488.81
143 A. 4.4.1.26 Pemasangan 1m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai 285,540.69
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
144 A.4.4.2.1. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm 77,345.55
145 A.4.4.2.2. Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm 69,801.09
146 A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm 66,577.07
147 A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm 64,343.19
148 A.4.4.2.5. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm 63,121.20
149 A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm 62,123.81
150 A.4.4.2.7. Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15 mm 61,590.09
151 A.4.4.2.8. Pemasangan 1 m2 plesteran 1SP : 8PP tebal 15 mm 61,056.38
152 A.4.4.2.9. Pemasangan 1 m2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm 63,269.21
153 A.4.4.2.10. Pemasangan 1 m2 plesteran 1SP : 2KP : 8PP tebal 15 mm 60,660.20
154 A.4.4.2.11. Pemasangan 1 m2 plesteran 1SM : 1KP : 1PP tebal 15 mm 53,531.94
155 A.4.4.2.12. Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 15 mm 54,803.30
156 A.4.4.2.13. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 20 mm 93,400.82
157 A.4.4.2.14. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm 75,083.62
158 A.4.4.2.15. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20 mm 86,043.92
159 A.4.4.2.16. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm 84,494.30
160 A.4.4.2.17. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 20 mm 83,084.74
161 A.4.4.2.18. Pemasangan 1 m2 plesteran 1SM : 1 KP : 2PP tebal 20 mm 76,257.20
162 A.4.4.2.19. Pemasangan 1 m2 berapen 1SP : 5PP tebal 15 mm 38,965.45
163 A.4.4.2.20. Pemasangan 1 m’ plesteran skoning 1SP : 3PP lebar 10 cm 62,609.11
164 A.4.4.2.21. Pemasangan 1 m2 plesteran granit 1SP : 2 granit tebal 1cm 175,311.75
165 A.4.4.2.22 Pemasangan 1 m2 plesteran traso 1SP : 2 traso tebal 1 cm 175,311.75
166 A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 50,594.71
167 A.4.4.2.24 Pemasangan 1 m2 finishing siar pasangan bata merah 29,406.88
168 A.4.4.2.25. Pemasangan 1 m2 finishing siar pasangan conblock ekspose 14,030.00
169 A.4.4.2.26. Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2PP 61,635.17
170 A.4.4.2.27. Pemasangan 1 m2 acian 37,605.00
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
171 A.4.4.3.2. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30 cm x30 cm 107,034.53
172 A.4.4.3.3. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20 cm x 20 cm 141,421.83
173 A.4.4.3.5. Pemasangan 1 m2 lantai ubin warna ukuran 30 cm x 30 cm 118,129.73
174 A.4.4.3.6. Pemasangan 1 m2 lantai ubin warna ukuran 20 cm x 20 cm 160,511.83
175 A.4.4.3.9. Pemasangan 1 m2 lantai ubin granit ukuran 40 cm x 40 cm 396,325.08
176 A.4.4.3.32. Pemasangan 1m2 lantai keramik artistik 10 cm x 20 cm 229,363.48
177 A.4.4.3.35. Pemasangan 1m2 lantai keramik ukuran 30 cm x 30 cm 176,818.83
178 A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20 cm x 20 cm 204,631.58
179 A.4.4.3.38. Pemasangan 1m2 lantai keramik mozaik ukuran 30 cm x 30 cm 212,570.61
180 A.4.4.3.39. Pemasangan 1 m’ plint keramik ukuran 10 cm x 20 cm 99,353.91
181 A.4.4.3.40. Pemasangan 1 m’ plint keramik ukuran 10 cm x 10 cm 136,096.41
182 A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5 cm x 20 cm 79,709.78
183 A.4.4.3.42. Pemasangan 1 m’ plint internal cove artistik 5 cm x 5 cm x 20 cm 263,780.91
184 A.4.4.3.43. Pemasangan 1 m2 lantai marmer ukuran 100cm x 100cm 1,113,373.08
185 A.4.4.3.44. Pemasangan 1 m2 lantai karpet 186,702.50
186 A.4.4.3.45. Pemasangan 1 m2 underlayer (pelapis bawah karpet) 114,994.25
187 A.4.4.3.46. Pemasangan 1 m2 lantai parquet kayu 341,693.75
188 A.4.4.3.47. Pemasangan 1 m2 lantai kayu gymfloor 341,693.75
189 A.4.4.3.49. Pemasangan 1 m2 dinding porselen 10 cm x 20 cm 257,067.78
190 A.4.4.3.50. Pemasangan 1 m2 dinding porselen 20 cm x 20 cm 247,108.78
191 A.4.4.3.51. Pemasangan 1 m2 dinding keramik artistik 10 cm x 20 cm 387,094.45
192 A.4.4.3.52. Pemasangan 1 m2 dinding keramik artistik 5 cm x 20 cm 388,129.45
193 A.4.4.3.53. Pemasangan 1 m2 dinding keramik 10 cm x 20 cm 257,067.78
194 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20 cm x 20 cm 248,431.28
195 A.4.4.3.55. Pemasangan 1 m2 dinding marmer 100 cm x 100 cm 1,217,854.03
196 A.4.4.3.56. Pemasangan 1 m2 dinding bata pelapis 3 cm x 7 cm x 24 cm 502,680.53
197 A.4.4.3.57. Pemasangan 1 m2 dinding batu paras 145,883.25
198 A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel hitam 142,549.98
199 A.4.4.3.59. Pemasangan 1 m2 lantai vynil ukuran 30 cm x 30 cm 191,642.80
200 A.4.4.3.60. Pemasangan 1 m2 wallpaper lebar 50 cm 238,055.75
201 A.4.4.3.61. Pemasangan 1m2 floor harderner 82,631.33
202 A.4.4.3.62. Pemasangan 1 m’ plint vynil 15cm x 30cm 42,136.00
203 A.4.4.3.63. Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm 60,858.00
204 A.4.4.3.64. Pemasangan 1 m2 paving block natural tebal 6 cm 165,195.20

II - 21
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp
205 A.4.4.3.65. Pemasangan 1 m2 paving block natural tebal 8 cm 793,801.30
206 A.4.4.3.66. Pemasangan 1 m2 paving block berwarna tebal 6 cm 174,138.75
207 A.4.4.3.67. Pemasangan 1 m2 paving block berwarna tebal 8 cm 802,744.85
A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
208 A.4.5.1.1. Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm 59,196.25
209 A.4.5.1.2. Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30) cm 731,998.00
210 A.4.5.1.3. Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60) cm 368,368.00
211 A.4.5.1.4. Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm 111,665.00
212 A.4.5.1.5. Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6 mm 49,105.00
213 A.4.5.1.6. Pemasangan 1 m2 langit-langit lambrisering kayu, tebal 9 mm 240,925.00
214 A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm 40,439.75
215 A.4.5.1.8. Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm berikut rangka alluminium 614,226.50
216 A.4.5.1.9. Pemasangan 1 m’ list langit-langit kayu profil 18,181.50
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP
217 A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil 50,217.63
218 A.4.5.2.2. Pemasangan 1 m2 atap genteng kodok glazuur 64,653.00
219 A.4.5.2.3. Pemasangan 1 m2 atap genteng palentong besar/super 45,103.00
220 A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong 94,498.72
221 A.4.5.2.5. Pemasangan 1 m’ bubung genteng kodok glazuur 105,998.72
222 A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar 110,598.72
223 A.4.5.2.7. Pemasangan 1 m2 roof light fibreglass 90 x 180 66,245.75
224 A.4.5.2.8. Pemasangan 1 m2 atap asbes gelombang 0,92 m x 2 ,5 m x 5 mm 44,367.00
225 A.4.5.2.9. Pemasangan 1 m2 atap asbes gelombang 0,92 m x 2,25 m x 5 mm 48,047.00
226 A.4.5.2.10. Pemasangan 1 m2 atap asbes gelombang 0,92 m x 2,00 m x 5 mm 47,224.75
227 A.4.5.2.11. Pemasangan 1 m2 atap asbes gelombang 0,92 m x 1,80 m x 5 mm 52,744.75
228 A.4.5.2.12. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 3,00 m x 4 mm 38,024.75
229 A.4.5.2.13. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 2,70 m x 4 mm 40,600.75
230 A.4.5.2.14. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 2,40 m x 4 mm 41,336.75
231 A.4.5.2.15. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 2,10 m x 4 mm 43,912.75
232 A.4.5.2.16. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 1,50 m x 4 mm 54,584.75
233 A.4.5.2.17. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 3,00 m x 6 mm 38,760.75
234 A.4.5.2.18. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 2,70 m x 6 mm 39,128.75
235 A.4.5.2.19. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 2,40 m x 6 mm 42,072.75
236 A.4.5.2.20. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 2,10 m x 6 mm 43,176.75
237 A.4.5.2.21. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 1,80 m x 6 mm 46,120.75
238 A.4.5.2.22. Pemasangan 1 m’ bubung stel gelombang 0,92 m 198,748.75
239 A.4.5.2.23. Pemasangan 1 m’ bubung stel gelombang 1,05 m 177,358.75
240 A.4.5.2.24. Pemasangan 1 m’ bubung stel gelombang 1,08 m 173,793.75
241 A.4.5.2.25. Pemasangan 1 m’ nok paten 0,92 m 113,188.75
242 A.4.5.2.26. Pemasangan 1 m’ nok paten 1,05 m 113,188.75
243 A.4.5.2.27. Pemasangan 1 m’ nok paten 1,08 m 113,188.75
244 A.4.5.2.28. Pemasangan 1 m’ nok stel rata 0,92 m 110,405.75
245 A.4.5.2.29. Pemasangan 1 m’ nok stel rata 1,05 m 106,058.75
246 A.4.5.2.30. Pemasangan 1 m2 genteng beton 96,243.50
247 A.4.5.2.32. Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana 107,594.00
248 A.4.5.2.33. Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai 146,234.00
249 A.4.5.2.34. Pemasangan 1 m2 atap sirap kayu 108,715.25
250 A.4.5.2.35. Pemasangan 1 m’ nok genteng beton 113,933.72
251 A.4.5.2.37. Pemasangan 1 m’ nok genteng metal 100,937.42
252 A.4.5.2.38. Pemasangan 1 m’ nok sirap 73,306.75
253 A.4.5.2.39. Pemasangan 1 m2 atap seng gelombang 67,298.00
254 A.4.5.2.40. Pemasangan 1 m’nok atap seng 44,694.75
255 A.4.5.2.41. Pemasangan 1 m2 atap alumunium 275,149.00
256 A.4.5.2.43. Pemasangan 1 m2 alumunium foil/sisalation 32,033.25
A.4.6.1 HARGA SATUAN PEKERJAAN KAYU
257 A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I 15,437,600.00
258 A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III 7,770,550.00
259 A.4.6.1.3. Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II 398,940.75
260 A.4.6.1.4. Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III 329,940.75
261 A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II 726,800.00
262 A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II 531,990.00
263 A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II 864,800.00
264 A.4.6.1.8. Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm 619,781.00
265 A.4.6.1.9. Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II 671,186.00
266 A.4.6.1.10. Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II 706,272.50
267 A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I 754,101.00
268 A.4.6.1.12. Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II 666,016.75
269 A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter 6,698,807.50
270 A.4.6.1.14. Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I 16,676,092.50
271 A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II 9,837,272.50
272 A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II 417,565.00
273 A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II 588,627.50
274 A.4.6.1.18. Pemasangan 1 m2 rangka atap sirap, kayu kelas II 108,727.90
275 A.4.6.1.19. Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III 171,810.00
276 A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III 175,432.50
277 A.4.6.1.21. Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II 99,417.50

II - 22
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp
278 A.4.6.1.22. Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II 99,532.50
279 A.4.6.1.23. Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III 187,800.75
280 A.4.6.1.25. Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II 384,663.50
281 A.4.6.1.26. Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas I 369,380.00
282 A.4.6.1.27. Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120 x 240) cm 62,042.50
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
283 A.4.6.2.1. Pemasangan 1 buah kunci tanam antik 337,444.50
284 A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa 214,590.00
285 A.4.6.2.3. Pemasangan 1 buah kunci kamar mandi 116,127.00
286 A.4.6.2.4. Pemasangan 1 buah kunci silinder 144,877.00
287 A.4.6.2.5. Pemasangan 1 buah engsel pintu 42,392.45
288 A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu 42,440.75
289 A.4.6.2.7. Pemasangan 1 buah engsel angin 57,678.25
290 A.4.6.2.8. Pemasangan 1 buah spring knip 46,753.25
291 A.4.6.2.9. Pemasangan 1 buah kait angin 30,078.25
292 A.4.6.2.10. Pemasangan 1 buah door closer 390,517.00
293 A.4.6.2.11. Pemasangan 1 buah kunci slot (grendel) 41,181.50
294 A.4.6.2.12. Pemasangan 1 buah door holder 94,967.00
295 A.4.6.2.13. Pemasangan 1 buah door stop 60,260.00
296 A.4.6.2.14. Pemasangan 1 buah rel pintu sorong 484,644.50
297 A.4.6.2.15. Pemasangan 1 buah kunci lemari 197,495.25
298 A.4.6.2.16. Pemasangan 1 m2 kaca tebal 3 mm 111,507.45
299 A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm 124,157.45
300 A.4.6.2.18. Pemasangan 1 m2 kaca tebal 8 mm 216,411.60
301 A.4.6.2.19. Pemasangan 1 m2 kaca buram tebal 12 mm 493,646.70
302 A.4.6.2.20. Pemasangan 1 m2 kaca cermin tebal 5 mm 192,228.25
303 A.4.6.2.21. Pemasangan 1 m2 kaca cermin tebal 8 mm 350,295.75
304 A.4.6.2.22. Pemasangan 1 m2 kaca wireglassed tebal 5 mm 287,103.25
305 A.4.6.2.23. Pemasangan 1 m2 kaca patri tebal 5 mm 2,558,882.25
A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
306 A.4.7.1.1. 1 m2 Pengikisan/pengerokan permukaan cat lama 15,617.00
307 A.4.7.1.2. 1 m2 Pencucian bidang permukaan tembok yang pernah dicat 14,812.00
308 A.4.7.1.3. 1 m2 Pengerokan karat pada permukaan baja cara manual 15,444.50
309 A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 39,790.00
310 A.4.7.1.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup) 55,763.50
311 A.4.7.1.6. Pelaburan 1 m2 bidang kayu dengan teak oil 31,435.25
312 A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur 44,761.08
313 A.4.7.1.8. Pelaburan 1 m2 bidang kayu dengan cat residu dan ter 21,027.75
314 A.4.7.1.9. Pelaburan 1 m2 bidang kayu dengan vernis 42,817.38
315 A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 24,427.73
316 A.4.7.1.11. Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 17,435.15
317 A.4.7.1.12. Pelaburan 1 m2 tembok dengan kalkarium 10,420.15
318 A.4.7.1.13. Pelaburan 1 m2 tembok dengan kapur sirih 17,808.33
319 A.4.7.1.14. Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan) 8,886.63
320 A.4.7.1.15. Pemasangan 1 m2 wallpaper 129,231.25
321 A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan menie besi 30,584.25
322 A.4.7.1.17. Pengecatan 1 m2 permukaan baja dengan menie besi dengan perancah 63,879.63
323 A.4.7.1.18. Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis 66,157.20
324 A.4.7.1.19. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir 33,637.50
325 A.4.7.1.20. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 3 lapis 156,469.00
326 A.4.7.1.21. Pengecatan 1 m2 permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir 137,183.50
327 A.4.7.1.22. Plituran 10 m2 dengan plitur melamic 2,130,950.00
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
328 A.5.1.1.1. (K3) Pemasangan 1 buah closet duduk/monoblock 1,959,450.50
329 A.5.1.1 2. Pemasangan 1 buah closet jongkok porselen 475,903.35
330 A.5.1.1 3. Pemasangan 1 buah closet jongkok teraso 422,428.35
331 A.5.1.1 4. (K3) Pemasangan 1 buah urinoir 1,207,705.85
332 A.5.1.1 5. (K3) Pemasangan 1 buah wastafel 1,375,184.95
333 A.5.1.1 7. (K3) Pemasangan 1 buah bak fiberglass vol 1 m3 1,196,747.50
334 A.5.1.1 9. Pemasangan 1 buah bak mandi teraso vol 0,30 m3 1,196,747.50
335 A.5.1.1 10. Pemasangan 1 buah bak air fiberglass vol 1 m3 370,041.25
336 A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel 945,530.00
337 A.5.1.1 13. Pemasangan 1 buah bak cuci piring teraso 759,454.25
338 A.5.1.1 14. Pemasangan 1 buah floor drain 109,135.00
339 A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm 481,416.45
340 A.5.1.1 16. Pemasangan 1 buah bak kontrol pasangan bata 45cm x 45cm tinggi 50 cm 772,480.30
341 A.5.1.1 17. Pemasangan 1 buah bak kontrol pasangan bata 60 cm x 60 cm tinggi 65 cm 911,393.52
342 A.5.1.1 18. Pemasangan 1 m’ pipa galvanis diameter ½” 65,868.17
343 A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau ¾ ” 66,297.50
344 A.5.1.1 20. Pemasangan 1 m’ pipa galvanis diameter ¾ ” 81,920.25
345 A.5.1.1 21. Pemasangan 1 m’ pipa galvanis diameter 1” 157,820.25
346 A.5.1.1 22. Pemasangan 1 m’ pipa galvanis diameter 1 ½” 242,742.00
347 A.5.1.1 23. Pemasangan 1 m’ pipa galvanis diameter 3” 198,449.75
348 A.5.1.1 24. Pemasangan 1 m’ pipa galvanis diameter 4” 498,392.75
349 A.5.1.1 25. Pemasangan 1 m’ pipa PVC tipe AW diameter ½ ” 22,646.95
350 A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter ¾ ” 28,149.70

II - 23
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp
351 A.5.1.1 27. Pemasangan 1 m’ pipa PVC tipe AW diameter 1” 30,937.30
352 A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe AW diameter 1 ½ ” 61,496.25
353 A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2” 74,444.10
354 A.5.1.1 30. Pemasangan 1 m’ pipa PVC tipe AW diameter 2 ½ ” 145,462.93
355 A.5.1.1 31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3” 145,462.93
356 A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4” 199,769.38
357 A.5.1.1 33. Pemasangan 1 m’ pipa air limbah jenis pipa tanah Ǿ 20 cm 394,124.32
358 A.5.1.1 34. Pemasangan 1 m’ pipa air limbah jenis pipa tanah diameter 15 cm 224,394.90
359 A.5.1.1 35. Pemasangan 1 m’ pipa beton diameter 15 – 20 cm 987,791.01
360 A.5.1.1.36. Pemasangan 1 m’ pipa beton diameter 30 – 100 cm 190,422.29
A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA DI LUAR GEDUNG
361 A.8.4.1.1 (K3) Pemasangan 1 m pipa PVC Ø 63 mm 72,519.00
362 A.8.4.1.2 (K3) Pemasangan 1 m pipa PVC Ø 90 mm 120,991.50
363 A.8.4.1.3 (K3) Pemasangan 1 m pipa PVC Ø 110 mm 164,323.50
364 A.8.4.1.5 (K3) Pemasngan 1 m pipa PVC Ø 200 mm 482,321.50
365 A.8.4.1.6 (K3) Pemasangan 1 m pipa PVC Ø 250 mm 734,723.50
366 A.8.4.1.17 (K3) Pemasangan 1 m pipa HDPE Ø 63 mm 111,814.50
367 A.8.4.1.19 (K3) Pemasangan 1 m pipa HDPE Ø 125 mm 200,962.50
368 A.8.4.1.21 (K3) Pemasangan 1 m pipa HDPE Ø 200 mm 391,529.00
369 A.8.4.1.22 (K3) Pemasangan 1 m pipa HDPE Ø 250 mm 655,580.50
370 A.8.4.1.33 (K3) Pemasangan 1 m pipa GIP Ø 63 mm 153,571.00
371 A.8.4.1.34 (K3) Pemasangan 1 m pipa GIP Ø 100 mm 346,610.00
372 A.8.4.1.35 (K3) Pemasangan 1 m pipa GIP Ø 125 mm 72,668.50
373 A.8.4.1.36 (K3) Pemasangan 1 m pipa GIP Ø 150 mm 490,348.50
374 A.8.4.1.37 (K3) Pemasangan 1 m pipa GIP Ø 200 mm 911,122.00
375 A.8.4.1.38 (K3) Pemasangan 1 m pipa GIP Ø 250 mm 1,160,200.50
376 A.8.4.1.49 (K3) Pemasangan 1 m pipa DCI Ø 100 mm 2,301,518.00
377 A.8.4.1.50 (K3) Pemasangan 1 m pipa DCI Ø 125 mm 2,675,716.50
378 A.8.4.1.51 (K3) Pemasangan 1 m pipa DCI Ø 150 mm 3,180,957.50
379 A.8.4.1.52 (K3) Pemasangan 1 m pipa DCI Ø 200 mm 4,053,577.50
380 A.8.4.1.53 (K3) Pemasangan 1 m pipa DCI Ø 250 mm 3,542,609.50
381 A.8.4.1.64 (K3) Pemasangan 1 m Pipa baja Ø 63 mm 272,458.00
382 A.8.4.1.65 (K3) Pemasangan 1 m pipa baja Ø 100 mm 353,970.00
383 A.8.4.1.66 (K3) Pemasangan 1 m pipa baja Ø 125 mm 421,463.50
384 A.8.4.1.67 (K3) Pemasangan 1 m pipa baja Ø 150 mm 503,585.00
385 A.8.4.1.68 (K3) Pemasangan 1 m pipa baja Ø 200 mm 832,657.50
386 A.8.4.1.69 (K3) Pemasangan pipa baja Ø 250 mm 1,044,924.50
A.8.4.2 HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA
387 A.8.4.2.1 (K3) Pemotongan 1 buah pipa PVC Ø 63 mm 36,115.75
388 A.8.4.2.2 (K3) Pemotongan 1 m pipa PVC Ø 90 mm 75,992.00
389 A.8.4.2.3 (K3) Pemotongan 1 buah pipa PVC Ø 110 mm 110,641.50
390 A.8.4.2.5 (K3) Pemotongan 1 buah pipa PVC Ø 200 mm 369,046.50
391 A.8.4.2.6 (K3) Pemotongan 1 buah pipa PVC Ø 250 mm 578,818.00
392 A.8.4.2.17 (K3) Pemotongan 1 buah pipa HDPE Ø 63 mm 35,422.30
393 A.8.4.2.19 (K3) Pemotongan 1 buah pipa HDPE Ø 125 mm 133,296.50
394 A.8.4.2.20 (K3) Pemotongan 1 buah pipa HDPE Ø 150 mm 21,252.00
395 A.8.4.2.21 (K3) Pemotongan 1 buah pipa HDPE Ø 200 mm 332,166.00
396 A.8.4.2.22 (K3) Pemotongan 1 buah pipaHDPE Ø 250 mm 510,151.50
397 A.8.4.2.33 (K3) Pemotongan 1 buah pipa GIP Ø 63 mm 100,901.00
398 A.8.4.2.34 (K3) Pemotongan 1 buah pipa GIP Ø 100 mm 291,180.00
400 A.8.4.2.36 (K3) Pemotongan 1 buah pipa GIP Ø 150 mm 429,536.50
401 A.8.4.2.37 (K3) Pemotongan 1 buah pipa GIP Ø 200 mm 837,131.00
402 A.8.4.2.38 (K3) Pemotongan 1 buah pipa GIP Ø 250 mm 1,083,150.50
517 A.8.4.2.39 (K3) Pemotongan 1 buah pipa GIP Ø 300 mm 81,673.00
518 A.8.4.2.40 (K3) Pemotongan 1 buah pipa GIP Ø 400 mm 118,956.00
519 A.8.4.2.41 (K3) Pemotongan 1 buah pipa GIP Ø 450 mm 137,068.50
520 A.8.4.2.42 (K3) Pemotongan 1 buah pipa GIP Ø 500 mm 152,628.00
521 A.8.4.2.43 (K3) Pemotongan1 buah pipa GIP Ø 600 mm 140,047.00
522 A.8.4.2.44 (K3) Pemotongan 1 buah pipa GIP Ø 800 mm 254,069.50
523 A.8.4.2.45 (K3) Pemotongan 1 buah pipa GIP Ø 900 mm 287,005.50
524 A.8.4.2.46 (K3) Pemotongan 1 buah pipa GIP Ø 1000 mm 320,033.50
525 A.8.4.2.47 (K3) Pemotongan 1 buah pipa GIP Ø 1100 mm 353,188.00
526 A.8.4.2.48 (K3) Pemotongan 1 buah pipa GIP Ø 1200 mm 386,216.00
A.8.4.3 HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA
414 A.8.4.3.1 (K3) Pemasangan 1 buah Valve Ø 150 mm 4,371,782.50
415 A.8.4.3.2 (K3) Pemasangan 1 buah Valve Ø 200 mm 7,695,374.50
416 A.8.4.3.3 (K3) Pemasangan 1 buah Valve Ø 250 mm 12,525,374.50
A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN PIPA
420 A.8.4.5.1 (K3) Pengetesan 1 m pipa Ø 50 mm 1,397.25
421 A.8.4.5.2 (K3) Pengetesan 1 m pipa Ø 75 mm 1,408.75
422 A.8.4.5.3 (K3) Pengetesan 1 m pipa Ø 100 mm 1,431.75
423 A.8.4.5.4 (K3) Pengetesan 1 m pipa Ø 150 mm 1,489.25
424 A.8.4.5.5 (K3) Pengetesan 1 m pipa Ø 200 mm 1,564.00
425 A.8.4.5.6 (K3) Pengetesan 1 m pipa Ø 250 mm 1,667.50
A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL
426 A.8.4.6.1 (K3) Pemasangan 1 buah titik lampu (Instalasi) 5,455,600.00
427 A.8.4.6.1 (K3) Pemasangan 1 buah MCB (Penyambungan Daya ke PLN) 5,321,050.00

II - 24
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp
- TAMBAHAN / LAIN-LAIN
428 - 1 Buah Pembuatan Papan Nama Proyek 352,820.00
429 SNI 7395:2008 N0.6.9 Memasang 1 m2 lantai ubin granit ukuran 40 x 40 403,000.25
430 SNI 03-7395:2008 N0.6.9 Memasang 1 m2 lantai keramik ukuran 40 x 40 115,047.73
431 SNI 03-7395:2008 N0.6.9 Memasang 1 m2 lantai granit ukuran 60 x 60 295,950.49
432 SNI 2839:2008 N0.6.8 Memasang 1 m' List Plafond Gypsum Profil 40,865.25
433 SNI 2839:2008 N0.6.8 1 m' Pasang Listplank Woodplank 53,532.50
434 ABK.990.07 Menurunkan 1 m2 atap genteng 2,070.00
435 ABK.990.09 Menurunkan 1 m2 rangka atap/Plafond 6,555.00
436 ABK.990.12 Menurunkan 1 m3 kayu rangka kuda-kuda 77,050.00
437 ABK.990.05 Membongkar 1 m2 lantai tegel/floor 6,976.67
438 SNI 2012 1 m³ Bongkaran Beton Bertulang 655,488.50
439 SNI 2012 1 m³ Bongkaran Dinding Tembok Bata Merah 617,538.50
440 ABK.300.19 1 m3 Pekerjaan Beton AD. 1:2:3 929,596.75
441 - 1m2 Pasang Plafond Rangka Holo dan Dengan Penutup GRC Berikut Pengecatan 107,709.00
442 - 1 Titik Pekerjaan Instalasi Lampu dan Stop Kontak 175,076.00
443 - 1 Bh Pekerjaan Stop Kontak 39,215.00
444 - 1 Bh Pekerjaan Lampu SL 18 Watt + Fitting 57,615.00
445 - 1 Unit Pekerjaan Sekring Kast 63,365.00
446 - 1 Bh Pekerjaan MCB Box 63,365.00
447 - 1 m' Pekerjaan Over Spaneng 38,088.00
448 - 1 Bh Pekerjaan Saklar Ganda 63,480.00
449 - 1 Bh Pekerjaan Saklar Tunggal 60,605.00
450 A.3.2.1.2.a Pemasangan pasangan 1 m3 batu belah campuran 1SP : 4PP 940,047.95
JALAN LINGKUNGAN
451 Analisa EI-311a : Galian Biasa / Kupasan (menggunakan alat berat) 121,609.97
452 Analisa EI-321.rob : Timbunan Biasa 361,637.76
453 Analisa EI-322.rob : Timbunan Pilihan 438,658.51
454 Analisa EI-331.rob : Penyiapan Badan Jalan 228.65
455 Analisa EI-611a : Lapis Resap Pengikat - Aspal Cair 14,053.74
456 Analisa EI-612a : Lapis Perekat - Aspal Cair 14,497.40
457 Analisa EI-621 : Agregat Penutup BURTU 17,722.29
458 Analisa EI-631.rob : Latasir Kelas A (SS-A) 61,183.90
459 Analisa EI-632.rob : Latasir Kelas B (SS-B) 71,372.83
460 Analisa EI-661 : Lapis Permukaan Penetrasi Macadam 2,068,214.73
461 Analisa EI-662 : Lapis Pondasi/Perata Penetrasi Macadam 2,188,331.47
462 Analisa EI-814 : Waterbound Macadam Utk. Pek. Minor 377,958.10
463 Analisa EI-817 : Penetrasi Macadam Utk.Pek.Minor (Perata) 2,022,619.07
AIR TANAH DAN PERPIPAAN
464 AT.02 1 m' Pengeboran Ø 8'' (Daerah Pegunungan) 476,298.95
465 AT.02.rob.1 1 m' Pengeboran sederhana 238,149.48
466 AT.03 1 m' Reaming Ø 8-12'' 440,410.90
467 AT.07 1 m' Pengadaan dan pemasangan cassing pipa PVC 6'' 375,402.26
468 AT.09 1 m' Pengadaan dan pemasangan cassing pipa PVC 8'' 540,145.80
469 AT.12 1 m3 Pengadaan dan pemasangan gravel pack 2,752,226.00
470 AT.13 1 jam pencucian sumur 176,904.50
471 AT.14 1 jam Uji Pemompaan 176,904.50
472 - 1 m³ Galian tanah biasa 62,750.00
473 - 1 m³ Galian tanah keras / berbatu 83,630.00
474 - 1 m³ Galian tanah berbatu / bongkar jalan 125,500.00
475 - 1 m³ Urugan tanah kembali 25,100.00
476 - 1 m³ Buang tanah sisa galian 27,500.00
477 - 1 m³ Urugan pasir 233,060.00
478 - 1 m³ Beton tumbuk 1:3:5 726,507.00
479 - 1 m² Pasang bekisting 199,680.00
480 - 1 m³ Trush block 1,009,817.00
481 - 1 m² Plesteran 1:3 52,397.10
482 - 1 m³ Pasangan batu kali 1:4 821,108.00
483 - 1 m² Siaran batu muka 55,151.10
484 - 1 m³ Beton bertulang 1:2:3 847,345.00
485 - 1 kg Pembesian dengan besi polos atau besi ulir 15,316.50
486 - 1 m² Pekerjaan bekisting dari multiplek 6mm 384,550.00
487 - 1 m² Pasangan bata merah 1 : 4 tebal 1/2 bata 128,489.70
488 - 1 m² Pengecatan 20,381.00
489 - 10 cm Pengelasan 43,240.00
490 - 1 m' Pemasangan pipa PVC dia. 350 mm melalui galian tanah berbatu / bongkar jalan 189,684.40
491 - 1 m' Pemasangan pipa PVC dia. 300 mm melalui galian tanah berbatu / bongkar jalan 177,776.00
492 - 1 m' Pemasangan pipa PVC dia. 250 mm melalui galian tanah berbatu / bongkar jalan 154,459.20
493 - 1 m' Pemasangan pipa PVC dia. 200 mm melalui galian tanah berbatu / bongkar jalan 121,037.20
494 - 1 m' Pemasangan pipa PVC dia. 160 mm melalui galian tanah berbatu / bongkar jalan 93,776.00
495 - 1 m' Pemasangan pipa PVC dia. 110 mm melalui galian tanah berbatu / bongkar jalan 75,550.80
496 - 1 m' Pemasangan pipa PVC dia. 90 mm melalui galian tanah berbatu / bongkar jalan 69,026.80
497 - 1 m' Pemasangan pipa PVC dia. 63 mm melalui galian tanah berbatu / bongkar jalan 43,271.60
498 - 1 m' Pemasangan pipa PVC dia. 50 mm melalui galian tanah berbatu / bongkar jalan 42,771.60
499 - 1 m' Pemasangan pipa PVC dia. 25 mm melalui galian tanah berbatu / bongkar jalan 20,758.00
500 - 1 m' Pemasangan pipa PVC dia. 350 mm melalui galian tanah keras / berbatu 152,838.80
501 - 1 m' Pemasangan pipa PVC dia. 300 mm melalui galian tanah keras / berbatu 143,233.25
502 - 1 m' Pemasangan pipa PVC dia. 250 mm melalui galian tanah keras / berbatu 124,522.15
503 - 1 m' Pemasangan pipa PVC dia. 200 mm melalui galian tanah keras / berbatu 95,915.20
504 - 1 m' Pemasangan pipa PVC dia. 160 mm melalui galian tanah keras / berbatu 74,934.50
505 - 1 m' Pemasangan pipa PVC dia. 110 mm melalui galian tanah keras / berbatu 60,477.60
506 - 1 m' Pemasangan pipa PVC dia. 90 mm melalui galian tanah keras / berbatu 55,628.40

II - 25
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp
507 - 1 m' Pemasangan pipa PVC dia. 63 mm melalui galian tanah keras / berbatu 35,735.00
508 - 1 m' Pemasangan pipa PVC dia. 50 mm melalui galian tanah keras / berbatu 35,235.00
509 - 1 m' Pemasangan pipa PVC dia. 25 mm melalui galian tanah keras / berbatu 15,733.60
510 - 1 m' Pemasangan pipa PVC dia. 350 mm melalui galian tanah biasa 134,464.40
511 - 1 m' Pemasangan pipa PVC dia. 300 mm melalui galian tanah biasa 126,007.25
512 - 1 m' Pemasangan pipa PVC dia. 250 mm melalui galian tanah biasa 109,592.95
513 - 1 m' Pemasangan pipa PVC dia. 200 mm melalui galian tanah biasa 83,387.20
514 - 1 m' Pemasangan pipa PVC dia. 160 mm melalui galian tanah biasa 65,538.50
515 - 1 m' Pemasangan pipa PVC dia. 110 mm melalui galian tanah biasa 52,960.80
516 - 1 m' Pemasangan pipa PVC dia. 90 mm melalui galian tanah biasa 48,946.80
517 - 1 m' Pemasangan pipa PVC dia. 63 mm melalui galian tanah biasa 31,976.60
518 - 1 m' Pemasangan pipa PVC dia. 50 mm melalui galian tanah biasa 31,476.60
519 - 1 m' Pemasangan pipa PVC dia. 25 mm melalui galian tanah biasa 13,228.00
520 - 1 m' Perbaikan pipa PVC dia. 350 mm melalui galian tanah berbatu / bongkar jalan 346,734.40
521 - 1 m' Perbaikan pipa PVC dia. 300 mm melalui galian tanah berbatu / bongkar jalan 293,852.30
522 - 1 m' Perbaikan pipa PVC dia. 250 mm melalui galian tanah berbatu / bongkar jalan 247,385.50
523 - 1 m' Perbaikan pipa PVC dia. 200 mm melalui galian tanah berbatu / bongkar jalan 207,237.20
524 - 1 m' Perbaikan pipa PVC dia. 160 mm melalui galian tanah berbatu / bongkar jalan 154,826.00
525 - 1 m' Perbaikan pipa PVC dia. 110 mm melalui galian tanah berbatu / bongkar jalan 125,950.80
526 - 1 m' Perbaikan pipa PVC dia. 90 mm melalui galian tanah berbatu / bongkar jalan 108,826.80
527 - 1 m' Perbaikan pipa PVC dia. 63 mm melalui galian tanah berbatu / bongkar jalan 68,421.60
528 - 1 m' Perbaikan pipa PVC dia. 50 mm melalui galian tanah berbatu / bongkar jalan 63,171.60
529 - 1 m' Perbaikan pipa PVC dia. 25 mm melalui galian tanah berbatu / bongkar jalan 37,708.00
530 - 1 m' Perbaikan pipa PVC dia. 350 mm melalui galian tanah keras / berbatu 309,888.80
531 - 1 m' Perbaikan pipa PVC dia. 300 mm melalui galian tanah keras / berbatu 259,172.05
532 - 1 m' Perbaikan pipa PVC dia. 250 mm melalui galian tanah keras / berbatu 217,448.45
533 - 1 m' Perbaikan pipa PVC dia. 200 mm melalui galian tanah keras / berbatu 182,115.20
534 - 1 m' Perbaikan pipa PVC dia. 160 mm melalui galian tanah keras / berbatu 135,984.50
535 - 1 m' Perbaikan pipa PVC dia. 110 mm melalui galian tanah keras / berbatu 110,877.60
536 - 1 m' Perbaikan pipa PVC dia. 90 mm melalui galian tanah keras / berbatu 95,428.40
537 - 1 m' Perbaikan pipa PVC dia. 63 mm melalui galian tanah keras / berbatu 60,885.00
538 - 1 m' Perbaikan pipa PVC dia. 50 mm melalui galian tanah keras / berbatu 55,635.00
539 - 1 m' Perbaikan pipa PVC dia. 25 mm melalui galian tanah keras / berbatu 32,683.60
540 - 1 m' Perbaikan pipa PVC dia. 350 mm melalui galian tanah biasa 291,514.40
541 - 1 m' Perbaikan pipa PVC dia. 300 mm melalui galian tanah biasa 242,083.55
542 - 1 m' Perbaikan pipa PVC dia. 250 mm melalui galian tanah biasa 202,519.25
543 - 1 m' Perbaikan pipa PVC dia. 200 mm melalui galian tanah biasa 169,587.20
544 - 1 m' Perbaikan pipa PVC dia. 160 mm melalui galian tanah biasa 126,588.50
545 - 1 m' Perbaikan pipa PVC dia. 110 mm melalui galian tanah biasa 103,360.80
546 - 1 m' Perbaikan pipa PVC dia. 90 mm melalui galian tanah biasa 88,746.80
547 - 1 m' Perbaikan pipa PVC dia. 63 mm melalui galian tanah biasa 57,126.60
548 - 1 m' Perbaikan pipa PVC dia. 50 mm melalui galian tanah biasa 51,876.60
549 - 1 m' Perbaikan pipa PVC dia. 25 mm melalui galian tanah biasa 30,178.00
550 - 400 m' Pengetesan pipa PVC dia. 350 mm 3,517,500.00
551 - 400 m' Pengetesan pipa PVC dia. 300 mm 2,935,500.00
552 - 400 m' Pengetesan pipa PVC dia. 250 mm 2,385,000.00
553 - 400 m' Pengetesan pipa PVC dia. 200 mm 1,866,000.00
554 - 400 m' Pengetesan pipa PVC dia. 160 mm 1,202,250.00
555 - 400 m' Pengetesan pipa PVC dia. 110 mm 1,162,500.00
556 - 400 m' Pengetesan pipa PVC dia. 90 mm 1,083,750.00
557 - 400 m' Pengetesan pipa PVC dia. 63 mm 1,036,500.00
558 - 400 m' Pengetesan pipa PVC dia. 50 mm 999,750.00
559 - 1 unit perbaikan gate valve dia. 350mm 688,214.28
560 - 1 unit perbaikan gate valve dia. 300mm 672,464.28
561 - 1 unit perbaikan gate valve dia. 250mm 661,964.28
562 - 1 unit perbaikan gate valve dia. 200mm 646,214.28
563 - 1 unit Perbaikan gate valve dia. 160 mm melalui galian tanah berbatu / bongkar jalan 453,711.60
564 - 1 unit Perbaikan gate valve dia. 110 mm melalui galian tanah berbatu / bongkar jalan 373,183.50
565 - 1 unit Perbaikan gate valve dia. 90 mm melalui galian tanah berbatu / bongkar jalan 326,371.50
566 - 1 unit Perbaikan gate valve dia. 63 mm melalui galian tanah berbatu / bongkar jalan 258,890.90
567 - 1 unit Perbaikan gate valve dia. 50 mm melalui galian tanah berbatu / bongkar jalan 238,390.90
568 - 1 unit Perbaikan gate valve dia. 25 mm melalui galian tanah berbatu / bongkar jalan 172,115.10
569 - 1 unit Perbaikan gate valve dia. 160 mm melalui galian tanah keras / berbatu 445,461.60
570 - 1 unit Perbaikan gate valve dia. 110 mm melalui galian tanah keras / berbatu 367,433.50
571 - 1 unit Perbaikan gate valve dia. 90 mm melalui galian tanah keras / berbatu 326,371.50
572 - 1 unit Perbaikan gate valve dia. 63 mm melalui galian tanah keras / berbatu 258,890.90
573 - 1 unit Perbaikan gate valve dia. 50 mm melalui galian tanah keras / berbatu 238,390.90
574 - 1 unit Perbaikan gate valve dia. 25 mm melalui galian tanah keras / berbatu 172,115.10
575 - 1 unit Perbaikan gate valve dia. 160 mm melalui galian tanah biasa 388,986.60
576 - 1 unit Perbaikan gate valve dia. 110 mm melalui galian tanah biasa 322,253.50
577 - 1 unit Perbaikan gate valve dia. 90 mm melalui galian tanah biasa 286,211.50
578 - 1 unit Perbaikan gate valve dia. 63 mm melalui galian tanah biasa 236,300.90
579 - 1 unit Perbaikan gate valve dia. 50 mm melalui galian tanah biasa 215,800.90
580 - 1 unit Perbaikan gate valve dia. 25 mm melalui galian tanah biasa 157,055.10
581 - 1 unit pemasangan gate valve dia. 200 mm 624,685.85
582 - 1 unit Pemasangan gate valve dia. 250 mm melalui galian tanah berbatu / bongkar jalan 614,221.40
583 - 1 unit Pemasangan gate valve dia. 160 mm melalui galian tanah berbatu / bongkar jalan 413,351.60
584 - 1 unit Pemasangan gate valve dia. 110 mm melalui galian tanah berbatu / bongkar jalan 333,823.50
585 - 1 unit Pemasangan feet kran dia. 90 mm melalui galian tanah berbatu / bongkar jalan 296,761.50
586 - 1 unit Pemasangan feet kran dia. 63 mm melalui galian tanah berbatu / bongkar jalan 224,530.90
587 - 1 unit Pemasangan feet kran dia. 50 mm melalui galian tanah berbatu / bongkar jalan 204,030.90
588 - 1 unit Pemasangan gate valve dia. 250 mm melalui galian tanah keras / berbatu 476,092.00

II - 26
HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp
589 - 1 unit Pemasangan gate valve dia. 160 mm melalui galian tanah keras / berbatu 413,351.60
590 - 1 unit Pemasangan gate valve dia. 110 mm melalui galian tanah keras / berbatu 333,823.50
591 - 1 unit Pemasangan feet kran dia. 90 mm melalui galian tanah keras / berbatu 296,761.50
592 - 1 unit Pemasangan feet kran dia. 63 mm melalui galian tanah keras / berbatu 224,530.90
593 - 1 unit Pemasangan feet kran dia. 50 mm melalui galian tanah keras / berbatu 204,030.90
594 - 1 unit Pemasangan feet kran dia. 25 mm melalui galian tanah keras / berbatu 142,755.10
595 - 1 unit Pemasangan gate valve dia. 160 mm melalui galian tanah biasa 356,736.60
596 - 1 unit Pemasangan gate valve dia. 110 mm melalui galian tanah biasa 288,503.50
597 - 1 unit Pemasangan feet kran dia. 90 mm melalui galian tanah biasa 256,461.50
598 - 1 unit Pemasangan feet kran dia. 63 mm melalui galian tanah biasa 201,800.90
599 - 1 unit Pemasangan feet kran dia. 50 mm melalui galian tanah biasa 181,300.90
600 - 1 unit Pemasangan feet kran dia. 25 mm melalui galian tanah biasa 127,555.10
601 - 1 unit Pemasangan Box Street dia. 8" 195,429.40
602 - 1 unit Pemasangan Box Street dia. 6" 81,209.60
603 - 1 unit Pemasangan Box Street dia. 4" 68,631.90
604 - 1 unit Pemasangan Box Street dia. 3" 64,617.90
605 - 1 unit Pemasangan Box Street dia. 2" 47,647.70
606 - 1 unit Pemasangan Box Street dia. 1 1/2" 47,147.70
607 - 1 unit Pemasangan Box Street dia. 1" 28,899.10
608 - 1 unit Peninggian Box Street 117,436.17
609 - 1 unit Pemasangan wash out dia. 160 mm 531,637.60
610 - 1 unit Pemasangan wash out dia. 110 mm 429,732.30
611 - 1 unit Pemasangan wash out dia. 90 mm 385,321.50
612 - 1 unit Pemasangan wash out dia. 63 mm 284,027.70
613 - 1 unit Pemasangan wash out dia. 50 mm 261,527.70
614 - 18 m' Pemasangan Pipa PVC dia. 2" Sistim Boring Horizontal 4,091,238.40
615 - 18 m' Pemasangan Pipa PVC dia. 3" Sistim Boring Horizontal 6,314,312.80
616 - 18 m' Pemasangan Pipa PVC dia. 4" Sistim Boring Horizontal 7,352,893.60
617 - 18 m' Pemasangan Pipa PVC dia. 6" Sistim Boring Horizontal 9,170,092.00
618 - 18 m' Pemasangan Pipa PVC dia. 8" Sistim Boring Horizontal 12,877,261.60
619 - 18 m' Pemasangan Pipa PVC dia. 10" Sistim Boring Horizontal 13,455,951.40
620 - 18 m' Pemasangan Pipa PVC dia. 12" Sistim Boring Horizontal 15,195,667.00
621 - 18 m' Pemasangan Pipa PVC dia. 14" Sistim Boring Horizontal 15,897,224.80
622 - 1 m' Pemasangan pipa GI dia. 200 mm melalui galian type FR/CR 112,577.65
623 - 1 unit Tiang Penyangga 706,444.00

Sumber, 2018

Kepala Dinas Perumahan, Kawasan Permukiman Dan Pertanahan Kabupaten Cirebon

H. SUKMA NUGRAHA, SH.,MM.


NIP. 19610301 198603 1 012

II - 27
DAFTAR ANALISA HARGA SATUAN
DINAS PERUMAHAN KAWASAN PERMUKIMAN DAN PERTANAHAN
KABUPATEN CIREBON
TAHUN ANGGARAN 2018

A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


A. 2.2.1.1 (K3) Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang kayu L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 56,300.00
B BAHAN
Dolken kayu Ø Batang 1.250 62,500.00 78,125.00
8-10/400 cm
Semen portland Kg 5.000 1,400.00 7,000.00
Pasir beton m3 0.005 231,000.00 1,155.00
Koral beton (kerikil) m3 0.009 200,000.00 1,800.00
Kayu 5/7 (kayu kelas III) m3 0.072 3,500,000.00 252,000.00
Paku biasa 2” – 5” Kg 0.060 18,000.00 1,080.00
Residu (ter kayu) Liter 0.400 14,500.00 5,800.00
JUMLAH HARGA BAHAN 346,960.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 403,260.00
E Overhead & Profit 15.00% 60,489.00
F Harga Satuan Pekerjaan (D+E) 463,749.00

A. 2.2.1.2 (K3) Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang kayu L.02 OH 0.400 100,000.00 40,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 60,300.00
B BAHAN
Dolken kayu Batang 1.250 62,500.00 78,125.00
f 8-10/400 cm
Semen portland Kg 2.500 1,400.00 3,500.00
Seng gelombang lbr 1.200 58,900.00 70,680.00
Pasir Beton m3 0.005 231,000.00 1,155.00
Koral Beton m3 0.009 200,000.00 1,800.00
Kayu 5/7 (kayu kelas III) m3 0.072 3,500,000.00 252,000.00
Paku biasa 2''-5'' Kg 0.060 18,000.00 1,080.00
Meni Besi ltr 0.450 25,000.00 11,250.00
JUMLAH HARGA BAHAN 419,590.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 479,890.00
E Overhead & Profit 15.00% 71,983.50
F Harga Satuan Pekerjaan (D+E) 551,873.50

III - 28
A. 2.2.1.3. (K3) Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang kayu L.02 OH 0.300 100,000.00 30,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 50,300.00
B BAHAN
Dolken kayu f Batang 1.000 62,500.00 62,500.00
8-10/400 cm
Semen portland Kg 2.000 1,400.00 2,800.00
Kawat duri M’ 25.000 14,700.00 367,500.00
Pasir beton m3 0.005 231,000.00 1,155.00
Koral beton m3 0.009 200,000.00 1,800.00
Paku biasa 2” – 5” Kg 0.060 18,000.00 1,080.00
JUMLAH HARGA BAHAN 374,335.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 424,635.00


E Overhead & Profit 15.00% 63,695.25
F Harga Satuan Pekerjaan (D+E) 488,330.25

A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 19,600.00
B BAHAN
Kayu balok 5/7 m3 0.012 3,500,000.00 42,000.00
Paku 2''-3'' Kg 0.020 18,000.00 360.00
Kayu papan 3/20 m3 0.007 33,600.00 235.20
JUMLAH HARGA BAHAN 42,595.20
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 62,195.20


E Overhead & Profit 15.00% 9,329.28
F Harga Satuan Pekerjaan (D+E) 71,524.48

A. 2.2.1.5. (K3) Pembuatan 1 m2 kantor sementara lantai plesteran (direksikeet)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 2.000 80,000.00 160,000.00
Tukang kayu L.02 OH 2.000 100,000.00 200,000.00
Tukang batu L.02 OH 1.000 100,000.00 100,000.00
Kepala tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 497,000.00

III - 29
B BAHAN
Dolken kayu Ø Batang 1.250 62,500.00 78,125.00
8-10/400 cm
Kayu (kelas III) m3 0.180 3,500,000.00 630,000.00
Paku biasa Kg 0.080 18,000.00 1,440.00
besi strip Kg 1.100 13,750.00 15,125.00
semen portland Kg 3.000 1,400.00 4,200.00
pasir pasang m3 0.150 207,900.00 31,185.00
pasir beton m3 0.100 231,000.00 23,100.00
koral beton m3 0.150 200,000.00 30,000.00
bata merah bh 30.000 800.00 24,000.00
seng pelat lbr 0.250 38,000.00 9,500.00
jendela naco bh 0.200 3,200.00 640.00
kaca polos m2 0.080 80,000.00 6,400.00
kunci tanam bh 0.150 20,000.00 3,000.00
plywood 4 mm lbr 0.060 106,500.00 6,390.00
JUMLAH HARGA BAHAN 863,105.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,360,105.00


E Overhead & Profit 15.00% 204,015.75
F Harga Satuan Pekerjaan (D+E) 1,564,120.75

A. 2.2.1.6. (K3) Pembuatan 1 m2 rumah jaga (konstruksi kayu )

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang kayu L.02 OH 1.500 100,000.00 150,000.00
Kepala tukang L.03 OH 0.150 105,000.00 15,750.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 251,250.00
B BAHAN
Dolken kayu Ø Batang 3.000 62,500.00 187,500.00
8-10/400 cm
Kayu (kelas III) m3 0.276 3,500,000.00 966,000.00
Paku biasa Kg 0.700 18,000.00 12,600.00
Seng gelombang Kg 1.500 58,900.00 88,350.00
JUMLAH HARGA BAHAN 1,254,450.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,505,700.00


E Overhead & Profit 15.00% 225,855.00
F Harga Satuan Pekerjaan (D+E) 1,731,555.00

A. 2.2.1.7. (K3) Pembuatan 1 m2 gudang semen dan peralatan

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang kayu L.02 OH 2.000 100,000.00 200,000.00
Kepala tukang L.03 OH 0.200 105,000.00 21,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 306,500.00
B BAHAN
Dolken kayu Batang 1.700 62,500.00 106,250.00
diameter 8-10/400 cm
Kayu (kelas III) m3 0.210 3,500,000.00 735,000.00
Paku biasa Kg 0.300 18,000.00 5,400.00

III - 30
Semen Portland Kg 10.500 1,400.00 14,700.00
Pasir beton m3 0.030 231,000.00 6,930.00
Koral beton m3 0.050 200,000.00 10,000.00
Seng gelombang Lbr 1.500 58,900.00 88,350.00
seng pelat Lbr 0.250 43,900.00 10,975.00
JUMLAH HARGA BAHAN 977,605.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,284,105.00


E Overhead & Profit 15.00% 192,615.75
F Harga Satuan Pekerjaan (D+E) 1,476,720.75

A. 2.2.1.8. (K3) Pembuatan 1 m2 bedeng pekerja

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang kayu L.02 OH 2.000 100,000.00 200,000.00
Kepala tukang L.03 OH 0.200 105,000.00 21,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 306,500.00
B BAHAN
Dolken kayu Batang 1.250 62,500.00 78,125.00
diameter 8-10/400 cm
Kayu (kelas III) m3 0.186 3,500,000.00 651,000.00
Paku biasa Kg 0.300 18,000.00 5,400.00
Semen Portland Kg 18.000 1,400.00 25,200.00
Pasir beton m3 0.030 231,000.00 6,930.00
Koral beton m3 0.050 200,000.00 10,000.00
Seng gelombang Lbr 1.500 58,900.00 88,350.00
plywood 4 mm Lbr 1.350 106,500.00 143,775.00
JUMLAH HARGA BAHAN 1,008,780.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,315,280.00


E Overhead & Profit 15.00% 197,292.00
F Harga Satuan Pekerjaan (D+E) 1,512,572.00

A. 2.2.1.9. (K3) Pembersihan 1 m2 lapangan dan perataan

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 13,500.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,500.00


E Overhead & Profit 15.00% 2,025.00
F Harga Satuan Pekerjaan (D+E) 15,525.00

III - 31
A. 2.2.1.10. (K3) Pembuatan 1 m2 steger/perancah dari bambu

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.02 OH 0.050 100,000.00 5,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 15,650.00
B BAHAN
Bambu diameter Batang 1.250 17,000.00 21,250.00
6-8/600 cm
Tali ijuk m3 0.186 192,000.00 35,712.00
JUMLAH HARGA BAHAN 56,962.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 72,612.00


E Overhead & Profit 15.00% 10,891.80
F Harga Satuan Pekerjaan (D+E) 83,503.80

A. 2.2.1.11. Pembuatan 1 buah kotak adukan ukuran 40 cm x 50 cm x 25 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Tukang kayu L.02 OH 0.300 100,000.00 30,000.00
Kepala tukang L.03 OH 0.030 105,000.00 3,150.00
JUMLAH TENAGA KERJA 33,150.00
B BAHAN
Kayu papan kelas m3 0.036 3,500,000.00 126,000.00
III
Kayu balok 5/7 m3 0.014 3,500,000.00 49,000.00
kelas III
Paku biasa kg 0.080 18,000.00 1,440.00
JUMLAH HARGA BAHAN 176,440.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 209,590.00


E Overhead & Profit 15.00% 31,438.50
F Harga Satuan Pekerjaan (D+E) 241,028.50

A. 2.2.1.12. Pembuatan 1 m2 jalan sementara

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 80,550.00
B BAHAN
Batu belah 10/15 cm m3 0.150 225,000.00 33,750.00
Batu pecah mesin 2-3 cm m3 0.090 250,000.00 22,500.00
Pasir pasang m3 0.010 207,900.00 2,079.00
JUMLAH HARGA BAHAN 58,329.00

III - 32
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 138,879.00


E Overhead & Profit 15.00% 20,831.85
F Harga Satuan Pekerjaan (D+E) 159,710.85

A. 2.2.1.13. Pembongkaran 1 m3 beton bertulang

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 13.334 80,000.00 1,066,720.00
Mandor L.04 OH 0.666 110,000.00 73,260.00
JUMLAH TENAGA KERJA 1,139,980.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,139,980.00


E Overhead & Profit 15.00% 170,997.00
F Harga Satuan Pekerjaan (D+E) 1,310,977.00

A. 2.2.1.14. Pembongkaran 1 m3 dinding tembok bata

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.667 80,000.00 533,360.00
Mandor L.04 OH 0.333 110,000.00 36,630.00
JUMLAH TENAGA KERJA 569,990.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 569,990.00


E Overhead & Profit 15.00% 85,498.50
F Harga Satuan Pekerjaan (D+E) 655,488.50

A. 2.2.1.15. Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 0.042 80,000.00 3,360.00
Tukang L.02 0.004 100,000.00 400.00
Kepala Tukang L.03 0.002 105,000.00 210.00
Mandor L.04 0.042 110,000.00 4,620.00
JUMLAH TENAGA KERJA 8,590.00
B BAHAN
Kawat jaring Lbr 0.143 567,000.00 81,307.80
JUMLAH HARGA BAHAN 81,307.80

III - 33
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 89,897.80


E Overhead & Profit 15.00% 13,484.67
F Harga Satuan Pekerjaan (D+E) 103,382.47

A.2.2.1.16. Pemasangan 1 m2 panel beton pracetak 5x50x240 cm untuk pagar

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.375 80,000.00 30,000.00
Tukang L.02 OH 0.125 100,000.00 12,500.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.019 110,000.00 2,090.00
JUMLAH TENAGA KERJA 45,850.00
B BAHAN
Panel beton Lbr 0.986 103,000.00 101,558.00
pracetak
Kolom beton Batang 0.525 175,000.00 91,875.00
pracetak
Semen PC Kg 45.000 1,400.00 63,000.00
Pasir beton m3 0.074 231,000.00 17,094.00
Koral m3 0.146 200,000.00 29,200.00
JUMLAH HARGA BAHAN 302,727.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 348,577.00


E Overhead & Profit 15.00% 52,286.55
F Harga Satuan Pekerjaan (D+E) 400,863.55

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.750 80,000.00 60,000.00
Mandor L.04 OH 0.025 110,000.00 2,750.00
JUMLAH TENAGA KERJA 62,750.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 62,750.00
E Overhead & Profit 15.00% 9,412.50
F Harga Satuan Pekerjaan (D+E) 72,162.50

A.2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.900 80,000.00 72,000.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 76,950.00
B BAHAN

JUMLAH HARGA BAHAN -

III - 34
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 76,950.00
E Overhead & Profit 15.00% 11,542.50
F Harga Satuan Pekerjaan (D+E) 88,492.50

A.2.3.1.3. Menggali 1 m3 tanah biasa sedalam 3 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.050 80,000.00 84,000.00
Mandor L.04 OH 0.067 110,000.00 7,370.00
JUMLAH TENAGA KERJA 91,370.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 91,370.00


E Overhead & Profit 15.00% 13,705.50
F Harga Satuan Pekerjaan (D+E) 105,075.50

A.2.3.1.4. Menggali 1 m3 tanah keras sedalam 1 m

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Mandor L.04 OH 0.032 110,000.00 3,520.00
JUMLAH TENAGA KERJA 83,520.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 83,520.00


E Overhead & Profit 15.00% 12,528.00
F Harga Satuan Pekerjaan (D+E) 96,048.00

A.2.3.1.5. Menggali 1 m3 tanah cadas sedalam 1 m

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Mandor L.04 OH 0.060 110,000.00 6,600.00
JUMLAH TENAGA KERJA 126,600.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 126,600.00


E Overhead & Profit 15.00% 18,990.00
F Harga Satuan Pekerjaan (D+E) 145,590.00

III - 35
A.2.3.1.6. Menggali 1 m3 tanah lumpur sedalam 1 m

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 100,950.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,950.00


E Overhead & Profit 15.00% 15,142.50
F Harga Satuan Pekerjaan (D+E) 116,092.50

A.2.3.1.7. Pengerjaan stripping 1 m2 tanah tebing setinggi 1 meter

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 80,000.00 4,000.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 4,550.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,550.00
E Overhead & Profit 15.00% 682.50
F Harga Satuan Pekerjaan (D+E) 5,232.50

A.2.3.1.8. (K3) Pembuangan 1 m3 tanah sejauh 30 meter

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.330 80,000.00 26,400.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 27,500.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 27,500.00
E Overhead & Profit 15.00% 4,125.00
F Harga Satuan Pekerjaan (D+E) 31,625.00

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 80,000.00 40,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 45,500.00

III - 36
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 45,500.00
E Overhead & Profit 15.00% 6,825.00
F Harga Satuan Pekerjaan (D+E) 52,325.00

A.2.3.1.10. (K3) Pemadatan tanah 1 m3 tanah ( per 20 cm)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 80,000.00 40,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 45,500.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 45,500.00
E Overhead & Profit 15.00% 6,825.00
F Harga Satuan Pekerjaan (D+E) 52,325.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 25,100.00
B BAHAN
Pasir urug 1.200 173,300.00 207,960.00
JUMLAH HARGA BAHAN 207,960.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 233,060.00
E Overhead & Profit 15.00% 34,959.00
F Harga Satuan Pekerjaan (D+E) 268,019.00

A.2.3.1.12. Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7TL

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.800 80,000.00 64,000.00
Tukang L.02 OH 0.400 100,000.00 40,000.00
Kepala Tukang L.03 OH 0.040 105,000.00 4,200.00
Mandor L.04 OH 0.080 110,000.00 8,800.00
JUMLAH TENAGA KERJA 117,000.00
B BAHAN
Kapur Padam/bakar m3 0.135 70,000.00 9,450.00
Pasir Pasang m3 0.400 207,900.00 83,160.00
Tanah Liat m3 0.948 100,000.00 94,800.00
JUMLAH HARGA BAHAN 187,410.00

III - 37
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 304,410.00


E Overhead & Profit 15.00% 45,661.50
F Harga Satuan Pekerjaan (D+E) 350,071.50

A.2.3.1.13. Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk bidang resapan

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 13,650.00
B BAHAN
Ijuk m3 6.000 12,000.00 72,000.00
JUMLAH HARGA BAHAN 72,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 85,650.00
E Overhead & Profit 15.00% 12,847.50
F Harga Satuan Pekerjaan (D+E) 98,497.50

A.2.3.1.14. Pengurugan 1 m3 sirtu padat

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Mandor L.04 OH 0.025 110,000.00 2,750.00
JUMLAH TENAGA KERJA 22,750.00
B BAHAN
Sirtu m3 1.200 173,300.00 207,960.00
JUMLAH HARGA BAHAN 207,960.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 230,710.00


E Overhead & Profit 15.00% 34,606.50
F Harga Satuan Pekerjaan (D+E) 265,316.50

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI

A.3.2.1.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Semen Portland Kg 202.000 1,400.00 282,800.00
Pasir pasang m3 0.485 207,900.00 100,831.50
JUMLAH HARGA BAHAN 653,631.50

III - 38
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 864,756.50
E Overhead & Profit 15.00% 129,713.48
F Harga Satuan Pekerjaan (D+E) 994,469.98

A.3.2.1.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Semen Portland Kg 163.000 1,400.00 228,200.00
Pasir pasang m3 0.520 207,900.00 108,108.00
JUMLAH HARGA BAHAN 606,308.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 817,433.00
E Overhead & Profit 15.00% 122,614.95
F Harga Satuan Pekerjaan (D+E) 940,047.95

A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Semen Portland Kg 136.000 1,400.00 190,400.00
Pasir pasang m3 0.544 207,900.00 113,097.60
JUMLAH HARGA BAHAN 573,497.60
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 784,622.60
E Overhead & Profit 15.00% 117,693.39
F Harga Satuan Pekerjaan (D+E) 902,315.99

A.3.2.1.4. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00

III - 39
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Semen Portland Kg 117.000 1,400.00 163,800.00
Pasir pasang m3 0.561 207,900.00 116,631.90
JUMLAH HARGA BAHAN 550,431.90
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 761,556.90
E Overhead & Profit 15.00% 114,233.54
F Harga Satuan Pekerjaan (D+E) 875,790.44

A.3.2.1.5. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 8PP

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Semen Portland Kg 91.000 1,400.00 127,400.00
Pasir pasang m3 0.584 207,900.00 121,413.60
JUMLAH HARGA BAHAN 518,813.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 729,938.60


E Overhead & Profit 15.00% 109,490.79
F Harga Satuan Pekerjaan (D+E) 839,429.39

A.3.2.1.6. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 1KP : 2PP

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Kapur (bakar) m3 0.170 70,000.00 11,900.00
Semen Portland kg 0.170 1,400.00 238.00
Pasir pasang m3 0.340 207,900.00 70,686.00
JUMLAH HARGA BAHAN 352,824.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 563,949.00


E Overhead & Profit 15.00% 84,592.35
F Harga Satuan Pekerjaan (D+E) 648,541.35

A.3.2.1.7. Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 3 KP : 10 PP

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00

III - 40
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Semen Portland Kg 61.000 1,400.00 85,400.00
Kapur m3 0.147 70,000.00 10,290.00
Pasir pasang m3 0.492 207,900.00 102,286.80
JUMLAH HARGA BAHAN 467,976.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 679,101.80


E Overhead & Profit 15.00% 101,865.27
F Harga Satuan Pekerjaan (D+E) 780,967.07

A.3.2.1.8. Pemasangan 1 m3 pondasi batu belah campuran ¼ SP : 1 KP : 4PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Semen Portland Kg 41.000 1,400.00 57,400.00
Kapur m3 0.131 70,000.00 9,170.00
Pasir pasang m3 0.523 207,900.00 108,731.70
JUMLAH HARGA BAHAN 445,301.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 656,426.70


E Overhead & Profit 15.00% 98,464.01
F Harga Satuan Pekerjaan (D+E) 754,890.71

A.3.2.1.9. (K3) Pemasangan 1 m3 batu kosong (anstamping)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.780 80,000.00 62,400.00
Tukang batu L.02 OH 0.390 100,000.00 39,000.00
Kepala tukang L.03 OH 0.039 105,000.00 4,095.00
Mandor L.04 OH 0.039 110,000.00 4,290.00
JUMLAH TENAGA KERJA 109,785.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Pasir urug m3 0.432 173,300.00 74,865.60
JUMLAH HARGA BAHAN 344,865.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 454,650.60


E Overhead & Profit 15.00% 68,197.59
F Harga Satuan Pekerjaan (D+E) 522,848.19

III - 41
A.3.2.1.10. Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 3.400 80,000.00 272,000.00
Tukang batu L.02 OH 0.850 100,000.00 85,000.00
Kepala tukang L.03 OH 0.085 105,000.00 8,925.00
Mandor L.04 OH 0.170 110,000.00 18,700.00
JUMLAH TENAGA KERJA 384,625.00
B BAHAN
Batu belah m3 0.480 225,000.00 108,000.00
Semen Portland Kg 194.000 1,400.00 271,600.00
Pasir beton m3 0.312 231,000.00 72,072.00
Kerikil m3 0.468 200,000.00 93,600.00
Besi beton Kg 126.000 13,000.00 1,638,000.00
Kawat beton Kg 1.800 20,000.00 36,000.00
JUMLAH HARGA BAHAN 2,219,272.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,603,897.00


E Overhead & Profit 15.00% 390,584.55
F Harga Satuan Pekerjaan (D+E) 2,994,481.55

A.3.2.1.11. Pemasangan 1 m3 pondasi sumuran, diameter 100 cm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 2.400 80,000.00 192,000.00
Tukang batu L.02 OH 0.800 100,000.00 80,000.00
Kepala tukang L.03 OH 0.080 105,000.00 8,400.00
Mandor L.04 OH 0.119 110,000.00 13,090.00
JUMLAH TENAGA KERJA 293,490.00
B BAHAN
Batu belah m3 0.450 225,000.00 101,250.00
Semen Portland Kg 194.000 1,400.00 271,600.00
Pasir beton m3 0.312 231,000.00 72,072.00
Kerikil m3 0.468 200,000.00 93,600.00
JUMLAH HARGA BAHAN 538,522.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 832,012.00


E Overhead & Profit 15.00% 124,801.80
F Harga Satuan Pekerjaan (D+E) 956,813.80

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 Mpa (sama dengan K 100), setara dengan beton rabat

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
Semen Portland kg 247.000 1,400.00 345,800.00
Pasir beton kg 869.000 165.00 143,385.00

III - 42
Kerikil (Maks 30 kg 999.000 185.19 185,000.00
mm)/menggunakan bt.pecah
mesin 2-3
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 684,935.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 856,505.00


E Overhead & Profit 15.00% 128,475.75
F Harga Satuan Pekerjaan (D+E) 984,980.75

A.4.1.1.2 Membuat 1 m3 beton mutu f’c = 9,8 Mpa (sama dengan K-125)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
1. Semen kg 276.000 1,400.00 386,400.00
Portland
2. Pasir beton kg 828.000 165.00 136,620.00
3. Kerikil kg 1,012.000 185.19 187,407.41
(Maks 30mm)
4. Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 721,177.41
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 892,747.41


E Overhead & Profit 15.00% 133,912.11
F Harga Satuan Pekerjaan (D+E) 1,026,659.52

A.4.1.1.3 Membuat 1 m3 beton mutu f’c = 12,2 Mpa (sama denga K 150)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
Semen portland kg 299.000 1,400.00 418,600.00
Pasir beton kg 799.000 165.00 131,835.00
Kerikil (Maks 30 mm) kg 1,017.000 185.19 188,333.33
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 749,518.33

III - 43
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 921,088.33


E Overhead & Profit 15.00% 138,163.25
F Harga Satuan Pekerjaan (D+E) 1,059,251.58
CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
1 MPA = 13.51kg/cm2

A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump (3-6) cm, w/c = 0,87

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Tukang batu L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.060 110,000.00 6,600.00
JUMLAH TENAGA KERJA 124,700.00
B BAHAN
Semen Portland kg 230.000 1,400.00 322,000.00
Pasir beton kg 893.000 165.00 147,345.00
Kerikil kg 1,027.000 148.15 152,148.15
(Maks 30 mm)/bukan bt.pecah 2-
3
Air Liter 200.000 50.00 10,000.00
JUMLAH HARGA BAHAN 631,493.15
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 756,193.15
E Overhead & Profit 15.00% 113,428.97
F Harga Satuan Pekerjaan (D+E) 869,622.12

A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa, slump (120 ± 20) mm (sama dengan K 175)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
Semen Portland kg 326.000 1,400.00 456,400.00
Pasir beton kg 760.000 165.00 125,400.00
Kerikil (Maks kg 1,029.000 185.19 190,555.56
30mm)/menggunakan bt.pecah 2-
3
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 783,105.56
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 954,675.56


E Overhead & Profit 15.00% 143,201.33
F Harga Satuan Pekerjaan (D+E) 1,097,876.89

III - 44
A.4.1.1.6 Membuat 1 m3 beton mutu f’c = 16,9 Mpa (sama dengan K 220)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
Semen Portland kg 352.000 1,400.00 492,800.00
Pasir beton kg 731.000 165.00 120,615.00
Kerikil (Maks kg 1,031.000 185.19 190,925.93
30mm)
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 815,090.93
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 986,660.93


E Overhead & Profit 15.00% 147,999.14
F Harga Satuan Pekerjaan (D+E) 1,134,660.06

A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 19,3 Mpa (sama dengan K 225)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
Semen Portland kg 371.000 1,400.00 519,400.00
Pasir beton kg 698.000 165.00 115,170.00
Kerikil (Maks kg 1,047.000 185.19 193,888.89
30mm)
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 839,208.89
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,010,778.89


E Overhead & Profit 15.00% 151,616.83
F Harga Satuan Pekerjaan (D+E) 1,162,395.72

A.4.1.1.8. Membuat 1 m3 beton mutu f’c = 21,7 Mpa (sama dengan K 250)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
Semen Portland kg 384.000 1,400.00 537,600.00
Pasir beton kg 692.000 165.00 114,180.00

III - 45
Kerikil kg 1,039.000 185.19 192,407.41
(Maksimum
30mm)
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 854,937.41
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,026,507.41


E Overhead & Profit 15.00% 153,976.11
F Harga Satuan Pekerjaan (D+E) 1,180,483.52

A.4.1.1.9. Membuat 1 m3 beton mutu f’c = 24,0 Mpa (sama dengan K 325)

Harga Jumlah
Uraian Kode Satuan Koefisien Satuan Harga
No (Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
Semen Portland kg 406.000 1,400.00 568,400.00
Pasir beton kg 684.000 165.00 112,860.00
Kerikil (Maks kg 1,026.000 185.19 190,000.00
30mm)
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 882,010.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,053,580.00


E Overhead & Profit 15.00% 158,037.00
F Harga Satuan Pekerjaan (D+E) 1,211,617.00

A.4.1.1.10. Membuat 1 m3 beton mutu f’c = 26,4 Mpa (sama dengan K 350)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 80,000.00 132,000.00
Tukang batu L.02 OH 0.275 100,000.00 27,500.00
Kepala tukang L.03 OH 0.028 105,000.00 2,940.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 171,570.00
B BAHAN
Semen Portland kg 413.000 1,400.00 578,200.00
Pasir beton kg 681.000 165.00 112,365.00
Kerikil (Maks kg 1,021.000 185.19 189,074.07
30mm)
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 890,389.07
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,061,959.07


E Overhead & Profit 15.00% 159,293.86
F Harga Satuan Pekerjaan (D+E) 1,221,252.94

III - 46
A.4.1.1.11. Membuat 1 m3 beton mutu f’c = 28,8 Mpa (sama dengan K 375)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 2.100 80,000.00 168,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.105 110,000.00 11,550.00
JUMLAH TENAGA KERJA 218,225.00
B BAHAN
Semen Portland kg 439.000 1,400.00 614,600.00
Pasir beton kg 670.000 165.00 110,550.00
Kerikil (Maks 30 kg 1,006.000 185.19 186,296.30
mm)
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 922,196.30
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,140,421.30


E Overhead & Profit 15.00% 171,063.19
F Harga Satuan Pekerjaan (D+E) 1,311,484.49

A.4.1.1.12. Membuat 1 m3 beton mutu f’c = 31,2 MPa, slump (120 ± 20) mm (sama dengan K 425)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 2.100 80,000.00 168,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.105 110,000.00 11,550.00
JUMLAH TENAGA KERJA 218,225.00
B BAHAN
Semen Portland kg 448.000 1,400.00 627,200.00
Pasir beton kg 667.000 165.00 110,055.00
Kerikil (Maks kg 1,000.000 185.19 185,185.19
30mm)
Air Liter 215.000 50.00 10,750.00
JUMLAH HARGA BAHAN 933,190.19
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,151,415.19
E Overhead & Profit 15.00% 172,712.28
F Harga Satuan Pekerjaan (D+E) 1,324,127.46

Untuk pekerjaan beton pracetak yang bisa diangkat 24 jam diperlukan penambahan bahan tambahan
sesuai Tabel berikut:
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.100 80,000.00 168,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.105 110,000.00 11,550.00
JUMLAH TENAGA KERJA 218,225.00
B BAHAN
Semen Portland kg 448.000 1,400.00 627,200.00
Pasir beton kg 667.000 165.00 110,055.00
Kerikil (maksimum kg 1,000.000 185.19 185,185.19
30 mm)
Bahan tambahan Liter 4.500 135,000.00 607,500.00
kimia (efoksi)

III - 47
Air Liter 200.000 50.00 10,000.00
JUMLAH HARGA BAHAN 1,539,940.19
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,758,165.19


E Overhead & Profit 15.00% 263,724.78
F Harga Satuan Pekerjaan (D+E) 2,021,889.96
CATATAN: Bobot isi pasir = 1400 kg/m3, Bobot isi kerikil = 1350 kg/m3, Buckling factor pasir = 20%

A.4.1.1.13 Membuat 1 m3 beton kedap air dengan strorox – 100

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.100 80,000.00 168,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.105 110,000.00 11,550.00
JUMLAH TENAGA KERJA 218,225.00
B BAHAN
Semen Portland kg 400.000 1,400.00 560,000.00
Pasir beton m3 0.480 231,000.00 110,880.00
Kerikil (2cm/3cm) m3 0.800 200,000.00 160,000.00
Strorox – 100 kg 1.200 76,500.00 91,800.00
JUMLAH HARGA BAHAN 922,680.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,140,905.00


E Overhead & Profit 15.00% 171,135.75
F Harga Satuan Pekerjaan (D+E) 1,312,040.75

A.4.1.1.14 Pemasangan 1 m’ PVC Waterstop lebar 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.060 80,000.00 4,800.00
Tukang Batu/Pipa L.02 OH 0.030 100,000.00 3,000.00
Kepala Tukang L.03 OH 0.003 105,000.00 315.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 8,445.00
B BAHAN
Waterstop lebar m 1.050 50,000.00 52,500.00
150 mm
JUMLAH HARGA BAHAN 52,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 60,945.00


E Overhead & Profit 15.00% 9,141.75
F Harga Satuan Pekerjaan (D+E) 70,086.75

A.4.1.1.15 Pemasangan 1 m’ PVC Waterstop lebar 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 80,000.00 5,600.00

III - 48
Tukang Batu/Pipa L.02 OH 0.035 100,000.00 3,500.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 10,290.00
B BAHAN
Waterstop lebar m 1.050 125,000.00 131,250.00
200 mm
JUMLAH HARGA BAHAN 131,250.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 141,540.00


E Overhead & Profit 15.00% 21,231.00
F Harga Satuan Pekerjaan (D+E) 162,771.00

A.4.1.1.16 Membuat 1 m’ PVC Waterstop lebar 230 mm – 320 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 80,000.00 6,400.00
Tukang Batu L.02 OH 0.040 100,000.00 4,000.00
Kepala Tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 11,260.00
B BAHAN
Waterstop lebar m 1.050 115,000.00 120,750.00
230 mm - 320 mm
JUMLAH HARGA BAHAN 120,750.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 132,010.00


E Overhead & Profit 15.00% 19,801.50
F Harga Satuan Pekerjaan (D+E) 151,811.50

A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 80,000.00 5,600.00
Tukang besi L.02 OH 0.070 100,000.00 7,000.00
Kepala tukang L.03 OH 0.007 105,000.00 735.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 13,775.00
B BAHAN
Besi beton kg 10.500 13,000.00 136,500.00
(polos/ulir)
Kawat beton kg 0.150 20,000.00 3,000.00
JUMLAH HARGA BAHAN 139,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 153,275.00


E Overhead & Profit 15.00% 22,991.25
F Harga Satuan Pekerjaan (D+E) 176,266.25

III - 49
A.4.1.1.18 Pemasangan 10 kg kabel prategang (prestressed) polos/strands

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 80,000.00 4,000.00
Tukang besi L.02 OH 0.050 100,000.00 5,000.00
Kepala tukang L.03 OH 0.005 105,000.00 525.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 9,855.00
B BAHAN
Besi beton kg 10.500 13,000.00 136,500.00
(polos/ulir)
Kawat beton kg 0.100 20,000.00 2,000.00
JUMLAH HARGA BAHAN 138,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 148,355.00


E Overhead & Profit 15.00% 22,253.25
F Harga Satuan Pekerjaan (D+E) 170,608.25

A.4.1.1.19 Pemasangan 10 kg jaring kawat baja (wiremesh)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 80,000.00 2,000.00
Tukang besi L.02 OH 0.025 100,000.00 2,500.00
Kepala tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 7,235.00
B BAHAN
Jaring kawat kg 10.200 9,176.24 93,597.67
baja dilas
Kawat beton kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 94,597.67
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 101,832.67


E Overhead & Profit 15.00% 15,274.90
F Harga Satuan Pekerjaan (D+E) 117,107.57

A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting untuk pondasi

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 80,000.00 41,600.00
Tukang kayu L.02 OH 0.260 100,000.00 26,000.00
Kepala tukang L.03 OH 0.026 105,000.00 2,730.00
Mandor L.04 OH 0.026 110,000.00 2,860.00
JUMLAH TENAGA KERJA 73,190.00
B BAHAN
Kayu kelas III m3 0.040 3,500,000.00 140,000.00
Paku 5 – 10 cm kg 0.300 18,000.00 5,400.00
Minyak bekisting Liter 0.100 10,000.00 1,000.00
JUMLAH HARGA BAHAN 146,400.00

III - 50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 219,590.00


E Overhead & Profit 15.00% 32,938.50
F Harga Satuan Pekerjaan (D+E) 252,528.50

A.4.1.1.21 (K3) Pemasangan 1 m2 bekisting untuk sloof

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.520 80,000.00 41,600.00
Tukang kayu L.02 OH 0.260 100,000.00 26,000.00
Kepala tukang L.03 OH 0.026 105,000.00 2,730.00
Mandor L.04 OH 0.026 110,000.00 2,860.00
JUMLAH TENAGA KERJA 73,190.00
B BAHAN
Kayu kelas III m3 0.045 3,500,000.00 157,500.00
Paku 5 cm – 10 cm kg 0.300 18,000.00 5,400.00
Minyak bekisting Liter 0.100 10,000.00 1,000.00
JUMLAH HARGA BAHAN 163,900.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,090.00


E Overhead & Profit 15.00% 35,563.50
F Harga Satuan Pekerjaan (D+E) 272,653.50

A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.660 80,000.00 52,800.00
Tukang kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala tukang L.03 OH 0.033 105,000.00 3,465.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 92,895.00
B BAHAN
Kayu kelas III m3 0.040 3,500,000.00 140,000.00
Paku 5 cm – 12 cm kg 0.400 18,000.00 7,200.00
Minyak bekisting Liter 0.200 10,000.00 2,000.00
Balok kayu kelas II m3 0.015 5,000,000.00 75,000.00
Plywood tebal 9 Lbr 0.350 106,500.00 37,275.00
mm
Dolken kayu f 8- Batang 2.000 62,500.00 125,000.00
10cm –panj 4 m
JUMLAH HARGA BAHAN 386,475.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 479,370.00


E Overhead & Profit 15.00% 71,905.50
F Harga Satuan Pekerjaan (D+E) 551,275.50

III - 51
A.4.1.1.23 (K3) Pemasangan 1 m2 bekisting untuk balok

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.660 80,000.00 52,800.00
Tukang kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala tukang L.03 OH 0.033 105,000.00 3,465.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 92,895.00
B BAHAN
Kayu kelas III m3 0.040 3,500,000.00 140,000.00
Paku 5 cm – 12 cm kg 0.400 18,000.00 7,200.00
Minyak bekisting Liter 0.200 10,000.00 2,000.00
Balok kayu kelas II m3 0.018 5,000,000.00 90,000.00
Plywood tebal 9 mm Lbr 0.350 106,500.00 37,275.00
Dolken kayu 62,500.00 125,000.00
f (8–10) cm Batang 2.000
panjang 4 m
JUMLAH HARGA BAHAN 401,475.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 494,370.00
E Overhead & Profit 15.00% 74,155.50
F Harga Satuan Pekerjaan (D+E) 568,525.50

A.4.1.1.24 (K3) Pemasangan 1 m2 bekisting untuk lantai

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.660 80,000.00 52,800.00
Tukang kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala tukang L.03 OH 0.033 105,000.00 3,465.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 92,895.00
B BAHAN
Kayu kelas III m3 0.040 3,500,000.00 140,000.00
Paku 5 cm – 12 cm kg 0.400 18,000.00 7,200.00
Minyak bekisting Liter 0.200 10,000.00 2,000.00
Balok kayu kelas II m3 0.015 5,000,000.00 75,000.00
Plywood tebal 9 mm Lbr 0.350 106,500.00 37,275.00
Dolken kayu galam, 62,500.00 375,000.00
(8–10) cm panjang Batang 6.000
4m
JUMLAH HARGA BAHAN 636,475.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 729,370.00
E Overhead & Profit 15.00% 109,405.50
F Harga Satuan Pekerjaan (D+E) 838,775.50

A.4.1.1.25 (K3) Pemasangan 1 m2 bekisting untuk dinding

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.0 OH 0.660 80,000.00 52,800.00
Tukang kayu 1
L.0 OH 0.330 100,000.00 33,000.00
Kepala tukang 2
L.0 OH 0.033 105,000.00 3,465.00
Mandor 3
L.0 OH 0.033 110,000.00 3,630.00
4 JUMLAH TENAGA KERJA 92,895.00
B BAHAN
Kayu kelas III m3 0.030 3,500,000.00 105,000.00

III - 52
Paku 5 cm – 12 cm kg 0.400 18,000.00 7,200.00
Minyak bekisting Liter 0.200 10,000.00 2,000.00
Balok kayu kelas II m3 0.020 5,000,000.00 100,000.00
Plywood tebal 9 mm Lbr 0.350 106,500.00 37,275.00
Dolken kayu , f 8– 62,500.00 187,500.00
Batang 3.000
10 cm, panj4 m
Penjaga jarak bekisting/spacer 18,000.00 72,000.00
(dari besi/baut) Buah 4.000

JUMLAH HARGA BAHAN 510,975.00


C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 603,870.00
E Overhead & Profit 15.00% 90,580.50
F Harga Satuan Pekerjaan (D+E) 694,450.50

A.4.1.1.26 (K3) Pemasangan 1 m2 bekisting untuk tangga

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.660 80,000.00 52,800.00
Tukang kayu L.02 OH 0.330 100,000.00 33,000.00
Kepala tukang L.03 OH 0.033 105,000.00 3,465.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 92,895.00
B BAHAN
Kayu kelas III m3 0.030 3,500,000.00 105,000.00
Paku 5 cm – 12 cm kg 0.400 18,000.00 7,200.00
Minyak bekisting Liter 0.150 10,000.00 1,500.00
Balok kayu kelas II m3 0.015 5,000,000.00 75,000.00
Plywood tebal 9 mm Lbr 0.350 106,500.00 37,275.00
Dolken kayu, Ø 8– 62,500.00 125,000.00
Batang 2.000
10 cm,panjang 4 m
JUMLAH HARGA BAHAN 350,975.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 443,870.00
E Overhead & Profit 15.00% 66,580.50
F Harga Satuan Pekerjaan (D+E) 510,450.50

A.4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.02 OH 0.050 100,000.00 5,000.00
Kepala tukang L.03 OH 0.005 105,000.00 525.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 18,405.00
B BAHAN
Kayu kelas III (papan) m3 0.026 3,500,000.00 92,400.00
Paku 5 cm – 12 cm kg 0.600 18,000.00 10,800.00
Dolken kayu , f 8–10 panjang 4m 62,500.00 31,250.00
Batang 0.500

JUMLAH HARGA BAHAN 134,450.00


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 152,855.00


E Overhead & Profit 15.00% 22,928.25
F Harga Satuan Pekerjaan (D+E) 175,783.25

III - 53
A.4.1.1.35 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.180 80,000.00 14,400.00
Tukang batu L.02 OH 0.020 100,000.00 2,000.00
Tukang kayu L.02 OH 0.020 100,000.00 2,000.00
Tukang besi L.02 OH 0.020 100,000.00 2,000.00
Kepala tukang L.03 OH 0.006 105,000.00 630.00
Mandor L.04 OH 0.009 110,000.00 990.00
JUMLAH TENAGA KERJA 22,020.00
B BAHAN
Kayu kelas III m3 0.002 3,500,000.00 7,000.00
Paku 5 cm – 12 cm kg 0.010 18,000.00 180.00
Besi beton polos kg 3.000 13,000.00 39,000.00
Kawat beton kg 0.450 20,000.00 9,000.00
Semen Portland kg 4.000 1,400.00 5,600.00
Pasir Beton m3 0.006 231,000.00 1,386.00
Kerikil m3 0.009 200,000.00 1,800.00
JUMLAH HARGA BAHAN 63,966.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 85,986.00


E Overhead & Profit 15.00% 12,897.90
F Harga Satuan Pekerjaan (D+E) 98,883.90

A.4.1.1.36 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.297 80,000.00 23,760.00
Tukang batu L.02 OH 0.033 100,000.00 3,300.00
Tukang kayu L.02 OH 0.033 100,000.00 3,300.00
Tukang besi L.02 OH 0.033 100,000.00 3,300.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,360.00
B BAHAN
Kayu kelas III m3 0.003 3,500,000.00 10,500.00
Paku 5 cm – 12 cm kg 0.020 18,000.00 360.00
Besi beton polos kg 3.600 13,000.00 46,800.00
Kawat beton kg 0.050 20,000.00 1,000.00
Semen Portland kg 5.500 1,400.00 7,700.00
Pasir beton m3 0.009 231,000.00 2,079.00
Kerikil m3 0.015 200,000.00 3,000.00
JUMLAH HARGA BAHAN 71,439.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 107,799.00
E Overhead & Profit 15.00% 16,169.85
F Harga Satuan Pekerjaan (D+E) 123,968.85

III - 54
A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
Untuk produksi pracetak bisa dilakukan dipabrik (cor di plant) atau di lapangan (cast in place). Indeks yang ada dalam pedoman ini hanya
untuk pekerjaan produksi yang dilakukan di lapangan, terutama untuk analisa cetakan (bekisting) pracetak baik untuk komponen kolom, balok
dan pelat.

A.4.1.2.1. (K3) Pembuatan 1 m2 lahan produksi tebal 8 cm beton f’c 14,5 MPa, slump (120 ± 20) mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.132 80,000.00 10,560.00
Tukang batu L.02 OH 0.022 100,000.00 2,200.00
Kepala tukang L.03 OH 0.002 105,000.00 210.00
Mandor L.04 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 13,740.00
B BAHAN
Semen PC Kg 26.080 1,400.00 36,512.00
Pasir beton Kg 60.800 165.00 10,032.00
Kerikil (menggunakan bt. Pecah 2- Kg 82.320 185.19 15,244.44
3)
Air L 17.200 50.00 860.00
JUMLAH HARGA BAHAN 62,648.44
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 76,388.44


E Overhead & Profit 15.00% 11,458.27
F Harga Satuan Pekerjaan (D+E) 87,846.71

A.4.1.2.2. (K3) Pembuatan 1 m2 lahan produksi tebal 10 cm beton f’c 14,5 MPa, slump (120 ± 20) mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.165 80,000.00 13,200.00
Tukang batu L.02 OH 0.028 100,000.00 2,800.00
Kepala tukang L.03 OH 0.003 105,000.00 315.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 17,195.00
B BAHAN
Semen PC Kg 32.600 1,400.00 45,640.00
Pasir beton Kg 76.000 165.00 12,540.00
Kerikil (maks 30mm) Kg 102.900 185.19 19,055.56
Air L 21.500 50.00 1,075.00
JUMLAH HARGA BAHAN 78,310.56
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 95,505.56


E Overhead & Profit 15.00% 14,325.83
F Harga Satuan Pekerjaan (D+E) 109,831.39

A.4.1.2.3. (K3) Pembuatan 1 m2 lahan produksi tebal 12 cm beton f’c 14,5 MPa, slump (120 ± 20) mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.198 80,000.00 15,840.00
Tukang batu L.02 OH 0.033 100,000.00 3,300.00

III - 55
Kepala tukang L.03 OH 0.003 105,000.00 315.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 20,555.00
B BAHAN
Semen PC Kg 39.120 1,400.00 54,768.00
Pasir beton Kg 91.200 165.00 15,048.00
Kerikil (maks 30mm) Kg 123.480 185.19 22,866.67
Air L 25.800 50.00 1,290.00
JUMLAH HARGA BAHAN 93,972.67
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 114,527.67


E Overhead & Profit 15.00% 17,179.15
F Harga Satuan Pekerjaan (D+E) 131,706.82

A.4.1.2.4. (K3) Pembuatan 1 m2 lahan produksi tebal 15 cm beton f’c 14,5 MPa, slump (120 ± 20) mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.248 80,000.00 19,840.00
Tukang batu L.02 OH 0.041 100,000.00 4,100.00
Kepala tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 25,790.00
B BAHAN
Semen PC Kg 48.900 1,400.00 68,460.00
Pasir beton Kg 114.000 165.00 18,810.00
Kerikil (maks 30 mm) Kg 154.350 185.19 28,583.33
Air L 32.250 50.00 1,612.50
JUMLAH HARGA BAHAN 117,465.83
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 143,255.83
E Overhead & Profit 15.00% 21,488.38
F Harga Satuan Pekerjaan (D+E) 164,744.21

A.4.1.2.5. Pembuatan 1 m2 bekisting untuk pelat beton pracetak ( 5 kali pakai)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.007 80,000.00 560.00
Tukang kayu L.02 OH 0.076 100,000.00 7,600.00
Kepala tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 9,110.00
B BAHAN
Lantai kerja t=10cm m3 0.008 869,622.12 6,956.98
Besi hollow (50 x 50 7,500.00 70,455.00
Kg 9.394
x 3) mm
Kayu kaso 5/7 (lebar 5 cm, tinggi 6,000,000.00 30,000.00
7 m3 0.005
cm)
Phenol film 12 mm Lbr 0.080 245,000.00 19,600.00
Minyak cetakan
L 0.200 10,000.00 2,000.00
(bekisting)
Dinabolt Ø 12mm
buah 3.882 2,545.00 9,879.69
(10 s.d.15 cm)
JUMLAH HARGA BAHAN 138,891.67

III - 56
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 148,001.67
E Overhead & Profit 15.00% 22,200.25
F Harga Satuan Pekerjaan (D+E) 170,201.92

A.4.1.2.6 Pembuatan 1 m2 bekisting untuk balok beton pracetak (10-12 kali pakai)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.004 80,000.00 320.00
Tukang kayu L.02 OH 0.038 100,000.00 3,800.00
Kepala tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 4,650.00
B BAHAN
Kayu kaso 5/7 (lebar 5 cm, tinggi m3 0.005 6,000,000.00 30,000.00
7 cm)
Phenol film 12 mm Lbr 0.043 245,000.00 10,535.00
Minyak cetakan L 0.200 10,000.00 2,000.00
(bekisting)
Paku (5 s.d.7) cm kg 0.046 18,000.00 828.00
Dinabolt Ø 12 mm buah 0.693 2,545.00 1,763.69
(10 s.d.15 cm)
JUMLAH HARGA BAHAN 45,126.69
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 49,776.69
E Overhead & Profit 15.00% 7,466.50
F Harga Satuan Pekerjaan (D+E) 57,243.19

A.4.1.2.7. Pembuatan 1 m2 bekisting untuk kolom beton pracetak (10-12 kali pakai)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.004 80,000.00 320.00
Tukang kayu L.02 OH 0.038 100,000.00 3,800.00
Kepala tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 4,650.00
B BAHAN
Kayu kaso 5/7 (lebar 5 m3 0.004 6,000,000.00 24,000.00
cm, tinggi 7 cm)
Phenol film 12 mm Lbr 0.048 245,000.00 11,760.00
Minyak cetakan L 0.200 10,000.00 2,000.00
(bekisting)
Paku (5 s.d.7) cm Kg 0.046 18,000.00 828.00
Dinabolt Ø 12 mm buah 0.693 2,545.00 1,763.69
(10-15cm)
JUMLAH HARGA BAHAN 40,351.69
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 45,001.69
E Overhead & Profit 15.00% 6,750.25
F Harga Satuan Pekerjaan (D+E) 51,751.94
A.4.1.2.8.
Pemasangan dan membuka bekisting 1 buah komponen pelat beton pracetak

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.053 80,000.00 4,240.00

III - 57
Tukang kayu L.02 OH 0.018 100,000.00 1,800.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 6,590.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 6,590.00
E Overhead & Profit 15.00% 988.50
F Harga Satuan Pekerjaan (D+E) 7,578.50

A.4.1.2.9. Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.089 80,000.00 7,120.00
Tukang kayu L.02 OH 0.030 100,000.00 3,000.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 10,670.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 10,670.00
E Overhead & Profit 15.00% 1,600.50
F Harga Satuan Pekerjaan (D+E) 12,270.50

A.4.1.2.10. Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.071 80,000.00 5,680.00
Tukang kayu L.02 OH 0.024 100,000.00 2,400.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 8,630.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 8,630.00
E Overhead & Profit 15.00% 1,294.50
F Harga Satuan Pekerjaan (D+E) 9,924.50

A.4.1.2.11. Penuangan/menebar beton 1 m3 komponen untuk pelat pracetak

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.064 80,000.00 5,120.00
Tukang batu L.02 OH 0.244 100,000.00 24,400.00
Tukang vibrator L.02 OH 0.128 100,000.00 12,800.00
Kepala tukang L.03 OH 0.034 105,000.00 3,570.00
Mandor L.04 OH 0.073 110,000.00 8,030.00
JUMLAH TENAGA KERJA 53,920.00
B BAHAN
JUMLAH HARGA BAHAN -

III - 58
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 53,920.00
E Overhead & Profit 15.00% 8,088.00
F Harga Satuan Pekerjaan (D+E) 62,008.00

A.4.1.2.12. Penuangan/menebar beton 1 m3 komponen untuk balok pracetak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.069 80,000.00 5,520.00
Tukang batu L.02 OH 0.242 100,000.00 24,200.00
Tukang vibrator L.02 OH 0.138 100,000.00 13,800.00
Kepala tukang L.03 OH 0.037 105,000.00 3,885.00
Mandor L.04 OH 0.073 110,000.00 8,030.00
JUMLAH TENAGA KERJA 55,435.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,435.00


E Overhead & Profit 15.00% 8,315.25
F Harga Satuan Pekerjaan (D+E) 63,750.25

A.4.1.2.13. Penuangan/menebar beton 1 m3 komponen kolom pracetak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.061 80,000.00 4,880.00
Tukang batu L.02 OH 0.213 100,000.00 21,300.00
Tukang vibrator L.02 OH 0.122 100,000.00 12,200.00
Kepala tukang L.03 OH 0.033 105,000.00 3,465.00
Mandor/Supervisor/ L.04 OH 0.073 110,000.00 8,030.00
Penyelia
JUMLAH TENAGA KERJA 49,875.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 49,875.00


E Overhead & Profit 15.00% 7,481.25
F Harga Satuan Pekerjaan (D+E) 57,356.25

A.4.1.2.14. Ereksi 1 buah komponen untuk pelat pracetak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Operator crane L.08 OH 0.067 130,000.00 8,710.00
Pembantu operator 80,000.00 5,360.00
L.09 OH 0.067
crane
Pekerja L.01 OH 0.067 80,000.00 5,360.00
Tukang batu L.02 OH 0.067 100,000.00 6,700.00

III - 59
Tukang ereksi L.02 OH 0.134 100,000.00 13,400.00
Kepala tukang L.03 OH 0.067 105,000.00 7,035.00
Mandor L.04 OH 0.067 110,000.00 7,370.00
JUMLAH TENAGA KERJA 53,935.00
B BAHAN
Solar L 6.676 6,150.00 41,057.40
JUMLAH HARGA BAHAN 41,057.40
C PERALATAN
Sewa crane unit hari 0.067 3,900,000.00 261,300.00
Sewa pipe support buah 1.100 297,000.00 326,700.00
hari
JUMLAH HARGA ALAT 588,000.00

D Jumlah (A+B+C) 682,992.40


E Overhead & Profit 15.00% 102,448.86
F Harga Satuan Pekerjaan (D+E) 785,441.26

Indeks kenaikan lantai ereksi komponen untuk pelat pracetak


Indeks kenaikan lantai Indeks
La ereksi pelat Lantai kenaika
nt n lantai
ai ereksi
pelat
1 1 13 1.114
2 1 14 1.134
3 1 15 1.155
4 1 16 1.176
5 1 17 1.197
6 1 18 1.219
7 1 19 1.241
8 1.018 20 1.264
9 1.037 21 1.287
10 1.055 22 1.310
11 1.075 23 1.334
12 1.094 24 1.358

A.4.1.2.15. Ereksi 1 buah komponen untuk balok pracetak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Operator crane L.0 OH 0.061 130,000.00 7,930.00
Pembantu operator crane 8
L.0 OH 0.061 80,000.00 4,880.00
Pekerja 9
L.0 OH 0.061 80,000.00 4,880.00
Tukang batu 1
L.0 OH 0.061 100,000.00 6,100.00
Tukang ereksi 2
L.0 OH 0.122 100,000.00 12,200.00
Kepala tukang 2
L.0 OH 0.061 105,000.00 6,405.00
Mandor 3
L.0 OH 0.061 110,000.00 6,710.00
4 JUMLAH TENAGA KERJA 49,105.00
B BAHAN
Solar L 6.110 6,150.00 37,576.50
JUMLAH HARGA BAHAN 37,576.50
C PERALATAN
Sewa crane unit 0.061 3,900,000.00 237,900.00
hari
Sewa scaffolding unit 1.100 297,000.00 326,700.00
hari
JUMLAH HARGA ALAT 564,600.00

D Jumlah (A+B+C) 651,281.50


E Overhead & Profit 15.00% 97,692.23
F Harga Satuan Pekerjaan (D+E) 748,973.73

III - 60
Indeks kenaikan lantai ereksi komponen untuk balok pracetak
Indeks kenaikan lantai Indeks
La ereksi balok Lantai kenaika
nt n lantai
ai ereksi
balok
1 1 13 1.068
2 1 14 1.080
3 1 15 1.092
4 1 16 1.104
5 1 17 1.116
6 1 18 1.129
7 1 19 1.141
8 1.011 20 1.154
9 1.022 21 1.166
10 1.034 22 1.179
11 1.045 23 1.192
12 1.057 24 1.206

A.4.1.2.16. Ereksi 1 buah komponen untuk kolom pracetak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Operator crane L.08 OH 0.083 130,000.00 10,790.00
Pembantu operator L.09 OH 0.083 80,000.00 6,640.00
crane
Pekerja L.01 OH 0.083 80,000.00 6,640.00
Tukang batu L.02 OH 0.083 100,000.00 8,300.00
Tukang ereksi L.02 OH 0.166 100,000.00 16,600.00
Kepala tukang L.03 OH 0.083 105,000.00 8,715.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 66,815.00
B BAHAN
Solar L 8.277 6,150.00 50,903.55
JUMLAH HARGA BAHAN 50,903.55
C PERALATAN
Sewa crane unit hari 0.083 3,900,000.00 323,700.00
Sewa pipe support buah hari 2.200 297,000.00 653,400.00
JUMLAH HARGA ALAT 977,100.00

D Jumlah (A+B+C) 1,094,818.55


E Overhead & Profit 15.00% 164,222.78
F Harga Satuan Pekerjaan (D+E) 1,259,041.33

Indeks kenaikan lantai ereksi komponen untuk kolom pracetak


Indeks kenaikan lantai Indeks
Lant ereksi kolom Lantai kenaikan
ai lantai
ereksi
1 1 13 1.162
2 1 14 1.191
3 1 15 1.221
4 1 16 1.252
5 1 17 1.284
6 1 18 1.317
7 1 19 1.350
8 1.025 20 1.384
9 1.051 21 1.419
10 1.078 22 1.455
11 1.105 23 1.492
12 1.133 24 1.530

III - 61
A.4.1.2.17. Langsir 1 buah komponen untuk pelat pracetak ( ± 20 m)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Operator crane L.08 OH 0.019 130,000.00 2,470.00
Pembantu operator L.09 OH 0.019 80,000.00 1,520.00
crane
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 100,000.00 3,800.00
JUMLAH TENAGA KERJA 9,310.00
B BAHAN
Solar L 1.897 6,150.00 11,666.55
JUMLAH HARGA BAHAN 11,666.55
C PERALATAN
Sewa crane unit hari 0.019 3,900,000.00 74,100.00
JUMLAH HARGA ALAT 74,100.00

D Jumlah (A+B+C) 95,076.55


E Overhead & Profit 15.00% 14,261.48
F Harga Satuan Pekerjaan (D+E) 109,338.03

A.4.1.2.18. Langsir 1 buah komponen untuk balok pracetak ( ± 20 m)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Operator crane L.08 OH 0.019 130,000.00 2,470.00
Pembantu operator
L.09 OH 0.019 80,000.00 1,520.00
crane
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 100,000.00 3,800.00
JUMLAH TENAGA KERJA 9,310.00
B BAHAN
Solar L 1.897 6,150.00 11,666.55
JUMLAH HARGA BAHAN 11,666.55
C PERALATAN
Sewa crane unit hari 0.019 3,900,000.00 74,100.00
JUMLAH HARGA ALAT 74,100.00

D Jumlah (A+B+C) 95,076.55


E Overhead & Profit 15.00% 14,261.48
F Harga Satuan Pekerjaan (D+E) 109,338.03

A.4.1.2.19. Langsir 1 buah komponen untuk kolom pracetak ( ± 20 m)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Operator crane L.08 OH 0.019 130,000.00 2,470.00
Pembantu operator L.09 OH 0.019 80,000.00 1,520.00
crane
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang batu L.02 OH 0.038 100,000.00 3,800.00
JUMLAH TENAGA KERJA 9,310.00
B BAHAN
Solar L 1.897 6,150.00 11,666.55
JUMLAH HARGA BAHAN 11,666.55

III - 62
C PERALATAN
Sewa crane unit hari 0.019 3,900,000.00 74,100.00
JUMLAH HARGA ALAT 74,100.00

D Jumlah (A+B+C) 95,076.55


E Overhead & Profit 15.00% 14,261.48
F Harga Satuan Pekerjaan (D+E) 109,338.03

A.4.1.2.20. Bahan 1 m3 grout campuran

Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien Harga Satuan
(Rp)
A TENAGA
JUMLAH TENAGA KERJA -
B BAHAN
Semen grout Kg 1,200.000 2,360.00 2,832,000.00
Screening Kg 650.000 200.00 130,000.00
Air L 350.000 50.00 17,500.00
JUMLAH HARGA BAHAN 2,979,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,979,500.00


E Overhead & Profit 15.00% 446,925.00
F Harga Satuan Pekerjaan (D+E) 3,426,425.00

A.4.1.2.21. Bahan 1 m3 grout (tidak campuran)

Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien Harga Satuan
(Rp)
A TENAGA
JUMLAH TENAGA KERJA -
B BAHAN
Semen grout Kg 1,850.000 2,360.00 4,366,000.00
Air L 400.00 50.00 20,000.00
JUMLAH HARGA BAHAN 4,386,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,386,000.00
E Overhead & Profit 15.00% 657,900.00
F Harga Satuan Pekerjaan (D+E) 5,043,900.00

A.4.1.2.22. Upah 1 titik pekerjaan grout pada joint beton pracetak

Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien Harga Satuan
(Rp)
A TENAGA
Tukang batu L.02 OH 0.367 100,000.00 36,700.00
Kepala tukang L.03 OH 0.074 105,000.00 7,770.00
Mandor L.04 OH 0.037 110,000.00 4,070.00
JUMLAH TENAGA KERJA 48,540.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,540.00


E Overhead & Profit 15.00% 7,281.00
F Harga Satuan Pekerjaan (D+E) 55,821.00

III - 63
A.4.1.2.23. Pemasangan 1 titik bekisting joint pracetak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.147 80,000.00 11,760.00
Tukang kayu L.02 OH 0.147 100,000.00 14,700.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 28,585.00
B BAHAN
Kayu kaso 5/7 (lebar m3 0.012 6,000,000.00 72,000.00
5 cm, tinggi 7 cm)
Papan cor (kayu kelas II) m3 0.004 5,000,000.00 20,000.00
Paku (5 s.d.7) cm Kg 0.264 18,000.00 4,752.00
JUMLAH HARGA BAHAN 96,752.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 125,337.00
E Overhead & Profit 15.00% 18,800.55
F Harga Satuan Pekerjaan (D+E) 144,137.55

A.4.1.2.24. Upah 1 titik joint dengan sling

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.220 80,000.00 17,600.00
Tukang kayu L.02 OH 0.022 100,000.00 2,200.00
Tukang besi L.02 OH 0.220 100,000.00 22,000.00
Mandor L.04 OH 0.011 110,000.00 1,210.00
JUMLAH TENAGA KERJA 43,010.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 43,010.00


E Overhead & Profit 15.00% 6,451.50
F Harga Satuan Pekerjaan (D+E) 49,461.50

A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

A.4.2.1.1. Pemasangan 1 kg besi profil

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.060 80,000.00 4,800.00
Tukang las L.03 OH 0.060 100,000.00 6,000.00
konstruksi
Kepala tukang L.03 OH 0.006 105,000.00 630.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 11,760.00
B BAHAN
Besi Profil Kg 1.150 13,750.00 15,812.50
JUMLAH HARGA BAHAN 15,812.50

III - 64
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,572.50


E Overhead & Profit 15.00% 4,135.88
F Harga Satuan Pekerjaan (D+E) 31,708.38

A.4.2.1.2. Pemasangan 1 kg rangka kuda-kuda baja IWF

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.060 80,000.00 4,800.00
Tukang las L.03 OH 0.060 100,000.00 6,000.00
konstruksi
Kepala tukang L.03 OH 0.006 105,000.00 630.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 11,760.00
B BAHAN
Besi baja IWF Kg 1.150 13,750.00 15,812.50
JUMLAH HARGA BAHAN 15,812.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,572.50


E Overhead & Profit 15.00% 4,135.88
F Harga Satuan Pekerjaan (D+E) 31,708.38

A.4.2.1.3. Pengerjaan 100 kg pekerjaan perakitan

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang besi L.03 OH 0.100 100,000.00 10,000.00
konstruksi
Kepala tukang L.03 OH 0.001 105,000.00 105.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 18,655.00
B BAHAN
Solar Liter 1.000 6,150.00 6,150.00
Minyak pelumas Liter 0.100 10,000.00 1,000.00
JUMLAH HARGA BAHAN 7,150.00
C PERALATAN
1. Sewa alat Jam 0.800 115,000.00 92,000.00
JUMLAH HARGA ALAT 92,000.00

D Jumlah (A+B+C) 117,805.00


E Overhead & Profit 15.00% 17,670.75
F Harga Satuan Pekerjaan (D+E) 135,475.75

A.4.2.1.4. Pembuatan 1 m2 pintu besi pelat baja tebal 2 mm rangkap, rangka baja siku

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.050 80,000.00 84,000.00
Tukang las biasa L.03 OH 1.050 100,000.00 105,000.00
Kepala tukang L.03 OH 0.105 105,000.00 11,025.00
Mandor L.04 OH 0.052 110,000.00 5,720.00
JUMLAH TENAGA KERJA 205,745.00

III - 65
B BAHAN
Besi siku L 30.30.3 Kg 15.000 12,100.00 181,500.00
Besi pelat baja Kg 32.800 7,500.00 246,000.00
Kawat las Kg 0.050 27,000.00 1,350.00
JUMLAH HARGA BAHAN 428,850.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 634,595.00


E Overhead & Profit 15.00% 95,189.25
F Harga Satuan Pekerjaan (D+E) 729,784.25

A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)

A TENAGA
Pekerja L.01 OH 0.040 80,000.00 3,200.00
Tukang las (bersertifikat) L.03 OH 0.020 110,000.00 2,200.00

Kepala tukang L.03 OH 0.002 105,000.00 210.00


Mandor L.04 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 5,830.00
B BAHAN
Kawat las listrik Kg 0.400 27,000.00 10,800.00
Solar Liter 0.300 6,150.00 1,845.00
Minyak pelumas Liter 0.040 10,000.00 400.00
JUMLAH HARGA BAHAN 13,045.00
C PERALATAN
Sewa alat Jam 0.170 115,000.00 19,550.00
JUMLAH HARGA ALAT 19,550.00

D Jumlah (A+B+C) 38,425.00


E Overhead & Profit 15.00% 5,763.75
F Harga Satuan Pekerjaan (D+E) 44,188.75

A.4.2.1.6. Pembuatan 1 m2 rangka jendela besi scuare tube

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.650 80,000.00 52,000.00
Tukang las biasa L.03 OH 0.650 100,000.00 65,000.00
Kepala tukang L.03 OH 0.065 105,000.00 6,825.00
Mandor L.04 OH 0.032 110,000.00 3,520.00
JUMLAH TENAGA KERJA 127,345.00
B BAHAN
Besi scuare tube m 4.760 19,025.83 90,562.97
Besi lis kaca (1 x 1) cm m 4.522 14,300.00 64,664.60
Pengelasan cm 20.000 4,418.88 88,377.50
JUMLAH HARGA BAHAN 243,605.07
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 370,950.07


E Overhead & Profit 15.00% 55,642.51
F Harga Satuan Pekerjaan (D+E) 426,592.58

III - 66
A.4.2.1.7. Pemasangan 1 m2 pintu rolling door besi

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Tukang las biasa L.03 OH 1.200 100,000.00 120,000.00
Kepala tukang L.03 OH 0.120 105,000.00 12,600.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 229,260.00
B BAHAN
Pintu gulung besi m2 1.000 1,100,000.00 1,100,000.00
JUMLAH HARGA BAHAN 1,100,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,329,260.00


E Overhead & Profit 15.00% 199,389.00
F Harga Satuan Pekerjaan (D+E) 1,528,649.00

A.4.2.1.8. Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.440 80,000.00 35,200.00
Tukang L.03 OH 0.440 100,000.00 44,000.00
Kepala tukang L.03 OH 0.044 105,000.00 4,620.00
Mandor L.04 OH 0.022 110,000.00 2,420.00
JUMLAH TENAGA KERJA 86,240.00
B BAHAN
Pintu lipat m2 1.000 3,000,000.00 3,000,000.00
JUMLAH HARGA BAHAN 3,000,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 3,086,240.00


E Overhead & Profit 15.00% 462,936.00
F Harga Satuan Pekerjaan (D+E) 3,549,176.00

A.4.2.1.9. Pemasangan 1 m2 sunscreen alluminium

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 80,000.00 6,400.00
Tukang L.03 OH 0.800 100,000.00 80,000.00
Kepala tukang L.03 OH 0.080 105,000.00 8,400.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 95,240.00
B BAHAN
Sunscreen alluminium m2 1.000 385,000.00 385,000.00
JUMLAH HARGA BAHAN 385,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 480,240.00


E Overhead & Profit 15.00% 72,036.00
F Harga Satuan Pekerjaan (D+E) 552,276.00

III - 67
A.4.2.1.10. Pemasangan 1 m2 rolling door alluminium

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang khusus L.03 OH 1.000 100,000.00 100,000.00
alumunium
Kepala tukang L.03 OH 0.100 105,000.00 10,500.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 196,000.00
B BAHAN
Rolling door alluminium m2 1.000 400,000.00 400,000.00
JUMLAH HARGA BAHAN 400,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 596,000.00


E Overhead & Profit 15.00% 89,400.00
F Harga Satuan Pekerjaan (D+E) 685,400.00

A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium


Catatan : untuk pekerjaan ini langsung nge link dari bahan, karena harga bahan merupakan harga terpasang yang telah di tambahkan Overhead & Profit

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.043 80,000.00 3,440.00
Tukang khusus L.03 OH 0.043 100,000.00 4,300.00
alumunium
Kepala tukang L.03 OH 0.004 105,000.00 451.50
Mandor L.04 OH 0.002 110,000.00 231.00
JUMLAH TENAGA KERJA 8,422.50
B BAHAN
Profil alluminium m 1.100 110,000.00 121,000.00
Skrup fixer buah 2.000 500.00 1,000.00
Sealant Tube 0.060 20,000.00 1,200.00
JUMLAH HARGA BAHAN 123,200.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 131,622.50


E Overhead & Profit 15.00% 19,743.38
F Harga Satuan Pekerjaan (D+E) 151,365.88

A.4.2.1.12. Pemasangan 1 m2 pintu alluminium strip lebar 8 cm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.085 80,000.00 6,800.00
Tukang khusus L.03 OH 0.085 100,000.00 8,500.00
alumunium
Kepala tukang L.03 OH 0.009 105,000.00 892.50
Mandor L.04 OH 0.004 110,000.00 462.00
JUMLAH TENAGA KERJA 16,654.50
B BAHAN
Profil alluminium m 4.400 110,000.00 484,000.00
Alluminium strip m 14.600 100,000.00 1,460,000.00
JUMLAH HARGA BAHAN 1,944,000.00

III - 68
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,960,654.50


E Overhead & Profit 15.00% 294,098.18
F Harga Satuan Pekerjaan (D+E) 2,254,752.68

A.4.2.1.13. Pemasangan 1 m2 pintu kaca rangka alluminium

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.085 80,000.00 6,800.00
Tukang khusus L.03 OH 0.085 100,000.00 8,500.00
alumunium
Kepala tukang L.03 OH 0.009 105,000.00 945.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 16,795.00
B BAHAN
Pintu alluminium m 4.400 110,000.00 484,000.00
Profil kaca m 4.500 12,375.00 55,687.50
Sealant Tube 0.270 20,000.00 5,400.00
JUMLAH HARGA BAHAN 545,087.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 561,882.50


E Overhead & Profit 15.00% 84,282.38
F Harga Satuan Pekerjaan (D+E) 646,164.88

A.4.2.1.14. Pemasangan 1 m2 venetions blinds dan vertical blinds

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 80,000.00 28,000.00
Tukang L.03 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 68,655.00
B BAHAN
Venetions blinds dan m2 1.000 106,200.00 106,200.00
vertical blinds (tirai)
JUMLAH HARGA BAHAN 106,200.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 174,855.00


E Overhead & Profit 15.00% 26,228.25
F Harga Satuan Pekerjaan (D+E) 201,083.25

A.4.2.1.15. Pemasangan 1 m2 terali besi strip (2 x 3) mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.670 80,000.00 133,600.00
Tukang las L.03 OH 1.670 100,000.00 167,000.00
Kepala tukang L.03 OH 0.167 105,000.00 17,535.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 327,265.00

III - 69
B BAHAN
Besi strip kg 6.177 13,750.00 84,933.75
Pengelasan cm 27.080 4,418.88 119,663.14
JUMLAH HARGA BAHAN 204,596.89
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 531,861.89


E Overhead & Profit 15.00% 79,779.28
F Harga Satuan Pekerjaan (D+E) 611,641.17

A.4.2.1.16. Pemasangan 1 m2 kawat nyamuk

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang L.03 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 19,600.00
B BAHAN
Kawat nyamuk m2 1.100 250,000.00 275,000.00
Pengelasan cm 11.110 4,418.88 49,093.70
Baja strip (0,2 x 2) cm kg 1.716 18,150.00 31,145.40
JUMLAH HARGA BAHAN 355,239.10
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 374,839.10


E Overhead & Profit 15.00% 56,225.87
F Harga Satuan Pekerjaan (D+E) 431,064.97

A.4.2.1.17. Pemasangan 1 m2 jendela nako & tralis

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 38,210.00
B BAHAN
Jendela nako m2 1.100 168,200.00 185,020.00
(rangka + kaca 5 mm)
Paku skrup buah 10.000 500.00 5,000.00
1 cm – 2,5 cm
Besi strip m 7.000 13,750.00 96,250.00
JUMLAH HARGA BAHAN 286,270.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 324,480.00


E Overhead & Profit 15.00% 48,672.00
F Harga Satuan Pekerjaan (D+E) 373,152.00

III - 70
A.4.2.1.18. Pemasangan 1 m’ talang datar/ jurai seng bjls 28 lebar 90 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 38,210.00
B BAHAN
Seng pelat m 1.050 43,900.00 46,095.00
Paku 1 cm - 2,5 cm kg 0.015 18,000.00 270.00
Papan kayu kelas II
m3 0.019 3,500,000.00 66,500.00
atau III
JUMLAH HARGA BAHAN 112,865.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 151,075.00


E Overhead & Profit 15.00% 22,661.25
F Harga Satuan Pekerjaan (D+E) 173,736.25

A.4.2.1.19 Pemasangan 1 m talang ½ lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang L.03 OH 0.300 100,000.00 30,000.00
Kepala tukang L.03 OH 0.030 105,000.00 3,150.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 46,030.00
B BAHAN
Seng pelat m 1.050 43,900.00 46,095.00
Paku 1 cm – 2,5 cm kg 0.010 18,000.00 180.00
Besi strip kg 0.500 13,750.00 6,875.00
JUMLAH HARGA BAHAN 53,150.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 99,180.00


E Overhead & Profit 15.00% 14,877.00
F Harga Satuan Pekerjaan (D+E) 114,057.00

A.4.2.1.20. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, untuk partisi

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang besi L.02 OH 0.250 100,000.00 25,000.00
Kepala tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 49,055.00
B BAHAN
Rangka metal M1 3.500 19,025.83 66,590.42
hollow 40.40.2 mm

III - 71
Assesoris Ls 1.000 66,590.42 66,590.42
(perkuatan, las dll)
JUMLAH HARGA BAHAN 133,180.83
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 182,235.83


E Overhead & Profit 15.00% 27,335.38
F Harga Satuan Pekerjaan (D+E) 209,571.21

A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, untuk plafon

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 80,000.00 28,000.00
Tukang besi L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 68,655.00
B BAHAN
Rangka metal M1 4.000 19,025.83 76,103.33
hollow 40.40.2 mm
Assesoris 76,103.33 76,103.33
(perkuatan, las Ls 100%xrangka
dll)
JUMLAH HARGA BAHAN 152,206.67
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 220,861.67


E Overhead & Profit 15.00% 33,129.25
F Harga Satuan Pekerjaan (D+E) 253,990.92

A.4.2.1.22. (K3) Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.734 80,000.00 58,720.00
Tukang besi L.02 OH 0.734 100,000.00 73,400.00
Kepala tukang L.03 OH 0.073 105,000.00 7,665.00
Mandor L.04 OH 0.037 110,000.00 4,070.00
JUMLAH TENAGA KERJA 143,855.00
B BAHAN
Baja ringan canai dingin C75 kg 3.065 13,970.00 42,818.05
JUMLAH HARGA BAHAN 42,818.05
C PERALATAN
Peralatan % 0.100 42,818.05 4,281.81
JUMLAH HARGA ALAT 4,281.81

D Jumlah (A+B+C) 190,954.86


E Overhead & Profit 15.00% 28,643.23
F Harga Satuan Pekerjaan (D+E) 219,598.08

III - 72
A.4.2.1.22. (K3) Pemasangan 1 m2 atap jurai rangka atap baja canai dingin profil C75

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.760 80,000.00 60,832.00
Tukang besi L.02 OH 0.760 100,000.00 76,040.00
Kepala tukang L.03 OH 0.076 105,000.00 7,980.00
Mandor L.04 OH 0.038 110,000.00 4,180.00
JUMLAH TENAGA KERJA 149,032.00
B BAHAN
Baja ringan canai 13,970.00 56,578.50
kg 4.050
dingin C75
JUMLAH HARGA BAHAN 56,578.50
C PERALATAN
Peralatan % 0.100 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 205,610.50


E Overhead & Profit 15.00% 30,841.58
F Harga Satuan Pekerjaan (D+E) 236,452.08

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

A. 4.4.1.1. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 2PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang batu L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 110,000.00 3,300.00
JUMLAH TENAGA KERJA 73,400.00
B BAHAN
Bata merah buah 140.000 800.00 112,000.00
Semen Portland Kg 43.500 1,400.00 60,900.00
Pasir pasang m3 0.080 207,900.00 16,632.00
JUMLAH HARGA BAHAN 189,532.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 262,932.00


E Overhead & Profit 15.00% 39,439.80
F Harga Satuan Pekerjaan (D+E) 302,371.80

A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang batu L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 110,000.00 3,300.00
JUMLAH TENAGA KERJA 73,400.00
B BAHAN
Bata merah buah 140.000 800.00 112,000.00
Semen Portland Kg 32.950 1,400.00 46,130.00
Pasir pasang m3 0.091 207,900.00 18,918.90
JUMLAH HARGA BAHAN 177,048.90

III - 73
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 250,448.90


E Overhead & Profit 15.00% 37,567.34
F Harga Satuan Pekerjaan (D+E) 288,016.24

A. 4.4.1.3. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 4PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang batu L.02 OH 0.200 100,000.00 20,000.00
Kepala bukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 110,000.00 3,300.00
JUMLAH TENAGA KERJA 73,400.00
B BAHAN
Bata merah buah 140.000 800.00 112,000.00
Semen Portland Kg 26.550 1,400.00 37,170.00
Pasir Pasang m3 0.093 207,900.00 19,334.70
JUMLAH HARGA BAHAN 168,504.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 241,904.70


E Overhead & Profit 15.00% 36,285.71
F Harga Satuan Pekerjaan (D+E) 278,190.41

A. 4.4.1.4. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang batu L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 110,000.00 3,300.00
JUMLAH TENAGA KERJA 73,400.00
B BAHAN
Bata merah buah 140.000 800.00 112,000.00
Semen Portland Kg 22.200 1,400.00 31,080.00
Pasir pasang m3 0.102 207,900.00 21,205.80
JUMLAH HARGA BAHAN 164,285.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 237,685.80


E Overhead & Profit 15.00% 35,652.87
F Harga Satuan Pekerjaan (D+E) 273,338.67

A. 4.4.1.5 Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal 1 batu campuran 1SP : 6PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang batu L.02 OH 0.200 100,000.00 20,000.00

III - 74
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 110,000.00 3,300.00
JUMLAH TENAGA KERJA 73,400.00
B BAHAN
Bata merah buah 140.000 800.00 112,000.00
Semen Portland Kg 18.500 1,400.00 25,900.00
Pasir pasang m3 0.122 207,900.00 25,363.80
JUMLAH HARGA BAHAN 163,263.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 236,663.80


E Overhead & Profit 15.00% 35,499.57
F Harga Satuan Pekerjaan (D+E) 272,163.37

A. 4.4.1.6 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang batu L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.030 110,000.00 3,300.00
JUMLAH TENAGA KERJA 73,400.00
B BAHAN
Bata merah buah 140.000 800.00 112,000.00
Semen Portland Kg 10.080 1,400.00 14,112.00
Kapur padam m3 0.028 70,000.00 1,925.00
Pasir pasang m3 0.093 207,900.00 19,230.75
JUMLAH HARGA BAHAN 147,267.75
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 220,667.75


E Overhead & Profit 15.00% 33,100.16
F Harga Satuan Pekerjaan (D+E) 253,767.91

A. 4.4.1.7 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 2PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen Portland Kg 18.950 1,400.00 26,530.00
Pasir pasang m3 0.038 207,900.00 7,900.20
JUMLAH HARGA BAHAN 90,430.20
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 127,130.20


E Overhead & Profit 15.00% 19,069.53
F Harga Satuan Pekerjaan (D+E) 146,199.73

III - 75
A. 4.4.1.8 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 3PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen Portland Kg 14.370 1,400.00 20,118.00
Pasir pasang m3 0.040 207,900.00 8,316.00
JUMLAH HARGA BAHAN 84,434.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 121,134.00


E Overhead & Profit 15.00% 18,170.10
F Harga Satuan Pekerjaan (D+E) 139,304.10

A.4.4.1.9 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen Portland Kg 11.500 1,400.00 16,100.00
Pasir pasang m3 0.043 207,900.00 8,939.70
JUMLAH HARGA BAHAN 81,039.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 117,739.70


E Overhead & Profit 15.00% 17,660.96
F Harga Satuan Pekerjaan (D+E) 135,400.66

A. 4.4.1.10 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :5PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen Portland Kg 9.680 1,400.00 13,552.00
Pasir pasang m3 0.045 207,900.00 9,355.50
JUMLAH HARGA BAHAN 78,907.50

III - 76
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 115,607.50


E Overhead & Profit 15.00% 17,341.13
F Harga Satuan Pekerjaan (D+E) 132,948.63

A. 4.4.1.11 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP : 6PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen Portland Kg 8.320 1,400.00 11,648.00
Pasir pasang m3 0.049 207,900.00 10,187.10
JUMLAH HARGA BAHAN 77,835.10
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 114,535.10


E Overhead & Profit 15.00% 17,180.27
F Harga Satuan Pekerjaan (D+E) 131,715.37

A. 4.4.1.12 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :8PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen Portland Kg 6.500 1,400.00 9,100.00
Pasir pasang m3 0.050 207,900.00 10,395.00
JUMLAH HARGA BAHAN 75,495.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 112,195.00


E Overhead & Profit 15.00% 16,829.25
F Harga Satuan Pekerjaan (D+E) 129,024.25

A. 4.4.1.13 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 3KP :10PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00

III - 77
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen Portland Kg 4.500 1,400.00 6,300.00
Kapur padam m3 0.015 70,000.00 1,050.00
Pasir pasang m3 0.050 207,900.00 10,395.00
JUMLAH HARGA BAHAN 73,745.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 110,445.00


E Overhead & Profit 15.00% 16,566.75
F Harga Satuan Pekerjaan (D+E) 127,011.75

A. 4.4.1.14 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :1PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen merah Kg 0.018 1,400.00 25.20
Kapur padam m3 0.018 70,000.00 1,260.00
Pasir pasang m3 0.018 207,900.00 3,742.20
JUMLAH HARGA BAHAN 61,027.40
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 97,727.40


E Overhead & Profit 15.00% 14,659.11
F Harga Satuan Pekerjaan (D+E) 112,386.51

A. 4.4.1.15 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SM : 1KP :2PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen merah Kg 0.014 1,400.00 19.60
Kapur padam m3 0.014 70,000.00 980.00
Pasir pasang m3 0.028 207,900.00 5,821.20
JUMLAH HARGA BAHAN 62,820.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 99,520.80


E Overhead & Profit 15.00% 14,928.12
F Harga Satuan Pekerjaan (D+E) 114,448.92

III - 78
A. 4.4.1.16 rob Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 3PP

Uraian Kode Satuan Harga Jumlah


Koefisien Asli Koefisien Rubahan Satuan Harga
No (Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 80,000.00 28,000.00
Tukang batu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 46,555.00
B BAHAN
HB-20 bh 12.500 12.500 1,750.00 21,875.00
Semen Portland Kg 30.320 3.032 1,400.00 4,244.80
Pasir pasang m3 0.728 0.073 207,900.00 15,135.12
Besi angker diameter 8 Kg 0.280 0.028 13,000.00 364.00
JUMLAH HARGA BAHAN 41,618.92
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 88,173.92


E Overhead & Profit 15.00% 13,226.09
F Harga Satuan Pekerjaan (D+E) 101,400.01
HB20 : Hollow Block tebal 20cm

A. 4.4.1.17 rob Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 4PP

No Uraian Kode Satuan Harga Jumlah


Koefisien Asli Koefisien Rubahan Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 80,000.00 28,000.00
Tukang batu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 46,555.00
B BAHAN
HB-20 buah 12.500 12.500 1,750.00 21,875.00
Semen Portland Kg 24.260 2.426 1,400.00 3,396.40
Pasir pasang m3 0.772 0.077 207,900.00 16,049.88
Besi angker diameter 8 Kg 0.280 0.280 13,000.00 3,640.00
JUMLAH HARGA BAHAN 44,961.28
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 91,516.28


E Overhead & Profit 15.00% 13,727.44
F Harga Satuan Pekerjaan (D+E) 105,243.72

A. 4.4.1.18 rob Pemasangan 1m2 dinding conblock HB15 campuran 1SP : 3PP

No Uraian Kode Satuan Harga Jumlah


Koefisien Asli Koefisien Rubahan Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.320 80,000.00 25,600.00
Tukang batu L.02 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.016 110,000.00 1,760.00
JUMLAH TENAGA KERJA 40,620.00

III - 79
B BAHAN
HB-15 buah 12.500 12.500 1,500.00 18,750.00
Semen Portland Kg 22.740 2.274 1,400.00 3,183.60
Pasir pasang m3 0.550 0.055 207,900.00 11,434.50
Besi angker diameter 8 Kg 0.280 0.280 13,000.00 3,640.00
JUMLAH HARGA BAHAN 37,008.10
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 77,628.10


E Overhead & Profit 15.00% 11,644.22
F Harga Satuan Pekerjaan (D+E) 89,272.32
HB15: Hollow Block tebal 15cm

A. 4.4.1.19 rob Pemasangan 1 m2 dinding conblock HB15 campuran 1SP :4PP

No Uraian Kode Satuan Harga Jumlah


Koefisien Asli Koefisien Rubahan Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.320 80,000.00 25,600.00
Tukang batu L.02 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.016 110,000.00 1,760.00
JUMLAH TENAGA KERJA 40,620.00
B BAHAN
HB-15 buah 12.500 12.500 1,500.00 18,750.00
Semen Portland Kg 18.200 1.820 1,400.00 2,548.00
Pasir pasang m3 0.582 0.058 207,900.00 12,099.78
Besi angker diameter 8 Kg 0.280 0.280 13,000.00 3,640.00
JUMLAH HARGA BAHAN 37,037.78
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 77,657.78


E Overhead & Profit 15.00% 11,648.67
F Harga Satuan Pekerjaan (D+E) 89,306.45

A. 4.4.1.20 rob Pemasangan 1 m2 dinding conblock HB10 campuran 1SP :3PP

No Uraian Kode Satuan Harga Jumlah


Koefisien Asli Koefisien Rubahan Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
HB-10 buah 12.500 12.500 1,350.00 16,875.00
Semen Portland Kg 15.160 1.516 1,400.00 2,122.40
Pasir pasang m3 0.364 0.036 207,900.00 7,567.56
Besi angker diameter 8 Kg 0.280 0.280 13,000.00 3,640.00
JUMLAH HARGA BAHAN 30,204.96
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 66,904.96


E Overhead & Profit 15.00% 10,035.74
F Harga Satuan Pekerjaan (D+E) 76,940.70
Hb10 : Hollow Block tebal 10 cm

III - 80
A. 4.4.1.21.rob Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 4PP

No Uraian Kode Satuan Harga Jumlah


Koefisien Asli Koefisien Rubahan Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
HB-10 buah 12.500 12.500 1,350.00 16,875.00
Semen Portland Kg 12.130 1.213 1,400.00 1,698.20
Pasir pasang m3 0.388 0.039 207,900.00 8,066.52
Besi angker diameter 8 Kg 0.280 0.280 13,000.00 3,640.00
JUMLAH HARGA BAHAN 30,279.72
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 66,979.72


E Overhead & Profit 15.00% 10,046.96
F Harga Satuan Pekerjaan (D+E) 77,026.68

A. 4.4.1.22 Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1SP :3PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata rooster m3 30.000 2,400.00 72,000.00
Semen Portland Kg 11.000 1,400.00 15,400.00
Pasir pasang m3 0.035 207,900.00 7,276.50
JUMLAH HARGA BAHAN 94,676.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 131,376.50


E Overhead & Profit 15.00% 19,706.48
F Harga Satuan Pekerjaan (D+E) 151,082.98

A. 4.4.1.23 Pemasangan 1 cm2 dinding terawang (rooster) 12x11x24 campuran 1SP :4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Bata berongga m3 30.000 2,400.00 72,000.00
Semen Portland Kg 11.000 1,400.00 15,400.00
Pasir pasang m3 0.035 207,900.00 7,276.50
JUMLAH HARGA BAHAN 94,676.50

III - 81
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 131,376.50


E Overhead & Profit 15.00% 19,706.48
F Harga Satuan Pekerjaan (D+E) 151,082.98

A. 4.4.1.25 Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.670 80,000.00 53,600.00
Tukang batu L.02 OH 1.300 100,000.00 130,000.00
Kepala tukang L.03 OH 0.130 105,000.00 13,650.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 197,580.00
B BAHAN
Bata ringan tebal 7,5cm buah 8.400 5,200.00 43,680.00
Mortar siap pakai Kg 0.473 3,750.00 1,773.75
JUMLAH HARGA BAHAN 45,453.75
C PERALATAN
Peralatan % 0.100 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 243,033.75


E Overhead & Profit 15.00% 36,455.06
F Harga Satuan Pekerjaan (D+E) 279,488.81

A. 4.4.1.26 Pemasangan 1m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.671 80,000.00 53,680.00
Tukang batu L.02 OH 1.300 100,000.00 130,000.00

III - 82
Kepala tukang L.03 OH 0.130 105,000.00 13,650.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 197,660.00
B BAHAN
Bata ringan tebal 10cm buah 8.400 6,000.00 50,400.00
Mortar siap pakai Kg 0.063 3,750.00 236.25
JUMLAH HARGA BAHAN 50,636.25
C PERALATAN
Peralatan % 0.100 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 248,296.25


E Overhead & Profit 15.00% 37,244.44
F Harga Satuan Pekerjaan (D+E) 285,540.69

A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

A.4.4.2.1. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm

Uraian Kode Satuan Koefisien Harga Jumlah


No Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
PC Kg 15.504 1,400.00 21,705.60
PP m3 0.016 207,900.00 3,326.40
JUMLAH HARGA BAHAN 25,032.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 67,257.00


E Overhead & Profit 15.00% 10,088.55
F Harga Satuan Pekerjaan (D+E) 77,345.55

A.4.4.2.2. Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
PC Kg 10.224 1,400.00 14,313.60
PP m3 0.020 207,900.00 4,158.00
JUMLAH HARGA BAHAN 18,471.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 60,696.60


E Overhead & Profit 15.00% 9,104.49
F Harga Satuan Pekerjaan (D+E) 69,801.09

III - 83
A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm

Uraian Kode Satuan Koefisien Harga Jumlah


No Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
PC Kg 7.776 1,400.00 10,886.40
PP m3 0.023 207,900.00 4,781.70
JUMLAH HARGA BAHAN 15,668.10
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,893.10


E Overhead & Profit 15.00% 8,683.97
F Harga Satuan Pekerjaan (D+E) 66,577.07

A.4.4.2.4. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
PC Kg 6.240 1,400.00 8,736.00
PP m3 0.024 207,900.00 4,989.60
JUMLAH HARGA BAHAN 13,725.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,950.60


E Overhead & Profit 15.00% 8,392.59
F Harga Satuan Pekerjaan (D+E) 64,343.19

A.4.4.2.5. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
PC Kg 5.184 1,400.00 7,257.60
PP m3 0.026 207,900.00 5,405.40
JUMLAH HARGA BAHAN 12,663.00

III - 84
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 54,888.00


E Overhead & Profit 15.00% 8,233.20
F Harga Satuan Pekerjaan (D+E) 63,121.20

A.4.4.2.6. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 15 mm

Uraian Kode Satuan Koefisien Harga Jumlah


No Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
PC Kg 4.416 1,400.00 6,182.40
PP m3 0.027 207,900.00 5,613.30
JUMLAH HARGA BAHAN 11,795.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 54,020.70


E Overhead & Profit 15.00% 8,103.11
F Harga Satuan Pekerjaan (D+E) 62,123.81

A.4.4.2.7. Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
PC Kg 3.936 1,400.00 5,510.40
PP m3 0.028 207,900.00 5,821.20
JUMLAH HARGA BAHAN 11,331.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 53,556.60


E Overhead & Profit 15.00% 8,033.49
F Harga Satuan Pekerjaan (D+E) 61,590.09

A.4.4.2.8. Pemasangan 1 m2 plesteran 1SP : 8PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00

III - 85
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
PC Kg 3.456 1,400.00 4,838.40
PP m3 0.029 207,900.00 6,029.10
JUMLAH HARGA BAHAN 10,867.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 53,092.50


E Overhead & Profit 15.00% 7,963.88
F Harga Satuan Pekerjaan (D+E) 61,056.38

A.4.4.2.9. Pemasangan 1 m2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.360 80,000.00 28,800.00
Tukang batu L.03 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 44,040.00
B BAHAN
PC Kg 5.760 1,400.00 8,064.00
KP m3 0.003 70,000.00 210.00
PP m3 0.013 207,900.00 2,702.70
JUMLAH HARGA BAHAN 10,976.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,016.70


E Overhead & Profit 15.00% 8,252.51
F Harga Satuan Pekerjaan (D+E) 63,269.21

A.4.4.2.10. Pemasangan 1 m2 plesteran 1SP : 2KP : 8PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.360 80,000.00 28,800.00
Tukang batu L.03 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 44,040.00
B BAHAN
PC Kg 3.000 1,400.00 4,200.00
KP m3 0.005 70,000.00 350.00
PP m3 0.020 207,900.00 4,158.00
JUMLAH HARGA BAHAN 8,708.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 52,748.00


E Overhead & Profit 15.00% 7,912.20
F Harga Satuan Pekerjaan (D+E) 60,660.20

III - 86
A.4.4.2.11. Pemasangan 1 m2 plesteran 1SM : 1KP : 1PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.360 80,000.00 28,800.00
Tukang batu L.03 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 44,040.00
B BAHAN
SM m3 0.009 934.38 8.41
KP m3 0.009 70,000.00 630.00
PP m3 0.009 207,900.00 1,871.10
JUMLAH HARGA BAHAN 2,509.51
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 46,549.51


E Overhead & Profit 15.00% 6,982.43
F Harga Satuan Pekerjaan (D+E) 53,531.94

A.4.4.2.12. Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.360 80,000.00 28,800.00
Tukang batu L.03 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 44,040.00
B BAHAN
SM m3 0.007 934.38 6.54
KP m3 0.007 70,000.00 490.00
PP m3 0.015 207,900.00 3,118.50
JUMLAH HARGA BAHAN 3,615.04
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,655.04


E Overhead & Profit 15.00% 7,148.26
F Harga Satuan Pekerjaan (D+E) 54,803.30

A.4.4.2.13. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 20 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang batu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.022 110,000.00 2,420.00
JUMLAH TENAGA KERJA 56,520.00
B BAHAN
PC Kg 13.632 1,400.00 19,084.80
PP m3 0.027 207,900.00 5,613.30
JUMLAH HARGA BAHAN 24,698.10

III - 87
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 81,218.10


E Overhead & Profit 15.00% 12,182.72
F Harga Satuan Pekerjaan (D+E) 93,400.82

A.4.4.2.14. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.260 80,000.00 20,800.00
Tukang batu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 44,330.00
B BAHAN
PC Kg 10.368 1,400.00 14,515.20
PP m3 0.031 207,900.00 6,444.90
JUMLAH HARGA BAHAN 20,960.10
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 65,290.10


E Overhead & Profit 15.00% 9,793.52
F Harga Satuan Pekerjaan (D+E) 75,083.62

A.4.4.2.15. Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang batu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.022 110,000.00 2,420.00
JUMLAH TENAGA KERJA 56,520.00
B BAHAN
PC Kg 8.320 1,400.00 11,648.00
PP m3 0.032 207,900.00 6,652.80
JUMLAH HARGA BAHAN 18,300.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 74,820.80


E Overhead & Profit 15.00% 11,223.12
F Harga Satuan Pekerjaan (D+E) 86,043.92

A.4.4.2.16. Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang batu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.022 110,000.00 2,420.00
JUMLAH TENAGA KERJA 56,520.00

III - 88
B BAHAN
PC Kg 6.912 1,400.00 9,676.80
PP m3 0.035 207,900.00 7,276.50
JUMLAH HARGA BAHAN 16,953.30
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 73,473.30


E Overhead & Profit 15.00% 11,021.00
F Harga Satuan Pekerjaan (D+E) 84,494.30

A.4.4.2.17. Pemasangan 1 m2 plesteran 1SP : 6PP tebal 20 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang Batu L.03 OH 0.200 100,000.00 20,000.00
Kepala Tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.022 110,000.00 2,420.00
JUMLAH TENAGA KERJA 56,520.00
B BAHAN
PC Kg 5.888 1,400.00 8,243.20
PP m3 0.036 207,900.00 7,484.40
JUMLAH HARGA BAHAN 15,727.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 72,247.60


E Overhead & Profit 15.00% 10,837.14
F Harga Satuan Pekerjaan (D+E) 83,084.74

A.4.4.2.18. Pemasangan 1 m2 plesteran 1SM : 1 KP : 2PP tebal 20 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.440 80,000.00 35,200.00
Tukang batu L.03 OH 0.220 100,000.00 22,000.00
Kepala tukang L.03 OH 0.022 105,000.00 2,310.00
Mandor L.04 OH 0.022 110,000.00 2,420.00
JUMLAH TENAGA KERJA 61,930.00
B BAHAN
SM m3 0.009 934.38 8.41
KP m3 0.009 70,000.00 630.00
PP m3 0.018 207,900.00 3,742.20
JUMLAH HARGA BAHAN 4,380.61
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 66,310.61


E Overhead & Profit 15.00% 9,946.59
F Harga Satuan Pekerjaan (D+E) 76,257.20

III - 89
A.4.4.2.19. Pemasangan 1 m2 berapen 1SP : 5PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang batu L.03 OH 0.075 100,000.00 7,500.00
Kepala tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 21,220.00
B BAHAN
PC Kg 5.184 1,400.00 7,257.60
PP m3 0.026 207,900.00 5,405.40
JUMLAH HARGA BAHAN 12,663.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,883.00


E Overhead & Profit 15.00% 5,082.45
F Harga Satuan Pekerjaan (D+E) 38,965.45

A.4.4.2.20. Pemasangan 1 m’ plesteran skoning 1SP : 3PP lebar 10 cm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 80,000.00 6,400.00
Tukang batu L.03 OH 0.400 100,000.00 40,000.00
Kepala tukang L.03 OH 0.040 105,000.00 4,200.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 51,040.00
B BAHAN
Semen PC Kg 0.500 1,400.00 700.00
Pasir pasang m3 0.013 207,900.00 2,702.70
JUMLAH HARGA BAHAN 3,402.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 54,442.70


E Overhead & Profit 15.00% 8,166.41
F Harga Satuan Pekerjaan (D+E) 62,609.11

A.4.4.2.21. Pemasangan 1 m2 plesteran granit 1SP : 2 granit tebal 1cm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 80,000.00 36,000.00
Tukang batu L.03 OH 0.225 100,000.00 22,500.00
Kepala tukang L.03 OH 0.023 105,000.00 2,415.00
Mandor L.04 OH 0.023 110,000.00 2,530.00
JUMLAH TENAGA KERJA 63,445.00
B BAHAN
Semen PC Kg 10.000 1,400.00 14,000.00
Batu granit Kg 15.000 5,000.00 75,000.00
JUMLAH HARGA BAHAN 89,000.00

III - 90
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 152,445.00


E Overhead & Profit 15.00% 22,866.75
F Harga Satuan Pekerjaan (D+E) 175,311.75

A.4.4.2.22 Pemasangan 1 m2 plesteran traso 1SP : 2 traso tebal 1 cm

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.450 80,000.00 36,000.00
Tukang batu L.03 OH 0.225 100,000.00 22,500.00
Kepala tukang L.03 OH 0.023 105,000.00 2,415.00
Mandor L.04 OH 0.023 110,000.00 2,530.00
JUMLAH TENAGA KERJA 63,445.00
B BAHAN
Semen PC Kg 10.000 1,400.00 14,000.00
Batu traso Kg 15.000 5,000.00 75,000.00
JUMLAH HARGA BAHAN 89,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 152,445.00


E Overhead & Profit 15.00% 22,866.75
F Harga Satuan Pekerjaan (D+E) 175,311.75

A.4.4.2.23. Pemasangan 1 m2 plesteran ciprat 1SP : 2PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 36,700.00
B BAHAN
Semen PC Kg 4.320 1,400.00 6,048.00
Pasir pasang m3 0.006 207,900.00 1,247.40
JUMLAH HARGA BAHAN 7,295.40
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 43,995.40


E Overhead & Profit 15.00% 6,599.31
F Harga Satuan Pekerjaan (D+E) 50,594.71

A.4.4.2.24 Pemasangan 1 m2 finishing siar pasangan bata merah

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang batu L.03 OH 0.075 100,000.00 7,500.00
Kepala tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 21,220.00

III - 91
B BAHAN
Semen PC Kg 3.108 1,400.00 4,351.20
JUMLAH HARGA BAHAN 4,351.20
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 25,571.20


E Overhead & Profit 15.00% 3,835.68
F Harga Satuan Pekerjaan (D+E) 29,406.88

A.4.4.2.25. Pemasangan 1 m2 finishing siar pasangan conblock ekspose

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.070 80,000.00 5,600.00
Tukang batu L.03 OH 0.035 100,000.00 3,500.00
Kepala tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 9,960.00
B BAHAN
Semen PC Kg 1.600 1,400.00 2,240.00
JUMLAH HARGA BAHAN 2,240.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,200.00


E Overhead & Profit 15.00% 1,830.00
F Harga Satuan Pekerjaan (D+E) 14,030.00

A.4.4.2.26. Pemasangan 1 m2 finishing siar pasangan batu kali, campuran 1SP : 2PP

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
Semen PC Kg 6.340 1,400.00 8,876.00
Pasir pasang m3 0.012 207,900.00 2,494.80
JUMLAH HARGA BAHAN 11,370.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 53,595.80


E Overhead & Profit 15.00% 8,039.37
F Harga Satuan Pekerjaan (D+E) 61,635.17

A.4.4.2.27. Pemasangan 1 m2 acian

No Uraian Kode Satuan Koefisien Harga Jumlah


Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang batu L.03 OH 0.100 100,000.00 10,000.00

III - 92
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 28,150.00
B BAHAN
Semen PC Kg 3.250 1,400.00 4,550.00
JUMLAH HARGA BAHAN 4,550.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,700.00


E Overhead & Profit 15.00% 4,905.00
F Harga Satuan Pekerjaan (D+E) 37,605.00

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.2. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30 cm x30 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang batu L.02 OH 0.125 100,000.00 12,500.00
Kepala tukang L.03 OH 0.013 105,000.00 1,365.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 35,295.00
B BAHAN
Ubin abu-abu Bh 11.870 2,900.00 34,423.00
Semen Portland kg 10.000 1,400.00 14,000.00
Pasir pasang M3 0.045 207,900.00 9,355.50
JUMLAH HARGA BAHAN 57,778.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 93,073.50


E Overhead & Profit 15.00% 13,961.03
F Harga Satuan Pekerjaan (D+E) 107,034.53

A.4.4.3.3. Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.270 80,000.00 21,600.00
Tukang batu L.02 OH 0.135 100,000.00 13,500.00
Kepala tukang L.03 OH 0.014 105,000.00 1,470.00
Mandor L.04 OH 0.014 110,000.00 1,540.00
JUMLAH TENAGA KERJA 38,110.00
B BAHAN
Ubin abu-abu buah 26.500 2,300.00 60,950.00
Semen Portland kg 10.400 1,400.00 14,560.00
Pasir pasang M3 0.045 207,900.00 9,355.50
JUMLAH HARGA BAHAN 84,865.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 122,975.50


E Overhead & Profit 15.00% 18,446.33
F Harga Satuan Pekerjaan (D+E) 141,421.83

III - 93
A.4.4.3.5. Pemasangan 1 m2 lantai ubin warna ukuran 30 cm x 30 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.260 80,000.00 20,800.00
Tukang batu L.02 OH 0.130 100,000.00 13,000.00
Kepala tukang L.03 OH 0.013 105,000.00 1,365.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 36,595.00
B BAHAN
Ubin warna Bh 11.870 3,300.00 39,171.00
Semen Portland kg 10.000 1,400.00 14,000.00
Semen warna Kg 0.600 6,000.00 3,600.00
Pasir pasang M3 0.045 207,900.00 9,355.50
JUMLAH HARGA BAHAN 66,126.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 102,721.50


E Overhead & Profit 15.00% 15,408.23
F Harga Satuan Pekerjaan (D+E) 118,129.73

A.4.4.3.6. Pemasangan 1 m2 lantai ubin warna ukuran 20 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.270 80,000.00 21,600.00
Tukang batu L.02 OH 0.135 100,000.00 13,500.00
Kepala tukang L.03 OH 0.014 105,000.00 1,470.00
Mandor L.04 OH 0.014 110,000.00 1,540.00
JUMLAH TENAGA KERJA 38,110.00
B BAHAN
Ubin warna Bh 26.500 2,700.00 71,550.00
Semen Portland kg 10.400 1,400.00 14,560.00
Semen warna Kg 1.000 6,000.00 6,000.00
Pasir pasang M3 0.045 207,900.00 9,355.50
JUMLAH HARGA BAHAN 101,465.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 139,575.50


E Overhead & Profit 15.00% 20,936.33
F Harga Satuan Pekerjaan (D+E) 160,511.83

A.4.4.3.9. Pemasangan 1 m2 lantai ubin granit ukuran 40 cm x 40 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang batu L.02 OH 0.125 100,000.00 12,500.00
Kepala tukang L.03 OH 0.013 105,000.00 1,365.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 35,295.00

III - 94
B BAHAN
Ubin granit Bh 6.630 42,000.00 278,460.00
Semen Portland kg 9.800 1,400.00 13,720.00
Semen warna Kg 1.300 6,000.00 7,800.00
Pasir pasang M3 0.045 207,900.00 9,355.50
JUMLAH HARGA BAHAN 309,335.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 344,630.50


E Overhead & Profit 15.00% 51,694.58
F Harga Satuan Pekerjaan (D+E) 396,325.08

A.4.4.3.32. Pemasangan 1m2 lantai keramik artistik 10 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Ubin keramik Bh 53.000 1,200.00 63,600.00
Semen Portland Kg 8.190 1,400.00 11,466.00
Pasir pasang M3 0.045 207,900.00 9,355.50
Semen warna Kg 2.750 6,000.00 16,500.00
JUMLAH HARGA BAHAN 100,921.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 199,446.50


E Overhead & Profit 15.00% 29,916.98
F Harga Satuan Pekerjaan (D+E) 229,363.48

A.4.4.3.35. Pemasangan 1m2 lantai keramik ukuran 30 cm x 30 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Ubin keramik Doos 1.050 27,500.00 28,875.00
Semen Portland Kg 10.000 1,400.00 14,000.00
Pasir pasang M3 0.045 207,900.00 9,355.50
Semen warna Kg 0.500 6,000.00 3,000.00
JUMLAH HARGA BAHAN 55,230.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 153,755.50


E Overhead & Profit 15.00% 23,063.33
F Harga Satuan Pekerjaan (D+E) 176,818.83

III - 95
A.4.4.3.36. Pemasangan 1m2 lantai keramik ukuran 20 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Ubin keramik Doos 1.050 50,000.00 52,500.00
Semen Portland Kg 10.400 1,400.00 14,560.00
Pasir pasang M3 0.045 207,900.00 9,355.50
Semen warna Kg 0.500 6,000.00 3,000.00
JUMLAH HARGA BAHAN 79,415.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 177,940.50


E Overhead & Profit 15.00% 26,691.08
F Harga Satuan Pekerjaan (D+E) 204,631.58

A.4.4.3.38. Pemasangan 1m2 lantai keramik mozaik ukuran 30 cm x 30 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Ubin keramik Bh 11.870 3,909.09 46,400.91
Semen Portland Kg 14.150 1,400.00 19,810.00
Pasir pasang M3 0.039 207,900.00 8,108.10
Semen warna Kg 2.000 6,000.00 12,000.00
JUMLAH HARGA BAHAN 86,319.01
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 184,844.01


E Overhead & Profit 15.00% 27,726.60
F Harga Satuan Pekerjaan (D+E) 212,570.61

A.4.4.3.39. Pemasangan 1 m’ plint keramik ukuran 10 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.090 80,000.00 7,200.00
Tukang batu L.02 OH 0.090 100,000.00 9,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 20,425.00

III - 96
B BAHAN
Plint keramik Bh 5.300 12,000.00 63,600.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir pasang M3 0.003 207,900.00 623.70
Semen warna Kg 0.025 6,000.00 150.00
JUMLAH HARGA BAHAN 65,969.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 86,394.70


E Overhead & Profit 15.00% 12,959.21
F Harga Satuan Pekerjaan (D+E) 99,353.91

A.4.4.3.40. Pemasangan 1 m’ plint keramik ukuran 10 cm x 10 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.090 80,000.00 7,200.00
Tukang batu L.02 OH 0.090 100,000.00 9,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 20,425.00
B BAHAN
Plint keramik Bh 10.600 9,000.00 95,400.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir pasang M3 0.003 207,900.00 623.70
Semen warna Kg 0.050 6,000.00 300.00
JUMLAH HARGA BAHAN 97,919.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 118,344.70


E Overhead & Profit 15.00% 17,751.71
F Harga Satuan Pekerjaan (D+E) 136,096.41

A.4.4.3.41. Pemasangan 1 m’ plint keramik ukuran 5 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.090 80,000.00 7,200.00
Tukang batu L.02 OH 0.090 100,000.00 9,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 20,425.00
B BAHAN
Plint keramik Bh 5.300 9,000.00 47,700.00
Semen Portland Kg 0.570 1,400.00 798.00
Pasir pasang M3 0.002 207,900.00 311.85
Semen warna Kg 0.013 6,000.00 78.00
JUMLAH HARGA BAHAN 48,887.85
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 69,312.85


E Overhead & Profit 15.00% 10,396.93
F Harga Satuan Pekerjaan (D+E) 79,709.78

III - 97
A.4.4.3.42. Pemasangan 1 m’ plint internal cove artistik 5 cm x 5 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.750 80,000.00 60,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.038 110,000.00 4,180.00
JUMLAH TENAGA KERJA 147,055.00
B BAHAN
Internal cove Bh 5.300 15,000.00 79,500.00
Semen Portland Kg 1.140 1,400.00 1,596.00
Pasir pasang M3 0.003 207,900.00 623.70
Semen warna Kg 0.100 6,000.00 600.00
JUMLAH HARGA BAHAN 82,319.70
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 229,374.70


E Overhead & Profit 15.00% 34,406.21
F Harga Satuan Pekerjaan (D+E) 263,780.91

A.4.4.3.43. Pemasangan 1 m2 lantai marmer ukuran 100cm x 100cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Marmer Bh 1.060 800,000.00 848,000.00
Semen Portland Kg 8.190 1,400.00 11,466.00
Pasir pasang M3 0.045 207,900.00 9,355.50
Semen warna Kg 0.134 6,000.00 804.00
JUMLAH HARGA BAHAN 869,625.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 968,150.50


E Overhead & Profit 15.00% 145,222.58
F Harga Satuan Pekerjaan (D+E) 1,113,373.08

A.4.4.3.44. Pemasangan 1 m2 lantai karpet

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.170 80,000.00 13,600.00
Tukang kayu L.02 OH 0.170 100,000.00 17,000.00
Kepala tukang L.03 OH 0.017 105,000.00 1,785.00
Mandor L.04 OH 0.009 110,000.00 990.00
JUMLAH TENAGA KERJA 33,375.00

III - 98
B BAHAN
Karpet m2 1.050 100,000.00 105,000.00
Lem Kg 0.350 68,500.00 23,975.00
JUMLAH HARGA BAHAN 128,975.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 162,350.00


E Overhead & Profit 15.00% 24,352.50
F Harga Satuan Pekerjaan (D+E) 186,702.50

A.4.4.3.45. Pemasangan 1 m2 underlayer (pelapis bawah karpet)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.120 80,000.00 9,600.00
Tukang kayu L.02 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 23,520.00
B BAHAN
Underlayer m2 1.050 50,000.00 52,500.00
Lem Kg 0.350 68,500.00 23,975.00
JUMLAH HARGA BAHAN 76,475.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 99,995.00


E Overhead & Profit 15.00% 14,999.25
F Harga Satuan Pekerjaan (D+E) 114,994.25

A.4.4.3.46. Pemasangan 1 m2 lantai parquet kayu

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang kayu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Parquet m2 1.050 150,000.00 157,500.00
Lem Kg 0.600 68,500.00 41,100.00
JUMLAH HARGA BAHAN 198,600.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 297,125.00


E Overhead & Profit 15.00% 44,568.75
F Harga Satuan Pekerjaan (D+E) 341,693.75

III - 99
A.4.4.3.47. Pemasangan 1 m2 lantai kayu gymfloor

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang kayu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Parquet m2 1.050 150,000.00 157,500.00
Lem Kg 0.600 68,500.00 41,100.00
JUMLAH HARGA BAHAN 198,600.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 297,125.00


E Overhead & Profit 15.00% 44,568.75
F Harga Satuan Pekerjaan (D+E) 341,693.75

A.4.4.3.49. Pemasangan 1 m2 dinding porselen 10 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 80,000.00 72,000.00
Tukang batu L.02 OH 0.450 100,000.00 45,000.00
Kepala tukang L.03 OH 0.045 105,000.00 4,725.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 126,675.00
B BAHAN
Porslen buah 53.000 1,200.00 63,600.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir pasang M3 0.018 207,900.00 3,742.20
Semen warna Kg 2.750 6,000.00 16,500.00
JUMLAH HARGA BAHAN 96,862.20
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 223,537.20


E Overhead & Profit 15.00% 33,530.58
F Harga Satuan Pekerjaan (D+E) 257,067.78

A.4.4.3.50. Pemasangan 1 m2 dinding porselen 20 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 80,000.00 72,000.00
Tukang batu L.02 OH 0.450 100,000.00 45,000.00
Kepala tukang L.03 OH 0.045 105,000.00 4,725.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 126,675.00
B BAHAN
Porslen buah 26.000 2,300.00 59,800.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir pasang M3 0.018 207,900.00 3,742.20
Semen warna Kg 1.940 6,000.00 11,640.00
JUMLAH HARGA BAHAN 88,202.20

III - 100
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 214,877.20


E Overhead & Profit 15.00% 32,231.58
F Harga Satuan Pekerjaan (D+E) 247,108.78

A.4.4.3.51. Pemasangan 1 m2 dinding keramik artistik 10 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 80,000.00 72,000.00
Tukang batu L.02 OH 0.450 100,000.00 45,000.00
Kepala tukang L.03 OH 0.045 105,000.00 4,725.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 126,675.00
B BAHAN
Keramik artistik buah 53.000 3,333.33 176,666.67
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir pasang M3 0.018 207,900.00 3,742.20
Semen warna Kg 2.750 6,000.00 16,500.00
JUMLAH HARGA BAHAN 209,928.87
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 336,603.87


E Overhead & Profit 15.00% 50,490.58
F Harga Satuan Pekerjaan (D+E) 387,094.45

A.4.4.3.52. Pemasangan 1 m2 dinding keramik artistik 5 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 80,000.00 72,000.00
Tukang batu L.02 OH 0.450 100,000.00 45,000.00
Kepala tukang L.03 OH 0.045 105,000.00 4,725.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 126,675.00
B BAHAN
Keramik artistik buah 106.000 1,666.67 176,666.67
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir pasang M3 0.018 207,900.00 3,742.20
Semen warna Kg 2.900 6,000.00 17,400.00
JUMLAH HARGA BAHAN 210,828.87
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 337,503.87


E Overhead & Profit 15.00% 50,625.58
F Harga Satuan Pekerjaan (D+E) 388,129.45

A.4.4.3.53. Pemasangan 1 m2 dinding keramik 10 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 80,000.00 72,000.00
Tukang batu L.02 OH 0.450 100,000.00 45,000.00

III - 101
Kepala tukang L.03 OH 0.045 105,000.00 4,725.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 126,675.00
B BAHAN
Keramik artistik buah 53.000 1,200.00 63,600.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir pasang M3 0.018 207,900.00 3,742.20
Semen warna Kg 2.750 6,000.00 16,500.00
JUMLAH HARGA BAHAN 96,862.20
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 223,537.20


E Overhead & Profit 15.00% 33,530.58
F Harga Satuan Pekerjaan (D+E) 257,067.78

A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20 cm x 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.900 80,000.00 72,000.00
Tukang batu L.02 OH 0.450 100,000.00 45,000.00
Kepala tukang L.03 OH 0.045 105,000.00 4,725.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 126,675.00
B BAHAN
Keramik artistik buah 26.500 2,300.00 60,950.00
Semen Portland Kg 9.300 1,400.00 13,020.00
Pasir pasang M3 0.018 207,900.00 3,742.20
Semen warna Kg 1.940 6,000.00 11,640.00
JUMLAH HARGA BAHAN 89,352.20
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 216,027.20


E Overhead & Profit 15.00% 32,404.08
F Harga Satuan Pekerjaan (D+E) 248,431.28

A.4.4.3.55. Pemasangan 1 m2 dinding marmer 100 cm x 100 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.300 80,000.00 104,000.00
Tukang batu L.02 OH 0.650 100,000.00 65,000.00
Kepala tukang L.03 OH 0.065 105,000.00 6,825.00
Mandor L.04 OH 0.065 110,000.00 7,150.00
JUMLAH TENAGA KERJA 182,975.00
B BAHAN
Marmer buah 1.060 800,000.00 848,000.00
Semen Portland Kg 12.440 1,400.00 17,416.00
Pasir pasang M3 0.025 207,900.00 5,197.50
Semen warna Kg 0.650 6,000.00 3,900.00
Paku 12 cm buah 3.030 500.00 1,515.00
JUMLAH HARGA BAHAN 876,028.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,059,003.50


E Overhead & Profit 15.00% 158,850.53
F Harga Satuan Pekerjaan (D+E) 1,217,854.03

III - 102
A.4.4.3.56. Pemasangan 1 m2 dinding bata pelapis 3 cm x 7 cm x 24 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang batu L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 140,750.00
B BAHAN
Bata pelapis buah 63.000 4,083.33 257,250.00
Semen Portland Kg 12.440 1,400.00 17,416.00
Pasir pasang M3 0.025 207,900.00 5,197.50
Semen warna Kg 2.750 6,000.00 16,500.00
JUMLAH HARGA BAHAN 296,363.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 437,113.50


E Overhead & Profit 15.00% 65,567.03
F Harga Satuan Pekerjaan (D+E) 502,680.53

A.4.4.3.57. Pemasangan 1 m2 dinding batu paras

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Batu paras buah 1.100 4,185.00 4,603.50
Semen Portland Kg 11.750 1,400.00 16,450.00
Pasir pasang M3 0.035 207,900.00 7,276.50
JUMLAH HARGA BAHAN 28,330.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 126,855.00


E Overhead & Profit 15.00% 19,028.25
F Harga Satuan Pekerjaan (D+E) 145,883.25

A.4.4.3.58. Pemasangan 1 m2 dinding batu tempel hitam

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang batu L.02 OH 0.350 100,000.00 35,000.00
Kepala tukang L.03 OH 0.035 105,000.00 3,675.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Batu tempel hitam Buah 1.100 1,550.00 1,705.00
Semen Portland Kg 11.750 1,400.00 16,450.00
Pasir pasang M3 0.035 207,900.00 7,276.50
JUMLAH HARGA BAHAN 25,431.50

III - 103
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 123,956.50


E Overhead & Profit 15.00% 18,593.48
F Harga Satuan Pekerjaan (D+E) 142,549.98

A.4.4.3.59. Pemasangan 1 m2 lantai vynil ukuran 30 cm x 30 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang batu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 29,455.00
B BAHAN
Vynil buah 11.870 10,909.09 129,490.91
Lem Kg 0.350 22,000.00 7,700.00
JUMLAH HARGA BAHAN 137,190.91
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 166,645.91


E Overhead & Profit 15.00% 24,996.89
F Harga Satuan Pekerjaan (D+E) 191,642.80

A.4.4.3.60. Pemasangan 1 m2 wallpaper lebar 50 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 80,000.00 28,000.00
Tukang batu L.02 OH 0.175 100,000.00 17,500.00
Kepala tukang L.03 OH 0.017 105,000.00 1,785.00
Mandor L.04 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 47,505.00
B BAHAN
Wallpaper m 2.200 70,000.00 154,000.00
Lem Kg 0.250 22,000.00 5,500.00
JUMLAH HARGA BAHAN 159,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 207,005.00


E Overhead & Profit 15.00% 31,050.75
F Harga Satuan Pekerjaan (D+E) 238,055.75

A.4.4.3.61. Pemasangan 1m2 floor harderner

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.120 80,000.00 9,600.00
Tukang batu L.02 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 23,520.00

III - 104
B BAHAN
Floor harderner Kg 5.000 9,666.67 48,333.33
JUMLAH HARGA BAHAN 48,333.33
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 71,853.33


E Overhead & Profit 15.00% 10,778.00
F Harga Satuan Pekerjaan (D+E) 82,631.33

A.4.4.3.62. Pemasangan 1 m’ plint vynil 15cm x 30cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 80,000.00 6,400.00
Tukang batu L.02 OH 0.080 100,000.00 8,000.00
Kepala tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 15,680.00
B BAHAN
Vynil buah 1.760 10,909.09 19,200.00
Lem Kg 0.080 22,000.00 1,760.00
JUMLAH HARGA BAHAN 20,960.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,640.00


E Overhead & Profit 15.00% 5,496.00
F Harga Satuan Pekerjaan (D+E) 42,136.00

A.4.4.3.63. Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.120 80,000.00 9,600.00
Tukang batu L.02 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 23,520.00
B BAHAN
Papan kayu kelas 1 M3 0.003 9,500,000.00 28,500.00
Paku/skrup 5 cm Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 29,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 52,920.00


E Overhead & Profit 15.00% 7,938.00
F Harga Satuan Pekerjaan (D+E) 60,858.00

A.4.4.3.64. Pemasangan 1 m2 paving block natural tebal 6 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang batu L.02 OH 0.500 100,000.00 50,000.00

III - 105
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 75,393.00
B BAHAN
Paving block 6 cm M2 1.010 50,000.00 50,500.00
Pasir beton M3 0.050 231,000.00 11,550.00
JUMLAH HARGA BAHAN 62,050.00
C PERALATAN
Peralatan % 0.100 62,050.00 6,205.00
JUMLAH HARGA ALAT 6,205.00

D Jumlah (A+B+C) 143,648.00


E Overhead & Profit 15.00% 21,547.20
F Harga Satuan Pekerjaan (D+E) 165,195.20

A.4.4.3.65. Pemasangan 1 m2 paving block natural tebal 8 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 80,000.00 40,000.00
Tukang batu L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 95,393.00
B BAHAN
Paving block 8 cm natural M2 1.010 62,000.00 62,620.00
Pasir beton M3 2.070 231,000.00 478,170.00
JUMLAH HARGA BAHAN 540,790.00
C PERALATAN
Peralatan % 0.100 540,790.00 54,079.00
JUMLAH HARGA ALAT 54,079.00

D Jumlah (A+B+C) 690,262.00


E Overhead & Profit 15.00% 103,539.30
F Harga Satuan Pekerjaan (D+E) 793,801.30

A.4.4.3.66. Pemasangan 1 m2 paving block berwarna tebal 6 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang batu L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 75,393.00
B BAHAN
Paving block 6cm berwarna M2 1.010 57,000.00 57,570.00
Pasir beton M3 0.050 231,000.00 11,550.00
JUMLAH HARGA BAHAN 69,120.00
C PERALATAN
Peralatan % 0.100 69,120.00 6,912.00
JUMLAH HARGA ALAT 6,912.00

D Jumlah (A+B+C) 151,425.00


E Overhead & Profit 15.00% 22,713.75
F Harga Satuan Pekerjaan (D+E) 174,138.75

A.4.4.3.67. Pemasangan 1 m2 paving block berwarna tebal 8 cm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.500 80,000.00 40,000.00
Tukang batu L.02 OH 0.500 100,000.00 50,000.00

III - 106
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 95,393.00
B BAHAN
Paving block 8 cm berwarna M2 1.010 69,000.00 69,690.00
Pasir beton M3 2.070 231,000.00 478,170.00
JUMLAH HARGA BAHAN 547,860.00
C PERALATAN
Peralatan % 0.100 547,860.00 54,786.00
JUMLAH HARGA ALAT 54,786.00

D Jumlah (A+B+C) 698,039.00


E Overhead & Profit 15.00% 104,705.85
F Harga Satuan Pekerjaan (D+E) 802,744.85

A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.1. Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.030 80,000.00 2,400.00
Tukang kayu L.02 OH 0.070 100,000.00 7,000.00
Kepala tukang L.03 OH 0.007 105,000.00 735.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 10,575.00
B BAHAN
Asbes semen m2 1.100 37,000.00 40,700.00
Paku tripleks kg 0.010 20,000.00 200.00
JUMLAH HARGA BAHAN 40,900.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 51,475.00


E Overhead & Profit 15.00% 7,721.25
F Harga Satuan Pekerjaan (D+E) 59,196.25

A.4.5.1.2. Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30) cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.120 80,000.00 9,600.00
Tukang kayu L.02 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 23,520.00
B BAHAN
Akustik Lembar 12.000 51,000.00 612,000.00
Paku tripleks kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 613,000.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 636,520.00


E Overhead & Profit 15.00% 95,478.00
F Harga Satuan Pekerjaan (D+E) 731,998.00

III - 107
A.4.5.1.3. Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60) cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.120 80,000.00 9,600.00
Tukang kayu L.02 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 23,520.00
B BAHAN
Akustik Lembar 5.800 51,000.00 295,800.00
Paku tripleks kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 296,800.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 320,320.00


E Overhead & Profit 15.00% 48,048.00
F Harga Satuan Pekerjaan (D+E) 368,368.00

A.4.5.1.4. Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 19,600.00
B BAHAN
Akustik Lembar 1.500 51,000.00 76,500.00
Paku tripleks kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 77,500.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 97,100.00


E Overhead & Profit 15.00% 14,565.00
F Harga Satuan Pekerjaan (D+E) 111,665.00

A.4.5.1.5. Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 19,600.00
B BAHAN
Tripleks Lembar 0.375 60,000.00 22,500.00
Paku tripleks kg 0.030 20,000.00 600.00
JUMLAH HARGA BAHAN 23,100.00

III - 108
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 42,700.00


E Overhead & Profit 15.00% 6,405.00
F Harga Satuan Pekerjaan (D+E) 49,105.00

A.4.5.1.6. Pemasangan 1 m2 langit-langit lambrisering kayu, tebal 9 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.800 80,000.00 64,000.00
Tukang kayu L.02 OH 0.800 100,000.00 80,000.00
Kepala tukang L.03 OH 0.080 105,000.00 8,400.00
Mandor L.04 OH 0.040 110,000.00 4,400.00
JUMLAH TENAGA KERJA 156,800.00
B BAHAN
Kayu papan m3 0.015 3,500,000.00 52,500.00
Paku tripleks kg 0.010 20,000.00 200.00
JUMLAH HARGA BAHAN 52,700.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 209,500.00


E Overhead & Profit 15.00% 31,425.00
F Harga Satuan Pekerjaan (D+E) 240,925.00

A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.02 OH 0.050 100,000.00 5,000.00
Kepala tukang L.03 OH 0.005 105,000.00 525.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 14,075.00
B BAHAN
Gypsum board Lembar 0.364 52,500.00 19,110.00
Paku skrup kg 0.110 18,000.00 1,980.00
JUMLAH HARGA BAHAN 21,090.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,165.00


E Overhead & Profit 15.00% 5,274.75
F Harga Satuan Pekerjaan (D+E) 40,439.75

A.4.5.1.8. Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) cm berikut rangka alluminium

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 80,000.00 40,000.00
Tukang besi L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.025 110,000.00 2,750.00
JUMLAH TENAGA KERJA 98,000.00

III - 109
B BAHAN
Profil Allum "T" m 3.600 99,000.00 356,400.00
Kawat Ø 4 mm kg 0.150 20,000.00 3,000.00
Ramset Buah 1.050 200.00 210.00
Akustik 60 x 120 Lembar 1.500 51,000.00 76,500.00
JUMLAH HARGA BAHAN 436,110.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 534,110.00


E Overhead & Profit 15.00% 80,116.50
F Harga Satuan Pekerjaan (D+E) 614,226.50

A.4.5.1.9. Pemasangan 1 m’ list langit-langit kayu profil

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 80,000.00 4,000.00
Tukang kayu L.02 OH 0.050 100,000.00 5,000.00
Kepala tukang L.03 OH 0.005 105,000.00 525.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 9,855.00
B BAHAN
List kayu profil m 1.05 5,500.00 5,775.00
Paku kg 0.010 18,000.00 180.00
JUMLAH HARGA BAHAN 5,955.00
C PERALATAN
-
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,810.00


E Overhead & Profit 15.00% 2,371.50
F Harga Satuan Pekerjaan (D+E) 18,181.50

A.4.5.1.10 Pemasangan 1 m2 rangka langit-langit besi hollow 40.40


Lihat pada kelompok Pekerjaan Besi dan Alumunium (A.9.21)

A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP


A.4.5.2.1. Pemasangan 1 m2 atap genteng palentong kecil

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.03 OH 0.075 100,000.00 7,500.00
Kepala tukang L.11 OH 0.008 105,000.00 787.50
Mandor L.15 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 21,167.50
B BAHAN
Genteng palentong buah 25.000 900.00 22,500.00
JUMLAH HARGA BAHAN 22,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 43,667.50


E Overhead & Profit 15.00% 6,550.13
F Harga Satuan Pekerjaan (D+E) 50,217.63

III - 110
A.4.5.2.2. Pemasangan 1 m2 atap genteng kodok glazuur

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.03 OH 0.075 100,000.00 7,500.00
Kepala tukang L.11 OH 0.008 105,000.00 840.00
Mandor L.15 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 21,220.00
B BAHAN
Genteng kodok buah 25.000 1,400.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 56,220.00


E Overhead & Profit 15.00% 8,433.00
F Harga Satuan Pekerjaan (D+E) 64,653.00

A.4.5.2.3. Pemasangan 1 m2 atap genteng palentong besar/super

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.03 OH 0.075 100,000.00 7,500.00
Kepala tukang L.11 OH 0.008 105,000.00 840.00
Mandor L.15 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 21,220.00
B BAHAN
Genteng palentong buah 12.000 1,500.00 18,000.00
JUMLAH HARGA BAHAN 18,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 39,220.00


E Overhead & Profit 15.00% 5,883.00
F Harga Satuan Pekerjaan (D+E) 45,103.00

A.4.5.2.4. Pemasangan 1 m’ bubung genteng palentong

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang kayu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.11 OH 0.020 105,000.00 2,100.00
Mandor L.15 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 54,320.00
B BAHAN
Genteng bubung Buah 5.000 2,000.00 10,000.00
Semen Portland Kg 8.000 1,400.00 11,200.00
Pasir pasang M3 0.032 207,900.00 6,652.80
JUMLAH HARGA BAHAN 27,852.80

III - 111
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 82,172.80


E Overhead & Profit 15.00% 12,325.92
F Harga Satuan Pekerjaan (D+E) 94,498.72

A.4.5.2.5. Pemasangan 1 m’ bubung genteng kodok glazuur

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang kayu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.11 OH 0.020 105,000.00 2,100.00
Mandor L.15 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 54,320.00
B BAHAN
Genteng bubung buah 5.000 4,000.00 20,000.00
Semen Portland Kg 8.000 1,400.00 11,200.00
Pasir pasang M3 0.032 207,900.00 6,652.80
JUMLAH HARGA BAHAN 37,852.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 92,172.80


E Overhead & Profit 15.00% 13,825.92
F Harga Satuan Pekerjaan (D+E) 105,998.72

A.4.5.2.6. Pemasangan 1 m’ bubung genteng palentong besar

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang kayu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.11 OH 0.020 105,000.00 2,100.00
Mandor L.15 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 54,320.00
B BAHAN
Genteng bubung buah 4.000 6,000.00 24,000.00
Semen Portland Kg 8.000 1,400.00 11,200.00
Pasir pasang M3 0.032 207,900.00 6,652.80
JUMLAH HARGA BAHAN 41,852.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 96,172.80


E Overhead & Profit 15.00% 14,425.92
F Harga Satuan Pekerjaan (D+E) 110,598.72

A.4.5.2.7. Pemasangan 1 m2 roof light fibreglass 90 x 180

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.067 100,000.00 6,700.00

III - 112
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,405.00
B BAHAN
Rooflight 90 x 180 Lbr 0.600 62,000.00 37,200.00
Paku biasa ½”-1” Kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 38,200.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,605.00


E Overhead & Profit 15.00% 8,640.75
F Harga Satuan Pekerjaan (D+E) 66,245.75

A.4.5.2.8. Pemasangan 1 m2 atap asbes gelombang 0,92 m x 2 ,5 m x 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.075 100,000.00 7,500.00
Kepala tukang L.11 OH 0.008 105,000.00 840.00
Mandor L.15 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 20,420.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.500 32,000.00 16,000.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 18,160.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,580.00


E Overhead & Profit 15.00% 5,787.00
F Harga Satuan Pekerjaan (D+E) 44,367.00

A.4.5.2.9. Pemasangan 1 m2 atap asbes gelombang 0,92 m x 2,25 m x 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.075 100,000.00 7,500.00
Kepala tukang L.11 OH 0.008 105,000.00 840.00
Mandor L.15 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 20,420.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.600 32,000.00 19,200.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 21,360.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 41,780.00


E Overhead & Profit 15.00% 6,267.00
F Harga Satuan Pekerjaan (D+E) 48,047.00

III - 113
A.4.5.2.10. Pemasangan 1 m2 atap asbes gelombang 0,92 m x 2,00 m x 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.600 32,000.00 19,200.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 21,360.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 41,065.00


E Overhead & Profit 15.00% 6,159.75
F Harga Satuan Pekerjaan (D+E) 47,224.75

A.4.5.2.11. Pemasangan 1 m2 atap asbes gelombang 0,92 m x 1,80 m x 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.750 32,000.00 24,000.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 26,160.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 45,865.00


E Overhead & Profit 15.00% 6,879.75
F Harga Satuan Pekerjaan (D+E) 52,744.75

A.4.5.2.12. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 3,00 m x 4 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.350 32,000.00 11,200.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 13,360.00

III - 114
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,065.00


E Overhead & Profit 15.00% 4,959.75
F Harga Satuan Pekerjaan (D+E) 38,024.75

A.4.5.2.13. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 2,70 m x 4 mm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.420 32,000.00 13,440.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 15,600.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,305.00


E Overhead & Profit 15.00% 5,295.75
F Harga Satuan Pekerjaan (D+E) 40,600.75

A.4.5.2.14. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 2,40 m x 4 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.440 32,000.00 14,080.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 16,240.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,945.00


E Overhead & Profit 15.00% 5,391.75
F Harga Satuan Pekerjaan (D+E) 41,336.75

A.4.5.2.15. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 2,10 m x 4 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00

III - 115
B BAHAN
Asbes gel 92 x 250 Lbr 0.510 32,000.00 16,320.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 18,480.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,185.00


E Overhead & Profit 15.00% 5,727.75
F Harga Satuan Pekerjaan (D+E) 43,912.75

A.4.5.2.16. Pemasangan 1 m2 atap asbes gelombang 1,05 m x 1,50 m x 4 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.800 32,000.00 25,600.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 27,760.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 47,465.00


E Overhead & Profit 15.00% 7,119.75
F Harga Satuan Pekerjaan (D+E) 54,584.75

A.4.5.2.17. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 3,00 m x 6 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.370 32,000.00 11,840.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 14,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,705.00


E Overhead & Profit 15.00% 5,055.75
F Harga Satuan Pekerjaan (D+E) 38,760.75

A.4.5.2.18. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 2,70 m x 6 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00

III - 116
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.380 32,000.00 12,160.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 14,320.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 34,025.00


E Overhead & Profit 15.00% 5,103.75
F Harga Satuan Pekerjaan (D+E) 39,128.75

A.4.5.2.19. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 2,40 m x 6 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.460 32,000.00 14,720.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 16,880.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,585.00


E Overhead & Profit 15.00% 5,487.75
F Harga Satuan Pekerjaan (D+E) 42,072.75

A.4.5.2.20. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 2,10 m x 6 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.490 32,000.00 15,680.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 17,840.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 37,545.00


E Overhead & Profit 15.00% 5,631.75
F Harga Satuan Pekerjaan (D+E) 43,176.75

III - 117
A.4.5.2.21. Pemasangan 1 m2 atap asbes gelombang 1,08 m x 1,80 m x 6 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 19,705.00
B BAHAN
Asbes gel 92 x 250 Lbr 0.570 32,000.00 18,240.00
Paku pancing 6 x 23 Kg 0.120 18,000.00 2,160.00
JUMLAH HARGA BAHAN 20,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 40,105.00


E Overhead & Profit 15.00% 6,015.75
F Harga Satuan Pekerjaan (D+E) 46,120.75

A.4.5.2.22. Pemasangan 1 m’ bubung stel gelombang 0,92 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.084 80,000.00 6,720.00
Tukang kayu L.03 OH 0.125 100,000.00 12,500.00
Kepala tukang L.11 OH 0.013 105,000.00 1,365.00
Mandor L.15 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,025.00
B BAHAN
Bubung stel gel. Lbr 2.400 62,000.00 148,800.00
Paku skrup 3,5” buah 6.000 500.00 3,000.00
JUMLAH HARGA BAHAN 151,800.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,825.00


E Overhead & Profit 15.00% 25,923.75
F Harga Satuan Pekerjaan (D+E) 198,748.75

A.4.5.2.23. Pemasangan 1 m’ bubung stel gelombang 1,05 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.084 80,000.00 6,720.00
Tukang kayu L.03 OH 0.125 100,000.00 12,500.00
Kepala tukang L.11 OH 0.013 105,000.00 1,365.00
Mandor L.15 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,025.00
B BAHAN
Bubung stel gel. Lbr 2.100 62,000.00 130,200.00
Paku skrup 3,5” buah 6.000 500.00 3,000.00
JUMLAH HARGA BAHAN 133,200.00

III - 118
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 154,225.00


E Overhead & Profit 15.00% 23,133.75
F Harga Satuan Pekerjaan (D+E) 177,358.75

A.4.5.2.24. Pemasangan 1 m’ bubung stel gelombang 1,08 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.084 80,000.00 6,720.00
Tukang kayu L.03 OH 0.125 100,000.00 12,500.00
Kepala tukang L.11 OH 0.013 105,000.00 1,365.00
Mandor L.15 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,025.00
B BAHAN
Bubung stel gel. Lbr 2.050 62,000.00 127,100.00
Paku skrup 3,5” buah 6.000 500.00 3,000.00
JUMLAH HARGA BAHAN 130,100.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 151,125.00


E Overhead & Profit 15.00% 22,668.75
F Harga Satuan Pekerjaan (D+E) 173,793.75

A.4.5.2.25. Pemasangan 1 m’ nok paten 0,92 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.084 80,000.00 6,720.00
Tukang kayu L.03 OH 0.125 100,000.00 12,500.00
Kepala tukang L.11 OH 0.013 105,000.00 1,365.00
Mandor L.15 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,025.00
B BAHAN
Nok paten 92 cm Lbr 1.200 62,000.00 74,400.00
Paku skrup 3,5” buah 6.000 500.00 3,000.00
JUMLAH HARGA BAHAN 77,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 98,425.00


E Overhead & Profit 15.00% 14,763.75
F Harga Satuan Pekerjaan (D+E) 113,188.75

A.4.5.2.26. Pemasangan 1 m’ nok paten 1,05 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.084 80,000.00 6,720.00
Tukang kayu L.03 OH 0.125 100,000.00 12,500.00

III - 119
Kepala tukang L.11 OH 0.013 105,000.00 1,365.00
Mandor L.15 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,025.00
B BAHAN
Nok paten 92 cm Lbr 1.200 62,000.00 74,400.00
Paku skrup 3,5” buah 6.000 500.00 3,000.00
JUMLAH HARGA BAHAN 77,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 98,425.00


E Overhead & Profit 15.00% 14,763.75
F Harga Satuan Pekerjaan (D+E) 113,188.75

A.4.5.2.27. Pemasangan 1 m’ nok paten 1,08 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.084 80,000.00 6,720.00
Tukang kayu L.03 OH 0.125 100,000.00 12,500.00
Kepala tukang L.11 OH 0.013 105,000.00 1,365.00
Mandor L.15 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,025.00
B BAHAN
Nok paten 92 cm Lbr 1.200 62,000.00 74,400.00
Paku skrup 3,5” buah 6.000 500.00 3,000.00
JUMLAH HARGA BAHAN 77,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 98,425.00


E Overhead & Profit 15.00% 14,763.75
F Harga Satuan Pekerjaan (D+E) 113,188.75

A.4.5.2.28. Pemasangan 1 m’ nok stel rata 0,92 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.11 OH 0.013 105,000.00 1,365.00
Mandor L.15 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 24,805.00
B BAHAN
Nok paten 92 cm Lbr 1.100 62,000.00 68,200.00
Paku skrup 3,5” buah 6.000 500.00 3,000.00
JUMLAH HARGA BAHAN 71,200.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 96,005.00


E Overhead & Profit 15.00% 14,400.75
F Harga Satuan Pekerjaan (D+E) 110,405.75

III - 120
A.4.5.2.29. Pemasangan 1 m’ nok stel rata 1,05 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.084 80,000.00 6,720.00
Tukang kayu L.03 OH 0.125 100,000.00 12,500.00
Kepala tukang L.11 OH 0.013 105,000.00 1,365.00
Mandor L.15 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,025.00
B BAHAN
Nok paten 92 cm Lbr 1.100 62,000.00 68,200.00
Paku skrup 3,5” buah 6.000 500.00 3,000.00
JUMLAH HARGA BAHAN 71,200.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 92,225.00


E Overhead & Profit 15.00% 13,833.75
F Harga Satuan Pekerjaan (D+E) 106,058.75

A.4.5.2.30. Pemasangan 1 m2 genteng beton

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang kayu L.03 OH 0.100 100,000.00 10,000.00
Kepala tukang L.11 OH 0.010 105,000.00 1,050.00
Mandor L.15 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 28,150.00
B BAHAN
Genteng beton buah 11.000 5,000.00 55,000.00
Paku biasa 2”-5” Kg 0.030 18,000.00 540.00
JUMLAH HARGA BAHAN 55,540.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 83,690.00


E Overhead & Profit 15.00% 12,553.50
F Harga Satuan Pekerjaan (D+E) 96,243.50

A.4.5.2.32. Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang kayu L.03 OH 0.100 100,000.00 10,000.00
Kepala tukang L.11 OH 0.010 105,000.00 1,050.00
Mandor L.15 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 27,160.00
B BAHAN
Genteng metal buah 1.300 48,000.00 62,400.00
Paku biasa ½”-1” Kg 0.200 20,000.00 4,000.00
JUMLAH HARGA BAHAN 66,400.00

III - 121
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 93,560.00


E Overhead & Profit 15.00% 14,034.00
F Harga Satuan Pekerjaan (D+E) 107,594.00

A.4.5.2.33. Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap jurai

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang kayu L.03 OH 0.100 100,000.00 10,000.00
Kepala tukang L.11 OH 0.010 105,000.00 1,050.00
Mandor L.15 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 27,160.00
B BAHAN
Genteng metal buah 2.000 48,000.00 96,000.00
Paku biasa ½”-1” Kg 0.200 20,000.00 4,000.00
JUMLAH HARGA BAHAN 100,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 127,160.00


E Overhead & Profit 15.00% 19,074.00
F Harga Satuan Pekerjaan (D+E) 146,234.00

A.4.5.2.34. Pemasangan 1 m2 atap sirap kayu

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.166 80,000.00 13,280.00
Tukang kayu L.03 OH 0.250 100,000.00 25,000.00
Kepala tukang L.11 OH 0.025 105,000.00 2,625.00
Mandor L.15 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 41,785.00
B BAHAN
Sirap kayu buah 30.000 1,625.00 48,750.00
Paku biasa ½”-1” Kg 0.200 20,000.00 4,000.00
JUMLAH HARGA BAHAN 52,750.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 94,535.00


E Overhead & Profit 15.00% 14,180.25
F Harga Satuan Pekerjaan (D+E) 108,715.25

A.4.5.2.35. Pemasangan 1 m’ nok genteng beton

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang kayu L.03 OH 0.200 100,000.00 20,000.00

III - 122
Kepala tukang L.11 OH 0.020 105,000.00 2,100.00
Mandor L.15 OH 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 56,300.00
B BAHAN
Nok genteng beton buah 3.500 4,000.00 14,000.00
Paku biasa ½”-1” Kg 0.050 20,000.00 1,000.00
Semen PC Kg 10.800 1,400.00 15,120.00
Pasir pasang M3 0.032 207,900.00 6,652.80
Semen warna Kg 1.000 6,000.00 6,000.00
JUMLAH HARGA BAHAN 42,772.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 99,072.80


E Overhead & Profit 15.00% 14,860.92
F Harga Satuan Pekerjaan (D+E) 113,933.72

A.4.5.2.37. Pemasangan 1 m’ nok genteng metal

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang kayu L.03 OH 0.150 100,000.00 15,000.00
Kepala tukang L.11 OH 0.015 105,000.00 1,575.00
Mandor L.15 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 38,005.00
B BAHAN
Nok genteng metal buah 1.100 44,333.33 48,766.67
Paku biasa ½”-1” Kg 0.050 20,000.00 1,000.00
JUMLAH HARGA BAHAN 49,766.67
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 87,771.67


E Overhead & Profit 15.00% 13,165.75
F Harga Satuan Pekerjaan (D+E) 100,937.42

A.4.5.2.38. Pemasangan 1 m’ nok sirap

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.125 80,000.00 10,000.00
Tukang kayu L.03 OH 0.250 100,000.00 25,000.00
Kepala tukang L.11 OH 0.025 105,000.00 2,625.00
Mandor L.15 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 38,285.00
B BAHAN
Seng pelat 3" x 6” Lbr 0.400 58,900.00 23,560.00
Paku biasa ½”-1” Kg 0.050 20,000.00 1,000.00
Paku biasa 2”-5” Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 25,460.00

III - 123
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,745.00


E Overhead & Profit 15.00% 9,561.75
F Harga Satuan Pekerjaan (D+E) 73,306.75

A.4.5.2.39. Pemasangan 1 m2 atap seng gelombang

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.120 80,000.00 9,600.00
Tukang kayu L.03 OH 0.060 100,000.00 6,000.00
Kepala tukang L.11 OH 0.006 105,000.00 630.00
Mandor L.15 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 16,890.00
B BAHAN
Seng gel 3”x6” Lbr 0.700 58,900.00 41,230.00
Paku biasa ½”-1” Kg 0.020 20,000.00 400.00
JUMLAH HARGA BAHAN 41,630.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 58,520.00


E Overhead & Profit 15.00% 8,778.00
F Harga Satuan Pekerjaan (D+E) 67,298.00

A.4.5.2.40. Pemasangan 1 m’nok atap seng

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.03 OH 0.070 100,000.00 7,000.00
Kepala tukang L.11 OH 0.007 105,000.00 735.00
Mandor L.15 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 20,395.00
B BAHAN
Seng pelat 3”x6” bjls 28 Lbr 0.300 58,900.00 17,670.00
Paku biasa ½”-1” Kg 0.040 20,000.00 800.00
JUMLAH HARGA BAHAN 18,470.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,865.00


E Overhead & Profit 15.00% 5,829.75
F Harga Satuan Pekerjaan (D+E) 44,694.75

A.4.5.2.41. Pemasangan 1 m2 atap alumunium

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.03 OH 0.750 100,000.00 75,000.00

III - 124
Kepala tukang L.11 OH 0.080 105,000.00 8,400.00
Mandor L.15 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 96,060.00
B BAHAN
Aluminium gel tebal 0,55 Lbr 1.050 136,000.00 142,800.00
Paku hak panjang 15 cm Kg 0.020 20,000.00 400.00
JUMLAH HARGA BAHAN 143,200.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 239,260.00


E Overhead & Profit 15.00% 35,889.00
F Harga Satuan Pekerjaan (D+E) 275,149.00

A.4.5.2.43. Pemasangan 1 m2 alumunium foil/sisalation

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.03 OH 0.050 100,000.00 5,000.00
Kepala tukang L.11 OH 0.005 105,000.00 525.00
Mandor L.15 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 18,405.00
B BAHAN
Aluminium foil M2 1.050 9,000.00 9,450.00
JUMLAH HARGA BAHAN 9,450.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,855.00


E Overhead & Profit 15.00% 4,178.25
F Harga Satuan Pekerjaan (D+E) 32,033.25

A.4.6.1 HARGA SATUAN PEKERJAAN KAYU

A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.000 80,000.00 560,000.00
Tukang kayu L.03 OH 21.000 100,000.00 2,100,000.00
Kepala tukang L.03 OH 2.100 105,000.00 220,500.00
Mandor L.04 OH 0.350 110,000.00 38,500.00
JUMLAH TENAGA KERJA 2,919,000.00
B BAHAN
Balok kayu m3 1.100 9,500,000.00 10,450,000.00
Paku 10 cm Kg 1.250 20,000.00 25,000.00
Lem kayu Kg 1.000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 10,505,000.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,424,000.00


E Overhead & Profit 15.00% 2,013,600.00
F Harga Satuan Pekerjaan (D+E) 15,437,600.00

III - 125
A.4.6.1.2. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.000 80,000.00 480,000.00
Tukang kayu L.03 OH 18.000 100,000.00 1,800,000.00
Kepala tukang L.03 OH 1.800 105,000.00 189,000.00
Mandor L.04 OH 0.300 110,000.00 33,000.00
JUMLAH TENAGA KERJA 2,502,000.00
B BAHAN
Balok kayu m3 1.200 3,500,000.00 4,200,000.00
Paku 10 cm Kg 1.250 20,000.00 25,000.00
Lem kayu Kg 1.000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 4,255,000.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 6,757,000.00


E Overhead & Profit 15.00% 1,013,550.00
F Harga Satuan Pekerjaan (D+E) 7,770,550.00

A.4.6.1.3. Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 80,000.00 28,000.00
Tukang kayu L.03 OH 1.050 100,000.00 105,000.00
Kepala tukang L.03 OH 0.105 105,000.00 11,025.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 146,005.00
B BAHAN
Papan kayu m3 0.040 5,000,000.00 200,000.00
Paku 5 – 7 cm Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 200,900.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 346,905.00


E Overhead & Profit 15.00% 52,035.75
F Harga Satuan Pekerjaan (D+E) 398,940.75

A.4.6.1.4. Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.350 80,000.00 28,000.00
Tukang kayu L.03 OH 1.050 100,000.00 105,000.00
Kepala tukang L.03 OH 0.105 105,000.00 11,025.00
Mandor L.04 OH 0.018 110,000.00 1,980.00
JUMLAH TENAGA KERJA 146,005.00
B BAHAN
Papan kayu m3 0.040 3,500,000.00 140,000.00
Paku 5 – 7 cm Kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 140,900.00

III - 126
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 286,905.00


E Overhead & Profit 15.00% 43,035.75
F Harga Satuan Pekerjaan (D+E) 329,940.75

A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang kayu L.03 OH 3.000 100,000.00 300,000.00
Kepala tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 417,000.00
B BAHAN
Papan kayu m3 0.040 5,000,000.00 200,000.00
Lem kayu Kg 0.500 30,000.00 15,000.00
JUMLAH HARGA BAHAN 215,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 632,000.00


E Overhead & Profit 15.00% 94,800.00
F Harga Satuan Pekerjaan (D+E) 726,800.00

A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.800 80,000.00 64,000.00
Tukang kayu L.03 OH 2.400 100,000.00 240,000.00
Kepala tukang L.03 OH 0.240 105,000.00 25,200.00
Mandor L.04 OH 0.040 110,000.00 4,400.00
JUMLAH TENAGA KERJA 333,600.00
B BAHAN
Papan kayu m3 0.024 5,000,000.00 120,000.00
Lem kayu Kg 0.300 30,000.00 9,000.00
JUMLAH HARGA BAHAN 129,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 462,600.00


E Overhead & Profit 15.00% 69,390.00
F Harga Satuan Pekerjaan (D+E) 531,990.00

A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang kayu L.03 OH 3.000 100,000.00 300,000.00

III - 127
Kepala tukang L.03 OH 0.300 105,000.00 31,500.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 417,000.00
B BAHAN
Papan kayu m3 0.064 5,000,000.00 320,000.00
Lem kayu Kg 0.500 30,000.00 15,000.00
JUMLAH HARGA BAHAN 335,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 752,000.00
E Overhead & Profit 15.00% 112,800.00
F Harga Satuan Pekerjaan (D+E) 864,800.00

A.4.6.1.8. Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.700 80,000.00 56,000.00
Tukang kayu L.03 OH 2.100 100,000.00 210,000.00
Kepala tukang L.03 OH 0.210 105,000.00 22,050.00
Mandor L.04 OH 0.035 110,000.00 3,850.00
JUMLAH TENAGA KERJA 291,900.00
B BAHAN
Papan kayu m3 0.025 5,000,000.00 125,000.00
Paku 1 cm – 2,5 cm kg 0.030 18,000.00 540.00
Lem kayu kg 0.500 30,000.00 15,000.00
Plywood tebal 4 mm Lembar 1.000 106,500.00 106,500.00
Ukuran (90 x 220) cm
JUMLAH HARGA BAHAN 247,040.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 538,940.00


E Overhead & Profit 15.00% 80,841.00
F Harga Satuan Pekerjaan (D+E) 619,781.00

A.4.6.1.9. Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.80 80,000.00 64,000.00
Tukang kayu L.03 OH 2.40 100,000.00 240,000.00
Kepala tukang L.03 OH 0.24 105,000.00 25,200.00
Mandor L.04 OH 0.04 110,000.00 4,400.00
JUMLAH TENAGA KERJA 333,600.00
B BAHAN
Papan kayu m3 0.026 5,000,000.00 128,000.00
Paku 1 cm – 2,5 cm kg 0.030 18,000.00 540.00
Lem kayu kg 0.500 30,000.00 15,000.00
Plywood 4 mm Lembar 1.000 106,500.00 106,500.00
(90 x 220) cm
JUMLAH HARGA BAHAN 250,040.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 583,640.00


E Overhead & Profit 15.00% 87,546.00
F Harga Satuan Pekerjaan (D+E) 671,186.00

III - 128
A.4.6.1.10. Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.670 80,000.00 53,600.00
Tukang kayu L.03 OH 2.000 100,000.00 200,000.00
Kepala tukang L.03 OH 0.200 105,000.00 21,000.00
Mandor L.04 OH 0.335 110,000.00 36,850.00
JUMLAH TENAGA KERJA 311,450.00
B BAHAN
Papan kayu m3 0.060 5,000,000.00 300,000.00
Paku 1 – 2,5 cm kg 0.150 18,000.00 2,700.00
JUMLAH HARGA BAHAN 302,700.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 614,150.00


E Overhead & Profit 15.00% 92,122.50
F Harga Satuan Pekerjaan (D+E) 706,272.50

A.4.6.1.11. Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.800 80,000.00 64,000.00
Tukang kayu L.03 OH 2.400 100,000.00 240,000.00
Kepala tukang L.03 OH 0.240 105,000.00 25,200.00
Mandor L.04 OH 0.040 110,000.00 4,400.00
JUMLAH TENAGA KERJA 333,600.00
B BAHAN
Papan kayu m3 0.025 9,500,000.00 237,500.00
Paku 1 – 2,5 cm kg 0.030 18,000.00 540.00
Lem kayu kg 0.300 30,000.00 9,000.00
Teakwood 4 mm Lembar 1.000 75,100.00 75,100.00
90 x 220 cm
JUMLAH HARGA BAHAN 322,140.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 655,740.00


E Overhead & Profit 15.00% 98,361.00
F Harga Satuan Pekerjaan (D+E) 754,101.00

A.4.6.1.12. Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.850 80,000.00 68,000.00
Tukang kayu L.03 OH 2.550 100,000.00 255,000.00
Kepala tukang L.03 OH 0.255 105,000.00 26,775.00
Mandor L.04 OH 0.043 110,000.00 4,730.00
JUMLAH TENAGA KERJA 354,505.00

III - 129
B BAHAN
Papan kayu m3 0.025 5,000,000.00 125,000.00
Paku 1 – 2,5 cm kg 0.030 18,000.00 540.00
Lem kayu kg 0.800 30,000.00 24,000.00
Teakwood 4 mm Lembar 1.000 75,100.00 75,100.00
90 x 220 cm
Formika Lembar 0.500 224,640.00
JUMLAH HARGA BAHAN
C PERALATAN -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 579,145.00
E Overhead & Profit 15.00% 86,871.75
F Harga Satuan Pekerjaan (D+E) 666,016.75

A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.000 80,000.00 320,000.00
Tukang kayu L.03 OH 12.000 100,000.00 1,200,000.00
Kepala tukang L.03 OH 1.200 105,000.00 126,000.00
Mandor L.04 OH 0.200 110,000.00 22,000.00
JUMLAH TENAGA KERJA 1,668,000.00
B BAHAN
Balok kayu m3 1.100 3,500,000.00 3,850,000.00
Besi strip tebal 5 mm kg 15.000 13,750.00 206,250.00
Paku 12 cm kg 5.600 18,000.00 100,800.00
JUMLAH HARGA BAHAN 4,157,050.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 5,825,050.00
E Overhead & Profit 15.00% 873,757.50
F Harga Satuan Pekerjaan (D+E) 6,698,807.50

A.4.6.1.14. Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.700 80,000.00 536,000.00
Tukang kayu L.03 OH 20.100 100,000.00 2,010,000.00
Kepala tukang L.03 OH 2.010 105,000.00 211,050.00
Mandor L.04 OH 0.335 110,000.00 36,850.00
JUMLAH TENAGA KERJA 2,793,900.00
B BAHAN
Balok kayu m3 1.200 9,500,000.00 11,400,000.00
Besi strip tebal 5 mm kg 15.000 13,750.00 206,250.00
Paku 12 cm kg 5.600 18,000.00 100,800.00
JUMLAH HARGA BAHAN 11,707,050.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 14,500,950.00
E Overhead & Profit 15.00% 2,175,142.50
F Harga Satuan Pekerjaan (D+E) 16,676,092.50

III - 130
A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.700 80,000.00 536,000.00
Tukang kayu L.03 OH 20.100 100,000.00 2,010,000.00
Kepala tukang L.03 OH 2.010 105,000.00 211,050.00
Mandor L.04 OH 0.335 110,000.00 36,850.00
JUMLAH TENAGA KERJA 2,793,900.00
B BAHAN
Balok kayu m3 1.100 5,000,000.00 5,500,000.00
Besi strip tebal 5 mm kg 15.000 13,750.00 206,250.00
Paku 12 cm kg 3.000 18,000.00 54,000.00
JUMLAH HARGA BAHAN 5,760,250.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 8,554,150.00


E Overhead & Profit 15.00% 1,283,122.50
F Harga Satuan Pekerjaan (D+E) 9,837,272.50

A.4.6.1.16. Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.03 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 19,600.00
B BAHAN
Kaso-kaso 5 x 7cm m3 0.014 6,000,000.00 84,000.00
Reng 2 x 3 cm m3 0.036 7,083,333.33 255,000.00
Paku 5 dan 10 cm kg 0.250 18,000.00 4,500.00
JUMLAH HARGA BAHAN 343,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 363,100.00


E Overhead & Profit 15.00% 54,465.00
F Harga Satuan Pekerjaan (D+E) 417,565.00

A.4.6.1.17. Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.03 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 19,600.00
B BAHAN
Kaso-kaso 5 x 7cm m3 0.014 6,000,000.00 84,000.00
Reng (3 x 4) cm m3 0.057 7,083,333.33 403,750.00
Paku 5 dan 10 cm kg 0.250 18,000.00 4,500.00
JUMLAH HARGA BAHAN 492,250.00

III - 131
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 511,850.00


E Overhead & Profit 15.00% 76,777.50
F Harga Satuan Pekerjaan (D+E) 588,627.50

A.4.6.1.18. Pemasangan 1 m2 rangka atap sirap, kayu kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.120 80,000.00 9,600.00
Tukang kayu L.03 OH 0.120 100,000.00 12,000.00
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 23,520.00
B BAHAN
Kayu kelas II m3 0.014 5,000,000.00 70,000.00
Paku 5 - 10 cm m3 0.057 18,000.00 1,026.00
JUMLAH HARGA BAHAN 71,026.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 94,546.00


E Overhead & Profit 15.00% 14,181.90
F Harga Satuan Pekerjaan (D+E) 108,727.90

A.4.6.1.19. Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II atau III

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.03 OH 0.300 100,000.00 30,000.00
Kepala tukang L.03 OH 0.030 105,000.00 3,150.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 53,400.00
B BAHAN
Kaso-kaso 5 x 7cm m3 0.015 6,000,000.00 92,400.00
Paku 7 cm – 10 cm kg 0.200 18,000.00 3,600.00
JUMLAH HARGA BAHAN 96,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 149,400.00


E Overhead & Profit 15.00% 22,410.00
F Harga Satuan Pekerjaan (D+E) 171,810.00

A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang kayu L.03 OH 0.300 100,000.00 30,000.00

III - 132
Kepala tukang L.03 OH 0.030 105,000.00 3,150.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 50,250.00
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.016 6,000,000.00 97,800.00
Paku 7 – 10 cm kg 0.250 18,000.00 4,500.00
JUMLAH HARGA BAHAN 102,300.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 152,550.00


E Overhead & Profit 15.00% 22,882.50
F Harga Satuan Pekerjaan (D+E) 175,432.50

A.4.6.1.21. Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 30,650.00
B BAHAN
Papan kayu m3 0.011 5,000,000.00 54,000.00
Paku 5 dan 7 cm kg 0.100 18,000.00 1,800.00
JUMLAH HARGA BAHAN 55,800.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 86,450.00


E Overhead & Profit 15.00% 12,967.50
F Harga Satuan Pekerjaan (D+E) 99,417.50

A.4.6.1.22. Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.03 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 30,650.00
B BAHAN
Papan kayu m3 0.011 5,000,000.00 55,000.00
Paku 5 dan 7 cm kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 55,900.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 86,550.00


E Overhead & Profit 15.00% 12,982.50
F Harga Satuan Pekerjaan (D+E) 99,532.50

III - 133
A.4.6.1.23. Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II atau III

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang kayu L.03 OH 0.450 100,000.00 45,000.00
Kepala tukang L.03 OH 0.045 105,000.00 4,725.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 62,605.00
B BAHAN
Balok kayu m3 0.028 3,500,000.00 98,000.00
Paku 5 dan 7 cm kg 0.150 18,000.00 2,700.00
JUMLAH HARGA BAHAN 100,700.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 163,305.00
E Overhead & Profit 15.00% 24,495.75
F Harga Satuan Pekerjaan (D+E) 187,800.75

A.4.6.1.25. Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang kayu L.03 OH 0.600 100,000.00 60,000.00
Kepala tukang L.03 OH 0.060 105,000.00 6,300.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 83,400.00
B BAHAN
Balok kayu, 6 x 12 m3 0.028 5,000,000.00 140,000.00
Paku 5 dan 10 kg 0.150 18,000.00 2,700.00
Plywood 4 mm, Lembar 0.860 106,500.00 91,590.00
120 x 240
Lem kayu kg 0.560 30,000.00 16,800.00
JUMLAH HARGA BAHAN 251,090.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 334,490.00
E Overhead & Profit 15.00% 50,173.50
F Harga Satuan Pekerjaan (D+E) 384,663.50

A.4.6.1.26. Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas I

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.600 80,000.00 48,000.00
Tukang kayu L.03 OH 1.800 100,000.00 180,000.00
Kepala tukang L.03 OH 0.180 105,000.00 18,900.00
Mandor L.04 OH 0.030 110,000.00 3,300.00
JUMLAH TENAGA KERJA 250,200.00
B BAHAN
Papan kayu m3 0.007 9,500,000.00 66,500.00
Paku 5 dan 10 kg 0.100 18,000.00 1,800.00
Paku skrup 10 cm kg 0.150 18,000.00 2,700.00
JUMLAH HARGA BAHAN 71,000.00

III - 134
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 321,200.00


E Overhead & Profit 15.00% 48,180.00
F Harga Satuan Pekerjaan (D+E) 369,380.00

A.4.6.1.27. Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120 x 240) cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 80,000.00 2,000.00
Tukang kayu L.03 OH 0.075 100,000.00 7,500.00
Kepala tukang L.03 OH 0.008 105,000.00 840.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 10,450.00
B BAHAN
Plywood 4 mm m3 0.400 106,500.00 42,600.00
Paku 1 dan 2,5 kg 0.050 18,000.00 900.00
JUMLAH HARGA BAHAN 43,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 53,950.00


E Overhead & Profit 15.00% 8,092.50
F Harga Satuan Pekerjaan (D+E) 62,042.50

A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.1. Pemasangan 1 buah kunci tanam antik

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.060 80,000.00 4,800.00
Tukang kayu L.02 OH 0.600 100,000.00 60,000.00
Kepala tukang L.03 OH 0.060 105,000.00 6,300.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 71,430.00
B BAHAN
Kunci tanam antik buah 1.000 222,000.00 222,000.00
JUMLAH HARGA BAHAN 222,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 293,430.00


E Overhead & Profit 15.00% 44,014.50
F Harga Satuan Pekerjaan (D+E) 337,444.50

A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA KERJA
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang kayu L.02 OH 0.500 100,000.00 50,000.00

III - 135
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 56,600.00
B BAHAN
Kunci tanam biasa buah 1.000 130,000.00 130,000.00
JUMLAH HARGA BAHAN 130,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 186,600.00


E Overhead & Profit 15.00% 27,990.00
F Harga Satuan Pekerjaan (D+E) 214,590.00

A.4.6.2.3. Pemasangan 1 buah kunci kamar mandi

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.005 80,000.00 400.00
Tukang kayu L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 55,980.00
B BAHAN
Kunci tanam KM buah 1.000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,980.00


E Overhead & Profit 15.00% 15,147.00
F Harga Satuan Pekerjaan (D+E) 116,127.00

A.4.6.2.4. Pemasangan 1 buah kunci silinder

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA KERJA
Pekerja L.01 OH 0.005 80,000.00 400.00
Tukang kayu L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 55,980.00
B BAHAN
Kunci silinder buah 1.000 70,000.00 70,000.00
JUMLAH HARGA BAHAN 70,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 125,980.00


E Overhead & Profit 15.00% 18,897.00
F Harga Satuan Pekerjaan (D+E) 144,877.00

A.4.6.2.5. Pemasangan 1 buah engsel pintu

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang kayu L.02 OH 0.150 100,000.00 15,000.00

III - 136
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 17,863.00
B BAHAN
Engsel pintu buah 1.000 19,000.00 19,000.00
JUMLAH HARGA BAHAN 19,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,863.00


E Overhead & Profit 15.00% 5,529.45
F Harga Satuan Pekerjaan (D+E) 42,392.45

A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang kayu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.001 110,000.00 55.00
JUMLAH TENAGA KERJA 11,905.00
B BAHAN
Engsel kupu-kupu buah 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 36,905.00


E Overhead & Profit 15.00% 5,535.75
F Harga Satuan Pekerjaan (D+E) 42,440.75

A.4.6.2.7. Pemasangan 1 buah engsel angin

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Tukang kayu L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.001 110,000.00 55.00
JUMLAH TENAGA KERJA 30,155.00
B BAHAN
Engsel angin buah 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 20,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,155.00


E Overhead & Profit 15.00% 7,523.25
F Harga Satuan Pekerjaan (D+E) 57,678.25

A.4.6.2.8. Pemasangan 1 buah spring knip

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang kayu L.02 OH 0.150 100,000.00 15,000.00

III - 137
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 18,655.00
B BAHAN
Spring knip buah 1.000 22,000.00 22,000.00
JUMLAH HARGA BAHAN 22,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 40,655.00


E Overhead & Profit 15.00% 6,098.25
F Harga Satuan Pekerjaan (D+E) 46,753.25

A.4.6.2.9. Pemasangan 1 buah kait angin

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang kayu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 18,655.00
B BAHAN
Kait angin buah 1.000 7,500.00 7,500.00
JUMLAH HARGA BAHAN 7,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,155.00


E Overhead & Profit 15.00% 3,923.25
F Harga Satuan Pekerjaan (D+E) 30,078.25

A.4.6.2.10. Pemasangan 1 buah door closer

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 80,000.00 4,000.00
Tukang kayu L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 59,580.00
B BAHAN
Door closer set 1.000 280,000.00 280,000.00
JUMLAH HARGA BAHAN 280,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 339,580.00


E Overhead & Profit 15.00% 50,937.00
F Harga Satuan Pekerjaan (D+E) 390,517.00

A.4.6.2.11. Pemasangan 1 buah kunci slot (grendel)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang kayu L.02 OH 0.200 100,000.00 20,000.00

III - 138
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 23,810.00
B BAHAN
Kunci slot buah 1.000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 12,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,810.00


E Overhead & Profit 15.00% 5,371.50
F Harga Satuan Pekerjaan (D+E) 41,181.50

A.4.6.2.12. Pemasangan 1 buah door holder

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 80,000.00 4,000.00
Tukang kayu L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 59,580.00
B BAHAN
Door holder buah 1.000 23,000.00 23,000.00
JUMLAH HARGA BAHAN 23,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 82,580.00


E Overhead & Profit 15.00% 12,387.00
F Harga Satuan Pekerjaan (D+E) 94,967.00

A.4.6.2.13. Pemasangan 1 buah door stop

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang kayu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 12,400.00
B BAHAN
Door stop buah 1.000 40,000.00 40,000.00
JUMLAH HARGA BAHAN 40,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 52,400.00


E Overhead & Profit 15.00% 7,860.00
F Harga Satuan Pekerjaan (D+E) 60,260.00

A.4.6.2.14. Pemasangan 1 buah rel pintu sorong

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.060 80,000.00 4,800.00
Tukang kayu L.02 OH 0.600 100,000.00 60,000.00

III - 139
Kepala tukang L.03 OH 0.060 105,000.00 6,300.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 71,430.00
B BAHAN
Rel pintu sorong Set 1.000 350,000.00 350,000.00
JUMLAH HARGA BAHAN 350,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 421,430.00


E Overhead & Profit 15.00% 63,214.50
F Harga Satuan Pekerjaan (D+E) 484,644.50

A.4.6.2.15. Pemasangan 1 buah kunci lemari

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 80,000.00 2,000.00
Tukang kayu L.02 OH 0.250 100,000.00 25,000.00
Kepala tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 29,735.00
B BAHAN
Kunci lemari Set 1.000 142,000.00 142,000.00
JUMLAH HARGA BAHAN 142,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 171,735.00


E Overhead & Profit 15.00% 25,760.25
F Harga Satuan Pekerjaan (D+E) 197,495.25

A.4.6.2.16. Pemasangan 1 m2 kaca tebal 3 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang kayu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 17,863.00
B BAHAN
Kaca tebal 3 mm m2 1.100 70,000.00 77,000.00
Sealant Kg 0.050 42,000.00 2,100.00
JUMLAH HARGA BAHAN 79,100.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 96,963.00


E Overhead & Profit 15.00% 14,544.45
F Harga Satuan Pekerjaan (D+E) 111,507.45

A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang kayu L.02 OH 0.150 100,000.00 15,000.00

III - 140
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 17,863.00
B BAHAN
Kaca tebal 5 mm m2 1.100 80,000.00 88,000.00
Sealant Kg 0.050 42,000.00 2,100.00
JUMLAH HARGA BAHAN 90,100.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 107,963.00


E Overhead & Profit 15.00% 16,194.45
F Harga Satuan Pekerjaan (D+E) 124,157.45

A.4.6.2.18. Pemasangan 1 m2 kaca tebal 8 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.017 80,000.00 1,360.00
Tukang kayu L.02 OH 0.170 100,000.00 17,000.00
Kepala tukang L.03 OH 0.017 105,000.00 1,785.00
Mandor L.04 OH 0.001 110,000.00 99.00
JUMLAH TENAGA KERJA 20,244.00
B BAHAN
Kaca tebal 8 mm m2 1.100 150,000.00 165,000.00
Sealant Kg 0.070 42,000.00 2,940.00
JUMLAH HARGA BAHAN 167,940.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 188,184.00


E Overhead & Profit 15.00% 28,227.60
F Harga Satuan Pekerjaan (D+E) 216,411.60

A.4.6.2.19. Pemasangan 1 m2 kaca buram tebal 12 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.025 80,000.00 2,000.00
Tukang kayu L.02 OH 0.250 100,000.00 25,000.00
Kepala tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 29,768.00
B BAHAN
Kaca buram 12 mm m2 1.100 360,500.00 396,550.00
Sealant Kg 0.070 42,000.00 2,940.00
JUMLAH HARGA BAHAN 399,490.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 429,258.00


E Overhead & Profit 15.00% 64,388.70
F Harga Satuan Pekerjaan (D+E) 493,646.70

III - 141
A.4.6.2.20. Pemasangan 1 m2 kaca cermin tebal 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang kayu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 18,655.00
B BAHAN
Kaca cermin 5 mm m2 1.100 135,000.00 148,500.00
JUMLAH HARGA BAHAN 148,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 167,155.00


E Overhead & Profit 15.00% 25,073.25
F Harga Satuan Pekerjaan (D+E) 192,228.25

A.4.6.2.21. Pemasangan 1 m2 kaca cermin tebal 8 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.017 80,000.00 1,360.00
Tukang kayu L.02 OH 0.170 100,000.00 17,000.00
Kepala tukang L.03 OH 0.017 105,000.00 1,785.00
Mandor L.04 OH 0.009 110,000.00 990.00
JUMLAH TENAGA KERJA 21,135.00
B BAHAN
Kaca cermin 8 mm m2 1.100 257,700.00 283,470.00
JUMLAH HARGA BAHAN 283,470.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 304,605.00


E Overhead & Profit 15.00% 45,690.75
F Harga Satuan Pekerjaan (D+E) 350,295.75

A.4.6.2.22. Pemasangan 1 m2 kaca wireglassed tebal 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.015 80,000.00 1,200.00
Tukang kayu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 18,655.00
B BAHAN
Kaca wireglassed 5 mm m2 1.100 210,000.00 231,000.00
JUMLAH HARGA BAHAN 231,000.00

C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 249,655.00


E Overhead & Profit 15.00% 37,448.25
F Harga Satuan Pekerjaan (D+E) 287,103.25

III - 142
A.4.6.2.23. Pemasangan 1 m2 kaca patri tebal 5 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.075 80,000.00 6,000.00
Tukang kayu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 23,015.00
B BAHAN
Kaca patri 5mm m2 1.100 2,000,000.00 2,200,000.00
Sealant Kg 0.050 42,000.00 2,100.00
JUMLAH HARGA BAHAN 2,202,100.00

C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 2,225,115.00


E Overhead & Profit 15.00% 333,767.25
F Harga Satuan Pekerjaan (D+E) 2,558,882.25

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.1. 1 m2 Pengikisan/pengerokan permukaan cat lama

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 12,330.00
B BAHAN
Soda api Kg 0.050 25,000.00 1,250.00
JUMLAH HARGA BAHAN 1,250.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,580.00


E Overhead & Profit 15.00% 2,037.00
F Harga Satuan Pekerjaan (D+E) 15,617.00

A.4.7.1.2. 1 m2 Pencucian bidang permukaan tembok yang pernah dicat

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 12,330.00
B BAHAN
Sabun Kg 0.050 11,000.00 550.00
JUMLAH HARGA BAHAN 550.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 12,880.00


E Overhead & Profit 15.00% 1,932.00
F Harga Satuan Pekerjaan (D+E) 14,812.00

III - 143
A.4.7.1.3. 1 m2 Pengerokan karat pada permukaan baja cara manual

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 12,880.00
B BAHAN
Sabun Kg 0.050 11,000.00 550.00
JUMLAH HARGA BAHAN 550.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 13,430.00


E Overhead & Profit 15.00% 2,014.50
F Harga Satuan Pekerjaan (D+E) 15,444.50

A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.0 OH 0.070 80,000.00 5,600.00
Tukang cat 1
L.0 OH 0.009 100,000.00 900.00
Kepala tukang 2
L.0 OH 0.006 105,000.00 630.00
Mandor 3
L.0 OH 0.003 110,000.00 330.00
4 JUMLAH TENAGA KERJA 7,460.00
B BAHAN
Cat menie Kg 0.200 25,000.00 5,000.00
Plamuur Kg 0.150 23,000.00 3,450.00
Cat dasar Kg 0.170 25,000.00 4,250.00
Cat penutup (setara avian) Kg 0.260 50,000.00 13,000.00
Kuas buah 0.010 12,000.00 120.00
Pengencer Kg 0.030 24,000.00 720.00
Ampelas Lbr 0.200 3,000.00 600.00
JUMLAH HARGA BAHAN 27,140.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 34,600.00
E Overhead & Profit 15.00% 5,190.00
F Harga Satuan Pekerjaan (D+E) 39,790.00

A.4.7.1.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.0 OH 0.070 80,000.00 5,600.00
Tukang cat 1
L.0 OH 0.105 100,000.00 10,500.00
Kepala tukang 2
L.0 OH 0.004 105,000.00 420.00
Mandor 3
L.0 OH 0.003 110,000.00 330.00
4 JUMLAH TENAGA KERJA 16,850.00
B BAHAN
Cat menie Kg 0.200 25,000.00 5,000.00
Plamuur Kg 0.150 23,000.00 3,450.00
Cat dasar Kg 0.170 25,000.00 4,250.00

III - 144
Cat penutup (setara avian) Kg 0.350 50,000.00 17,500.00
Kuas buah 0.010 12,000.00 120.00
Pengencer Kg 0.030 24,000.00 720.00
Ampelas Lbr 0.200 3,000.00 600.00
JUMLAH HARGA BAHAN 31,640.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 48,490.00
E Overhead & Profit 15.00% 7,273.50
F Harga Satuan Pekerjaan (D+E) 55,763.50

A.4.7.1.6. Pelaburan 1 m2 bidang kayu dengan teak oil

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.040 80,000.00 3,200.00
Tukang cat L.02 OH 0.063 100,000.00 6,300.00
Kepala tukang L.03 OH 0.063 105,000.00 6,615.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 16,445.00
B BAHAN
Teak oil L 0.360 30,250.00 10,890.00
JUMLAH HARGA BAHAN 10,890.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,335.00


E Overhead & Profit 15.00% 4,100.25
F Harga Satuan Pekerjaan (D+E) 31,435.25

A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.040 80,000.00 3,200.00
Tukang cat L.02 OH 0.060 100,000.00 6,000.00
Kepala tukang L.03 OH 0.016 105,000.00 1,680.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 11,210.00
B BAHAN
Politur L 0.150 37,950.00 5,692.50
Politur jadi L 0.372 43,065.00 16,020.18
Ampelas Lbr 2.000 3,000.00 6,000.00
JUMLAH HARGA BAHAN 27,712.68
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,922.68


E Overhead & Profit 15.00% 5,838.40
F Harga Satuan Pekerjaan (D+E) 44,761.08

A.4.7.1.8. Pelaburan 1 m2 bidang kayu dengan cat residu dan ter

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.100 80,000.00 8,000.00
Mandor L.04 OH 0.006 110,000.00 660.00

III - 145
JUMLAH TENAGA KERJA 8,660.00
B BAHAN
Residu atau ter L 0.350 27,500.00 9,625.00
JUMLAH HARGA BAHAN 9,625.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 18,285.00


E Overhead & Profit 15.00% 2,742.75
F Harga Satuan Pekerjaan (D+E) 21,027.75

A.4.7.1.9. Pelaburan 1 m2 bidang kayu dengan vernis

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.160 80,000.00 12,800.00
Tukang cat L.02 OH 0.160 100,000.00 16,000.00
Kepala tukang L.03 OH 0.016 105,000.00 1,680.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 30,810.00
B BAHAN
Vernis L 0.150 34,650.00 5,197.50
Dempul Kg 0.050 18,500.00 925.00
Ampelas Lbr 0.100 3,000.00 300.00
JUMLAH HARGA BAHAN 6,422.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 37,232.50


E Overhead & Profit 15.00% 5,584.88
F Harga Satuan Pekerjaan (D+E) 42,817.38

A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang cat L.02 OH 0.063 100,000.00 6,300.00
Kepala tukang L.03 OH 0.006 105,000.00 661.50
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 8,891.50
B BAHAN
Plamuur Kg 0.100 27,000.00 2,700.00
Cat dasar Kg 0.100 25,000.00 2,500.00
Cat penutup Kg 0.260 27,500.00 7,150.00
JUMLAH HARGA BAHAN 12,350.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 21,241.50


E Overhead & Profit 15.00% 3,186.23
F Harga Satuan Pekerjaan (D+E) 24,427.73

A.4.7.1.11. Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.028 80,000.00 2,240.00
Tukang cat L.02 OH 0.042 100,000.00 4,200.00

III - 146
Kepala tukang L.03 OH 0.004 105,000.00 441.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 7,211.00
B BAHAN
Cat dasar Kg 0.120 25,000.00 3,000.00
Cat penutup Kg 0.180 27,500.00 4,950.00
JUMLAH HARGA BAHAN 7,950.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,161.00


E Overhead & Profit 15.00% 2,274.15
F Harga Satuan Pekerjaan (D+E) 17,435.15

A.4.7.1.12. Pelaburan 1 m2 tembok dengan kalkarium

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.028 80,000.00 2,240.00
Tukang cat L.02 OH 0.042 100,000.00 4,200.00
Kepala tukang L.03 OH 0.004 105,000.00 441.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 7,211.00
B BAHAN
Kalkarium Kg 0.100 18,500.00 1,850.00
JUMLAH HARGA BAHAN 1,850.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 9,061.00


E Overhead & Profit 15.00% 1,359.15
F Harga Satuan Pekerjaan (D+E) 10,420.15

A.4.7.1.13. Pelaburan 1 m2 tembok dengan kapur sirih

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.150 80,000.00 12,000.00
Tukang cat L.02 OH 0.001 100,000.00 100.00
Kepala tukang L.03 OH 0.000 105,000.00 10.50
Mandor L.04 OH 0.003 110,000.00 275.00
JUMLAH TENAGA KERJA 12,385.50
B BAHAN
Kapur sirih Kg 0.150 2,000.00 300.00
Ampelas Lbr 0.100 3,000.00 300.00
Alang-alang Ikat 0.250 10,000.00 2,500.00
JUMLAH HARGA BAHAN 3,100.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 15,485.50


E Overhead & Profit 15.00% 2,322.83
F Harga Satuan Pekerjaan (D+E) 17,808.33

III - 147
A.4.7.1.14. Pelaburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.040 80,000.00 3,200.00
Tukang cat L.02 OH 0.005 100,000.00 500.00
Kepala tukang L.03 OH 0.001 105,000.00 52.50
Mandor L.04 OH 0.003 110,000.00 275.00
JUMLAH TENAGA KERJA 4,027.50
B BAHAN
Kapur sirih Kg 0.300 2,000.00 600.00
Ampelas Lbr 0.200 3,000.00 600.00
Alang-alang Ikat 0.250 10,000.00 2,500.00
JUMLAH HARGA BAHAN 3,700.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 7,727.50


E Overhead & Profit 15.00% 1,159.13
F Harga Satuan Pekerjaan (D+E) 8,886.63

A.4.7.1.15. Pemasangan 1 m2 wallpaper

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang cat L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.003 110,000.00 275.00
JUMLAH TENAGA KERJA 23,975.00
B BAHAN
Wall paper m2 1.200 70,000.00 84,000.00
Lem Kg 0.200 22,000.00 4,400.00
JUMLAH HARGA BAHAN 88,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 112,375.00


E Overhead & Profit 15.00% 16,856.25
F Harga Satuan Pekerjaan (D+E) 129,231.25

A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan menie besi

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.020 80,000.00 1,600.00
Tukang cat L.02 OH 0.200 100,000.00 20,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.003 110,000.00 275.00
JUMLAH TENAGA KERJA 23,975.00
B BAHAN
Menie besi Kg 0.100 25,000.00 2,500.00
Kwas buah 0.010 12,000.00 120.00
JUMLAH HARGA BAHAN 2,620.00

III - 148
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,595.00


E Overhead & Profit 15.00% 3,989.25
F Harga Satuan Pekerjaan (D+E) 30,584.25

A.4.7.1.17. Pengecatan 1 m2 permukaan baja dengan menie besi dengan perancah

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang cat L.02 OH 0.225 100,000.00 22,500.00
Kepala tukang L.02 OH 0.023 105,000.00 2,362.50
Mandor L.04 OH 0.008 110,000.00 825.00
JUMLAH TENAGA KERJA 45,687.50
B BAHAN
Menie besi Kg 0.100 25,000.00 2,500.00
Pengencer L 0.010 24,000.00 240.00
Kwas buah 0.010 12,000.00 120.00
Perancah kayu m3 0.002 3,500,000.00 7,000.00
JUMLAH HARGA BAHAN 9,860.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,547.50


E Overhead & Profit 15.00% 8,332.13
F Harga Satuan Pekerjaan (D+E) 63,879.63

A.4.7.1.18. Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang cat L.02 OH 0.250 100,000.00 25,000.00
Kepala tukang L.03 OH 0.025 105,000.00 2,625.00
Mandor L.04 OH 0.001 110,000.00 143.00
JUMLAH TENAGA KERJA 47,768.00
B BAHAN
Menie A Kg 0.100 25,000.00 2,500.00
Menie B Kg 0.100 25,000.00 2,500.00
Cat Kg 0.080 55,000.00 4,400.00
Kwas buah 0.010 12,000.00 120.00
Pengencer L 0.010 24,000.00 240.00
JUMLAH HARGA BAHAN 9,760.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,528.00


E Overhead & Profit 15.00% 8,629.20
F Harga Satuan Pekerjaan (D+E) 66,157.20

A.4.7.1.19. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat mutakhir

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.060 80,000.00 4,800.00
Tukang cat L.02 OH 0.060 100,000.00 6,000.00

III - 149
Kepala tukang L.03 OH 0.012 105,000.00 1,260.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 12,390.00
B BAHAN
Cat Kg 0.300 55,000.00 16,500.00
Kwas buah 0.010 12,000.00 120.00
Pengencer L 0.010 24,000.00 240.00
JUMLAH HARGA BAHAN 16,860.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 29,250.00


E Overhead & Profit 15.00% 4,387.50
F Harga Satuan Pekerjaan (D+E) 33,637.50

A.4.7.1.20. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 3 lapis

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang cat L.02 OH 0.800 100,000.00 80,000.00
Kepala tukang L.03 OH 0.080 105,000.00 8,400.00
Mandor L.04 OH 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 122,600.00
B BAHAN
Cat dasar Kg 0.110 25,000.00 2,750.00
Cat antara Kg 0.170 35,000.00 5,950.00
Cat penutup Kg 0.080 55,000.00 4,400.00
Kwas buah 0.010 12,000.00 120.00
Pengencer L 0.010 24,000.00 240.00
JUMLAH HARGA BAHAN 13,460.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 136,060.00


E Overhead & Profit 15.00% 20,409.00
F Harga Satuan Pekerjaan (D+E) 156,469.00

A.4.7.1.21. Pengecatan 1 m2 permukaan baja galvanis secara semprot sistem 3 lapis cat mutakhir

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang cat L.02 OH 0.700 100,000.00 70,000.00
Kepala tukang L.03 OH 0.070 105,000.00 7,350.00
Mandor L.04 OH 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 111,550.00
B BAHAN
Cat dasar Kg 0.300 25,000.00 7,500.00
Pengencer L 0.010 24,000.00 240.00
JUMLAH HARGA BAHAN 7,740.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 119,290.00


E Overhead & Profit 15.00% 17,893.50
F Harga Satuan Pekerjaan (D+E) 137,183.50

III - 150
A.4.7.1.22. Plituran 10 m2 dengan plitur melamic

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.000 80,000.00 160,000.00
Tukang cat L.02 OH 12.000 100,000.00 1,200,000.00
Kepala tukang L.03 OH 1.200 105,000.00 126,000.00
Mandor L.04 OH 0.100 110,000.00 11,000.00
JUMLAH TENAGA KERJA 1,497,000.00
B BAHAN
Wood filler kg 1.500 30,000.00 45,000.00
Woodstain kg 1.500 50,000.00 75,000.00
Sanding kg 1.500 50,000.00 75,000.00
Melamic kg 2.400 50,000.00 120,000.00
Thinner L 2.000 11,500.00 23,000.00
Ampelas Lbr 6.000 3,000.00 18,000.00
Lbr JUMLAH HARGA BAHAN 356,000.00
C PERALATAN
Compressor jam 68,310.00 -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,853,000.00


E Overhead & Profit 15.00% 277,950.00
F Harga Satuan Pekerjaan (D+E) 2,130,950.00

A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


A.5.1.1.1. (K3) Pemasangan 1 buah closet duduk/monoblock

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.300 80,000.00 264,000.00
Tukang batu L.02 OH 1.100 100,000.00 110,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.160 110,000.00 17,600.00
JUMLAH TENAGA KERJA 392,650.00
B BAHAN
Closet duduk Unit 1.000 1,237,000.00 1,237,000.00
Perlengkapan Ls 6% x closet 74,220.00 74,220.00
JUMLAH HARGA BAHAN 1,311,220.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,703,870.00


E Overhead & Profit 15.00% 255,580.50
F Harga Satuan Pekerjaan (D+E) 1,959,450.50

A.5.1.1 2. Pemasangan 1 buah closet jongkok porselen

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang batu L.02 OH 1.500 100,000.00 150,000.00
Kepala tukang L.03 OH 0.150 105,000.00 15,750.00
Mandor L.04 OH 0.160 110,000.00 17,600.00
JUMLAH TENAGA KERJA 263,350.00
B BAHAN
Closet jongkok Unit 1.000 140,000.00 140,000.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir pasang M3 0.010 207,900.00 2,079.00
JUMLAH HARGA BAHAN 150,479.00

III - 151
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 413,829.00


E Overhead & Profit 15.00% 62,074.35
F Harga Satuan Pekerjaan (D+E) 475,903.35

A.5.1.1 3. Pemasangan 1 buah closet jongkok teraso

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang batu L.02 OH 1.500 100,000.00 150,000.00
Kepala tukang L.03 OH 0.150 105,000.00 15,750.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 251,250.00
B BAHAN
Closet jongkok Unit 1.000 100,000.00 100,000.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir pasang M3 0.010 207,900.00 2,079.00
Bata merah buah 7.000 800.00 5,600.00
JUMLAH HARGA BAHAN 116,079.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 367,329.00


E Overhead & Profit 15.00% 55,099.35
F Harga Satuan Pekerjaan (D+E) 422,428.35

A.5.1.1 4. (K3) Pemasangan 1 buah urinoir

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Tukang batu L.02 OH 1.000 100,000.00 100,000.00
Kepala tukang L.03 OH 0.100 105,000.00 10,500.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 196,000.00
B BAHAN
Urinoir Unit 1.000 649,000.00 649,000.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir pasang M3 0.010 207,900.00 2,079.00
Perlengkapan % 0.300 194,700.00 194,700.00
JUMLAH HARGA BAHAN 854,179.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,050,179.00


E Overhead & Profit 15.00% 157,526.85
F Harga Satuan Pekerjaan (D+E) 1,207,705.85

A.5.1.1 5. (K3) Pemasangan 1 buah wastafel

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.200 80,000.00 96,000.00
Tukang batu L.02 OH 1.450 100,000.00 145,000.00

III - 152
Kepala tukang L.03 OH 0.150 105,000.00 15,750.00
Mandor L.04 OH 0.060 110,000.00 6,600.00
JUMLAH TENAGA KERJA 263,350.00
B BAHAN
Wastafel Unit 1.200 686,000.00 823,200.00
Semen Portland Kg 6.000 1,400.00 8,400.00
Pasir pasang M3 0.010 207,900.00 2,079.00
Perlengkapan % 0.120 98,784.00 98,784.00
JUMLAH HARGA BAHAN 932,463.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,195,813.00


E Overhead & Profit 15.00% 179,371.95
F Harga Satuan Pekerjaan (D+E) 1,375,184.95

A.5.1.1 7. (K3) Pemasangan 1 buah bak fiberglass vol 1 m3

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.000 80,000.00 240,000.00
Tukang batu L.02 OH 4.500 100,000.00 450,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.900 110,000.00 99,000.00
JUMLAH TENAGA KERJA 794,250.00
B BAHAN
Bak fiberglass Unit 1.000 220,000.00 220,000.00
Perlengkapan Ls 0.120 26,400.00 26,400.00
JUMLAH HARGA BAHAN 246,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,040,650.00


E Overhead & Profit 15.00% 156,097.50
F Harga Satuan Pekerjaan (D+E) 1,196,747.50

A.5.1.1 9. Pemasangan 1 buah bak mandi teraso vol 0,30 m3

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.000 80,000.00 240,000.00
Tukang batu L.02 OH 4.500 100,000.00 450,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.900 110,000.00 99,000.00
JUMLAH TENAGA KERJA 794,250.00
B BAHAN
Bak fiberglass Unit 1.000 220,000.00 220,000.00
Perlengkapan Ls 0.120 26,400.00 26,400.00
JUMLAH HARGA BAHAN 246,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,040,650.00


E Overhead & Profit 15.00% 156,097.50
F Harga Satuan Pekerjaan (D+E) 1,196,747.50

III - 153
A.5.1.1 10. Pemasangan 1 buah bak air fiberglass vol 1 m3

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.450 100,000.00 45,000.00
Kepala tukang L.03 OH 0.045 105,000.00 4,725.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 75,375.00
B BAHAN
Bak air fiberglass Unit 1.000 220,000.00 220,000.00
Perlengkapan % 0.120 26,400.00 26,400.00
JUMLAH HARGA BAHAN 246,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 321,775.00


E Overhead & Profit 15.00% 48,266.25
F Harga Satuan Pekerjaan (D+E) 370,041.25

A.5.1.1 12. Pemasangan 1 buah bak cuci piring stainlessteel

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.030 80,000.00 2,400.00
Tukang batu L.02 OH 0.300 100,000.00 30,000.00
Kepala tukang L.03 OH 0.030 105,000.00 3,150.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 37,200.00
B BAHAN
Bak cuci piring Unit 1.000 400,000.00 400,000.00
Waterdrain buah 1.000 385,000.00 385,000.00
JUMLAH HARGA BAHAN 785,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 822,200.00


E Overhead & Profit 15.00% 123,330.00
F Harga Satuan Pekerjaan (D+E) 945,530.00

A.5.1.1 13. Pemasangan 1 buah bak cuci piring teraso

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.050 80,000.00 4,000.00
Tukang batu L.02 OH 0.500 100,000.00 50,000.00
Kepala tukang L.03 OH 0.050 105,000.00 5,250.00
Mandor L.04 OH 0.025 110,000.00 2,750.00
JUMLAH TENAGA KERJA 62,000.00
B BAHAN
Bak cuci piring Unit 1.000 175,000.00 175,000.00
Waterdrain buah 1.000 385,000.00 385,000.00
Semen portland Kg 20.000 1,400.00 28,000.00
Pasir pasang M3 0.050 207,900.00 10,395.00
JUMLAH HARGA BAHAN 598,395.00

III - 154
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 660,395.00


E Overhead & Profit 15.00% 99,059.25
F Harga Satuan Pekerjaan (D+E) 759,454.25

A.5.1.1 14. Pemasangan 1 buah floor drain

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 12,400.00
B BAHAN
Floor drain Unit 1.000 82,500.00 82,500.00
JUMLAH HARGA BAHAN 82,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 94,900.00


E Overhead & Profit 15.00% 14,235.00
F Harga Satuan Pekerjaan (D+E) 109,135.00

A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.160 80,000.00 172,800.00
Tukang batu L.02 OH 0.720 100,000.00 72,000.00
Kepala tukang L.03 OH 0.072 105,000.00 7,560.00
Mandor L.04 OH 0.011 110,000.00 1,210.00
JUMLAH TENAGA KERJA 253,570.00
B BAHAN
Bata merah buah 40.000 800.00 32,000.00
Semen portland Kg 44.000 1,400.00 61,600.00
Pasir pasang M3 0.070 207,900.00 14,553.00
Pasir beton M3 0.060 231,000.00 13,860.00
Kerikil M3 0.070 200,000.00 14,000.00
Baja tulangan Kg 1.600 18,150.00 29,040.00
JUMLAH HARGA BAHAN 165,053.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 418,623.00


E Overhead & Profit 15.00% 62,793.45
F Harga Satuan Pekerjaan (D+E) 481,416.45

A.5.1.1 16. Pemasangan 1 buah bak kontrol pasangan bata 45cm x 45cm tinggi 50 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.200 80,000.00 256,000.00
Tukang cat L.02 OH 1.500 100,000.00 150,000.00

III - 155
Kepala tukang L.03 OH 0.011 105,000.00 1,155.00
Mandor L.04 OH 0.016 110,000.00 1,760.00
JUMLAH TENAGA KERJA 408,915.00
B BAHAN
Bata merah buah 70.000 800.00 56,000.00
Semen portland Kg 77.000 1,400.00 107,800.00
Pasir pasang M3 0.130 207,900.00 27,027.00
Pasir beton M3 0.090 231,000.00 20,790.00
Kerikil M3 0.020 200,000.00 4,000.00
Baja tulangan Kg 2.600 18,150.00 47,190.00
JUMLAH HARGA BAHAN 262,807.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 671,722.00


E Overhead & Profit 15.00% 100,758.30
F Harga Satuan Pekerjaan (D+E) 772,480.30

A.5.1.1 17. Pemasangan 1 buah bak kontrol pasangan bata 60 cm x 60 cm tinggi 65 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.200 80,000.00 256,000.00
Tukang batu L.02 OH 1.150 100,000.00 115,000.00
Kepala tukang L.03 OH 0.011 105,000.00 1,155.00
Mandor L.04 OH 0.016 110,000.00 1,760.00
JUMLAH TENAGA KERJA 373,915.00
B BAHAN
Bata merah buah 123.000 800.00 98,400.00
Semen portland Kg 114.000 1,400.00 159,600.00
Pasir pasang M3 0.184 207,900.00 38,253.60
Pasir beton M3 0.120 231,000.00 27,720.00
Kerikil M3 0.033 200,000.00 6,600.00
Baja tulangan Kg 4.850 18,150.00 88,027.50
JUMLAH HARGA BAHAN 418,601.10
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 792,516.10
E Overhead & Profit 15.00% 118,877.42
F Harga Satuan Pekerjaan (D+E) 911,393.52

A.5.1.1 18. Pemasangan 1 m’ pipa galvanis diameter ½”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 80,000.00 4,320.00
Tukang batu L.02 OH 0.090 100,000.00 9,000.00
Kepala tukang L.03 OH 0.009 105,000.00 945.00
Mandor L.04 OH 0.027 110,000.00 2,970.00
JUMLAH TENAGA KERJA 17,235.00
B BAHAN
Pipa galvanis ½” M 1.200 25,833.33 31,000.00
Perlengkapan Ls 0.350 25,833.33 9,041.67
JUMLAH HARGA BAHAN 40,041.67
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,276.67


E Overhead & Profit 15.00% 8,591.50
F Harga Satuan Pekerjaan (D+E) 65,868.17

III - 156
A.5.1.1 19. Pemasangan 1 buah kran diameter ½” atau ¾ ”

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA KERJA
Pekerja L.01 OH 0.010 80,000.00 800.00
Tukang batu L.02 OH 0.400 100,000.00 40,000.00
Kepala tukang L.03 OH 0.040 105,000.00 4,200.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 45,550.00
B BAHAN
Kran air M 1.000 12,000.00 12,000.00
Sealtape Buah 0.025 4,000.00 100.00
JUMLAH HARGA BAHAN 12,100.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 57,650.00


E Overhead & Profit 15.00% 8,647.50
F Harga Satuan Pekerjaan (D+E) 66,297.50

A.5.1.1 20. Pemasangan 1 m’ pipa galvanis diameter ¾ ”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 80,000.00 4,320.00
Tukang batu L.02 OH 0.090 100,000.00 9,000.00
Kepala tukang L.03 OH 0.009 105,000.00 945.00
Mandor L.04 OH 0.027 110,000.00 2,970.00
JUMLAH TENAGA KERJA 17,235.00
B BAHAN
Pipa galvanis 3/4” M 1.200 33,333.33 40,000.00
Perlengkapan % 0.350 14,000.00 14,000.00
JUMLAH HARGA BAHAN 54,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 71,235.00


E Overhead & Profit 15.00% 10,685.25
F Harga Satuan Pekerjaan (D+E) 81,920.25

A.5.1.1 21. Pemasangan 1 m’ pipa galvanis diameter 1”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 80,000.00 4,320.00
Tukang batu L.02 OH 0.090 100,000.00 9,000.00
Kepala tukang L.03 OH 0.009 105,000.00 945.00
Mandor L.04 OH 0.027 110,000.00 2,970.00
JUMLAH TENAGA KERJA 17,235.00
B BAHAN
Pipa galvanis 1” M 1.200 50,000.00 60,000.00
Perlengkapan % 0.350 60,000.00 60,000.00
JUMLAH HARGA BAHAN 120,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 137,235.00


E Overhead & Profit 15.00% 20,585.25
F Harga Satuan Pekerjaan (D+E) 157,820.25

III - 157
A.5.1.1 22. Pemasangan 1 m’ pipa galvanis diameter 1 ½”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.108 80,000.00 8,640.00
Tukang batu L.02 OH 0.180 100,000.00 18,000.00
Kepala tukang L.03 OH 0.018 105,000.00 1,890.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 29,080.00
B BAHAN
Pipa galvanis 11/2” M 1.200 75,833.33 91,000.00
Perlengkapan % 0.350 91,000.00 91,000.00
JUMLAH HARGA BAHAN 182,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 211,080.00


E Overhead & Profit 15.00% 31,662.00
F Harga Satuan Pekerjaan (D+E) 242,742.00

A.5.1.1 23. Pemasangan 1 m’ pipa galvanis diameter 3”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 80,000.00 10,800.00
Tukang batu L.02 OH 0.225 100,000.00 22,500.00
Kepala tukang L.03 OH 0.023 105,000.00 2,415.00
Mandor L.04 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 36,485.00
B BAHAN
Pipa galvanis 3” M 1.200 84,000.00 100,800.00
Perlengkapan % 0.350 35,280.00 35,280.00
JUMLAH HARGA BAHAN 136,080.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 172,565.00


E Overhead & Profit 15.00% 25,884.75
F Harga Satuan Pekerjaan (D+E) 198,449.75

A.5.1.1 24. Pemasangan 1 m’ pipa galvanis diameter 4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.135 80,000.00 10,800.00
Tukang batu L.02 OH 0.225 100,000.00 22,500.00
Kepala tukang L.03 OH 0.023 105,000.00 2,415.00
Mandor L.04 OH 0.007 110,000.00 770.00
JUMLAH TENAGA KERJA 36,485.00
B BAHAN
Pipa galvanis 4” M 1.200 245,000.00 294,000.00
Perlengkapan % 0.350 102,900.00 102,900.00
JUMLAH HARGA BAHAN 396,900.00

III - 158
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 433,385.00


E Overhead & Profit 15.00% 65,007.75
F Harga Satuan Pekerjaan (D+E) 498,392.75

A.5.1.1 25. Pemasangan 1 m’ pipa PVC tipe AW diameter ½ ”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 80,000.00 2,880.00
Tukang batu L.02 OH 0.060 100,000.00 6,000.00
Kepala tukang L.03 OH 0.006 105,000.00 630.00
Mandor L.04 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 9,730.00
B BAHAN
Pipa PVC 1/2” M 1.200 6,150.00 7,380.00
Perlengkapan % 0.350 2,583.00 2,583.00
JUMLAH HARGA BAHAN 9,963.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 19,693.00


E Overhead & Profit 15.00% 2,953.95
F Harga Satuan Pekerjaan (D+E) 22,646.95

A.5.1.1 26. Pemasangan 1 m’ pipa PVC tipe AW diameter ¾ ”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.030 80,000.00 2,400.00
Tukang batu L.02 OH 0.060 100,000.00 6,000.00
Kepala tukang L.03 OH 0.006 105,000.00 630.00
Mandor L.04 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 9,250.00
B BAHAN
Pipa PVC 3/4” M 1.200 9,400.00 11,280.00
Perlengkapan % 0.350 3,948.00 3,948.00
JUMLAH HARGA BAHAN 15,228.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 24,478.00


E Overhead & Profit 15.00% 3,671.70
F Harga Satuan Pekerjaan (D+E) 28,149.70

A.5.1.1 27. Pemasangan 1 m’ pipa PVC tipe AW diameter 1”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.036 80,000.00 2,880.00
Tukang batu L.02 OH 0.060 100,000.00 6,000.00
Kepala tukang L.03 OH 0.006 105,000.00 630.00
Mandor L.04 OH 0.002 110,000.00 220.00
JUMLAH TENAGA KERJA 9,730.00

III - 159
B BAHAN
Pipa PVC 1” M 1.200 10,600.00 12,720.00
Perlengkapan % 0.350 4,452.00 4,452.00
JUMLAH HARGA BAHAN 17,172.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 26,902.00


E Overhead & Profit 15.00% 4,035.30
F Harga Satuan Pekerjaan (D+E) 30,937.30

A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe AW diameter 1 ½ ”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 80,000.00 4,320.00
Tukang batu L.02 OH 0.090 100,000.00 9,000.00
Kepala tukang L.03 OH 0.009 105,000.00 945.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 14,595.00
B BAHAN
Pipa PVC 11/2” M 1.200 24,000.00 28,800.00
Perlengkapan % 0.350 10,080.00 10,080.00
JUMLAH HARGA BAHAN 38,880.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 53,475.00


E Overhead & Profit 15.00% 8,021.25
F Harga Satuan Pekerjaan (D+E) 61,496.25

A.5.1.1 29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.054 80,000.00 4,320.00
Tukang batu L.02 OH 0.090 100,000.00 9,000.00
Kepala tukang L.03 OH 0.009 105,000.00 945.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 14,595.00
B BAHAN
Pipa PVC 2” M 1.200 30,950.00 37,140.00
Perlengkapan % 0.350 12,999.00 12,999.00
JUMLAH HARGA BAHAN 50,139.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 64,734.00


E Overhead & Profit 15.00% 9,710.10
F Harga Satuan Pekerjaan (D+E) 74,444.10

A.5.1.1 30. Pemasangan 1 m’ pipa PVC tipe AW diameter 2 ½ ”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 80,000.00 6,480.00
Tukang batu L.02 OH 0.135 100,000.00 13,500.00

III - 160
Kepala tukang L.03 OH 0.014 105,000.00 1,417.50
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,837.50
B BAHAN
Pipa PVC 21/2” M 1.200 64,600.00 77,520.00
Perlengkapan % 0.350 27,132.00 27,132.00
JUMLAH HARGA BAHAN 104,652.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 126,489.50


E Overhead & Profit 15.00% 18,973.43
F Harga Satuan Pekerjaan (D+E) 145,462.93

A.5.1.1 31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 80,000.00 6,480.00
Tukang batu L.02 OH 0.135 100,000.00 13,500.00
Kepala tukang L.03 OH 0.014 105,000.00 1,417.50
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,837.50
B BAHAN
Pipa PVC 3” M 1.200 64,600.00 77,520.00
Perlengkapan % 0.350 27,132.00 27,132.00
JUMLAH HARGA BAHAN 104,652.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 126,489.50


E Overhead & Profit 15.00% 18,973.43
F Harga Satuan Pekerjaan (D+E) 145,462.93

A.5.1.1 32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4”

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 80,000.00 6,480.00
Tukang batu L.02 OH 0.135 100,000.00 13,500.00
Kepala tukang L.03 OH 0.014 105,000.00 1,417.50
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 21,837.50
B BAHAN
Pipa PVC 4” M 1.200 93,750.00 112,500.00
Perlengkapan % 0.350 39,375.00 39,375.00
JUMLAH HARGA BAHAN 151,875.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 173,712.50


E Overhead & Profit 15.00% 26,056.88
F Harga Satuan Pekerjaan (D+E) 199,769.38

III - 161
A.5.1.1 33. Pemasangan 1 m’ pipa air limbah jenis pipa tanah Ǿ 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.080 80,000.00 6,400.00
Tukang batu L.02 OH 0.040 100,000.00 4,000.00
Kepala tukang L.03 OH 0.004 105,000.00 420.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 11,260.00
B BAHAN
Pipa tanah buah 1.600 173,200.00 277,120.00
Semen portlan Kg 35.000 1,400.00 49,000.00
Pasir pasang M3 0.014 207,900.00 2,910.60
Pasir urug M3 0.014 173,300.00 2,426.20
JUMLAH HARGA BAHAN 331,456.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 342,716.80


E Overhead & Profit 15.00% 51,407.52
F Harga Satuan Pekerjaan (D+E) 394,124.32

A.5.1.1 34. Pemasangan 1 m’ pipa air limbah jenis pipa tanah diameter 15 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.060 80,000.00 4,800.00
Tukang batu L.02 OH 0.030 100,000.00 3,000.00
Kepala tukang L.03 OH 0.003 105,000.00 315.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 8,445.00
B BAHAN
Pipa tanah dia 15 buah 1.600 113,200.00 181,120.00
Semen portlan Kg 0.680 1,400.00 952.00
Pasir pasang M3 0.013 207,900.00 2,702.70
Pasir urug M3 0.011 173,300.00 1,906.30
JUMLAH HARGA BAHAN 186,681.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 195,126.00


E Overhead & Profit 15.00% 29,268.90
F Harga Satuan Pekerjaan (D+E) 224,394.90

A.5.1.1 35. Pemasangan 1 m’ pipa beton diameter 15 – 20 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.140 80,000.00 11,200.00
Tukang batu L.02 OH 0.070 100,000.00 7,000.00
Kepala tukang L.03 OH 0.007 105,000.00 735.00
Mandor L.04 OH 7.000 110,000.00 770,000.00
JUMLAH TENAGA KERJA 788,935.00
B BAHAN
Pipa beton dia. 15-20 buah 1.100 44,275.00 48,702.50
Bata merah M3 0.027 800.00 21.60
Semen portlan Kg 3.920 1,400.00 5,488.00
Pasir pasang M3 0.056 207,900.00 11,642.40
Pasir urug M3 0.024 173,300.00 4,159.20
JUMLAH HARGA BAHAN 70,013.70

III - 162
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 858,948.70


E Overhead & Profit 15.00% 128,842.31
F Harga Satuan Pekerjaan (D+E) 987,791.01

A.5.1.1.36. Pemasangan 1 m’ pipa beton diameter 30 – 100 cm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.380 80,000.00 30,400.00
Tukang batu L.02 OH 0.190 100,000.00 19,000.00
Kepala tukang L.03 OH 0.019 105,000.00 1,995.00
Mandor L.04 OH 0.019 110,000.00 2,090.00
JUMLAH TENAGA KERJA 53,485.00
B BAHAN
Pipa beton dia. 30-100 buah 1.100 66,000.00 72,600.00
Bata merah M3 0.550 800.00 440.00
Semen portlan Kg 10.300 1,400.00 14,420.00
Pasir pasang M3 0.061 207,900.00 12,681.90
Pasir urug M3 0.069 173,300.00 11,957.70
JUMLAH HARGA BAHAN 112,099.60
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 165,584.60
E Overhead & Profit 15.00% 24,837.69
F Harga Satuan Pekerjaan (D+E) 190,422.29

A.8.4.1 HARGA SATUAN PEKERJAAN PEMASANGAN PIPA DI LUAR GEDUNG


A.8.4.1.1 (K3) Pemasangan 1 m pipa PVC Ø 63 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 80,000.00 6,480.00
Tukang pipa L.02 OH 0.041 100,000.00 4,100.00
Mandor L.04 OH 0.008 110,000.00 880.00
11,460.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa PVC Ø 63 mm m 1.000 30,600.00 30,600.00
JUMLAH HARGA BAHAN 30,600.00
C PERALATAN
Sewa Tripot/Tackel hari 0.006 3,500,000.00 21,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 21,000.00
D Jumlah (A+B+C) 63,060.00
E Overhead & Profit 15.00% 9,459.00
F Harga Satuan Pekerjaan (D+E) 72,519.00
Catatan:
Koefisien peralatan yang digunakan pada A.8.4.1 ini adalah seperti yang tercantum pada tabel. Apabila ada tambahan
peralatan yang digunakan, harus disesuaikan dengan spesifikasi dan gambar kerja.

A.8.4.1.2 (K3) Pemasangan 1 m pipa PVC Ø 90 mm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.094 80,000.00 7,520.00
Tukang pipa L.02 OH 0.047 100,000.00 4,700.00

III - 163
Mandor L.04 OH 0.009 110,000.00 990.00
JUMLAH TENAGA KERJA 13,210.00
B BAHAN
Pipa PVC Ø 90 mm m 1.000 64,000.00 64,000.00
JUMLAH HARGA BAHAN 64,000.00
C PERALATAN
Sewa Tripot/Tackel hari 0.008 3,500,000.00 28,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 28,000.00

D Jumlah (A+B+C) 105,210.00


E Overhead & Profit 15.00% 15,781.50
F Harga Satuan Pekerjaan (D+E) 120,991.50

A.8.4.1.3 (K3) Pemasangan 1 m pipa PVC Ø 110 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.105 80,000.00 8,400.00
Tukang pipa L.02 OH 0.053 100,000.00 5,300.00
Mandor L.04 OH 0.011 110,000.00 1,210.00
JUMLAH TENAGA KERJA 14,910.00
B BAHAN
Pipa PVC Ø 110 mm m 1.000 92,980.00 92,980.00
JUMLAH HARGA BAHAN 92,980.00
C PERALATAN
Sewa Tripot/Tackel hari 0.010 3,500,000.00 35,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 35,000.00

D Jumlah (A+B+C) 142,890.00


E Overhead & Profit 15.00% 21,433.50
F Harga Satuan Pekerjaan (D+E) 164,323.50

A.8.4.1.5 (K3) Pemasngan 1 m pipa PVC Ø 200 mm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.189 80,000.00 15,120.00
Tukang pipa L.02 OH 0.095 100,000.00 9,500.00
Mandor L.04 OH 0.019 110,000.00 2,090.00
JUMLAH TENAGA KERJA 26,710.00
B BAHAN
Pipa PVC Ø 200 mm m 1.000 308,700.00 308,700.00
JUMLAH HARGA BAHAN 308,700.00
C PERALATAN
Sewa Tripot/Tackel hari 0.024 3,500,000.00 84,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 84,000.00

D Jumlah (A+B+C) 419,410.00


E Overhead & Profit 15.00% 62,911.50
F Harga Satuan Pekerjaan (D+E) 482,321.50

A.8.4.1.6 (K3) Pemasangan 1 m pipa PVC Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.256 80,000.00 20,480.00
Tukang pipa L.02 OH 0.128 100,000.00 12,800.00

III - 164
Mandor L.04 OH 0.026 110,000.00 2,860.00
JUMLAH TENAGA KERJA 36,140.00
B BAHAN
Pipa PVC Ø 250 mm m 1.000 483,750.00 483,750.00
JUMLAH HARGA BAHAN 483,750.00
C PERALATAN
Sewa Tripot/Tackel hari 0.034 3,500,000.00 119,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 119,000.00

D Jumlah (A+B+C) 638,890.00


E Overhead & Profit 15.00% 95,833.50
F Harga Satuan Pekerjaan (D+E) 734,723.50

A.8.4.1.17 (K3) Pemasangan 1 m pipa HDPE Ø 63 mm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.035 80,000.00 2,800.00
Tukang pipa L.02 OH 0.017 100,000.00 1,700.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 4,830.00
B BAHAN
Pipa HDPE Ø 63 mm m 1.000 25,900.00 25,900.00
JUMLAH HARGA BAHAN 25,900.00
C PERALATAN
Sewa Tripot/Tackel hari 0.019 3,500,000.00 66,500.00
& handle crane 2 T
JUMLAH HARGA ALAT 66,500.00

D Jumlah (A+B+C) 97,230.00


E Overhead & Profit 15.00% 14,584.50
F Harga Satuan Pekerjaan (D+E) 111,814.50

A.8.4.1.19 (K3) Pemasangan 1 m pipa HDPE Ø 125 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.045 80,000.00 3,600.00
Tukang pipa L.02 OH 0.023 100,000.00 2,300.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 6,450.00
B BAHAN
Pipa HDPE Ø 125 mm m 1.000 101,800.00 101,800.00
JUMLAH HARGA BAHAN 101,800.00
C PERALATAN
Sewa Tripot/Tackel hari 0.019 3,500,000.00 66,500.00
& handle crane 2 T
JUMLAH HARGA ALAT 66,500.00

D Jumlah (A+B+C) 174,750.00


E Overhead & Profit 15.00% 26,212.50
F Harga Satuan Pekerjaan (D+E) 200,962.50

A.8.4.1.21 (K3) Pemasangan 1 m pipa HDPE Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.102 80,000.00 8,160.00
Tukang pipa L.02 OH 0.051 100,000.00 5,100.00

III - 165
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 14,360.00
B BAHAN
Pipa HDPE Ø 200 mm m 1.000 259,600.00 259,600.00
JUMLAH HARGA BAHAN 259,600.00
C PERALATAN
Sewa Tripot/Tackel hari 0.019 3,500,000.00 66,500.00
& handle crane 2 T
JUMLAH HARGA ALAT 66,500.00

D Jumlah (A+B+C) 340,460.00


E Overhead & Profit 15.00% 51,069.00
F Harga Satuan Pekerjaan (D+E) 391,529.00

A.8.4.1.22 (K3) Pemasangan 1 m pipa HDPE Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.133 80,000.00 10,640.00
Tukang pipa L.02 OH 0.067 100,000.00 6,700.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 18,770.00
B BAHAN
Pipa HDPE Ø 250 mm m 1.000 404,300.00 404,300.00
JUMLAH HARGA BAHAN 404,300.00
C PERALATAN
Sewa Tripot/Tackel hari 0.042 3,500,000.00 147,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 147,000.00

D Jumlah (A+B+C) 570,070.00


E Overhead & Profit 15.00% 85,510.50
F Harga Satuan Pekerjaan (D+E) 655,580.50

A.8.4.1.33 (K3) Pemasangan 1 m pipa GIP Ø 63 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.345 80,000.00 27,600.00
Tukang pipa L.02 OH 0.172 100,000.00 17,200.00
Mandor L.04 OH 0.034 110,000.00 3,740.00
JUMLAH TENAGA KERJA 48,540.00
B BAHAN
Pipa GIP Ø 63 mm m 1.000 85,000.00 85,000.00
JUMLAH HARGA BAHAN 85,000.00
C PERALATAN
Sewa Tripot/Tackel 3,500,000.00 -
& handle crane 2 T hari -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 133,540.00


E Overhead & Profit 15.00% 20,031.00
F Harga Satuan Pekerjaan (D+E) 153,571.00

A.8.4.1.34 (K3) Pemasangan 1 m pipa GIP Ø 100 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.400 80,000.00 32,000.00
Tukang pipa L.02 OH 0.200 100,000.00 20,000.00

III - 166
Mandor L.04 OH 0.040 110,000.00 4,400.00
JUMLAH TENAGA KERJA 56,400.00
B BAHAN
Pipa GIP Ø 100 mm m 1.000 245,000.00 245,000.00
JUMLAH HARGA BAHAN 245,000.00
C PERALATAN
Sewa Tripot/Tackel hari - 3,500,000.00 -
& handle crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 301,400.00


E Overhead & Profit 15.00% 45,210.00
F Harga Satuan Pekerjaan (D+E) 346,610.00

A.8.4.1.35 (K3) Pemasangan 1 m pipa GIP Ø 125 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.448 80,000.00 35,840.00
Tukang pipa L.02 OH 0.224 100,000.00 22,400.00
Mandor L.04 OH 0.045 110,000.00 4,950.00
JUMLAH TENAGA KERJA 63,190.00
B BAHAN
Pipa GIP Ø 125 mm m 1.000 - -
JUMLAH HARGA BAHAN -
C PERALATAN
Sewa Tripot/Tackel hari - 3,500,000.00 -
& handle crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 63,190.00


E Overhead & Profit 15.00% 9,478.50
F Harga Satuan Pekerjaan (D+E) 72,668.50

A.8.4.1.36 (K3) Pemasangan 1 m pipa GIP Ø 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.506 80,000.00 40,480.00
Tukang pipa L.02 OH 0.253 100,000.00 25,300.00
Mandor L.04 OH 0.051 110,000.00 5,610.00
JUMLAH TENAGA KERJA 71,390.00
B BAHAN
Pipa GIP Ø 150 mm m 1.000 355,000.00 355,000.00
JUMLAH HARGA BAHAN 355,000.00
C PERALATAN
Sewa Tripot/Tackel hari - 3,500,000.00 -
& handle crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 426,390.00


E Overhead & Profit 15.00% 63,958.50
F Harga Satuan Pekerjaan (D+E) 490,348.50

A.8.4.1.37 (K3) Pemasangan 1 m pipa GIP Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.796 80,000.00 63,680.00
Tukang pipa L.02 OH 0.398 100,000.00 39,800.00

III - 167
Mandor L.04 OH 0.080 110,000.00 8,800.00
JUMLAH TENAGA KERJA 112,280.00
B BAHAN
Pipa GIP Ø 200 mm m 1.000 680,000.00 680,000.00
JUMLAH HARGA BAHAN 680,000.00
C PERALATAN
Sewa Tripot/Tackel hari - 3,500,000.00 -
& handle crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 792,280.00


E Overhead & Profit 15.00% 118,842.00
F Harga Satuan Pekerjaan (D+E) 911,122.00

A.8.4.1.38 (K3) Pemasangan 1 m pipa GIP Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.949 80,000.00 75,920.00
Tukang pipa L.02 OH 0.475 100,000.00 47,500.00
Mandor L.04 OH 0.095 110,000.00 10,450.00
JUMLAH TENAGA KERJA 133,870.00
B BAHAN
Pipa GIP Ø 250 mm m 1.000 875,000.00 875,000.00
JUMLAH HARGA BAHAN 875,000.00
C PERALATAN
Sewa Tripot/Tackel hari - 3,500,000.00 -
& handle crane 2 T
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,008,870.00


E Overhead & Profit 15.00% 151,330.50
F Harga Satuan Pekerjaan (D+E) 1,160,200.50

A.8.4.1.49 (K3) Pemasangan 1 m pipa DCI Ø 100 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.489 80,000.00 39,120.00
Tukang pipa L.02 OH 0.098 100,000.00 9,800.00
Mandor L.04 OH 0.040 110,000.00 4,400.00
JUMLAH TENAGA KERJA 53,320.00
B BAHAN
Pipa DCI Ø 100 mm m 1.000 618,000.00 618,000.00
JUMLAH HARGA BAHAN 618,000.00
C PERALATAN
Sewa Tripot/Tackel hari 0.380 3,500,000.00 1,330,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 1,330,000.00

D Jumlah (A+B+C) 2,001,320.00


E Overhead & Profit 15.00% 300,198.00
F Harga Satuan Pekerjaan (D+E) 2,301,518.00

A.8.4.1.50 (K3) Pemasangan 1 m pipa DCI Ø 125 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.547 80,000.00 43,760.00
Tukang pipa L.02 OH 0.109 100,000.00 10,900.00

III - 168
Mandor L.04 OH 0.055 110,000.00 6,050.00
JUMLAH TENAGA KERJA 60,710.00
B BAHAN
Pipa DCI Ø 125 mm m 1.000 936,000.00 936,000.00
JUMLAH HARGA BAHAN 936,000.00
C PERALATAN
Sewa Tripot/Tackel hari 0.380 3,500,000.00 1,330,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 1,330,000.00

D Jumlah (A+B+C) 2,326,710.00


E Overhead & Profit 15.00% 349,006.50
F Harga Satuan Pekerjaan (D+E) 2,675,716.50

A.8.4.1.51 (K3) Pemasangan 1 m pipa DCI Ø 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.613 80,000.00 49,040.00
Tukang pipa L.02 OH 0.123 100,000.00 12,300.00
Mandor L.04 OH 0.061 110,000.00 6,710.00
JUMLAH TENAGA KERJA 68,050.00
B BAHAN
Pipa DCI Ø 150 mm m 1.000 1,368,000.00 1,368,000.00
JUMLAH HARGA BAHAN 1,368,000.00
C PERALATAN
Sewa Tripot/Tackel hari 0.380 3,500,000.00 1,330,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 1,330,000.00

D Jumlah (A+B+C) 2,766,050.00


E Overhead & Profit 15.00% 414,907.50
F Harga Satuan Pekerjaan (D+E) 3,180,957.50

A.8.4.1.52 (K3) Pemasangan 1 m pipa DCI Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.855 80,000.00 68,400.00
Tukang pipa L.02 OH 0.171 100,000.00 17,100.00
Mandor L.04 OH 0.085 110,000.00 9,350.00
JUMLAH TENAGA KERJA 94,850.00
B BAHAN
Pipa DCI Ø 200 mm M 1.000 2,100,000.00 2,100,000.00
JUMLAH HARGA BAHAN 2,100,000.00
C PERALATAN
Sewa Tripot/Tackel hari 0.380 3,500,000.00 1,330,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 1,330,000.00

D Jumlah (A+B+C) 3,524,850.00


E Overhead & Profit 15.00% 528,727.50
F Harga Satuan Pekerjaan (D+E) 4,053,577.50

A.8.4.1.53 (K3) Pemasangan 1 m pipa DCI Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.951 80,000.00 76,080.00
Tukang pipa L.02 OH 0.190 100,000.00 19,000.00

III - 169
Mandor L.04 OH 0.095 110,000.00 10,450.00
JUMLAH TENAGA KERJA 105,530.00
B BAHAN
Pipa DCI Ø 250 mm M 1.000 2,800,000.00 2,800,000.00
JUMLAH HARGA BAHAN 2,800,000.00
C PERALATAN
Sewa Tripot/Tackel hari 0.050 3,500,000.00 175,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 175,000.00

D Jumlah (A+B+C) 3,080,530.00


E Overhead & Profit 15.00% 462,079.50
F Harga Satuan Pekerjaan (D+E) 3,542,609.50

A.8.4.1.64 (K3) Pemasangan 1 m Pipa baja Ø 63 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.499 80,000.00 39,920.00
Tukang pipa L.02 OH 0.100 100,000.00 10,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 55,420.00
B BAHAN
Pipa baja Ø 63 mm m 1.000 167,500.00 167,500.00
JUMLAH HARGA BAHAN 167,500.00
C PERALATAN
Sewa Tripot/Tackel hari 0.004 3,500,000.00 14,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 14,000.00
D Jumlah (A+B+C) 236,920.00
E Overhead & Profit 15.00% 35,538.00
F Harga Satuan Pekerjaan (D+E) 272,458.00

A.8.4.1.65 (K3) Pemasangan 1 m pipa baja Ø 100 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.579 80,000.00 46,320.00
Tukang pipa L.02 OH 0.116 100,000.00 11,600.00
Mandor L.04 OH 0.058 110,000.00 6,380.00
JUMLAH TENAGA KERJA 64,300.00
B BAHAN
Pipa baja Ø 100 mm m 1.000 229,500.00 229,500.00
JUMLAH HARGA BAHAN 229,500.00
C PERALATAN
Sewa Tripot/Tackel hari 0.004 3,500,000.00 14,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 14,000.00
D Jumlah (A+B+C) 307,800.00
E Overhead & Profit 15.00% 46,170.00
F Harga Satuan Pekerjaan (D+E) 353,970.00

A.8.4.1.66 (K3) Pemasangan 1 m pipa baja Ø 125 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.648 80,000.00 51,840.00
Tukang pipa L.02 OH 0.130 100,000.00 13,000.00
Mandor L.04 OH 0.065 110,000.00 7,150.00
JUMLAH TENAGA KERJA 71,990.00

III - 170
B BAHAN
Pipa baja Ø 125 mm m 1.000 280,500.00 280,500.00
JUMLAH HARGA BAHAN 280,500.00
C PERALATAN
Sewa Tripot/Tackel hari 0.004 3,500,000.00 14,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 14,000.00
D Jumlah (A+B+C) 366,490.00
E Overhead & Profit 15.00% 54,973.50
F Harga Satuan Pekerjaan (D+E) 421,463.50

A.8.4.1.67 (K3) Pemasangan 1 m pipa baja Ø 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.708 80,000.00 56,640.00
Tukang pipa L.02 OH 0.142 100,000.00 14,200.00
Mandor L.04 OH 0.071 110,000.00 7,810.00
JUMLAH TENAGA KERJA 78,650.00
B BAHAN
Pipa baja Ø 150 mm m 1.000 345,250.00 345,250.00
JUMLAH HARGA BAHAN 345,250.00
C PERALATAN
Sewa Tripot/Tackel hari 0.004 3,500,000.00 14,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 14,000.00
D Jumlah (A+B+C) 437,900.00
E Overhead & Profit 15.00% 65,685.00
F Harga Satuan Pekerjaan (D+E) 503,585.00

A.8.4.1.68 (K3) Pemasangan 1 m pipa baja Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.113 80,000.00 89,040.00
Tukang pipa L.02 OH 0.223 100,000.00 22,300.00
Mandor L.04 OH 0.111 110,000.00 12,210.00
JUMLAH TENAGA KERJA 123,550.00
B BAHAN
Pipa baja Ø 200 mm m 1.000 586,500.00 586,500.00
JUMLAH HARGA BAHAN 586,500.00
C PERALATAN
Sewa Tripot/Tackel hari 0.004 3,500,000.00 14,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 14,000.00
D Jumlah (A+B+C) 724,050.00
E Overhead & Profit 15.00% 108,607.50
F Harga Satuan Pekerjaan (D+E) 832,657.50

A.8.4.1.69 (K3) Pemasangan pipa baja Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.325 80,000.00 106,000.00
Tukang pipa L.02 OH 0.265 100,000.00 26,500.00
Mandor L.04 OH 0.133 110,000.00 14,630.00
JUMLAH TENAGA KERJA 147,130.00
B BAHAN
Pipa baja Ø 250 mm m 1.000 747,500.00 747,500.00
JUMLAH HARGA BAHAN 747,500.00

III - 171
C PERALATAN
Sewa Tripot/Tackel hari 0.004 3,500,000.00 14,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 14,000.00
D Jumlah (A+B+C) 908,630.00
E Overhead & Profit 15.00% 136,294.50
F Harga Satuan Pekerjaan (D+E) 1,044,924.50

A.8.4.2 HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA


A.8.4.2.1 (K3) Pemotongan 1 buah pipa PVC Ø 63 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.005 80,000.00 400.00
Tukang pipa L.02 OH 0.002 100,000.00 200.00
Mandor L.04 OH 0.001 110,000.00 55.00
JUMLAH TENAGA KERJA 655.00
B BAHAN
Pipa PVC Ø 63 mm buah 1.000 30,600.00 30,600.00
JUMLAH HARGA BAHAN 30,600.00
C PERALATAN
Peralatan potong pipa T1/manual hari 0.003 50,000.00 150.00
(gergaji) /saw

JUMLAH HARGA ALAT 150.00

D Jumlah (A+B+C) 31,405.00


E Overhead & Profit 15.00% 4,710.75
F Harga Satuan Pekerjaan (D+E) 36,115.75

A.8.4.2.2 (K3) Pemotongan 1 m pipa PVC Ø 90 mm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.014 80,000.00 1,120.00
Tukang pipa L.02 OH 0.007 100,000.00 700.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA 1,930.00
B BAHAN KERJA
Pipa PVC Ø 90 mm buah 1.000 64,000.00 64,000.00
JUMLAH HARGA BAHAN 64,000.00
C PERALATAN
Peralatan potong pipa T1/manual hari 0.003 50,000.00 150.00
(gergaji) /saw

JUMLAH HARGA ALAT 150.00

D Jumlah (A+B+C) 66,080.00


E Overhead & Profit 15.00% 9,912.00
F Harga Satuan Pekerjaan (D+E) 75,992.00

A.8.4.2.3 (K3) Pemotongan 1 buah pipa PVC Ø 110 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.022 80,000.00 1,760.00
Tukang pipa L.02 OH 0.011 100,000.00 1,100.00
Mandor L.04 OH 0.002 110,000.00 220.00
JUMLAH TENAGA 3,080.00
B BAHAN KERJA
Pipa PVC Ø 110 mm buah 1.000 92,980.00 92,980.00
JUMLAH HARGA BAHAN 92,980.00

III - 172
C PERALATAN
Peralatan potong pipa T1/manual hari 0.003 50,000.00 150.00
(gergaji) /saw

JUMLAH HARGA ALAT 150.00


D Jumlah (A+B+C) 96,210.00
E Overhead & Profit 15.00% 14,431.50
F Harga Satuan Pekerjaan (D+E) 110,641.50

A.8.4.2.5 (K3) Pemotongan 1 buah pipa PVC Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.081 80,000.00 6,480.00
Tukang pipa L.02 OH 0.040 100,000.00 4,000.00
Mandor L.04 OH 0.008 110,000.00 880.00
JUMLAH TENAGA KERJA 11,360.00
B BAHAN
Pipa PVC Ø 200 mm buah 1.000 308,700.00 308,700.00
JUMLAH HARGA BAHAN 308,700.00
C PERALATAN
Peralatan potong pipa T1/manual hari 0.017 50,000.00 850.00
(gergaji) /saw

JUMLAH HARGA ALAT 850.00

D Jumlah (A+B+C) 320,910.00


E Overhead & Profit 15.00% 48,136.50
F Harga Satuan Pekerjaan (D+E) 369,046.50

A.8.4.2.6 (K3) Pemotongan 1 buah pipa PVC Ø 250 mm

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Pekerja L.01 OH 0.128 80,000.00 10,240.00
Tukang pipa L.02 OH 0.064 100,000.00 6,400.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 18,070.00
B BAHAN
Pipa PVC Ø 250 mm buah 1.000 483,750.00 483,750.00
JUMLAH HARGA BAHAN 483,750.00
C PERALATAN
Peralatan potong pipa T1/manual hari 0.030 50,000.00 1,500.00
(gergaji) /saw

JUMLAH HARGA ALAT 1,500.00

D Jumlah (A+B+C) 503,320.00


E Overhead & Profit 15.00% 75,498.00
F Harga Satuan Pekerjaan (D+E) 578,818.00

A.8.4.2.17 (K3) Pemotongan 1 buah pipa HDPE Ø 63 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.002 80,000.00 160.00
Tukang pipa L.02 OH 0.001 100,000.00 100.00
Mandor L.04 OH 0.000 110,000.00 22.00
Operator L.08 OH 0.034 130,000.00 4,420.00
JUMLAH TENAGA KERJA 4,702.00

III - 173
B BAHAN
Pipa HDPE Ø 63 mm buah 1.000 25,900.00 25,900.00
JUMLAH HARGA BAHAN 25,900.00
C PERALATAN
Peralatan potong hari 0.004 50,000.00 200.00
pipa T2/mekanik/cilinder saw
JUMLAH HARGA ALAT 200.00

D Jumlah (A+B+C) 30,802.00


E Overhead & Profit 15.00% 4,620.30
F Harga Satuan Pekerjaan (D+E) 35,422.30

A.8.4.2.19 (K3) Pemotongan 1 buah pipa HDPE Ø 125 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.009 80,000.00 720.00
Tukang pipa L.02 OH 0.005 100,000.00 500.00
Mandor L.04 OH 0.001 110,000.00 110.00
Operator L.08 OH 0.096 130,000.00 12,480.00
JUMLAH TENAGA KERJA 13,810.00
B BAHAN
Pipa HDPE Ø 125 mm buah 1.000 101,800.00 101,800.00
JUMLAH HARGA BAHAN 101,800.00
C PERALATAN
Peralatan potong hari 0.006 50,000.00 300.00
pipa T2/mekanik/cilinder saw
JUMLAH HARGA ALAT 300.00

D Jumlah (A+B+C) 115,910.00


E Overhead & Profit 15.00% 17,386.50
F Harga Satuan Pekerjaan (D+E) 133,296.50

A.8.4.2.21 (K3) Pemotongan 1 buah pipa HDPE Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.044 80,000.00 3,520.00
Tukang pipa L.02 OH 0.022 100,000.00 2,200.00
Mandor L.04 OH 0.004 110,000.00 440.00
Operator L.08 OH 0.171 130,000.00 22,230.00
JUMLAH TENAGA KERJA 28,390.00
B BAHAN
Pipa HDPE Ø 200 mm buah 1.000 259,600.00 259,600.00
JUMLAH HARGA BAHAN 259,600.00
C PERALATAN
Peralatan potong hari 0.017 50,000.00 850.00
pipa T2/mekanik/cilinder saw
JUMLAH HARGA ALAT 850.00

D Jumlah (A+B+C) 288,840.00


E Overhead & Profit 15.00% 43,326.00
F Harga Satuan Pekerjaan (D+E) 332,166.00

A.8.4.2.22 (K3) Pemotongan 1 buah pipaHDPE Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.067 80,000.00 5,360.00
Tukang pipa L.02 OH 0.033 100,000.00 3,300.00

III - 174
Mandor L.04 OH 0.007 110,000.00 770.00
Operator L.08 OH 0.221 130,000.00 28,730.00
JUMLAH TENAGA KERJA 38,160.00
B BAHAN
Pipa HDPE Ø 250 mm buah 1.000 404,300.00 404,300.00
JUMLAH HARGA BAHAN 404,300.00
C PERALATAN
Peralatan potong hari 0.023 50,000.00 1,150.00
pipa T2/mekanik/cilinder saw
JUMLAH HARGA ALAT 1,150.00

D Jumlah (A+B+C) 443,610.00


E Overhead & Profit 15.00% 66,541.50
F Harga Satuan Pekerjaan (D+E) 510,151.50

A.8.4.2.33 (K3) Pemotongan 1 buah pipa GIP Ø 63 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.019 80,000.00 1,520.00
Tukang pipa L.02 OH 0.010 100,000.00 1,000.00
Mandor L.04 OH 0.002 110,000.00 220.00
2,740.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa GIP Ø 63 mm buah 1.000 85,000.00 85,000.00
JUMLAH HARGA BAHAN 85,000.00
C PERALATAN
Peralatan potong pipa T2/mekanik hari - 50,000.00 -
/ cilinder saw

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 87,740.00
E Overhead & Profit 15.00% 13,161.00
F Harga Satuan Pekerjaan (D+E) 100,901.00

A.8.4.2.34 (K3) Pemotongan 1 buah pipa GIP Ø 100 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.058 80,000.00 4,640.00
Tukang pipa L.02 OH 0.029 100,000.00 2,900.00
Mandor L.04 OH 0.006 110,000.00 660.00
8,200.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa GIP Ø 100 mm buah 1.000 245,000.00 245,000.00
JUMLAH HARGA BAHAN 245,000.00
C PERALATAN
Peralatan potong hari - 50,000.00 -
pipa T2/mekanik/cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 253,200.00


E Overhead & Profit 15.00% 37,980.00
F Harga Satuan Pekerjaan (D+E) 291,180.00

III - 175
A.8.4.2.36 (K3) Pemotongan 1 buah pipa GIP Ø 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.131 80,000.00 10,480.00
Tukang pipa L.02 OH 0.066 100,000.00 6,600.00
Mandor L.04 OH 0.013 110,000.00 1,430.00
18,510.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa GIP Ø 150 mm buah 1.000 355,000.00 355,000.00
JUMLAH HARGA BAHAN 355,000.00
C PERALATAN
Peralatan potong hari - 50,000.00 -
pipa T2/mekanik/cilinder saw
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 373,510.00
E Overhead & Profit 15.00% 56,026.50
F Harga Satuan Pekerjaan (D+E) 429,536.50

A.8.4.2.37 (K3) Pemotongan 1 buah pipa GIP Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.340 80,000.00 27,200.00
Tukang pipa L.02 OH 0.170 100,000.00 17,000.00
Mandor L.04 OH 0.034 110,000.00 3,740.00
47,940.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa GIP Ø 200 mm buah 1.000 680,000.00 680,000.00
JUMLAH HARGA BAHAN 680,000.00
C PERALATAN
Peralatan potong pipa T2/mekanik hari - 50,000.00 -
/ cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 727,940.00


E Overhead & Profit 15.00% 109,191.00
F Harga Satuan Pekerjaan (D+E) 837,131.00

A.8.4.2.38 (K3) Pemotongan 1 buah pipa GIP Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.475 80,000.00 38,000.00
Tukang pipa L.02 OH 0.237 100,000.00 23,700.00
Mandor L.04 OH 0.047 110,000.00 5,170.00
66,870.00
JUMLAH TENAGA KERJA
B BAHAN
Pipa GIP Ø 250 mm buah 1.000 875,000.00 875,000.00
JUMLAH HARGA BAHAN 875,000.00
C PERALATAN
Peralatan potong pipa T2/mekanik hari - 50,000.00 -
/ cilinder saw
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 941,870.00


E Overhead & Profit 15.00% 141,280.50
F Harga Satuan Pekerjaan (D+E) 1,083,150.50

III - 176
A.8.4.3 HARGA SATUAN PEKERJAAN PEMASANGAN AKSESORIS PIPA
A.8.4.3.1 (K3) Pemasangan 1 buah Valve Ø 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.429 80,000.00 114,320.00
Tukang pipa L.02 OH 0.715 100,000.00 71,500.00
Mandor L.04 OH 0.143 110,000.00 15,730.00
201,550.00
JUMLAH TENAGA KERJA
B BAHAN
Valve Ø 150 mm buah 1.000 3,250,000.00 3,250,000.00
JUMLAH HARGA BAHAN 3,250,000.00
C PERALATAN
Sewa Tripot/Tackel hari 0.100 3,500,000.00 350,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 350,000.00

D Jumlah (A+B+C) 3,801,550.00


E Overhead & Profit 15.00% 570,232.50
F Harga Satuan Pekerjaan (D+E) 4,371,782.50

A.8.4.3.2 (K3) Pemasangan 1 buah Valve Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.714 80,000.00 137,120.00
Tukang pipa L.02 OH 0.857 100,000.00 85,700.00
Mandor L.04 OH 0.171 110,000.00 18,810.00
241,630.00
JUMLAH TENAGA KERJA
B BAHAN
Valve Ø 200 mm buah 1.000 5,400,000.00 5,400,000.00
JUMLAH HARGA BAHAN 5,400,000.00
C PERALATAN
Sewa Tripot/Tackel hari 0.300 3,500,000.00 1,050,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 1,050,000.00

D Jumlah (A+B+C) 6,691,630.00


E Overhead & Profit 15.00% 1,003,744.50
F Harga Satuan Pekerjaan (D+E) 7,695,374.50

A.8.4.3.3 (K3) Pemasangan 1 buah Valve Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.714 80,000.00 137,120.00
Tukang pipa L.02 OH 0.857 100,000.00 85,700.00
Mandor L.04 OH 0.171 110,000.00 18,810.00
241,630.00
JUMLAH TENAGA KERJA
B BAHAN
Valve Ø 250 mm buah 1.000 9,250,000.00 9,250,000.00
JUMLAH HARGA BAHAN 9,250,000.00

III - 177
C PERALATAN
Sewa Tripot/Tackel hari 0.400 3,500,000.00 1,400,000.00
& handle crane 2 T
JUMLAH HARGA ALAT 1,400,000.00

D Jumlah (A+B+C) 10,891,630.00


E Overhead & Profit 15.00% 1,633,744.50
F Harga Satuan Pekerjaan (D+E) 12,525,374.50

A.8.4.5 HARGA SATUAN PEKERJAAN PENGETESAN PIPA


A.8.4.5.1 (K3) Pengetesan 1 m pipa Ø 50 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.008 80,000.00 640.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 728.00
B BAHAN
Air test (air bersih) m3 0.002 5,000.00 10.00
Bahan bakar liter 0.060 6,550.00 393.00
Oli liter 0.002 42,000.00 84.00
JUMLAH HARGA BAHAN 487.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,215.00
E Overhead & Profit 15.00% 182.25
F Harga Satuan Pekerjaan (D+E) 1,397.25

A.8.4.5.2 (K3) Pengetesan 1 m pipa Ø 75 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.008 80,000.00 640.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 728.00
B BAHAN
Air test (air bersih) m3 0.004 5,000.00 20.00
Bahan bakar liter 0.060 6,550.00 393.00
Oli liter 0.002 42,000.00 84.00
JUMLAH HARGA BAHAN 497.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,225.00
E Overhead & Profit 15.00% 183.75
F Harga Satuan Pekerjaan (D+E) 1,408.75

A.8.4.5.3 (K3) Pengetesan 1 m pipa Ø 100 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.008 80,000.00 640.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 728.00

III - 178
B BAHAN
Air test (air bersih) m3 0.008 5,000.00 40.00
Bahan bakar liter 0.060 6,550.00 393.00
Oli liter 0.002 42,000.00 84.00
JUMLAH HARGA BAHAN 517.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,245.00
E Overhead & Profit 15.00% 186.75
F Harga Satuan Pekerjaan (D+E) 1,431.75

A.8.4.5.4 (K3) Pengetesan 1 m pipa Ø 150 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.008 80,000.00 640.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 728.00
B BAHAN
Air test (air bersih) m3 0.018 5,000.00 90.00
Bahan bakar liter 0.060 6,550.00 393.00
Oli liter 0.002 42,000.00 84.00
JUMLAH HARGA BAHAN 567.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,295.00
E Overhead & Profit 15.00% 194.25
F Harga Satuan Pekerjaan (D+E) 1,489.25

A.8.4.5.5 (K3) Pengetesan 1 m pipa Ø 200 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.008 80,000.00 640.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 728.00
B BAHAN
Air test (air bersih) m3 0.031 5,000.00 155.00
Bahan bakar liter 0.060 6,550.00 393.00
Oli liter 0.002 42,000.00 84.00
JUMLAH HARGA BAHAN 632.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,360.00
E Overhead & Profit 15.00% 204.00
F Harga Satuan Pekerjaan (D+E) 1,564.00

A.8.4.5.6 (K3) Pengetesan 1 m pipa Ø 250 mm

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.008 80,000.00 640.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 728.00

III - 179
B BAHAN
Air test (air bersih) m3 0.049 5,000.00 245.00
Bahan bakar liter 0.060 6,550.00 393.00
Oli liter 0.002 42,000.00 84.00
JUMLAH HARGA BAHAN 722.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 1,450.00
E Overhead & Profit 15.00% 217.50
F Harga Satuan Pekerjaan (D+E) 1,667.50

A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL


A.8.4.6.1 (K3) Pemasangan 1 buah titik lampu (Instalasi)

Harga Satuan (Rp) Jumlah Harga (Rp)


No Uraian Kode Satuan Koefisien
A TENAGA
Upah % 1.000 2,372,000.00 2,372,000.00
JUMLAH TENAGA KERJA 2,372,000.00
B BAHAN
Pipa listrik 5/8” btg 3.000 5,000.00 15,000.00
Kabel m 24.000 6,500.00 156,000.00
T Dus buah 3.000 2,000.00 6,000.00
L Bow buah 4.000 2,000.00 8,000.00
Las Dop buah 3.000 3,000.00 9,000.00
Klem buah 24.000 90,000.00 2,160,000.00
Mongkok buah 1.000 1,000.00 1,000.00
Saklar buah 1.000 12,500.00 12,500.00
Fitting buah 1.000 4,500.00 4,500.00
JUMLAH HARGA BAHAN 2,372,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,744,000.00
E Overhead & Profit 15.00% 711,600.00
F Harga Satuan Pekerjaan (D+E) 5,455,600.00

A.8.4.6.1 (K3) Pemasangan 1 buah MCB (Penyambungan Daya ke PLN)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Upah % 1.000 2,313,500.00 2,313,500.00
JUMLAH TENAGA KERJA 2,313,500.00
B BAHAN
Pipa listrik 5/8” btg 3.000 5,000.00 15,000.00
Kabel m 15.000 6,500.00 97,500.00
T Dus buah 1.000 2,000.00 2,000.00
L Bow buah 2.000 2,000.00 4,000.00
Klem biasa buah 24.000 90,000.00 2,160,000.00
MCB buah 1.000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 2,313,500.00
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 4,627,000.00
E Overhead & Profit 15.00% 694,050.00
F Harga Satuan Pekerjaan (D+E) 5,321,050.00

III - 180
TAMBAHAN / LAIN-LAIN

- 1 Buah Pembuatan Papan Nama Proyek

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pembantu tukang oh 0.200 80,000.00 16,000.00
Tukang kayu oh 0.600 100,000.00 60,000.00
Kepala tukang oh 0.060 105,000.00 6,300.00
Mandor oh 0.020 110,000.00 2,200.00
JUMLAH TENAGA KERJA 84,500.00

B BAHAN
Kayu Kaso 5/7 (kayu hutan) m3 0.020 3,500,000.00 70,000.00
Paku Biasa 2-5 kg 0.250 18,000.00 4,500.00
Kayu Dolken dia.8 8-10/4 m' btg 1.500 62,500.00 93,750.00
Triplek 6 mm lbr 0.350 83,000.00 29,050.00
Cetak papan nama dg bhn flexi cetak digital m' 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 222,300.00
C PERALATAN -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 306,800.00


E Overhead & Profit 15.00% 46,020.00
F Harga Satuan Pekerjaan (D+E) 352,820.00

SNI 7395:2008 N0.6.9 Memasang 1 m2 lantai ubin granit ukuran 40 x 40

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pembantu tukang oh 0.250 80,000.00 20,000.00
Tukang batu oh 0.125 100,000.00 12,500.00
Kepala tukang oh 0.013 105,000.00 1,365.00
Mandor oh 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 35,295.00
B BAHAN
ubin granit bh 0.020 42,000.00 840.00
portland cement kg 0.250 1,400.00 350.00
pasir pasang m3 1.500 207,900.00 311,850.00
semen warna kg 0.350 6,000.00 2,100.00
JUMLAH HARGA BAHAN 315,140.00
C PERALATAN -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 350,435.00


E Overhead & Profit 15.00% 52,565.25
F Harga Satuan Pekerjaan (D+E) 403,000.25

SNI 03-7395:2008 N0.6.9 Memasang 1 m2 lantai keramik ukuran 40 x 40

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pembantu tukang oh 0.250 80,000.00 20,000.00
Tukang batu oh 0.120 100,000.00 12,000.00
Kepala tukang oh 0.012 105,000.00 1,260.00
Mandor oh 0.013 110,000.00 1,430.00
JUMLAH TENAGA KERJA 34,690.00

III - 181
B BAHAN
keramik 40 x 40 bh 6.630 5,200.00 34,476.00
portland cement kg 9.800 1,400.00 13,720.00
pasir pasang m3 0.045 207,900.00 9,355.50
semen warna kg 1.300 6,000.00 7,800.00
JUMLAH HARGA BAHAN 65,351.50
C PERALATAN -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 100,041.50


E Overhead & Profit 15.00% 15,006.23
F Harga Satuan Pekerjaan (D+E) 115,047.73

SNI 03-7395:2008 N0.6.9 Memasang 1 m2 lantai granit ukuran 60 x 60

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pembantu tukang oh 0.375 80,000.00 30,000.00
Tukang batu oh 0.180 100,000.00 18,000.00
Kepala tukang oh 0.018 105,000.00 1,890.00
Mandor oh 0.020 110,000.00 2,145.00
JUMLAH TENAGA KERJA 52,035.00
B BAHAN
granito 60 x 60 bh 3.000 53,000.00 159,000.00
portland cement kg 14.700 1,400.00 20,580.00
pasir pasang m3 0.068 207,900.00 14,033.25
semen warna kg 1.950 6,000.00 11,700.00
JUMLAH HARGA BAHAN 205,313.25
C PERALATAN -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 257,348.25


E Overhead & Profit 15.00% 38,602.24
F Harga Satuan Pekerjaan (D+E) 295,950.49

SNI 2839:2008 N0.6.8 Memasang 1 m' List Plafond Gypsum Profil

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pembantu tukang oh 0.060 80,000.00 4,800.00
Tukang batu oh 0.060 100,000.00 6,000.00
Kepala tukang oh 0.006 105,000.00 630.00
Mandor oh 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 11,760.00
B BAHAN
List gypsum profil m' 1.050 20,000.00 21,000.00
Tepung gypsum kg 0.150 18,500.00 2,775.00

JUMLAH HARGA BAHAN 23,775.00


C PERALATAN -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 35,535.00


E Overhead & Profit 15.00% 5,330.25
F Harga Satuan Pekerjaan (D+E) 40,865.25

SNI 2839:2008 N0.6.8 1 m' Pasang Listplank Woodplank

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pembantu tukang oh 0.100 80,000.00 8,000.00

III - 182
Tukang batu oh 0.200 100,000.00 20,000.00
Kepala tukang oh 0.020 105,000.00 2,100.00
Mandor oh 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 30,650.00
B BAHAN
woodplank bh 0.250 60,000.00 15,000.00
Paku biasa 2" - 5" kg 0.050 18,000.00 900.00

JUMLAH HARGA BAHAN 15,900.00


C PERALATAN -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 46,550.00


E Overhead & Profit 15.00% 6,982.50
F Harga Satuan Pekerjaan (D+E) 53,532.50

ABK.990.07 Menurunkan 1 m2 atap genteng

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Mandor L.15 OH 0.100 110,000.00 11,000.00
JUMLAH TENAGA KERJA 27,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 27,000.00


E Overhead & Profit 15.00% 4,050.00
JUMLAH 31,050.00
F Harga Satuan Pekerjaan (D+E) Untuk 1 m2, maka : Upah diambil : 2/3 X Rp 3,105.00 2,070.00

ABK.990.09 Menurunkan 1 m2 rangka atap/Plafond

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.000 80,000.00 80,000.00
Mandor L.04 OH 0.050 110,000.00 5,500.00
JUMLAH TENAGA KERJA 85,500.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 85,500.00


E Overhead & Profit 15.00% 12,825.00
JUMLAH 98,325.00
F Harga Satuan Pekerjaan (D+E) Untuk 1 m2, maka : Upah diambil : 2/3 X Rp 9,832.50 6,555.00

ABK.990.12 Menurunkan 1 m3 kayu rangka kuda-kuda

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.00 80,000.00 320,000.00

III - 183
Tukang kayu L.02 OH 6.00 100,000.00 600,000.00
Kepala tukang L.03 OH 0.60 105,000.00 63,000.00
Mandor L.04 OH 0.20 110,000.00 22,000.00
JUMLAH TENAGA KERJA 1,005,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,005,000.00


E Overhead & Profit 15.00% 150,750.00
JUMLAH 1,155,750.00
F Harga Satuan Pekerjaan (D+E) Untuk 1 m2, maka : Upah diambil : 2/3 X Rp 115,575.00 77,050.00

ABK.990.05 Membongkar 1 m2 lantai tegel/floor

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.00 80,000.00 80,000.00
Mandor L.04 OH 0.10 110,000.00 11,000.00
JUMLAH TENAGA KERJA 91,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 91,000.00


E Overhead & Profit 15.00% 13,650.00
JUMLAH 104,650.00
F Harga Satuan Pekerjaan (D+E) Untuk 1 m2, maka : Upah diambil : 2/3 X Rp 10,465.00 6,976.67

SNI 2012 1 m³ Bongkaran Beton Bertulang

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.667 80,000.00 533,360.00
Mandor L.04 OH 0.333 110,000.00 36,630.00
JUMLAH TENAGA KERJA 569,990.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 569,990.00


E Overhead & Profit 15.00% 85,498.50
F Harga Satuan Pekerjaan (D+E) 655,488.50

III - 184
SNI 2012 1 m³ Bongkaran Dinding Tembok Bata Merah

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.667 80,000.00 533,360.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 536,990.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 536,990.00


E Overhead & Profit 15.00% 80,548.50
F Harga Satuan Pekerjaan (D+E) 617,538.50

ABK.300.19 1 m3 Pekerjaan Beton AD. 1:2:3

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A BAHAN
Semen portland kg 232 1,400.00 324,800.00
Pasir beton m3 0.52 231,000.00 120,120.00
Spleet 2/3 cm m3 0.78 250,000.00 195,000.00
JUMLAH HARGA BAHAN 639,920.00
B TENAGA
Pekerja Oh 1.65 80,000.00 132,000.00
Tukang batu Oh 0.25 100,000.00 25,000.00
Kepala tukang Oh 0.025 105,000.00 2,625.00
Mandor Oh 0.08 110,000.00 8,800.00
JUMLAH TENAGA KERJA 168,425.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 808,345.00


E Overhead & Profit 15.00% 121,251.75
F Harga Satuan Pekerjaan (D+E) 929,596.75

- 1m2 Pasang Plafond Rangka Holo dan Dengan Penutup GRC Berikut Pengecatan

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A BAHAN
GRC 4 mm lbr 0.35 60,000.00 21,000.00
Holo 4/4 meni btg 1.00 12,100.00 12,100.00
Holo 2/4 meni btg 0.34 11,000.00 3,740.00
Kawat Bwg 12 kg 0.10 10,000.00 1,000.00
Paku screw 2.5 cm bh 20.00 50.00 1,000.00
Adhesive kg 0.02 6,000.00 120.00
Kain kasa m' 2.00 400.00 800.00
Cat penutup 2 kali kg 0.03 25,000.00 750.00
Paku beton bh 4.00 175.00 700.00
JUMLAH HARGA BAHAN 41,210.00
B TENAGA
Pekerja oh 0.17 80,000.00 13,600.00
Tukang oh 0.28 100,000.00 28,000.00
Kep Tukang oh 0.03 105,000.00 3,150.00
Mandor oh 0.07 110,000.00 7,700.00
JUMLAH TENAGA KERJA 52,450.00

III - 185
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 93,660.00


E Overhead & Profit 15.00% 14,049.00
F Harga Satuan Pekerjaan (D+E) 107,709.00

- 1 Titik Pekerjaan Instalasi Lampu dan Stop Kontak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A BAHAN
Kabel Listrik NYA 3 x 2,5 mm m' 11.00 6,500.00 71,500.00
Instalasi lapu dan stop kontak ttk 1.00 32,500.00 32,500.00
JUMLAH HARGA BAHAN 104,000.00
B TENAGA
Pembantu tukang Listrik Oh 0.48 80,000.00 38,400.00
Tukang Listrik Oh 0.048 100,000.00 4,800.00
Kepala tukang Listrik Oh 0.048 105,000.00 5,040.00
JUMLAH TENAGA KERJA 48,240.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 152,240.00


E Overhead & Profit 15.00% 22,836.00
F Harga Satuan Pekerjaan (D+E) 175,076.00

- 1 Bh Pekerjaan Stop Kontak

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Stop Kontak bh 1.000 14,000.00 14,000.00
JUMLAH HARGA BAHAN 14,000.00
TENAGA
Pembantu tukang Listrik Oh 0.2 80,000.00 16,000.00
Tukang Listrik Oh 0.02 100,000.00 2,000.00
Kepala tukang Listrik Oh 0.02 105,000.00 2,100.00
JUMLAH TENAGA KERJA 20,100.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 34,100.00


E Overhead & Profit 15.00% 5,115.00
F Harga Satuan Pekerjaan (D+E) 39,215.00

- 1 Bh Pekerjaan Lampu SL 18 Watt + Fitting

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Lampu SL 18 watt + fitting bh 1.000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 30,000.00
TENAGA
Pembantu tukang Listrik Oh 0.2 80,000.00 16,000.00
Tukang Listrik Oh 0.02 100,000.00 2,000.00
Kepala tukang Listrik 0 0.02 105,000.00 2,100.00
JUMLAH TENAGA KERJA 20,100.00

III - 186
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 50,100.00


E Overhead & Profit 15.00% 7,515.00
F Harga Satuan Pekerjaan (D+E) 57,615.00

- 1 Unit Pekerjaan Sekring Kast

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Sekring Kast bh 1.000 40,000.00 40,000.00
JUMLAH HARGA BAHAN 40,000.00
TENAGA
Pembantu tukang Listrik Oh 0.2 80,000.00 16,000.00
Tukang Listrik Oh 0.02 100,000.00 2,000.00
Kepala tukang Listrik Oh 0.02 105,000.00 2,100.00
JUMLAH TENAGA KERJA 20,100.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 60,100.00


E Overhead & Profit 15.00% 9,015.00
F Harga Satuan Pekerjaan (D+E) 69,115.00

- 1 Bh Pekerjaan MCB Box

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
MCB BOX bh 1.000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
TENAGA
Pembantu tukang Listrik Oh 0.2 80,000.00 16,000.00
Tukang Listrik Oh 0.02 100,000.00 2,000.00
Kepala tukang Listrik Oh 0.02 105,000.00 2,100.00
JUMLAH TENAGA KERJA 20,100.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,100.00


E Overhead & Profit 15.00% 8,265.00
F Harga Satuan Pekerjaan (D+E) 63,365.00

- 1 m' Pekerjaan Over Spaneng

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Over Spaneng m' 1.000 9,000.00 9,000.00
JUMLAH HARGA BAHAN 9,000.00
TENAGA
Pembantu tukang Listrik Oh 0.24 80,000.00 19,200.00
Tukang Listrik Oh 0.024 100,000.00 2,400.00
Kepala tukang Listrik Oh 0.024 105,000.00 2,520.00
JUMLAH TENAGA KERJA 24,120.00

III - 187
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 33,120.00


E Overhead & Profit 15.00% 4,968.00
F Harga Satuan Pekerjaan (D+E) 38,088.00

- 1 Bh Pekerjaan Saklar Ganda

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Saklar Ganda bh 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 15,000.00
TENAGA
Pembantu tukang Listrik Oh 0.4 80,000.00 32,000.00
Tukang Listrik Oh 0.04 100,000.00 4,000.00
Kepala tukang Listrik Oh 0.04 105,000.00 4,200.00
JUMLAH TENAGA KERJA 40,200.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 55,200.00


E Overhead & Profit 15.00% 8,280.00
F Harga Satuan Pekerjaan (D+E) 63,480.00

- 1 Bh Pekerjaan Saklar Tunggal

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
BAHAN
Saklar tunggal bh 1.000 12,500.00 12,500.00
JUMLAH HARGA BAHAN 12,500.00
TENAGA
Pembantu tukang Listrik Oh 0.4 80,000.00 32,000.00
Tukang Listrik Oh 0.04 100,000.00 4,000.00
Kepala tukang Listrik Oh 0.04 105,000.00 4,200.00
JUMLAH TENAGA KERJA 40,200.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 52,700.00


E Overhead & Profit 15.00% 7,905.00
F Harga Satuan Pekerjaan (D+E) 60,605.00

A.3.2.1.2.a Pemasangan pasangan 1 m3 batu belah campuran 1SP : 4PP

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.500 80,000.00 120,000.00
Tukang batu L.02 OH 0.750 100,000.00 75,000.00
Kepala tukang L.03 OH 0.075 105,000.00 7,875.00
Mandor L.04 OH 0.075 110,000.00 8,250.00
JUMLAH TENAGA KERJA 211,125.00
B BAHAN
Batu belah m3 1.200 225,000.00 270,000.00
Semen Portland Kg 163.000 1,400.00 228,200.00
Pasir pasang m3 0.520 207,900.00 108,108.00
JUMLAH HARGA BAHAN 606,308.00

III - 188
C PERALATAN

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) 817,433.00
E Overhead & Profit 15.00% 122,614.95
F Harga Satuan Pekerjaan (D+E) 940,047.95

Sumber, 2018

Kepala Dinas Perumahan, Kawasan Permukiman Dan Pertanahan


Kabupaten Cirebon

H. SUKMA NUGRAHA, SH.,MM.


NIP. 19610301 198603 1 012

III - 189
Analisa EI-311a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.1.(1a)


JENIS PEKERJAAN : Galian Biasa / Kupasan (menggunakan alat berat)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0511 11,428.57 584.01


2. Mandor (L03) Jam 0.0256 15,714.29 401.50

JUMLAH HARGA TENAGA 985.51

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Excavator (E10) Jam 0.0256 530,505.76 13,554.54


2. Dump Truck (E08) Jam 0.3344 272,784.44 91,207.75
3. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 104,762.29

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 105,747.80


E. OVERHEAD & PROFIT 15.0 % x D 15,862.17
F. HARGA SATUAN PEKERJAAN ( D + E ) 121,609.97
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 190
Analisa EI-321.rob

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.2.(1).rob


JENIS PEKERJAAN : Timbunan Biasa
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0403 11,428.57 460.62


2. Mandor (L02) Jam 0.0101 15,714.29 158.34

JUMLAH HARGA TENAGA 618.96

B. BAHAN

1. Bahan timbunan (M08) M3 1.1100 125,000.00 138,750.00

JUMLAH HARGA BAHAN 138,750.00

C. PERALATAN
1. Excavator (E10) Jam 0.0101 530,505.76 5,345.45
2. Dump Truck (E08) Jam 0.6103 272,784.44 166,492.21
3. Motor Grader (E13) Jam 0.0037 0.00 0.00
4 Vibro Roller (E19) Jam 0.0042 344,765.59 1,442.29
5. Water tank truck (E23) Jam 0.0070 258,774.99 1,818.70
6 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 175,098.65

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 314,467.62


E. OVERHEAD & PROFIT 15.0 % x D 47,170.14
F. HARGA SATUAN PEKERJAAN ( D + E ) 361,637.76
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 191
Analisa EI-322.rob

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.2.(2).rob


JENIS PEKERJAAN : Timbunan Pilihan
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 2.4294 11,428.57 27,764.38


2. Mandor (L03) Jam 0.6073 15,714.29 9,544.01

JUMLAH HARGA TENAGA 37,308.39

B. BAHAN

1. Bahan pilihan (M09) (M09) M3 1.1100 150,000.00 166,500.00

JUMLAH HARGA BAHAN 166,500.00

C. PERALATAN
1. Wheel Loader (E15) Jam 0.0085 353,363.06 3,005.21
2. Dump Truck (E08) Jam 0.6073 272,784.44 165,674.50
3. Motor Grader (E13) Jam 0.0040 0.00 0.00
3. Tandem (E17) Jam 0.0161 443,067.01 7,135.38
4. Water Tanker (E23) Jam 0.0070 258,774.99 1,818.70
5. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 177,633.79

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 381,442.18


E. OVERHEAD & PROFIT 15.0 % x D 57,216.33
F. HARGA SATUAN PEKERJAAN ( D + E ) 438,658.51
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 192
Analisa EI-331.rob

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.3.(1).rob


JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0024 11,428.57 27.21


2. Mandor (L02) jam 0.0006 15,714.29 9.35

JUMLAH HARGA TENAGA 36.56

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN
1. Motor Grader (E13) jam 0.0006 0.00 0.00
2. Vibro Roller (E19) jam 0.0005 344,765.59 162.26
3 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 162.26

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 198.82


E. OVERHEAD & PROFIT 15.0 % x D 29.82
F. HARGA SATUAN PEKERJAAN ( D + E ) 228.65
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 193
Analisa EI-611a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.1 (1)(a)


JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair
SATUAN PEMBAYARAN : Liter

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 11,428.57 23.81


2. Mandor (L03) Jam 0.0004 15,714.29 6.55

JUMLAH HARGA TENAGA 30.36

B. BAHAN

1. Aspal (M10) Kg 0.6790 12,200.00 8,283.51


2. Kerosene (M11) liter 0.3708 10,225.00 3,791.43

JUMLAH HARGA BAHAN 12,074.94

C. PERALATAN

1. Asp. Distributor E41 Jam 0.0002 374,495.18 78.02


2. Compressor E05 Jam 0.0002 179,166.49 37.33

JUMLAH HARGA PERALATAN 115.35

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 12,220.64


E. OVERHEAD & PROFIT 15.0 % x D 1,833.10
F. HARGA SATUAN PEKERJAAN ( D + E ) 14,053.74
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 194
Analisa EI-612a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.1 (2)(a)


JENIS PEKERJAAN : Lapis Perekat - Aspal Cair
SATUAN PEMBAYARAN : Liter

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 11,428.57 23.81


2. Mandor (L03) Jam 0.0004 15,714.29 6.55

JUMLAH HARGA TENAGA 30.36

B. BAHAN

1. Aspal (M10) Kg 0.8487 12,200.00 10,354.38


2. Kerosene (M11) liter 0.2060 10,225.00 2,106.35

JUMLAH HARGA BAHAN 12,460.73

C. PERALATAN

1. Asp. Distributor E41 Jam 0.0002 374,495.18 78.02


2. Compressor E05 Jam 0.0002 179,166.49 37.33

JUMLAH HARGA PERALATAN 115.35

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 12,606.44


E. OVERHEAD & PROFIT 15.0 % x D 1,890.97
F. HARGA SATUAN PEKERJAAN ( D + E ) 14,497.40
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 195
Analisa EI-621

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.2 (1)


JENIS PEKERJAAN : Agregat Penutup BURTU
SATUAN PEMBAYARAN : M2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2126 11,428.57 2,429.89


2. Mandor (L02) Jam 0.0106 15,714.29 167.05

JUMLAH HARGA TENAGA 2,596.94

B. BAHAN

1. Chipping (M41) Kg 23.0000 129.99 2,989.71

JUMLAH HARGA BAHAN 2,989.71

C. PERALATAN

1. Wheel Loader E15 Jam 0.0106 353,363.06 3,756.52


2. Dump Truck E08 Jam 0.0214 272,784.44 5,829.24
3. P. Tyre Roller E18 Jam 0.0005 442,515.74 238.28
4. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 9,824.04

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 15,410.69


E. OVERHEAD & PROFIT 15.0 % x D 2,311.60
F. HARGA SATUAN PEKERJAAN ( D + E ) 17,722.29
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 196
Analisa EI-631.rob

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.3 (1).rob


JENIS PEKERJAAN : Latasir Kelas A (SS-A)
SATUAN PEMBAYARAN : Ton, m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1406 11,428.57 1,606.43


2. Mandor (L03) Jam 0.0201 15,714.29 315.55

JUMLAH HARGA TENAGA 1,921.97

B. BAHAN

1. Pasir Kasar M01a M3 0.2086 200,000.00 41,712.33


2. Pasir Halus M01c M3 0.4171 180,000.00 75,082.19
3 Semen/Filler (M05) Kg 31.5000 400.00 12,600.00
4 Aspal (M10) Kg 103.0000 12,200.00 1,256,600.00

JUMLAH HARGA BAHAN 1,385,994.52

C. PERALATAN
1. Wheel Loader E15 Jam 0.0096 353,363.06 3,382.17
2. AMP E01 Jam 0.0201 6,233,983.42 125,180.39
3. Genset E12 Jam 0.0201 449,852.17 9,033.18
4. Dump Truck (3,5 ton) E08 Jam 0.0122 272,784.44 3,328.82
5. Asphalt Finisher E02 Jam 0.0386 - 0.00
6. Tandem Roller E17 Jam 0.0317 443,067.01 14,057.38
7 P. Tyre Roller E18 Jam 0.0109 - 0.00
8 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 154,981.95

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,542,898.44


E. OVERHEAD & PROFIT 15.0 % x D 231,434.77
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,774,333.21
MAKA HARGA UNTUK 1 M2 61,183.90
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 197
Analisa EI-632.rob

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.3 (2).rob


JENIS PEKERJAAN : Latasir Kelas B (SS-B)
SATUAN PEMBAYARAN : Ton, m2

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1406 11,428.57 1,606.43


2. Mandor (L03) Jam 0.0201 15,714.29 315.55

JUMLAH HARGA TENAGA 1,921.97

B. BAHAN

1. Pasir Kasar (M01a) M3 0.0139 200,000.00 2,784.66


2. Pasir Halus (M01c) M3 0.0139 180,000.00 2,506.19
3 Semen (M05) 31.5000 400.00 12,600.00
4 Aspal (M10) 92.7000 12,200.00 1,130,940.00

JUMLAH HARGA BAHAN 1,148,830.85

C. PERALATAN
1. Wheel Loader E15 Jam 0.0096 353,363.06 3,382.17
2. AMP E01 Jam 0.0201 6,233,983.42 125,180.39
3. Genset E12 Jam 0.0201 449,852.17 9,033.18
4. Dump Truck E08 Jam 0.0163 272,784.44 4,438.43
5. Asphalt Finisher E02 Jam 0.0290 - 0.00
6. Tandem Roller E17 Jam 0.0238 443,067.01 10,543.04
7 P. Tyre Roller E18 Jam 0.0082 - 0.00
8 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 152,577.21

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,303,330.03


E. OVERHEAD & PROFIT 15.0 % x D 195,499.50
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,498,829.53
MAKA HARGA UNTUK 1 M2 71,372.83
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 198
Analisa EI-661

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.6.(1)


JENIS PEKERJAAN : Lapis Permukaan Penetrasi Macadam
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1417 11,428.57 1,619.93


2. Mandor (L03) Jam 0.0142 15,714.29 222.74

JUMLAH HARGA TENAGA 1,842.66

B. BAHAN

1. Agregat Kasar (M03) M3 1.6690 250,892.68 418,743.41


2. Agregat Halus (M04) M3 0.1479 250,892.68 37,103.85
3 Aspal (M10) Kg 98.5857 12,200.00 1,202,745.71

JUMLAH HARGA BAHAN 1,658,592.97

C. PERALATAN

1. Wheel Loader E15 Jam 0.0071 353,363.06 2,504.34


2. Dump Truck E09 Jam 0.1823 458,230.39 83,531.39
3. 3-Wheel Roller E16 Jam 0.0435 222,018.09 9,653.83
4. Asp. Sprayer E03 Jam 0.3788 111,731.09 42,322.38
5. Alat bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 138,011.96

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,798,447.59


E. OVERHEAD & PROFIT 15.0 % x D 269,767.14
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,068,214.73
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 199
Analisa EI-662

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.6.(2)


JENIS PEKERJAAN : Lapis Pondasi/Perata Penetrasi Macadam
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1417 11,428.57 1,619.93


2. Mandor (L03) Jam 0.0142 15,714.29 222.74

JUMLAH HARGA TENAGA 1,842.66

B. BAHAN

1. Agregat Kasar (M03) M3 1.7746 250,892.68 445,246.16


2. Agregat Halus (M04) M3 0.2465 250,892.68 61,839.74
3 Aspal (M10) Kg 103.0000 12,200.00 1,256,600.00

JUMLAH HARGA BAHAN 1,763,685.90

C. PERALATAN

1. Wheel Loader E15 Jam 0.0071 353,363.06 2,504.34


2. Dump Truck E09 Jam 0.1823 458,230.39 83,531.39
3. 3-Wheel Roller E16 Jam 0.0406 222,018.09 9,010.25
4. Asp. Sprayer E03 Jam 0.3788 111,731.09 42,322.38
5. Alat bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 137,368.37

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,902,896.93


E. OVERHEAD & PROFIT 15.0 % x D 285,434.54
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,188,331.47
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 200
Analisa EI-814

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 8.1 (4)


JENIS PEKERJAAN : Waterbound Macadam Utk. Pek. Minor
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam 0.1631 11,428.57 1,864.09


2. Mandor (L03) Jam 0.0102 15,714.29 160.20

JUMLAH HARGA TENAGA 2,024.29

B. BAHAN

1. Agregat Kasar M3 0.9350 250,892.68 234,584.65


2. Agregat Halus M3 0.1650 250,892.68 41,397.29

JUMLAH HARGA BAHAN 275,981.94

C. PERALATAN

1. Wheel Loader E15 Jam 0.0102 353,363.06 3,602.28


2. Dump Truck E09 Jam 0.0897 458,230.39 41,106.45
3. 3-Wheel Roller E16 Jam 0.0268 222,018.09 5,944.26
4. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 50,652.98

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 328,659.22


E. OVERHEAD & PROFIT 15.0 % x D 49,298.88
F. HARGA SATUAN PEKERJAAN ( D + E ) 377,958.10
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

IV - 201
Analisa EI-817

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 8.1 (7)


JENIS PEKERJAAN : Penetrasi Macadam Utk.Pek.Minor (Perata)
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja Biasa (L01) Jam 0.1701 11,428.57 1,943.91


2. Mandor (L03) Jam 0.0170 15,714.29 267.29

JUMLAH HARGA TENAGA 2,211.20

B. BAHAN

1. Agregat Kasar M3 1.7556 250,892.68 440,456.03


2. Agregat Halus M3 0.0000 250,892.68 0.00
3 Aspal (M10) Kg 99.2727 12,200.00 1,211,127.27

JUMLAH HARGA BAHAN 1,651,583.30

C. PERALATAN

1. Wheel Loader E15 Jam 0.0085 353,363.06 3,005.21


2. Dump Truck E09 Jam 0.2081 458,230.39 95,375.19
3. 3-Wheel Roller E16 Jam 0.0118 222,018.09 2,614.78
4. Asp. Sprayer E03 Jam 0.0359 111,731.09 4,009.50
5. Alat bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 105,004.69

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,758,799.19


E. OVERHEAD & PROFIT 15.0 % x D 263,819.88
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,022,619.07
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Sumber, 2018

Kepala Dinas Perumahan, Kawasan Permukiman Dan Pertanahan


Kabupaten Cirebon

H. SUKMA NUGRAHA, SH.,MM.


NIP. 19610301 198603 1 012

IV - 202
DAFTAR SATUAN ANALISA
DINAS PERUMAHAN KAWASAN PERMUKIMAN DAN PERTANAHAN
KABUPATEN CIREBON
TAHUN ANGGARAN 2017

HARGA SATUAN
NO KODE ANALISA SATUAN PEKERJAAN
Rp

1 A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP 902,315.99


2 A.4.2.1.5. Pengerjaan 10 cm pengelasan dengan las listrik 44,188.75
3 A. 4.4.1.16 rob Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 3PP 101,400.01
4 A. 4.4.1.17 rob Pemasangan 1m2 dinding conblock HB20 campuran 1SP : 4PP 105,243.72
5 A. 4.4.1.18 rob Pemasangan 1m2 dinding conblock HB15 campuran 1SP : 3PP 89,272.32
6 A. 4.4.1.19 rob Pemasangan 1 m2 dinding conblock HB15 campuran 1SP :4PP 89,306.45
7 A. 4.4.1.20 rob Pemasangan 1 m2 dinding conblock HB10 campuran 1SP :3PP 76,940.70
8 A. 4.4.1.21.rob Pemasangan 1 m2 dinding conblock HB10 campuran 1SP : 4PP 77,026.68
9 A. 4.4.1.24.rob Pemasangan 1 m2 dinding bata berongga ekspose 5x11x23 campuran 1SP :3PP 244,777.82
A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL
426 A.8.4.6.1 (K3) Pemasangan 1 buah titik lampu (Instalasi) 5,455,600.00
427 A.8.4.6.1 (K3) Pemasangan 1 buah MCB (Penyambungan Daya ke PLN) 5,321,050.00
- TAMBAHAN / LAIN-LAIN
428 - 1 Buah Pembuatan Papan Nama Proyek 352,820.00
429 SNI 7395:2008 N0.6.9Memasang 1 m2 lantai ubin granit ukuran 40 x 40 403,000.25
430 SNI 03-7395:2008 N0.6.9
Memasang 1 m2 lantai keramik ukuran 40 x 40 115,047.73
431 SNI 03-7395:2008 N0.6.9
Memasang 1 m2 lantai granit ukuran 60 x 60 295,950.49
432 SNI 2839:2008 N0.6.8Memasang 1 m' List Plafond Gypsum Profil 40,865.25
433 SNI 2839:2008 N0.6.81 m' Pasang Listplank Woodplank 53,532.50
434 ABK.990.07 Menurunkan 1 m2 atap genteng 2,070.00
435 ABK.990.09 Menurunkan 1 m2 rangka atap/Plafond 6,555.00
436 ABK.990.12 Menurunkan 1 m3 kayu rangka kuda-kuda 77,050.00
437 ABK.990.05 Membongkar 1 m2 lantai tegel/floor 6,976.67
438 SNI 2012 1 m³ Bongkaran Beton Bertulang 655,488.50
439 SNI 2012 1 m³ Bongkaran Dinding Tembok Bata Merah 617,538.50
440 ABK.300.19 1 m3 Pekerjaan Beton AD. 1:2:3 929,596.75
441 - 1m2 Pasang Plafond Rangka Holo dan Dengan Penutup GRC Berikut Pengecatan 107,709.00
442 - 1 Titik Pekerjaan Instalasi Lampu dan Stop Kontak 175,076.00
443 - 1 Bh Pekerjaan Stop Kontak 39,215.00
444 - 1 Bh Pekerjaan Lampu SL 18 Watt + Fitting 57,615.00
445 - 1 Unit Pekerjaan Sekring Kast 63,365.00
446 - 1 Bh Pekerjaan MCB Box 63,365.00
447 - 1 m' Pekerjaan Over Spaneng 38,088.00
448 - 1 Bh Pekerjaan Saklar Ganda 63,480.00
449 - 1 Bh Pekerjaan Saklar Tunggal 60,605.00
JALAN LINGKUNGAN
450 Analisa EI-311a : Galian Biasa / Kupasan (menggunakan alat berat) 121,609.97
451 Analisa EI-321.rob : Timbunan Biasa 361,637.76
452 Analisa EI-322.rob : Timbunan Pilihan 438,658.51
453 Analisa EI-331.rob : Penyiapan Badan Jalan 228.65
454 Analisa EI-611a : Lapis Resap Pengikat - Aspal Cair 14,053.74
455 Analisa EI-612a : Lapis Perekat - Aspal Cair 14,497.40
456 Analisa EI-621 : Agregat Penutup BURTU 17,722.29
457 Analisa EI-631.rob : Latasir Kelas A (SS-A) 61,183.90
458 Analisa EI-632.rob : Latasir Kelas B (SS-B) 71,372.83
459 Analisa EI-661 : Lapis Permukaan Penetrasi Macadam 2,068,214.73
460 Analisa EI-662 : Lapis Pondasi/Perata Penetrasi Macadam 2,188,331.47
461 Analisa EI-814 : Waterbound Macadam Utk. Pek. Minor 377,958.10
462 Analisa EI-817 : Penetrasi Macadam Utk.Pek.Minor (Perata) 2,022,619.07

Sumber, 2017

Kepala Dinas Perumahan, Kawasan Permukiman Dan Pertanahan Kabupaten Cirebon

H. SUKMA NUGRAHA, SH.,MM.


NIP. 19610301 198603 1 012
AT.02 1 m' Pengeboran Ø 8'' (Daerah Pegunungan)

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3088 80,000.00 24,704.00
Tukang bor L.02 OH 0.0772 100,000.00 7,720.00
Mandor L.04 OH 0.0309 110,000.00 3,399.00
JUMLAH TENAGA KERJA 35,823.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
Driling rig + perlengkapan m 0.541 700,000.00 378,350.00
JUMLAH HARGA ALAT 378,350.00
D Jumlah (A+B+C) 414,173.00
E Overhead & Profit 15.00% 62,125.95
F Harga Satuan Pekerjaan (D+E) 476,298.95

AT.02.rob. 1 m' Pengeboran sederhana

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1544 80,000.00 12,352.00
Tukang bor L.02 OH 0.0386 100,000.00 3,860.00
Mandor L.04 OH 0.0155 110,000.00 1,699.50
JUMLAH TENAGA KERJA 17,911.50
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
Driling rig + perlengkapan m 0.270 700,000.00 189,175.00
JUMLAH HARGA ALAT 189,175.00
D Jumlah (A+B+C) 207,086.50
E Overhead & Profit 15.00% 31,062.98
F Harga Satuan Pekerjaan (D+E) 238,149.48

AT.03 1 m' Reaming Ø 8-12''

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2840 80,000.00 22,720.00
Tukang bor L.02 OH 0.0710 100,000.00 7,100.00

V - 204
Mandor L.04 OH 0.0286 110,000.00 3,146.00
JUMLAH TENAGA KERJA 32,966.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
Driling rig + perlengkapan m' 0.500 700,000.00 350,000.00
JUMLAH HARGA ALAT 350,000.00
D Jumlah (A+B+C) 382,966.00
E Overhead & Profit 15.00% 57,444.90
F Harga Satuan Pekerjaan (D+E) 440,410.90

AT.07 1 m' Pengadaan dan pemasangan cassing pipa PVC 6''

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0720 80,000.00 5,760.00
Tukang bor L.02 OH 0.0180 100,000.00 1,800.00
Mandor L.04 OH 0.0071 110,000.00 781.00
JUMLAH TENAGA KERJA 8,341.00
B BAHAN
Pipa PVC 6'' m 1.0500 199,650.00 209,632.50
Centralizer Ls 0.1000 209,632.50 20,963.25
JUMLAH HARGA BAHAN 230,595.75
C PERALATAN
Driling rig + perlengkapan jam 0.1250 700,000.00 87,500.00
JUMLAH HARGA ALAT 87,500.00
D Jumlah (A+B+C) 326,436.75
E Overhead & Profit 15.00% 48,965.51
F Harga Satuan Pekerjaan (D+E) 375,402.26

AT.09 1 m' Pengadaan dan pemasangan cassing pipa PVC 8''

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0800 80,000.00 6,400.00
Tukang bor L.02 OH 0.0200 100,000.00 2,000.00
Mandor L.04 OH 0.0082 110,000.00 902.00
JUMLAH TENAGA KERJA 9,302.00
B BAHAN
Pipa PVC 8'' m 1.0500 312,000.00 327,600.00
Centralizer Ls 0.1000 327,600.00 32,760.00
JUMLAH HARGA BAHAN 360,360.00
C PERALATAN
Driling rig + perlengkapan m 0.1429 700,000.00 100,030.00
JUMLAH HARGA ALAT 100,030.00
D Jumlah (A+B+C) 469,692.00
E Overhead & Profit 15.00% 70,453.80
F Harga Satuan Pekerjaan (D+E) 540,145.80

V - 205
AT.12 1 m3 Pengadaan dan pemasangan gravel pack

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.0400 80,000.00 83,200.00
Tukang bor L.02 OH 0.2600 100,000.00 26,000.00
Mandor L.04 OH 0.1040 110,000.00 11,440.00
JUMLAH TENAGA KERJA 120,640.00
B BAHAN
Gravel pack pelabuhan m3 1.0000 1,000,000.00 1,000,000.00
ratu/sukabumi
JUMLAH HARGA BAHAN 1,000,000.00
C PERALATAN
Driling rig + perlengkapan m 1.8180 700,000.00 1,272,600.00
JUMLAH HARGA ALAT 1,272,600.00
D Jumlah (A+B+C) 2,393,240.00
E Overhead & Profit 15.00% 358,986.00
F Harga Satuan Pekerjaan (D+E) 2,752,226.00

AT.13 1 jam pencucian sumur

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.5720 80,000.00 45,760.00
Tukang bor L.02 OH 0.1430 100,000.00 14,300.00
Mandor L.04 OH 0.0570 110,000.00 6,270.00
JUMLAH TENAGA KERJA 66,330.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Driling rig + perlengkapan jam 1.0000 87,500.00 87,500.00
JUMLAH HARGA ALAT 87,500.00
D Jumlah (A+B+C) 153,830.00
E Overhead & Profit 15.00% 23,074.50
F Harga Satuan Pekerjaan (D+E) 176,904.50

AT.14 1 jam Uji Pemompaan

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.5720 80,000.00 45,760.00
Tukang bor L.02 OH 0.1430 100,000.00 14,300.00
Mandor L.04 OH 0.0570 110,000.00 6,270.00
JUMLAH TENAGA KERJA 66,330.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Driling rig + perlengkapan jam 1.0000 87,500.00 87,500.00
JUMLAH HARGA ALAT 87,500.00
D Jumlah (A+B+C) 153,830.00
E Overhead & Profit 15.00% 23,074.50
F Harga Satuan Pekerjaan (D+E) 176,904.50

V - 206
1 m³ Galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

pekerja OH 0.750 80,000.00 60,000.00


mandor OH 0.025 110,000.00 2,750.00
JUMLAH 62,750.00

1 m³ Galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

pekerja 1.000 80,000.00 80,000.00


mandor 0.033 110,000.00 3,630.00
JUMLAH 83,630.00

1 m³ Galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

pekerja 1.500 80,000.00 120,000.00


mandor 0.050 110,000.00 5,500.00
JUMLAH 125,500.00

1 m³ Urugan tanah kembali

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

pekerja 0.300 80,000.00 24,000.00


mandor 0.010 110,000.00 1,100.00
JUMLAH 25,100.00

1 m³ Buang tanah sisa galian

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

pekerja 0.330 80,000.00 26,400.00


mandor 0.010 110,000.00 1,100.00
JUMLAH 27,500.00

1 m³ Urugan pasir

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ pasir urug 1.200 173,300.00 207,960.00


pekerja 0.300 80,000.00 24,000.00
mandor 0.010 110,000.00 1,100.00
JUMLAH 233,060.00

V - 207
1 m³ Beton tumbuk 1:3:5

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ koral beton ( sirtu tersaring ) 0.940 184,800.00 173,712.00


m³ pasir beton 0.470 231,000.00 108,570.00
kg semen portland 197 1,400.00 275,800.00
tukang batu 0.250 100,000.00 25,000.00
kepala tukang 0.025 105,000.00 2,625.00
mandor 0.080 110,000.00 8,800.00
pekerja 1.650 80,000.00 132,000.00
JUMLAH 726,507.00

1 m² Pasang bekisting

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ kayu hutan / papan / kaso 0.040 3,500,000.00 140,000.00


kg paku biasa 2" - 5" 0.300 18,000.00 5,400.00
ltr pelumas bekisting 0.100 10,000.00 1,000.00
tukang kayu 0.260 100,000.00 26,000.00
kepala tukang 0.026 105,000.00 2,730.00
mandor 0.005 110,000.00 550.00
pekerja 0.300 80,000.00 24,000.00
JUMLAH 199,680.00

1 m³ Trush block

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ galian tanah keras / berbatu 1.000 83,630.00 83,630.00


m³ beton tumbuk 1:3:5 1.000 726,507.00 726,507.00
m² bekisting 1.000 199,680.00 199,680.00
JUMLAH 1,009,817.00

1 m² Plesteran 1:3

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

kg semen portland 6.480 1,400.00 9,072.00


m³ pasir pasang 0.019 207,900.00 3,950.10
tukang batu 0.150 100,000.00 15,000.00
kepala tukang 0.015 105,000.00 1,575.00
mandor 0.200 110,000.00 22,000.00
pekerja 0.010 80,000.00 800.00
JUMLAH 52,397.10

1 m³ Pasangan batu kali 1:4

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ batu belah 10/15 cm 1.100 225,000.00 247,500.00


kg semen portland 163 1,400.00 228,200.00
m³ pasir pasang 0.520 207,900.00 108,108.00

V - 208
tukang batu 0.600 100,000.00 60,000.00
kepala tukang 0.060 105,000.00 6,300.00
mandor 1.500 110,000.00 165,000.00
pekerja 0.075 80,000.00 6,000.00
JUMLAH 821,108.00

1 m² Siaran batu muka

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

zak semen portland 0.132 70,000.00 9,240.00


m³ pasir pasang 0.009 207,900.00 1,871.10
tukang batu 0.120 100,000.00 12,000.00
kepala tukang 0.012 105,000.00 1,260.00
mandor 0.018 110,000.00 1,980.00
pekerja 0.360 80,000.00 28,800.00
JUMLAH 55,151.10

1 m³ Beton bertulang 1:2:3

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ batu split 0.780 300,000.00 234,000.00


m³ pasir beton 0.520 231,000.00 120,120.00
kg semen portland 232 1,400.00 324,800.00
tukang batu 0.250 100,000.00 25,000.00
kepala tukang 0.025 105,000.00 2,625.00
mandor 0.080 110,000.00 8,800.00
pekerja 1.650 80,000.00 132,000.00
JUMLAH 847,345.00

1 kg Pembesian dengan besi polos atau besi ulir

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

kg besi beton ( polos / ulir ) 1.050 13,000.00 13,650.00


kg kawat beton 0.015 20,000.00 300.00
tukang besi 0.007 100,000.00 700.00
kepala tukang 0.0007 105,000.00 73.50
mandor 0.0003 110,000.00 33.00
pekerja 0.007 80,000.00 560.00
JUMLAH 15,316.50

1 m² Pekerjaan bekisting dari multiplek 6mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

lbr multiplek 15 mm 0.350 280,000.00 98,000.00


m³ kayu hutan / papan / kaso 0.050 3,500,000.00 175,000.00
kg paku 0.400 18,000.00 7,200.00
tukang kayu 0.500 100,000.00 50,000.00
kepala tukang 0.050 105,000.00 5,250.00
mandor 0.010 110,000.00 1,100.00
pekerja 0.600 80,000.00 48,000.00
JUMLAH 384,550.00

V - 209
1 m² Pasangan bata merah 1 : 4 tebal 1/2 bata

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

bh bata merah 5 x 11 x 22 cm 70.000 800.00 56,000.00


kg semen portland 11.500 1,400.00 16,100.00
m³ pasir pasang 0.043 207,900.00 8,939.70
tukang batu 0.100 100,000.00 10,000.00
kepala tukang 0.010 105,000.00 1,050.00
mandor 0.320 110,000.00 35,200.00
pekerja 0.015 80,000.00 1,200.00
JUMLAH 128,489.70

1 m² Pengecatan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

kg cat dasar 0.120 25,000.00 3,000.00


kg cat penutup 2 kali 0.360 27,500.00 9,900.00
lbr hampelas 0.200 3,000.00 600.00
tukang cat 0.042 100,000.00 4,200.00
kepala tukang 0.0042 105,000.00 441.00
pekerja 0.028 80,000.00 2,240.00
JUMLAH 20,381.00

10 cm Pengelasan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

kg kawat las 0.250 27,000.00 6,750.00


jam mesin las 0.042 200,000.00 8,400.00
jam mesin blower 0.042 300,000.00 12,600.00
kg tabung gas 0.250 15,000.00 3,750.00
ls alat bantu 1.000 5,000.00 5,000.00
tukang las 0.042 110,000.00 4,620.00
pekerja 0.021 80,000.00 1,680.00
mandor 0.004 110,000.00 440.00
JUMLAH 43,240.00
Untuk 1 m' pengelasan 432,400.00

1 m' Pemasangan pipa PVC dia. 350 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.880 125,500.00 110,440.00


m³ Urugan pasir 0.240 233,060.00 55,934.40
m³ Urugan tanah kembali 0.600 25,100.00 15,060.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
m' Pemasangan pipa PVC dia. 350 mm 1 5,500.00 5,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 189,684.40

V - 210
1 m' Pemasangan pipa PVC dia. 300 mm melalui galian tanah berbatu / bongkar jalan

m³ Galian tanah berbatu / bongkar jalan 0.825 125,500.00 103,537.50


m³ Urugan pasir 0.225 233,060.00 52,438.50
m³ Urugan tanah kembali 0.563 25,100.00 14,118.75
m³ Buang tanah sisa galian 0.038 27,500.00 1,031.25
m' Pemasangan pipa PVC dia. 300 mm 1 5,000.00 5,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 177,776.00

1 m' Pemasangan pipa PVC dia. 250 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.715 125,500.00 89,732.50


m³ Urugan pasir 0.195 233,060.00 45,446.70
m³ Urugan tanah kembali 0.488 25,100.00 12,236.25
m³ Buang tanah sisa galian 0.033 27,500.00 893.75
m' Pemasangan pipa PVC dia. 250 mm 1 4,500.00 4,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 154,459.20

1 m' Pemasangan pipa PVC dia. 200 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.600 125,500.00 75,300.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.450 25,100.00 11,295.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
m' Pemasangan pipa PVC dia. 200 mm 1 4,000.00 4,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 121,037.20

1 m' Pemasangan pipa PVC dia. 160 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.450 125,500.00 56,475.00


m³ Urugan pasir 0.100 233,060.00 23,306.00
m³ Urugan tanah kembali 0.325 25,100.00 8,157.50
m³ Buang tanah sisa galian 0.025 27,500.00 687.50
m' Pemasangan pipa PVC dia. 160 mm 1 3,500.00 3,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 93,776.00

1 m' Pemasangan pipa PVC dia. 110 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.260 25,100.00 6,526.00

V - 211
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
m' Pemasangan pipa PVC dia. 110 mm 1 3,000.00 3,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 75,550.80

1 m' Pemasangan pipa PVC dia. 90 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.320 125,500.00 40,160.00


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.220 25,100.00 5,522.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
m' Pemasangan pipa PVC dia. 90 mm 1 2,500.00 2,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 69,026.80

1 m' Pemasangan pipa PVC dia. 63 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.180 125,500.00 22,590.00


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 63 mm 1 2,000.00 2,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 43,271.60

1 m' Pemasangan pipa PVC dia. 50 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.180 125,500.00 22,590.00


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 50 mm 1 1,500.00 1,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 42,771.60

1 m' Pemasangan pipa PVC dia. 25 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.120 125,500.00 15,060.00


m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 25 mm 1 1,000.00 1,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 20,758.00

V - 212
1 m' Pemasangan pipa PVC dia. 350 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.880 83,630.00 73,594.40


m³ Urugan pasir 0.240 233,060.00 55,934.40
m³ Urugan tanah kembali 0.600 25,100.00 15,060.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
m' Pemasangan pipa PVC dia. 350 mm 1 5,500.00 5,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 152,838.80

1 m' Pemasangan pipa PVC dia. 300 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.825 83,630.00 68,994.75


m³ Urugan pasir 0.225 233,060.00 52,438.50
m³ Urugan tanah kembali 0.563 25,100.00 14,118.75
m³ Buang tanah sisa galian 0.038 27,500.00 1,031.25
m' Pemasangan pipa PVC dia. 300 mm 1 5,000.00 5,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 143,233.25

1 m' Pemasangan pipa PVC dia. 250 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.715 83,630.00 59,795.45


m³ Urugan pasir 0.195 233,060.00 45,446.70
m³ Urugan tanah kembali 0.488 25,100.00 12,236.25
m³ Buang tanah sisa galian 0.033 27,500.00 893.75
m' Pemasangan pipa PVC dia. 250 mm 1 4,500.00 4,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 124,522.15

1 m' Pemasangan pipa PVC dia. 200 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.600 83,630.00 50,178.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.450 25,100.00 11,295.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
m' Pemasangan pipa PVC dia. 200 mm 1 4,000.00 4,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 95,915.20

1 m' Pemasangan pipa PVC dia. 160 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.450 83,630.00 37,633.50


m³ Urugan pasir 0.100 233,060.00 23,306.00

V - 213
m³ Urugan tanah kembali 0.325 25,100.00 8,157.50
m³ Buang tanah sisa galian 0.025 27,500.00 687.50
m' Pemasangan pipa PVC dia. 160 mm 1 3,500.00 3,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 74,934.50

1 m' Pemasangan pipa PVC dia. 110 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.360 83,630.00 30,106.80


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.260 25,100.00 6,526.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
m' Pemasangan pipa PVC dia. 110 mm 1 3,000.00 3,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 60,477.60

1 m' Pemasangan pipa PVC dia. 90 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.320 83,630.00 26,761.60


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.220 25,100.00 5,522.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
m' Pemasangan pipa PVC dia. 90 mm 1 2,500.00 2,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 55,628.40

1 m' Pemasangan pipa PVC dia. 63 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.180 83,630.00 15,053.40


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 63 mm 1 2,000.00 2,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 35,735.00

1 m' Pemasangan pipa PVC dia. 50 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.180 83,630.00 15,053.40


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 50 mm 1 1,500.00 1,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 35,235.00

V - 214
1 m' Pemasangan pipa PVC dia. 25 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.120 83,630.00 10,035.60


m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 25 mm 1 1,000.00 1,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 15,733.60

1 m' Pemasangan pipa PVC dia. 350 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.880 62,750.00 55,220.00


m³ Urugan pasir 0.240 233,060.00 55,934.40
m³ Urugan tanah kembali 0.600 25,100.00 15,060.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
m' Pemasangan pipa PVC dia. 350 mm 1 5,500.00 5,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 134,464.40

1 m' Pemasangan pipa PVC dia. 300 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.825 62,750.00 51,768.75


m³ Urugan pasir 0.225 233,060.00 52,438.50
m³ Urugan tanah kembali 0.563 25,100.00 14,118.75
m³ Buang tanah sisa galian 0.038 27,500.00 1,031.25
m' Pemasangan pipa PVC dia. 300 mm 1 5,000.00 5,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 126,007.25

1 m' Pemasangan pipa PVC dia. 250 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.715 62,750.00 44,866.25


m³ Urugan pasir 0.195 233,060.00 45,446.70
m³ Urugan tanah kembali 0.488 25,100.00 12,236.25
m³ Buang tanah sisa galian 0.033 27,500.00 893.75
m' Pemasangan pipa PVC dia. 250 mm 1 4,500.00 4,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 109,592.95

1 m' Pemasangan pipa PVC dia. 200 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.600 62,750.00 37,650.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.450 25,100.00 11,295.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
m' Pemasangan pipa PVC dia. 200 mm 1 4,000.00 4,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 83,387.20

V - 215
1 m' Pemasangan pipa PVC dia. 160 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.450 62,750.00 28,237.50


m³ Urugan pasir 0.100 233,060.00 23,306.00
m³ Urugan tanah kembali 0.325 25,100.00 8,157.50
m³ Buang tanah sisa galian 0.025 27,500.00 687.50
m' Pemasangan pipa PVC dia. 160 mm 1 3,500.00 3,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 65,538.50

1 m' Pemasangan pipa PVC dia. 110 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.360 62,750.00 22,590.00


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.260 25,100.00 6,526.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
m' Pemasangan pipa PVC dia. 110 mm 1 3,000.00 3,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 52,960.80

1 m' Pemasangan pipa PVC dia. 90 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.320 62,750.00 20,080.00


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.220 25,100.00 5,522.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
m' Pemasangan pipa PVC dia. 90 mm 1 2,500.00 2,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 48,946.80

1 m' Pemasangan pipa PVC dia. 63 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.180 62,750.00 11,295.00


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 63 mm 1 2,000.00 2,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 31,976.60

1 m' Pemasangan pipa PVC dia. 50 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.180 62,750.00 11,295.00


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50

V - 216
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 50 mm 1 1,500.00 1,500.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 31,476.60

1 m' Pemasangan pipa PVC dia. 25 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.120 62,750.00 7,530.00


m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
m' Pemasangan pipa PVC dia. 25 mm 1 1,000.00 1,000.00
ls Perapihan 1 1,650.00 1,650.00
JUMLAH 13,228.00

1 m' Perbaikan pipa PVC dia. 350 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.880 125,500.00 110,440.00


m³ Urugan pasir 0.240 233,060.00 55,934.40
m³ Urugan tanah kembali 0.600 25,100.00 15,060.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan pipa PVC dia. 350 mm 1 144,500.00 144,500.00
ls Perapihan 1 19,700.00 19,700.00
JUMLAH 346,734.40

1 m' Perbaikan pipa PVC dia. 300 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.825 125,500.00 103,537.50


m³ Urugan pasir 0.225 233,060.00 52,438.50
m³ Urugan tanah kembali 0.563 25,100.00 14,131.30
m³ Buang tanah sisa galian 0.038 27,500.00 1,045.00
ls Perbaikan pipa PVC dia. 300 mm 1 105,000.00 105,000.00
ls Perapihan 1 17,700.00 17,700.00
JUMLAH 293,852.30

1 m' Perbaikan pipa PVC dia. 250 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.715 125,500.00 89,732.50


m³ Urugan pasir 0.195 233,060.00 45,446.70
m³ Urugan tanah kembali 0.488 25,100.00 12,248.80
m³ Buang tanah sisa galian 0.033 27,500.00 907.50
ls Perbaikan pipa PVC dia. 250 mm 1 83,350.00 83,350.00
ls Perapihan 1 15,700.00 15,700.00
JUMLAH 247,385.50

V - 217
1 m' Perbaikan pipa PVC dia. 200 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.600 125,500.00 75,300.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.450 25,100.00 11,295.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan pipa PVC dia. 200 mm 1 76,150.00 76,150.00
ls Perapihan 1 15,700.00 15,700.00
JUMLAH 207,237.20

1 m' Perbaikan pipa PVC dia. 160 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.450 125,500.00 56,475.00


m³ Urugan pasir 0.100 233,060.00 23,306.00
m³ Urugan tanah kembali 0.325 25,100.00 8,157.50
m³ Buang tanah sisa galian 0.025 27,500.00 687.50
ls Perbaikan pipa PVC dia. 160 mm 1 52,500.00 52,500.00
ls Perapihan 1 13,700.00 13,700.00
JUMLAH 154,826.00

1 m' Perbaikan pipa PVC dia. 110 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.260 25,100.00 6,526.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
ls Perbaikan pipa PVC dia. 110 mm 1 43,350.00 43,350.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 125,950.80

1 m' Perbaikan pipa PVC dia. 90 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.320 125,500.00 40,160.00


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.220 25,100.00 5,522.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
ls Perbaikan pipa PVC dia. 90 mm 1 32,250.00 32,250.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 108,826.80

1 m' Perbaikan pipa PVC dia. 63 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.180 125,500.00 22,590.00


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50

V - 218
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 63 mm 1 17,100.00 17,100.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 68,421.60

1 m' Perbaikan pipa PVC dia. 50 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.180 125,500.00 22,590.00


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 50 mm 1 11,850.00 11,850.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 63,171.60

1 m' Perbaikan pipa PVC dia. 25 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.120 125,500.00 15,060.00


m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 25 mm 1 7,900.00 7,900.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 37,708.00

1 m' Perbaikan pipa PVC dia. 350 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.880 83,630.00 73,594.40


m³ Urugan pasir 0.240 233,060.00 55,934.40
m³ Urugan tanah kembali 0.600 25,100.00 15,060.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan pipa PVC dia. 350 mm 1 144,500.00 144,500.00
ls Perapihan 1 19,700.00 19,700.00
JUMLAH 309,888.80

1 m' Perbaikan pipa PVC dia. 300 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.825 83,630.00 68,994.75


m³ Urugan pasir 0.225 233,060.00 52,438.50
m³ Urugan tanah kembali 0.563 25,100.00 14,131.30
m³ Buang tanah sisa galian 0.033 27,500.00 907.50
ls Perbaikan pipa PVC dia. 300 mm 1 105,000.00 105,000.00
ls Perapihan 1 17,700.00 17,700.00
JUMLAH 259,172.05

V - 219
1 m' Perbaikan pipa PVC dia. 250 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.715 83,630.00 59,795.45


m³ Urugan pasir 0.195 233,060.00 45,446.70
m³ Urugan tanah kembali 0.488 25,100.00 12,248.80
m³ Buang tanah sisa galian 0.033 27,500.00 907.50
ls Perbaikan pipa PVC dia. 250 mm 1 83,350.00 83,350.00
ls Perapihan 1 15,700.00 15,700.00
JUMLAH 217,448.45

1 m' Perbaikan pipa PVC dia. 200 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.600 83,630.00 50,178.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.450 25,100.00 11,295.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan pipa PVC dia. 200 mm 1 76,150.00 76,150.00
ls Perapihan 1 15,700.00 15,700.00
JUMLAH 182,115.20

1 m' Perbaikan pipa PVC dia. 160 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.450 83,630.00 37,633.50


m³ Urugan pasir 0.100 233,060.00 23,306.00
m³ Urugan tanah kembali 0.325 25,100.00 8,157.50
m³ Buang tanah sisa galian 0.025 27,500.00 687.50
ls Perbaikan pipa PVC dia. 160 mm 1 52,500.00 52,500.00
ls Perapihan 1 13,700.00 13,700.00
JUMLAH 135,984.50

1 m' Perbaikan pipa PVC dia. 110 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.360 83,630.00 30,106.80


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.260 25,100.00 6,526.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
ls Perbaikan pipa PVC dia. 110 mm 1 43,350.00 43,350.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 110,877.60

1 m' Perbaikan pipa PVC dia. 90 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.320 83,630.00 26,761.60


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.220 25,100.00 5,522.00

V - 220
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
ls Perbaikan pipa PVC dia. 90 mm 1 32,250.00 32,250.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 95,428.40

1 m' Perbaikan pipa PVC dia. 63 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.180 83,630.00 15,053.40


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 63 mm 1 17,100.00 17,100.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 60,885.00

1 m' Perbaikan pipa PVC dia. 50 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.180 83,630.00 15,053.40


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 50 mm 1 11,850.00 11,850.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 55,635.00

1 m' Perbaikan pipa PVC dia. 25 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.120 83,630.00 10,035.60


m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 25 mm 1 7,900.00 7,900.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 32,683.60

1 m' Perbaikan pipa PVC dia. 350 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.880 62,750.00 55,220.00


m³ Urugan pasir 0.240 233,060.00 55,934.40
m³ Urugan tanah kembali 0.600 25,100.00 15,060.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan pipa PVC dia. 350 mm 1 144,500.00 144,500.00
ls Perapihan 1 19,700.00 19,700.00
JUMLAH 291,514.40

V - 221
1 m' Perbaikan pipa PVC dia. 300 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.825 62,750.00 51,768.75


m³ Urugan pasir 0.225 233,060.00 52,438.50
m³ Urugan tanah kembali 0.563 25,100.00 14,131.30
m³ Buang tanah sisa galian 0.038 27,500.00 1,045.00
ls Perbaikan pipa PVC dia. 300 mm 1 105,000.00 105,000.00
ls Perapihan 1 17,700.00 17,700.00
JUMLAH 242,083.55

1 m' Perbaikan pipa PVC dia. 250 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.715 62,750.00 44,866.25


m³ Urugan pasir 0.195 233,060.00 45,446.70
m³ Urugan tanah kembali 0.488 25,100.00 12,248.80
m³ Buang tanah sisa galian 0.033 27,500.00 907.50
ls Perbaikan pipa PVC dia. 250 mm 1 83,350.00 83,350.00
ls Perapihan 1 15,700.00 15,700.00
JUMLAH 202,519.25

1 m' Perbaikan pipa PVC dia. 200 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.600 62,750.00 37,650.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.450 25,100.00 11,295.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan pipa PVC dia. 200 mm 1 76,150.00 76,150.00
ls Perapihan 1 15,700.00 15,700.00
JUMLAH 169,587.20

1 m' Perbaikan pipa PVC dia. 160 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.450 62,750.00 28,237.50


m³ Urugan pasir 0.100 233,060.00 23,306.00
m³ Urugan tanah kembali 0.325 25,100.00 8,157.50
m³ Buang tanah sisa galian 0.025 27,500.00 687.50
ls Perbaikan pipa PVC dia. 160 mm 1 52,500.00 52,500.00
ls Perapihan 1 13,700.00 13,700.00
JUMLAH 126,588.50

1 m' Perbaikan pipa PVC dia. 110 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.360 62,750.00 22,590.00


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.260 25,100.00 6,526.00

V - 222
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
ls Perbaikan pipa PVC dia. 110 mm 1 43,350.00 43,350.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 103,360.80

1 m' Perbaikan pipa PVC dia. 90 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.320 62,750.00 20,080.00


m³ Urugan pasir 0.080 233,060.00 18,644.80
m³ Urugan tanah kembali 0.220 25,100.00 5,522.00
m³ Buang tanah sisa galian 0.020 27,500.00 550.00
ls Perbaikan pipa PVC dia. 90 mm 1 32,250.00 32,250.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 88,746.80

1 m' Perbaikan pipa PVC dia. 63 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.180 62,750.00 11,295.00


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 63 mm 1 17,100.00 17,100.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 57,126.60

1 m' Perbaikan pipa PVC dia. 50 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.180 62,750.00 11,295.00


m³ Urugan pasir 0.060 233,060.00 13,983.60
m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 50 mm 1 11,850.00 11,850.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 51,876.60

1 m' Perbaikan pipa PVC dia. 25 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.120 62,750.00 7,530.00


m³ Urugan tanah kembali 0.105 25,100.00 2,635.50
m³ Buang tanah sisa galian 0.015 27,500.00 412.50
ls Perbaikan pipa PVC dia. 25 mm 1 7,900.00 7,900.00
ls Perapihan 1 11,700.00 11,700.00
JUMLAH 30,178.00

V - 223
400 m' Pengetesan pipa PVC dia. 350 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 157,500.00 157,500.00


ls biaya perpompaan 1.000 105,000.00 105,000.00
m³ penyediaan air bersih 37.000 31,500.00 1,165,500.00
hr biaya mesin test, BBM, dan servis 7.000 52,500.00 367,500.00
mekanik 3.500 100,000.00 350,000.00
tukang pipa 7.000 100,000.00 700,000.00
kepala tukang 0.700 105,000.00 73,500.00
pekerja 7.000 80,000.00 560,000.00
mandor 0.350 110,000.00 38,500.00
JUMLAH 3,517,500.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 3,517,500.00 8,793.75

400 m' Pengetesan pipa PVC dia. 300 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 157,500.00 157,500.00


ls biaya perpompaan 1.000 105,000.00 105,000.00
m³ penyediaan air bersih 28.000 31,500.00 882,000.00
hr biaya mesin test, BBM, dan servis 6.000 52,500.00 315,000.00
mekanik 3.000 100,000.00 300,000.00
tukang pipa 6.000 100,000.00 600,000.00
kepala tukang 0.600 105,000.00 63,000.00
pekerja 6.000 80,000.00 480,000.00
mandor 0.300 110,000.00 33,000.00
JUMLAH 2,935,500.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 2,935,500.00 7,338.75

400 m' Pengetesan pipa PVC dia. 250 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 157,500.00 157,500.00


ls biaya perpompaan 1.000 105,000.00 105,000.00
m³ penyediaan air bersih 20.000 31,500.00 630,000.00
hr biaya mesin test, BBM, dan servis 5.000 52,500.00 262,500.00
mekanik 2.500 100,000.00 250,000.00
tukang pipa 5.000 100,000.00 500,000.00
kepala tukang 0.500 105,000.00 52,500.00
pekerja 5.000 80,000.00 400,000.00
mandor 0.250 110,000.00 27,500.00
JUMLAH 2,385,000.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 2,385,000.00 5,962.50

400 m' Pengetesan pipa PVC dia. 200 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 157,500.00 157,500.00


ls biaya perpompaan 1.000 105,000.00 105,000.00
m³ penyediaan air bersih 13.000 31,500.00 409,500.00

V - 224
hr biaya mesin test, BBM, dan servis 4.000 52,500.00 210,000.00
mekanik 2.000 100,000.00 200,000.00
tukang pipa 4.000 100,000.00 400,000.00
kepala tukang 0.400 105,000.00 42,000.00
pekerja 4.000 80,000.00 320,000.00
mandor 0.200 110,000.00 22,000.00
JUMLAH 1,866,000.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 1,866,000.00 4,665.00

400 m' Pengetesan pipa PVC dia. 160 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 157,500.00 157,500.00


ls biaya perpompaan 1.000 105,000.00 105,000.00
m³ penyediaan air bersih 7.000 31,500.00 220,500.00
hr biaya mesin test, BBM, dan servis 2.500 52,500.00 131,250.00
tukang pipa 3.000 100,000.00 300,000.00
kepala tukang 0.300 105,000.00 31,500.00
pekerja 3.000 80,000.00 240,000.00
mandor 0.150 110,000.00 16,500.00
JUMLAH 1,202,250.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 1,202,250.00 3,005.63

400 m' Pengetesan pipa PVC dia. 110 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 186,000.00 186,000.00


ls biaya perpompaan 1.000 126,000.00 126,000.00
m³ penyediaan air bersih 5.000 31,500.00 157,500.00
hr biaya mesin test, BBM, dan servis 2.000 52,500.00 105,000.00
tukang pipa 3.000 100,000.00 300,000.00
kepala tukang 0.300 105,000.00 31,500.00
pekerja 3.000 80,000.00 240,000.00
mandor 0.150 110,000.00 16,500.00
JUMLAH 1,162,500.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 1,162,500.00 2,906.25

400 m' Pengetesan pipa PVC dia. 90 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 186,000.00 186,000.00


ls biaya perpompaan 1.000 126,000.00 126,000.00
m³ penyediaan air bersih 2.500 31,500.00 78,750.00
hr biaya mesin test, BBM, dan servis 2.000 52,500.00 105,000.00
tukang pipa 3.000 100,000.00 300,000.00
kepala tukang 0.300 105,000.00 31,500.00
pekerja 3.000 80,000.00 240,000.00
mandor 0.150 110,000.00 16,500.00
JUMLAH 1,083,750.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 1,083,750.00 2,709.38

V - 225
400 m' Pengetesan pipa PVC dia. 63 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 186,000.00 186,000.00


ls biaya perpompaan 1.000 126,000.00 126,000.00
m³ penyediaan air bersih 1.000 31,500.00 31,500.00
hr biaya mesin test, BBM, dan servis 2.000 52,500.00 105,000.00
tukang pipa 3.000 100,000.00 300,000.00
kepala tukang 0.300 105,000.00 31,500.00
pekerja 3.000 80,000.00 240,000.00
mandor 0.150 110,000.00 16,500.00
JUMLAH 1,036,500.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 1,036,500.00 2,591.25

400 m' Pengetesan pipa PVC dia. 50 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls penyediaan alat bantu dan pek. pengedopan 1.000 186,000.00 186,000.00


ls biaya perpompaan 1.000 126,000.00 126,000.00
m³ penyediaan air bersih 0.250 31,500.00 7,875.00
hr biaya mesin test, BBM, dan servis 1.750 52,500.00 91,875.00
tukang pipa 3.000 100,000.00 300,000.00
kepala tukang 0.300 105,000.00 31,500.00
pekerja 3.000 80,000.00 240,000.00
mandor 0.150 110,000.00 16,500.00
JUMLAH 999,750.00
Per m' Pengetesan Pipa PVC dia. 350 mm = 1/400 x Rp. 999,750.00 2,499.38

1 unit perbaikan gate valve dia. 350mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls bongkar box street (beton) 1 22,000.00 22,000.00


m³ galian tanah keras / berbatu 3.375 83,630.00 282,251.25
ls perbaikan gate valve dia. 350mm 1 210,000.00 210,000.00
m³ urugan tanah kembali 2.250 25,100.00 56,475.00
m³ pasang box street dia. 160 mm beton tumbuk 1 : 0.075 726,507.00 54,488.03
ls perapihan 1 63,000.00 63,000.00
JUMLAH 688,214.28

1 unit perbaikan gate valve dia. 300mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls bongkar box street (beton) 1 22,000.00 22,000.00


m³ galian tanah keras / berbatu 3.375 83,630.00 282,251.25
ls perbaikan gate valve dia. 300mm 1 210,000.00 210,000.00
m³ urugan tanah kembali 2.250 25,100.00 56,475.00
m³ pasang box street dia. 300mm beton tumbuk 1 : 0.075 726,507.00 54,488.03
ls perapihan 1 47,250.00 47,250.00
JUMLAH 672,464.28

V - 226
1 unit perbaikan gate valve dia. 250mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls bongkar box street (beton) 1 22,000.00 22,000.00


m³ galian tanah keras / berbatu 3.375 83,630.00 282,251.25
ls perbaikan gate valve dia. 250mm 1 210,000.00 210,000.00
m³ urugan tanah kembali 2.250 25,100.00 56,475.00
m³ pasang box street dia. 250mm beton tumbuk 1 : 0.075 726,507.00 54,488.03
ls perapihan 1 36,750.00 36,750.00
JUMLAH 661,964.28

1 unit perbaikan gate valve dia. 200mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

ls bongkar box street (beton) 1 22,000.00 22,000.00


m³ galian tanah keras / berbatu 3.375 83,630.00 282,251.25
ls perbaikan gate valve dia. 200mm 1 210,000.00 210,000.00
m³ urugan tanah kembali 2.250 25,100.00 56,475.00
m³ pasang box street dia. 200mm beton tumbuk 1 : 0.075 726,507.00 54,488.03
ls perapihan 1 21,000.00 21,000.00
JUMLAH 646,214.28

1 unit Perbaikan gate valve dia. 160 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.900 125,500.00 112,950.00


m³ Urugan pasir 0.200 233,060.00 46,612.00
m³ Urugan tanah kembali 0.650 25,100.00 16,315.00
m³ Buang tanah sisa galian 0.050 27,500.00 1,375.00
ls Perbaikan gate valve dia. 160 mm 1 152,250.00 152,250.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 160 mm 1 81,209.60 81,209.60
ls Perapihan 1 21,000.00 21,000.00
JUMLAH 453,711.60

1 unit Perbaikan gate valve dia. 110 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.720 125,500.00 90,360.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.520 25,100.00 13,052.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan gate valve dia. 110 mm 1 120,750.00 120,750.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 110 mm 1 68,631.90 68,631.90
ls Perapihan 1 20,000.00 20,000.00
JUMLAH 373,183.50

V - 227
1 unit Perbaikan gate valve dia. 90 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.640 125,500.00 80,320.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.440 25,100.00 11,044.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan gate valve dia. 90 mm 1 95,000.00 95,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 90 mm 1 64,617.90 64,617.90
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 326,371.50

1 unit Perbaikan gate valve dia. 63 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 63 mm 1 95,000.00 95,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 63 mm 1 47,647.70 47,647.70
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 258,890.90

1 unit Perbaikan gate valve dia. 50 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 50 mm 1 75,000.00 75,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 50 mm 1 47,147.70 47,147.70
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 238,390.90

1 unit Perbaikan gate valve dia. 25 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.240 125,500.00 30,120.00


m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 25 mm 1 75,000.00 75,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 25 mm 1 28,899.10 28,899.10
ls Perapihan 1 10,000.00 10,000.00
JUMLAH 172,115.10

V - 228
1 unit Perbaikan gate valve dia. 160 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.900 125,500.00 112,950.00


m³ Urugan pasir 0.200 233,060.00 46,612.00
m³ Urugan tanah kembali 0.650 25,100.00 16,315.00
m³ Buang tanah sisa galian 0.050 27,500.00 1,375.00
ls Perbaikan gate valve dia. 160 mm 1 145,000.00 145,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 160 mm 1 81,209.60 81,209.60
ls Perapihan 1 20,000.00 20,000.00
JUMLAH 445,461.60

1 unit Perbaikan gate valve dia. 110 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.720 125,500.00 90,360.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.520 25,100.00 13,052.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan gate valve dia. 110 mm 1 115,000.00 115,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 110 mm 1 68,631.90 68,631.90
ls Perapihan 1 20,000.00 20,000.00
JUMLAH 367,433.50

1 unit Perbaikan gate valve dia. 90 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.640 125,500.00 80,320.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.440 25,100.00 11,044.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan gate valve dia. 90 mm 1 95,000.00 95,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 90 mm 1 64,617.90 64,617.90
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 326,371.50

1 unit Perbaikan gate valve dia. 63 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 63 mm 1 95,000.00 95,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 63 mm 1 47,647.70 47,647.70
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 258,890.90

V - 229
1 unit Perbaikan gate valve dia. 50 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 50 mm 1 75,000.00 75,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 50 mm 1 47,147.70 47,147.70
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 238,390.90

1 unit Perbaikan gate valve dia. 25 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.240 125,500.00 30,120.00


m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 25 mm 1 75,000.00 75,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 25 mm 1 28,899.10 28,899.10
ls Perapihan 1 10,000.00 10,000.00
JUMLAH 172,115.10

1 unit Perbaikan gate valve dia. 160 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.900 62,750.00 56,475.00


m³ Urugan pasir 0.200 233,060.00 46,612.00
m³ Urugan tanah kembali 0.650 25,100.00 16,315.00
m³ Buang tanah sisa galian 0.050 27,500.00 1,375.00
ls Perbaikan gate valve dia. 160 mm 1 145,000.00 145,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 160 mm 1 81,209.60 81,209.60
ls Perapihan 1 20,000.00 20,000.00
JUMLAH 388,986.60

1 unit Perbaikan gate valve dia. 110 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.720 62,750.00 45,180.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.520 25,100.00 13,052.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan gate valve dia. 110 mm 1 115,000.00 115,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 110 mm 1 68,631.90 68,631.90
ls Perapihan 1 20,000.00 20,000.00
JUMLAH 322,253.50

V - 230
1 unit Perbaikan gate valve dia. 90 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.640 62,750.00 40,160.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.440 25,100.00 11,044.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Perbaikan gate valve dia. 90 mm 1 95,000.00 95,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 90 mm 1 64,617.90 64,617.90
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 286,211.50

1 unit Perbaikan gate valve dia. 63 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.360 62,750.00 22,590.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 63 mm 1 95,000.00 95,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 63 mm 1 47,647.70 47,647.70
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 236,300.90

1 unit Perbaikan gate valve dia. 50 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.360 62,750.00 22,590.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 50 mm 1 75,000.00 75,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 50 mm 1 47,147.70 47,147.70
ls Perapihan 1 15,000.00 15,000.00
JUMLAH 215,800.90

1 unit Perbaikan gate valve dia. 25 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.240 62,750.00 15,060.00


m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Perbaikan gate valve dia. 25 mm 1 75,000.00 75,000.00
ls Bongkar box street 1 22,000.00 22,000.00
unit Pemasangan box street dia. 25 mm 1 28,899.10 28,899.10
ls Perapihan 1 10,000.00 10,000.00
JUMLAH 157,055.10

V - 231
1 unit pemasangan gate valve dia. 200 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ galian tanah keras / berbatu 3.375 83,630.00 282,251.25


ls pemasangan gate valve dia. 200mm 1 183,750.00 183,750.00
m³ urugan tanah kembali 2.250 25,100.00 56,475.00
unit pasang box street dia. 160 mm beton tumbuk 1 1 81,209.60 81,209.60
ls perapihan 1 21,000.00 21,000.00
JUMLAH 624,685.85

1 unit Pemasangan gate valve dia. 250 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.900 125,500.00 112,950.00


m³ Urugan pasir 0.200 233,060.00 46,612.00
m³ Urugan tanah kembali 0.650 25,100.00 16,315.00
m³ Buang tanah sisa galian 0.050 27,500.00 1,375.00
ls Pemasangan gate valve dia. 250 mm 1 238,900.00 238,900.00
unit Pemasangan box street dia. 250 mm 1 195,429.40 195,429.40
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 614,221.40

1 unit Pemasangan gate valve dia. 160 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.900 125,500.00 112,950.00


m³ Urugan pasir 0.200 233,060.00 46,612.00
m³ Urugan tanah kembali 0.650 25,100.00 16,315.00
m³ Buang tanah sisa galian 0.050 27,500.00 1,375.00
ls Pemasangan gate valve dia. 160 mm 1 152,250.00 152,250.00
unit Pemasangan box street dia. 160 mm 1 81,209.60 81,209.60
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 413,351.60

1 unit Pemasangan gate valve dia. 110 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.720 125,500.00 90,360.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.520 25,100.00 13,052.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Pemasangan gate valve dia. 110 mm 1 120,750.00 120,750.00
unit Pemasangan box street dia. 110 mm 1 68,631.90 68,631.90
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 333,823.50

V - 232
1 unit Pemasangan feet kran dia. 90 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.640 125,500.00 80,320.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.440 25,100.00 11,044.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Pemasangan feet kran dia. 90 mm 1 99,750.00 99,750.00
unit Pemasangan box street dia. 90 mm 1 64,617.90 64,617.90
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 296,761.50

1 unit Pemasangan feet kran dia. 63 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Pemasangan feet kran dia. 63 mm 1 95,000.00 95,000.00
unit Pemasangan box street dia. 63 mm 1 47,647.70 47,647.70
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 224,530.90

1 unit Pemasangan feet kran dia. 50 mm melalui galian tanah berbatu / bongkar jalan

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah berbatu / bongkar jalan 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Pemasangan feet kran dia. 50 mm 1 75,000.00 75,000.00
unit Pemasangan box street dia. 50 mm 1 47,147.70 47,147.70
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 204,030.90

1 unit Pemasangan gate valve dia. 250 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.900 125,500.00 112,950.00


m³ Urugan pasir 0.200 233,060.00 46,612.00
m³ Urugan tanah kembali 0.650 25,100.00 16,315.00
m³ Buang tanah sisa galian 0 27,500.00 1,375.00
ls Pemasangan gate valve dia. 250 mm 1 238,900.00 238,900.00
unit Pemasangan box street dia. 110 mm 1 57,300.00 57,300.00
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 476,092.00

V - 233
1 unit Pemasangan gate valve dia. 160 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.900 125,500.00 112,950.00


m³ Urugan pasir 0.200 233,060.00 46,612.00
m³ Urugan tanah kembali 0.650 25,100.00 16,315.00
m³ Buang tanah sisa galian 0.050 27,500.00 1,375.00
ls Pemasangan gate valve dia. 160 mm 1 152,250.00 152,250.00
unit Pemasangan box street dia. 160 mm 1 81,209.60 81,209.60
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 413,351.60

1 unit Pemasangan gate valve dia. 110 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.720 125,500.00 90,360.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.520 25,100.00 13,052.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Pemasangan gate valve dia. 110 mm 1 120,750.00 120,750.00
unit Pemasangan box street dia. 110 mm 1 68,631.90 68,631.90
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 333,823.50

1 unit Pemasangan feet kran dia. 90 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.640 125,500.00 80,320.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.440 25,100.00 11,044.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Pemasangan feet kran dia. 90 mm 1 99,750.00 99,750.00
unit Pemasangan box street dia. 90 mm 1 64,617.90 64,617.90
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 296,761.50

1 unit Pemasangan feet kran dia. 63 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Pemasangan feet kran dia. 63 mm 1 95,000.00 95,000.00
unit Pemasangan box street dia. 63 mm 1 47,647.70 47,647.70
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 224,530.90

V - 234
1 unit Pemasangan feet kran dia. 50 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.360 125,500.00 45,180.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Pemasangan feet kran dia. 50 mm 1 75,000.00 75,000.00
unit Pemasangan box street dia. 50 mm 1 47,147.70 47,147.70
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 204,030.90

1 unit Pemasangan feet kran dia. 25 mm melalui galian tanah keras / berbatu

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.240 125,500.00 30,120.00


m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Pemasangan feet kran dia. 25 mm 1 75,000.00 75,000.00
unit Pemasangan box street dia. 25 mm 1 28,899.10 28,899.10
ls Perapihan 1 2,640.00 2,640.00
JUMLAH 142,755.10

1 unit Pemasangan gate valve dia. 160 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.900 62,750.00 56,475.00


m³ Urugan pasir 0.200 233,060.00 46,612.00
m³ Urugan tanah kembali 0.650 25,100.00 16,315.00
m³ Buang tanah sisa galian 0.050 27,500.00 1,375.00
ls Pemasangan gate valve dia. 160 mm 1 152,250.00 152,250.00
unit Pemasangan box street dia. 160 mm 1 81,209.60 81,209.60
ls Perapihan 1 2,500.00 2,500.00
JUMLAH 356,736.60

1 unit Pemasangan gate valve dia. 110 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.720 62,750.00 45,180.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.520 25,100.00 13,052.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Pemasangan gate valve dia. 110 mm 1 120,750.00 120,750.00
unit Pemasangan box street dia. 110 mm 1 68,631.90 68,631.90
ls Perapihan 1 2,500.00 2,500.00
JUMLAH 288,503.50

V - 235
1 unit Pemasangan feet kran dia. 90 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.640 62,750.00 40,160.00


m³ Urugan pasir 0.160 233,060.00 37,289.60
m³ Urugan tanah kembali 0.440 25,100.00 11,044.00
m³ Buang tanah sisa galian 0.040 27,500.00 1,100.00
ls Pemasangan feet kran dia. 90 mm 1 99,750.00 99,750.00
unit Pemasangan box street dia. 90 mm 1 64,617.90 64,617.90
ls Perapihan 1 2,500.00 2,500.00
JUMLAH 256,461.50

1 unit Pemasangan feet kran dia. 63 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.360 62,750.00 22,590.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Pemasangan feet kran dia. 63 mm 1 95,000.00 95,000.00
unit Pemasangan box street dia. 63 mm 1 47,647.70 47,647.70
ls Perapihan 1 2,500.00 2,500.00
JUMLAH 201,800.90

1 unit Pemasangan feet kran dia. 50 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.360 62,750.00 22,590.00


m³ Urugan pasir 0.120 233,060.00 27,967.20
m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Pemasangan feet kran dia. 50 mm 1 75,000.00 75,000.00
unit Pemasangan box street dia. 50 mm 1 47,147.70 47,147.70
ls Perapihan 1 2,500.00 2,500.00
JUMLAH 181,300.90

1 unit Pemasangan feet kran dia. 25 mm melalui galian tanah biasa

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah biasa 0.240 62,750.00 15,060.00


m³ Urugan tanah kembali 0.210 25,100.00 5,271.00
m³ Buang tanah sisa galian 0.030 27,500.00 825.00
ls Pemasangan feet kran dia. 25 mm 1 75,000.00 75,000.00
unit Pemasangan box street dia. 25 mm 1 28,899.10 28,899.10
ls Perapihan 1 2,500.00 2,500.00
JUMLAH 127,555.10

V - 236
1 unit Pemasangan Box Street dia. 8"

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

bh Pemasangan Box Street dia. 8" 1.000 5,500.00 5,500.00


m' Pemasangan pipa dia. 8" 1.000 169,587.20 169,587.20
m³ Beton tumbuk 1:3:5 0.028 726,507.00 20,342.20
JUMLAH 195,429.40

1 unit Pemasangan Box Street dia. 6"

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

bh Pemasangan Box Street dia. 6" 1.000 5,500.00 5,500.00


m' Pemasangan pipa dia. 6" 1.000 65,538.50 65,538.50
m³ Beton tumbuk 1:3:5 0.014 726,507.00 10,171.10
JUMLAH 81,209.60

1 unit Pemasangan Box Street dia. 4"

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

bh Pemasangan Box Street dia. 4" 1.000 5,500.00 5,500.00


m' Pemasangan pipa dia. 4" 1.000 52,960.80 52,960.80
m³ Beton tumbuk 1:3:5 0.014 726,507.00 10,171.10
JUMLAH 68,631.90

1 unit Pemasangan Box Street dia. 3"

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

bh Pemasangan Box Street dia. 3" 1.000 5,500.00 5,500.00


m' Pemasangan pipa dia. 3" 1.000 48,946.80 48,946.80
m³ Beton tumbuk 1:3:5 0.014 726,507.00 10,171.10
JUMLAH 64,617.90

1 unit Pemasangan Box Street dia. 2"

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

bh Pemasangan Box Street dia. 2" 1.000 5,500.00 5,500.00


m' Pemasangan pipa dia. 2" 1.000 31,976.60 31,976.60
m³ Beton tumbuk 1:3:5 0.014 726,507.00 10,171.10
JUMLAH 47,647.70

1 unit Pemasangan Box Street dia. 1 1/2"

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

bh Pemasangan Box Street dia. 1 1/2" 1.000 5,500.00 5,500.00


m' Pemasangan pipa dia. 1 1/2" 1.000 31,476.60 31,476.60
m³ Beton tumbuk 1:3:5 0.014 726,507.00 10,171.10
JUMLAH 47,147.70

V - 237
1 unit Pemasangan Box Street dia. 1"

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

bh Pemasangan Box Street dia. 1" 1.000 5,500.00 5,500.00


m' Pemasangan pipa dia. 1" 1.000 13,228.00 13,228.00
m³ Beton tumbuk 1:3:5 0.014 726,507.00 10,171.10
JUMLAH 28,899.10

1 unit Peninggian Box Street

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ beton tumbuk 1 : 3 : 5 0.024 726,507.00 17,436.17


tukang 1.000 100,000.00 100,000.00
JUMLAH 117,436.17

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 ls Bongkar Box Street 22,000.00
1 ls Pemasangan / Perbaikan Accessories
Accessories dia. 3/4" 75,000.00
Accessories dia. 1" 75,000.00
Accessories dia. 1 1/2" 75,000.00
Accessories dia. 2" 95,000.00
Accessories dia. 3" 99,750.00
Accessories dia. 4" 120,750.00
Accessories dia. 6" 152,250.00
Accessories dia. 8" 183,750.00
Accessories dia. 10" 238,900.00
Accessories dia. 12" 310,500.00
Accessories dia. 14" 403,600.00
1 m³ Perbaikan Aspal Hotmix 1,260,000.00

1 unit Pemasangan wash out dia. 160 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 1.800 83,630.00 150,534.00


m³ Urugan pasir 0.400 233,060.00 93,224.00
m³ Urugan tanah kembali 1.300 25,100.00 32,630.00
m³ Buang tanah sisa galian 0.100 27,500.00 2,750.00
m' Pemasangan pipa PVC dia. 160 mm 4 3,500.00 14,000.00
ls Pemasangan gate valve dia. 160 mm 1 152,250.00 152,250.00
unit Pemasangan box street dia. 160 mm 1 81,209.60 81,209.60
ls Perapihan 1 5,040.00 5,040.00
JUMLAH 531,637.60

V - 238
1 unit Pemasangan wash out dia. 110 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 1.440 83,630.00 120,427.20


m³ Urugan pasir 0.320 233,060.00 74,579.20
m³ Urugan tanah kembali 1.040 25,100.00 26,104.00
m³ Buang tanah sisa galian 0.080 27,500.00 2,200.00
m' Pemasangan pipa PVC dia. 110 mm 4 3,000.00 12,000.00
ls Pemasangan gate valve dia. 110 mm 1 120,750.00 120,750.00
unit Pemasangan box street dia. 110 mm 1 68,631.90 68,631.90
ls Perapihan 1 5,040.00 5,040.00
JUMLAH 429,732.30

1 unit Pemasangan wash out dia. 90 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 1.280 83,630.00 107,046.40


m³ Urugan pasir 0.320 233,060.00 74,579.20
m³ Urugan tanah kembali 0.880 25,100.00 22,088.00
m³ Buang tanah sisa galian 0.080 27,500.00 2,200.00
m' Pemasangan pipa PVC dia. 90 mm 4 2,500.00 10,000.00
ls Pemasangan gate valve dia. 90 mm 1 99,750.00 99,750.00
unit Pemasangan box street dia. 90 mm 1 64,617.90 64,617.90
ls Perapihan 1 5,040.00 5,040.00
JUMLAH 385,321.50

1 unit Pemasangan wash out dia. 63 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.720 83,630.00 60,213.60


m³ Urugan pasir 0.240 233,060.00 55,934.40
m³ Urugan tanah kembali 0.420 25,100.00 10,542.00
m³ Buang tanah sisa galian 0.060 27,500.00 1,650.00
m' Pemasangan pipa PVC dia. 63 mm 4 2,000.00 8,000.00
ls Pemasangan gate valve dia. 63 mm 1 95,000.00 95,000.00
unit Pemasangan box street dia. 63 mm 1 47,647.70 47,647.70
ls Perapihan 1 5,040.00 5,040.00
JUMLAH 284,027.70

1 unit Pemasangan wash out dia. 50 mm

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.720 83,630.00 60,213.60


m³ Urugan pasir 0.240 233,060.00 55,934.40
m³ Urugan tanah kembali 0.420 25,100.00 10,542.00
m³ Buang tanah sisa galian 0.060 27,500.00 1,650.00
m' Pemasangan pipa PVC dia. 50 mm 4 1,500.00 6,000.00
ls Pemasangan gate valve dia. 50mm 1 75,000.00 75,000.00
unit Pemasangan box street dia. 50 mm 1 47,147.70 47,147.70
ls Perapihan 1 5,040.00 5,040.00
JUMLAH 261,527.70

V - 239
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 unit Crossing Jalan Sistim Boring
m' pekerjaan boring tanah pipa dia. 2" 1 165,700.00
m' pekerjaan boring tanah pipa dia. 3" 1 185,100.00
m' pekerjaan boring tanah pipa dia. 4" 1 283,800.00
m' pekerjaan boring tanah pipa dia. 6" 1 335,200.00
m' pekerjaan boring tanah pipa dia. 8" 1 418,600.00
m' pekerjaan boring tanah pipa dia. 10" 1 598,300.00
m' pekerjaan boring tanah pipa dia. 12" 1 598,300.00
m' pekerjaan boring tanah pipa dia. 14" 1 672,500.00
m' pekerjaan boring tanah pipa dia. 16" 1 700,000.00

Pemasangan Pipa Sistim Boring


18 m' Pemasangan Pipa PVC dia. 2" Sistim Boring Horizontal

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 1.080 83,630.00 90,320.40


m³ Urugan tanah kembali 0.630 25,100.00 15,813.00
m³ Buang tanah sisa galian 0.090 27,500.00 2,475.00
m' Pengeboran tanah dia. 3" 18 185,100.00 3,331,800.00
ls Pemasangan pipa dia. 2" 18 35,735.00 643,230.00
ls Pemadatan dan Perapihan kembali 1 7,600.00 7,600.00
JUMLAH 4,091,238.40
Per m' Pemasangan Pipa PVC dia. 2" Sistem Boring = 1/18 x Rp. 227,291.02

18 m' Pemasangan Pipa PVC dia. 3" Sistim Boring Horizontal

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 1.920 83,630.00 160,569.60


m³ Urugan tanah kembali 1.320 25,100.00 33,132.00
m³ Buang tanah sisa galian 0.120 27,500.00 3,300.00
m' Pengeboran tanah dia. 4" 18 283,800.00 5,108,400.00
ls Pemasangan pipa dia. 3" 18 55,628.40 1,001,311.20
ls Pemadatan dan Perapihan kembali 1 7,600.00 7,600.00
JUMLAH 6,314,312.80
Per m' Pemasangan Pipa PVC dia. 3" Sistem Boring = 1/18 x Rp. 350,795.16

18 m' Pemasangan Pipa PVC dia. 4" Sistim Boring Horizontal

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 2.160 83,630.00 180,640.80


m³ Urugan tanah kembali 1.560 25,100.00 39,156.00
m³ Buang tanah sisa galian 0.120 27,500.00 3,300.00
m' Pengeboran tanah dia. 6" 18 335,200.00 6,033,600.00
ls Pemasangan pipa dia. 4" 18 60,477.60 1,088,596.80
ls Pemadatan dan Perapihan kembali 1 7,600.00 7,600.00
JUMLAH 7,352,893.60
Per m' Pemasangan Pipa PVC dia. 4" Sistem Boring = 1/18 x Rp. 408,494.09

V - 240
18 m' Pemasangan Pipa PVC dia. 6" Sistim Boring Horizontal

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 2.700 83,630.00 225,801.00


m³ Urugan tanah kembali 1.950 25,100.00 48,945.00
m³ Buang tanah sisa galian 0.150 27,500.00 4,125.00
m' Pengeboran tanah dia. 8" 18 418,600.00 7,534,800.00
ls Pemasangan pipa dia. 6" 18 74,934.50 1,348,821.00
ls Pemadatan dan Perapihan kembali 1 7,600.00 7,600.00
JUMLAH 9,170,092.00
Per m' Pemasangan Pipa PVC dia. 6" Sistem Boring = 1/18 x Rp. 509,449.56

18 m' Pemasangan Pipa PVC dia. 8" Sistim Boring Horizontal

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 3.600 83,630.00 301,068.00


m³ Urugan tanah kembali 2.700 25,100.00 67,770.00
m³ Buang tanah sisa galian 0.180 27,500.00 4,950.00
m' Pengeboran tanah dia. 10" 18 598,300.00 10,769,400.00
ls Pemasangan pipa dia. 8" 18 95,915.20 1,726,473.60
ls Pemadatan dan Perapihan kembali 1 7,600.00 7,600.00
JUMLAH 12,877,261.60
Per m' Pemasangan Pipa PVC dia. 8" Sistem Boring = 1/18 x Rp. 715,403.42

18 m' Pemasangan Pipa PVC dia. 10" Sistim Boring Horizontal

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 4.290 83,630.00 358,772.70


m³ Urugan tanah kembali 2.925 25,100.00 73,417.50
m³ Buang tanah sisa galian 0.195 27,500.00 5,362.50
m' Pengeboran tanah dia. 12" 18 598,300.00 10,769,400.00
ls Pemasangan pipa dia. 10" 18 124,522.15 2,241,398.70
ls Pemadatan dan Perapihan kembali 1 7,600.00 7,600.00
JUMLAH 13,455,951.40
Per m' Pemasangan Pipa PVC dia. 10" Sistem Boring = 1/18 x Rp. 747,552.86

18 m' Pemasangan Pipa PVC dia. 12" Sistim Boring Horizontal

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 4.950 83,630.00 413,968.50


m³ Urugan tanah kembali 3.375 25,100.00 84,712.50
m³ Buang tanah sisa galian 0.225 27,500.00 6,187.50
m' Pengeboran tanah dia. 14" 18 672,500.00 12,105,000.00
ls Pemasangan pipa dia. 12" 18 143,233.25 2,578,198.50
ls Pemadatan dan Perapihan kembali 1 7,600.00 7,600.00
JUMLAH 15,195,667.00
Per m' Pemasangan Pipa PVC dia. 12" Sistem Boring = 1/18 x Rp. 844,203.72

V - 241
18 m' Pemasangan Pipa PVC dia. 14" Sistim Boring Horizontal

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 5.280 83,630.00 441,566.40


m³ Urugan tanah kembali 3.600 25,100.00 90,360.00
m³ Buang tanah sisa galian 0.240 27,500.00 6,600.00
m' Pengeboran tanah dia. 16" 18 700,000.00 12,600,000.00
ls Pemasangan pipa dia. 14" 18 152,838.80 2,751,098.40
ls Pemadatan dan Perapihan kembali 1 7,600.00 7,600.00
JUMLAH 15,897,224.80
Per m' Pemasangan Pipa PVC dia. 14" Sistem Boring = 1/18 x Rp. 883,179.16

1 m' Pemasangan pipa GI dia. 200 mm melalui galian type FR/CR

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.495 83,630.00 41,396.85


m³ Urugan pasir 0.155 233,060.00 36,124.30
m³ Urugan tanah kembali 0.315 25,100.00 7,906.50
m³ Buang tanah sisa galian 0.180 27,500.00 4,950.00
m' Pemasangan pipa GI dia. 200 mm & Acc. 1 20,000.00 20,000.00
ls Perapihan 1 2,200.00 2,200.00
JUMLAH 112,577.65

1 m' Pemasangan pipa GI dia. 200 mm melalui galian type FR/CR

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m³ Galian tanah keras / berbatu 0.495 83,630.00 41,396.85


m³ Urugan pasir 0.155 233,060.00 36,124.30
m³ Urugan tanah kembali 0.315 25,100.00 7,906.50
m³ Buang tanah sisa galian 0.180 27,500.00 4,950.00
m' Pemasangan pipa GI dia. 200 mm & Acc. 1 18,200.00 18,200.00
ls Perapihan 1 2,200.00 2,200.00
JUMLAH 110,777.65

V - 242
1 unit Tiang Penyangga

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)

m' Pipa GI dia. 90 mm 2 129,350.00 258,700.00


m' Pengelasan 0.560 432,400.00 242,144.00
bh mur baud uk. 5/8" 2 1,600.00 3,200.00
bh cleam pipa 1 7,000.00 7,000.00
ls pemasangan 1 195,400.00 195,400.00
JUMLAH 706,444.00

Sumber, 2018

Kepala Dinas Perumahan, Kawasan Permukiman Dan


Pertanahan Kabupaten Cirebon

H. SUKMA NUGRAHA, SH.,MM.


NIP. 19610301 198603 1 012

V - 243
DAFTAR HARGA SATUAN BAHAN, UPAH DAN ALAT
DINAS PERUMAHAN KAWASAN PERMUKIMAN DAN PERTANAHAN
KABUPATEN CIREBON
TAHUN ANGGARAN 2018

HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
A. BAHAN :

I. BATU
1 Abu Batu m3 251,667.00
2 Atras ( tanah urug ) m3 125,000.00
3 Batu apung kg 4,300.00
4 Batu belah 10/15 cm m3 225,000.00
5 Batu belah 15/20 cm (Krakal) m3 225,000.00
6 Batu pecah mesin 0.5-1 cm m3 300,000.00
7 Batu pecah mesin 1-2 cm m3 300,000.00
8 Batu pecah mesin 2-3 cm m3 250,000.00
9 Batu pecah mesin 3-5 cm m3 250,000.00
10 Batu tempel Palimanan 10 X 20 bh 2,800.00
11 Batu tempel kapur tekstur tidak rata m2 80,000.00
12 Chipping m3 245,300.00
13 Filler kg 400.00
14 Kapur bakar (padam) m3 70,000.00
15 Kapur Sirih kg 2,000.00
16 Kerikil Ø 1-3 cm m3 200,000.00
17 Gravel Pack (pelabuhan ratu/sukabumi) m3 1,000,000.00

II. PASIR
1 Pasir beton m3 231,000.00
2 Pasir aspal m3 231,000.00
3 Pasir pasang m3 207,900.00
4 Pasir urug m3 173,300.00
5 Sirtu m3 173,300.00
6 Sirtu tersaring m3 184,800.00
7 Tanah urug pilhan m3 125,000.00
8 Tanah urug biasa m3 100,000.00
9 Tanah merah m3 112,500.00

III. BESI / PIPA / KAWAT


1 Besi WF/Besi Profil kg 13,750.00
2 Besi strip kg 13,750.00
3 Besi beton kg 13,000.00
4 Besi Wire Mesh M8 Lembar 567,000.00
5 Besi stainless dia. 0,5" m' 38,000.00
6 Besi stainless dia. 1" m' 60,000.00
7 Besi stainless dia. 1,5" m' 75,000.00
8 Besi stainless dia. 2" m' 80,000.00
9 Besi stainless dia. 2,5" m' 125,000.00
10 Besi stainless dia. 3" m' 152,000.00
11 Besi galvanis dia. 0.5" m' 25,000.00
12 Besi galvanis dia. 1" m' 27,000.00
13 Besi galvanis dia. 1.5" m' 45,000.00
14 Besi galvanis dia. 2" m' 57,000.00
15 Besi galvanis dia. 2.5" m' 80,500.00
16 Besi galvanis dia. 3" m' 84,000.00
17 Besi biasa dia. 2" btg 250,000.00
18 Besi biasa dia. 3" btg 310,000.00
19 Dop besi Ø 3 " bh 60,000.00
20 Kawat beton / Kawat tali kg 20,000.00

VI - 244
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
21 Kawat bronjong pabrikan dia. 3 mm (uk 2x1x0.5) unit 460,800.00
22 Kawat bronjong dia. 4 mm kg 20,000.00
23 Kawat galvanis dia. 4 mm kg 20,000.00
24 Kawat galvanis dia. 6 mm kg 24,000.00
25 Kawat duri m' 14,700.00
26 Pipa besi galvanis 2" btg/6m' 370,000.00
27 Pipa besi galvanis 3" btg/6m' 504,000.00
28 Pipa PVC Ø 2" S-12,5 ( 8 - 10 bar ) m' 30,950.00
29 Pipa PVC Ø 3" S-12,5 ( 8 - 10 bar ) m' 64,600.00
30 Pipa PVC / paralon 2 inch btg 185,700.00
31 Pipa PVC / paralon 3 inch btg 387,600.00
32 Pipa Reducer PVC Ø 3"-4" SNI bh 83,750.00
33 Pipa Knee/bend PVC Ø 1/2" SNI bh 2,100.00
34 Pipa Knee/bend PVC Ø 3/4" SNI bh 2,550.00
35 Pipa Knee/bend PVC Ø 1" SNI bh 3,800.00
36 Pipa Knee/bend PVC Ø 1 1/2" SNI bh 8,200.00
37 Pipa Knee/bend PVC Ø 2" SNI bh 21,400.00
38 Pipa Knee/bend PVC Ø 3" SNI bh 48,850.00
39 Pipa Knee/bend PVC Ø 4" SNI bh 128,100.00
40 Pipa Knee/bend PVC Ø 6" SNI bh 523,700.00
41 Plat baja tebal 5 mm - 20 mm kg 13,000.00
42 Ram kawat harmonika m2 25,000.00
43 Socket besi O 3 " bh 45,000.00
44 Toren Penguin 250 lt bh 525,000.00
45 Toren 500 lt bh 860,000.00
46 Toren 1000 lt bh 1,500,000.00
47 Toren 2000 lt bh 3,500,000.00
48 Sling Ø 32 mm m 305,000.00
49 Sling Ø 16 mm m 225,000.00
50 Klem sling Ø 32 mm set 450,000.00
51 Warfel / jarum keras Ø 32 mm bh 200,000.00
52 Causen sling Ø 32 mm bh 195,000.00
53 Klem kokat sling Ø 32 mm bh 250,000.00
54 Segel sling Ø 32 mm bh 250,000.00
55 Warfel sling Ø 16 mm bh 165,000.00
56 Segel sling Ø 16 mm bh 140,000.00
57 Klem kokat sling Ø 16 mm bh 90,000.00
58 Causen sling Ø 16 mm bh 145,000.00
59 Jarum keras Ø 16 mm bh 165,000.00

IV. PABRIKAN / TOKO


1 Alumunium foil m2 9,000.00
2 Alumunium pelapis pintu KM Tebal 0.2 lbr 35,000.00
3 Alumunium pelapis pintu KM Tebal 0.3 lbr 50,000.00
4 Alumunium pelapis pintu KM Tebal 0.4 lbr 70,000.00
5 Asbes gelombang 1500 x 1050 x 4 mm lbr 42,500.00
6 Asbes gelombang 1800 x 920 x 4 mm lbr 32,000.00
7 Asbes gelombang 2100 x 1050 x 4 mm lbr 57,000.00
8 Asbes gelombang 2400 x 1050 x 4 mm lbr 65,000.00
9 Asbes gelombang 2700 x 1050 x 4 mm lbr 75,000.00
10 Asbes gelombang 3000 x 1050 x 4 mm lbr 85,000.00
11 Ampelas lbr 3,000.00
12 Bak mandi keramik volume 0,3 m3 bh 185,000.00
13 Bak mandi fiber 120 L bh 220,000.00
14 Batu apung kg 4,300.00
15 Baut 3/4 " bh 6,700.00
16 Baut 5/8 " bh 6,700.00
17 Baut 1/2 " bh 6,000.00
18 Baut 1/2 " panjang 30 cm bh 8,550.00
19 Baut lawa-lawa 12 cm bh 14,000.00
20 Beading penurunan ( PC ) gypsum m' 10,000.00
21 Beading horison gypsum m' 10,000.00
22 Cat Menie kg 25,000.00
23 Cat genteng Matex kg 50,000.00
24 Cat genteng maxilite kg 55,000.00

VI - 245
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
25 Cat penutup kayu Bee brand kg 50,000.00
26 Cat penutup kayu Vim kg 25,000.00
27 Cat penutup kayu Ftalit kg 46,000.00
28 Cat penutup kayu Avian kg 50,000.00
29 Cat penutup tembok Vinilex kg 27,500.00
30 Cat penutup tembok Metrolit kg 26,600.00
31 Cat penutup tembok catylac kg 20,000.00
32 Cat penutup tembok Q Luc kg 11,600.00
33 Cat penutup tembok Property kg 11,000.00
34 Cat penutup besi kg 55,000.00
35 Cat Sinkromat kg 90,000.00
36 Closet duduk ( mono block ) porselen merk INA bh 1,237,000.00
37 Closet duduk ( siram ) porselen merk INA bh 545,000.00
38 Closet jongkok porselen merk INA/KIA bh 140,000.00
39 Closet jongkok porselen merk Avena bh 100,000.00
40 Dempul kayu kg 18,500.00
41 Dinding keramik uk. 10 x 20 cm bh 1,200.00
42 Dinding keramik uk. 20 x 20 cm bh 2,300.00
43 Dinding keramik uk. 20 x 25 cm bh 2,500.00
44 Dinding keramik uk. 30 x 30 cm bh 5,200.00
45 Door closer bh 175,000.00
46 Daun Jendela alumunium 3 '' m' 136,850.00
47 Jendela Alumunium + Kaca (uk.120 cm x 60 cm) warna silver unit 800,000.00
48 Jendela Alumunium + Kaca (uk.120 cm x 60 cm) warna Black/Brown unit 800,000.00
49 Jendela Alumunium + Kaca (uk.120 cm x 60 cm) warna White unit 900,000.00
50 Pintu Allumunium + Kaca (uk.210 cm x 90 cm) warna silver unit 1,210,000.00
51 Pintu Allumunium + Kaca (uk.210 cm x 90 cm) warna Black/Brown unit 1,320,000.00
52 Pintu Allumunium + Kaca (uk.210 cm x 90 cm) warna White unit 1,500,000.00
53 Pintu Kamar Mandi (Spandrel) uk. 200 cm x 70 cm warna silver unit 990,000.00
54 Pintu Kamar Mandi (Spandrel) uk. 200 cm x 70 cm warna Black/Brown unit 1,200,000.00
55 Pintu Kamar Mandi (Spandrel) uk. 200 cm x 70 cm warna White unit 1,210,000.00
56 Elastomer 30x30x5 bh 750,000.00
57 Elastomer 50x40x5 bh 3,000,000.00
58 Engsel jendela set 12,000.00
59 Engsel pintu set 19,000.00
60 Engsel meubeler bh 3,800.00
61 Eternit tebal 4 mm uk. 1 m x 1 m lbr 6,900.00
62 Eternit tebal 4 mm uk. 1 m x 0,5 m lbr 3,450.00
63 Flincote ltr 22,000.00
64 Loster Jati bh 25,000.00
65 Glass beat kg 25,000.00
66 Glass Block bh 17,500.00
67 Gas elpiji kg 10,200.00
68 Grendel pintu / jendela bh 6,000.00
69 Gypsum board lbr 52,500.00
70 GRC tebal 4 mm lbr 60,000.00
71 Fiber Gelombang 180 x80 lbr 45,000.00
72 Kaca nako tebal 5 mm berikut teralis bh 11,400.00
73 Kaca polos tebal 3 mm m2 70,000.00
74 Kaca polos tebal 5 mm m2 80,000.00
75 Kaca polos tebal 5 mm ryben m2 90,000.00
76 Kait angin bh 7,500.00
77 Kran air Onda bh 12,000.00
78 Kunci gembok bh 20,000.00
79 Kunci pintu ukuran besar bh 130,000.00
80 Kunci pintu ukuran sedang bh 85,000.00
81 Kunci dan daun pintu dari fiber bh 350,000.00
82 Kusen Alumunium 3" warna natural/silver m' 66,000.00
83 Kusen Alumunium 3" warna coklat dop m' 71,500.00
84 Kusen Alumunium 3" warna coklat kilap m' 82,500.00
85 Kusen Alumunium 4" warna natural m' 82,500.00
86 Kusen Alumunium 4" warna coklat dop m' 88,000.00
87 Kusen Alumunium 4" warna coklat kilap m' 99,000.00
88 Kusen Alumunium 3" YKK m' 100,000.00
89 Kusen Alumunium 4" YKK m' 1,300,000.00

VI - 246
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
90 Langko - langko kuda - kuda bh 18,000.00
91 Lantai granit 60 x 60 cm ex. Granito corak bh 66,500.00
92 Lantai granit 60 x 60 cm ex. Granito polos bh 95,000.00
93 Lantai granit 40 x 40 cm ex. Essenza bh 43,500.00
94 Lantai granit 40 x 40 cm ex. Granito bh 42,000.00
95 Lantai granit 60 x 60 cm ex. Granito bh 53,000.00
96 Lantai keramik uk. 10 x 20 cm bh 1,200.00
97 Lantai keramik uk. 20 x 20 cm bh 2,000.00
98 Lantai keramik uk. 30 x 30 cm bh 2,500.00
99 Lantai keramik uk. 40 x 40 cm ( putih polos ) bh 5,200.00
100 Lantai terakota 20 x 5 cm bh 5,100.00
101 Lem kayu ltr 30,000.00
102 Lemkra/zat addictive kg 17,300.00
103 Lemkra Just Do It kg 5,200.00
104 Lemkra FS Nat kg 17,000.00
105 List kayu B.3 ( lebar sisi 3 cm ) m' 5,000.00
106 List kayu B.4 ( lebar sisi 4 cm ) m' 5,500.00
107 List keliling gypsum lebar 7 cm m' 16,000.00
108 List keliling gypsum lebar 10 cm m' 17,500.00
109 List keliling gypsum lebar 12 cm m' 20,000.00
110 List drop m' 8,900.00
111 Melamin / folywood lbr 102,000.00
112 Mozaik uk. 20 x 20 cm bh 1,900.00
113 Multiplex tebal 12 mm lbr 220,000.00
114 Multiplex tebal 15 mm lbr 280,000.00
115 Paku biasa 1/2" - 1" kg 20,000.00
116 Paku biasa 2" - 5" kg 18,000.00
117 Paku pancing 60 x 230 bh 825.00
118 Paku sekrup 3" - 5 " bh 500.00
119 Paku ulir bh 200.00
120 Plamir kayu / kualitas 1 kg 23,000.00
121 Plamir tembok kg 27,000.00
122 Plester Mutiara kg 8,000.00
123 Pintu kamer mandi fiber polos Daimaru bh 200,000.00
124 Pintu kamer mandi fiber Kaca Daimaru bh 250,000.00
125 Pintu kamer mandi Almunium Kettler bh 700,000.00
126 Polycarbonate m2 115,000.00
127 Plywood lbr 106,500.00
128 Portland Cement ( PC ) tiga roda zak 70,000.00
129 Portland Cement ( PC ) holcim zak 68,000.00
130 Portland Cement ( PC ) gresik zak 68,000.00
131 Rubber joint 25x10x5 bh 250,000.00
132 Joint Sealent kg 42,000.00
133 Expansion Cap m2 7,600.00
134 Polytene 125 mikron kg 27,500.00
135 Curing Compound Ltr 12,500.00
136 Roster / batu kerawang bh 4,000.00
137 Semen portland kg 1,400.00
138 Semen warna kg 6,000.00
139 Seng BJLS 30 L. 90 cm m' 43,900.00
140 Seng gelombang 3' - 6 " BJLS 30 lbr 58,900.00
141 Sirlak kg 19,500.00
142 Spirtus ltr 9,000.00
143 Skim Coat kg 4,400.00
144 Taekwood 4 mm 1200 x 2400 mm lbr 92,400.00
145 Taekwood 4 mm 900 x 2400 mm lbr 75,100.00
146 Ter kayu kg 14,500.00
147 Thermoplastic Glass beat kg 25,000.00
148 Tiner / minyak cat ltr 11,500.00
149 Triplek 3 mm lbr 52,000.00
150 Triplek 4 mm lbr 60,000.00
151 Triplek 6 mm lbr 83,000.00
152 Triplek 9 mm lbr 102,500.00
153 Triplek 12 mm lbr 200,000.00
154 Tempat cuci piring Beleza bh 400,000.00

VI - 247
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
155 Tempat cuci piring Benoti bh 175,000.00
156 Tempat cuci piring Royal bh 160,000.00
157 TG 302 kg 43,600.00
158 Washtafel bh 686,000.00
159 Woodplank corak 4 m lbr 60,000.00
160 Woodplank polos 2 m lbr 32,500.00
161 Ubin abu2 kepala basah 20 x 20 cm bh 2,300.00
162 Ubin abu2 kepala basah 30 x 30 cm bh 2,900.00
163 Ubin wafel ukuran 20 x 20 cm bh 2,300.00
164 Ubin warna 20 x 20 cm bh 2,700.00
165 Ubin warna 30 x 30 cm bh 3,300.00
166 Washtafel bh 686,000.00
167 Woodplank corak 4 m lbr 60,000.00
168 Woodplank polos 2 m lbr 32,500.00
169 Zincalume m2 75,000.00
170 Rangka plafon memakai Hollow dengan penutup GRC m2 88,200.00
tebal 4 mm + pengecatan
171 Tyfo Epoxy S Kg 650,000.00
172 Tyfo SHE51A m2 800,000.00
173 Karung plastik bh 2,500.00

174 Rangka atap baja ringan


a. Atap Baja Ringan memakai Genteng Keramik/Plentong
( jarak reng 22-28 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 165,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 200,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 210,000.00
b. Atap Baja Ringan Genteng Metal/Spandek ( jarak reng 37,5-90 cm)
- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium G.550 m2 155,000.00
- Atap Baja Ringan Perisai Bentang < 9 m Zinc-Alumunium G.550 m2 162,500.00
- Atap Baja Ringan Joglo Bentang < 9 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Pelana Bentang 10-12 m Zinc-Alumunium G.550 m2 160,000.00
- Atap Baja Ringan Perisai Bentang 10-12 m Zinc-Alumunium G.550 m2 175,000.00
- Atap Baja Ringan Joglo Bentang 10-12 m Zinc-Alumunium G.550 m2 185,000.00
- Atap Baja Ringan Pelana Bentang > 12 m Zinc-Alumunium G.550 m2 170,000.00
- Atap Baja Ringan Perisai Bentang > 12 m Zinc-Alumunium G.550 m2 180,000.00
- Atap Baja Ringan Joglo Bentang > 12 m Zinc-Alumunium G.550 m2 190,000.00

175 Pintu Air Sorong


- Pintu Air Sorong Baja B = 0.40-0.60 ( 1 drat stang tanpa roda gigi ) Unit 12,340,000.00
- Pintu Air Sorong Baja B = 0.70-0.80 ( 1 drat stang tanpa roda gigi ) Unit 13,995,000.00
- Pintu Air Sorong Baja B = 0.90-1.00 ( 1 drat stang tanpa roda gigi ) Unit 17,600,000.00
- Pintu Air Sorong Baja B = 0.70-1.00 ( 1 drat stang + roda gigi ) Unit 19,600,000.00
- Pintu Air Sorong Baja B = 1.00-1.10 ( 2 drat stang + roda gigi ) Unit 37,100,000.00
- Pintu Air Sorong Baja B = 1.50-1.80 ( 2 drat stang + roda gigi ) Unit 53,045,000.00
- Pintu Air Sorong Baja B = 2.00-2.50 ( 2 drat stang + roda gigi ) Unit 69,260,000.00
176 Gigi Payung / Jantung Besar bh 1,590,000.00
177 Gigi Payung / Jantung Sedang bh 1,395,000.00
178 Gigi Piring Besar bh 3,725,000.00
179 Gigi Piring Sedang bh 2,420,000.00
180 Blok Laher bh 2,225,000.00
181 Bron mur drat 5 " bh 4,140,000.00
182 Drat stang 2" x 100 bh 3,175,000.00
183 Drat stang 3/4" x 100 bh 1,015,000.00
184 Drat stang 1,5" x 100 bh 1,970,000.00
185 Dudukan as horisontal bh 2,350,000.00
186 As Horisontal bh 2,035,000.00
187 Karet sel 8 x 3 cm bh 695,000.00
188 As Pemutar bh 950,000.00

VI - 248
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
189 Laher/Bearing bh 445,000.00
190 Engkel Kemudi Sedang bh 570,000.00
191 Daun Pintu B.50, H.50 bh 1,270,000.00
192 Pintu Klep B=0,5 m unit 2,475,000.00
193 Pintu Klep B=1,0 m unit 3,850,000.00
194 Pintu Klep B=1,5 m unit 5,500,000.00

V. ASPAL
1 Aspal kemasan kg 12,200.00
2 Aspal curah kg 12,000.00
3 Aspal Emulsi ltr 11,400.00

VI. MINYAK
1 Premium liter 6,550.00
2 Premium (non subsidi) liter 6,550.00
3 Solar liter 5,150.00
4 Solar (non subsidi) liter 6,150.00
5 Minyak tanah liter 10,225.00
6 Olie SAE 20, 40, 60, 80 dan 120 liter 42,000.00
7 Pelumas bekisting liter 10,000.00
8 Stempet kg 25,000.00

VII.CETAKAN
1 Bata merah bh 800.00
2 Bata berongga bh 2,400.00
3 Batako bh 3,200.00
4 Genteng glazuur turbo ex Jatiwangi bh 3,500.00
5 Genteng nok/bubung diglazuur ex Jatiwangi bh 4,000.00
6 Genteng nok/bubung press mesin ex Jatiwangi bh 2,500.00
7 Genteng nok/bubung press tangan ex Jatiwangi bh 2,000.00
8 Genteng nok/bubung morando diglazuur bh 4,500.00
9 Genteng morando bh 3,500.00
10 Genteng nok/bubung morando bh 4,000.00
11 Genteng press diglazuur ex Jatiwangi bh 2,500.00
12 Genteng press mesin ex Jatiwangi bh 2,200.00
13 Genteng press tangan ex Jatiwangi bh 1,600.00
14 Genteng Type Viktoria bh 9,000.00
15 Genteng nok/bubung Type Viktoria bh 12,500.00
16 Genteng nok/bubung ujung Type Viktoria bh 20,000.00
17 Genteng nok/bubung ujung pertigaan Type Viktoria bh 25,000.00
18 Genteng beton bh 5,000.00
19 Genteng metal 70 x 80 cm lbr 48,000.00
20 Gorong-gorong buis beton dia. 150 cm bh/0,5 m' 520,000.00
21 Gorong-gorong buis beton dia. 100 cm bh/0,5 m' 150,000.00
22 Gorong-gorong buis beton dia. 80 cm bh/0,5 m' 130,000.00
23 Gorong-gorong buis beton dia. 60 cm bh/m' 140,000.00
24 Gorong-gorong buis beton dia. 50 cm bh/m' 120,000.00
25 Gorong-gorong buis beton dia. 40 cm bh/m' 100,000.00
26 Gorong-gorong buis beton dia. 30 cm bh/m' 80,000.00
27 Gorong-gorong buis beton dia. 20 cm bh/m' 60,000.00
28 Kansten Cetak bh 82,500.00
29 Gravel dia. 60 cm bh 75,000.00
30 Gravel dia. 40 cm bh 45,000.00
31 Gravel dia. 20 cm bh 35,000.00
32 Nok steel gelombang 1050 x 5 mm m' 29,000.00
33 Nok steel gelombang 920 x 5 mm m' 22,500.00
34 Nok / bubung genteng beton bh 6,000.00
35 Paving Block K.175 Segi Enam Netural tebal 8 cm m2 62,000.00
36 Paving Block K.175 Segi Enam motif tebal 8 cm m2 64,000.00
37 Paving Block K.175 Segi Enam warna tebal 8 cm m2 69,000.00
38 Paving Block K.175 Segi Enam Netural tebal 7 cm m2 55,000.00
39 Paving Block K.175 Segi Enam motif tebal 7 cm m2 58,000.00
40 Paving Block K.175 Segi Enam warna tebal 7 cm m2 64,000.00
41 Paving Block K.175 Segi Enam Netural tebal 6 cm m2 50,000.00
42 Paving Block K.175 Segi Enam motif tebal 6 cm m2 53,000.00

VI - 249
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
43 Paving Block K.175 Segi Enam warna tebal 6 cm m2 57,000.00
44 Paving Block K.125 Segi Enam Netural tebal 6 cm m2 43,000.00
45 Paving Block K.125 Segi Enam warna tebal 6 cm m2 47,000.00
46 Box Culvert Ukuran 400 x 400 x1200 Buah 1,333,943.00
47 Box Culvert Ukuran 500 x 500 x1200 Buah 1,675,619.00
48 Box Culvert Ukuran 600 x 600 x1200 Buah 2,109,008.00
49 Box Culvert Ukuran 800 x 800 x1200 Buah 3,433,210.00
50 Box Culvert Ukuran 1000 x 1000 x1200 Buah 4,698,969.00
51 Box Culvert Ukuran 1200 x1200 x1200 Buah 6,545,363.00
52 Box Culvert Ukuran 1500 x 1500 x1200 Buah 11,167,800.00
53 Box Culvert Ukuran 2000 x 2000 x1200 Buah 16,856,252.00
54 U- Ditch Ukuran 300 x 300 x 1200 Buah 336,300.00
55 U- Ditch Ukuran 300 x 400 x 1200 Buah 379,300.00
56 U- Ditch Ukuran 300 x 500BUT x 1200 Buah 446,400.00
57 U- Ditch Ukuran 400 x 400 x 1200 Buah 450,400.00
58 U- Ditch Ukuran 400 x 500 x 1200 Buah 553,200.00
59 U- Ditch Ukuran 400 x 600 x 1200 Buah 623,700.00
60 U- Ditch Ukuran 500 x 500 x 1200 Buah 701,900.00
61 U- Ditch Ukuran 500 x 600 x 1200 Buah 793,300.00
62 U- Ditch Ukuran 500 x 700 x 1200 Buah 859,400.00
63 U- Ditch Ukuran 600 x 600 x 1200 Buah 836,400.00
64 U- Ditch Ukuran 600 x 700 x 1200 Buah 957,500.00
65 U- Ditch Ukuran 600 x 800 x 1200 Buah 999,100.00
66 U- Ditch Ukuran 800 x 800 x 1200 Buah 1,195,400.00
67 U- Ditch Ukuran 800 x 900 x 1200 Buah 1,311,021.00
68 U- Ditch Ukuran 800 x 1000 x 1200 Buah 1,467,900.00
69 U- Ditch Ukuran 1000 x 1000 x 1200 Buah 2,113,400.00
70 U- Ditch Ukuran 1000 x 1100 x 1200 Buah 2,312,258.00
71 U- Ditch Ukuran 1000 x 1200 x 1200 Buah 2,499,000.00
72 U- Ditch Ukuran 1200 x 1200 x 1200 Buah 3,122,400.00
73 U- Ditch Ukuran 1200 x 1400 x 1200 Buah 3,595,700.00
74 U- Ditch Ukuran 1400 x 1400 x 1200 Buah 3,941,500.00
75 U- Ditch Ukuran 1400 x 1600 x 1200 Buah 4,120,200.00
76 U- Ditch Ukuran 1500 x 1500 x 1200 Buah 4,480,000.00
77 U- Ditch Ukuran 1600 x 1600 x 1200 Buah 5,906,288.00
78 U- Ditch Ukuran 2000 x 2000 x 1200 Buah 10,878,370.00
79 Cover U - Ditch 300, Heavy Duty Ukuran 300 x 300 x 600 Buah 120,000.00
80 Cover U - Ditch 400, Heavy Duty Ukuran 400 x 400 x 600 Buah 150,000.00
81 Cover U - Ditch 500, Heavy Duty Ukuran 500 x 500 x 600 Buah 192,000.00
82 Cover U - Ditch 600, Heavy Duty Ukuran 600 x 600 x 600 Buah 258,000.00
83 Cover U - Ditch 800, Heavy Duty Ukuran 800 x 800 x 600 Buah 354,000.00
84 Cover U - Ditch 1000, Heavy Duty Ukuran 1000 x 1000 x 1200 Buah 1,646,145.00
85 Cover U - Ditch 1200, Heavy Duty Ukuran 1200 x 1200 x 1200 Buah 2,091,298.00
86 Cover U - Ditch 300, Light Duty Ukuran 300 x 300 x 600 Buah 91,460.00
87 Cover U - Ditch 400, Light Duty Ukuran 400 x 400 x 600 Buah 152,939.00
88 Cover U - Ditch 500, Light Duty Ukuran 500 x 500 x 600 Buah 236,682.00
89 Cover U - Ditch 600, Light Duty Ukuran 600 x 600 x 600 Buah 277,541.00
90 Cover U - Ditch 800, Light Duty Ukuran 800 x 800 x 600 Buah 369,001.00
91 Cover U - Ditch 1000, Light Duty Ukuran 1000 x 1000 x 1200 Buah 1,059,058.00
92 Cover U - Ditch 1200, Light Duty Ukuran 1200 x 1200 x 1200 Buah 1,350,135.00
93 Jersey Barrfer Ukuran 800 x 500 x 1000 Buah 1,213,410.00
94 Tiang pancang beton Pratekan m3 4,600,000.00
95 Digital printing m2 25,000.00

VIII. KAYU
1 Bambu Ø6 - Ø8 / 6 m btg 17,000.00
2 Kayu deplank 8/20 - 4 m (Jati Jateng) m3 10,500,000.00
3 Kayu deplank 8/20 - 4 m (Balau) m3 9,500,000.00
4 Kayu deplank 8/20 - 4 m (Borneo) m3 5,000,000.00
5 Kayu dolken O 8 - 10 /4 m btg 62,500.00
6 Kayu dolken O 12 - 15 /4 m btg 87,500.00
7 Kayu dolken O 5 /3 m btg 13,100.00
8 Kayu hutan/kayu perancah acuan (kayu kelas III) m3 3,500,000.00
9 Kayu kamper m3 8,200,000.00
10 Kayu kaso 5/7 meranti m3 6,000,000.00

VI - 250
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
11 Kayu kaso 5/7 meranti btg 80,000.00
12 Kayu kruing m3 7,274,000.00
13 Kayu lanan m3 6,546,000.00
14 Kayu meranti m3 6,000,000.00
15 Kayu jati Jabar m3 8,200,000.00
16 Kayu Balau (kayu kelas I) m3 9,500,000.00
17 Kayu Borneo (kayu kelas II) m3 5,000,000.00
18 Kayu bakar m3 150,000.00
19 Reng kayu borneo ukuran 2/3 cm btg 17,000.00 0.0024
20 Reng 2 x 3 cm m3 7,083,333.33
21 Tali Ijuk kg 12,000.00 192,000.00

IX. LAIN-LAIN
1 Air L 50.00 (10 m3 air
2 Air bersih m3 5,000.00
3 Kayu kelas III (0,03 * 0,02 * 2 * 0,8)* harga bahan per m3 kg 33,600.00
4 Jendela naco (0,04 * harga kaca) bh 3,200.00
5 seng pelat (asumsi L.90 P.1 m) lbr 38,000.00
6 kawat jaring lbr 567,000.00
7 panel beton pracetak lbr 103,000.00
8 kolom beton pracetak batang 175,000.00
9 bahan tambahan kimia (efoksi) Liter 135,000.00
10 Strorox – 100 kg 76,500.00
11 Waterstop lebar 150 mm m' 50,000.00
12 Waterstop lebar 200 mm m' 125,000.00
13 Waterstop lebar 230 mm - 320 mm m' 115,000.00
14 Jaring kawat baja dilas (1 lembar = 61,79 kg)untuk wiremesh M8 kg 9,176.24
15 Penjaga jarak bekisting/spacer (dari besi/baut) bh 18,000.00
16 Besi scuare tube m' 19,025.83
17 Besi lis kaca (1 x 1) cm m' 14,300.00
18 Pengelasan cm 4,418.88
19 Besi hollow (50 x 50 x 3) mm kg 7,500.00
20 Dinabolt Ø 12mm bh 2,545.00
21 Phenol film 12 mm lbr 245,000.00
22 Semen grout kg 2,360.00 setara MU 8
23 Screening kg 200.00 harga /m3 =
24 Besi siku L 30.30.3 kg 12,100.00
25 Besi pelat baja kg 7,500.00
26 Kawat las kg 27,000.00
27 Pintu gulung besi m2 1,100,000.00
28 Pintu lipat m2 3,000,000.00
29 Rolling door alluminium m2 400,000.00
30 Profil alluminium (silver) m' 110,000.00
31 Sealant tube 20,000.00
32 Venetions blinds dan vertical blinds (tirai) m2 106,200.00
33 Profil kaca (allumunium) m' 12,375.00
34 Sunscreen alluminium m2 385,000.00
35 Kawat nyamuk m2 250,000.00
36 Baja strip (0,2 x 2) cm kg 18,150.00
37 Jendela nako (rangka + kaca 5 mm) m2 168,200.00
38 Rangka metal hollow 40.40.2 mm m' 19,025.83
39 Baja ringan canai dingin C75 kg 13,970.00
40 HB (Batako Berlobang)-20 m3 437,500.00
41 HB (Batako Berlobang)-15 m3 500,000.00
42 HB (Batako Berlobang)-10 m3 675,000.00
43 Besi angker diameter 8 kg 13,000.00
44 Bata ringan tebal 7,5cm m3 650,000.00
45 Bata ringan tebal 10cm m3 750,000.00
46 Mortar siap pakai kg 3,750.00
47 Semen Mortar (SM) m3 934.38
48 Batu granit kg 5,000.00
49 Batu traso kg 5,000.00
50 ubin keramik mozaik ukuran 30 cm x 30 cm bh 3,909.09
51 plint keramik ukuran 10 cm x 20 cm bh 12,000.00
52 plint keramik ukuran 10 cm x 10 cm bh 9,000.00

VI - 251
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
53 plint keramik ukuran 5 cm x 20 cm bh 9,000.00
54 plint internal cove artistik 5 cm x 5 cm x 20 cm bh 15,000.00
55 lantai marmer ukuran 100cm x 100cm bh 800,000.00
56 Karpet m2 100,000.00
57 Lem untuk karpet kg 68,500.00
58 underlayer (pelapis bawah karpet) m2 50,000.00
59 parquet kayu m2 150,000.00
60 dinding keramik artistik 10 cm x 20 cm bh 3,333.33
61 dinding keramik artistik 5 cm x 20 cm bh 1,666.67
62 dinding marmer 100 cm x 100 cm bh 800,000.00
63 bata pelapis 3 cm x 7 cm x 24 cm bh 4,083.33
64 batu paras bh 4,185.00
65 batu tempel hitam bh 1,550.00
66 Vynil bh 10,909.09
67 Lem vynil kg 22,000.00
68 Wallpaper m' 70,000.00
69 Floor harderner kg 9,666.67
70 Asbes semen m2 37,000.00
71 Akustik lbr 51,000.00
72 Profil Allum "T" m' 99,000.00
73 Ramset bh 200.00
74 Rooflight 90 x 180 lbr 62,000.00
75 Bubung stel gelombang lbr 62,000.00
76 Nok paten 92 cm lbr 62,000.00
77 Sirap kayu bh 1,625.00
78 Aluminium gel tebal 0,55 lbr 136,000.00
79 Kunci tanam antik (belluci) bh 222,000.00
80 Kunci tanam KM bh 45,000.00
81 Kunci silinder bh 70,000.00
82 Engsel kupu-kupu bh 25,000.00
83 Engsel angin bh 20,000.00
84 Spring knip bh 22,000.00
85 Door closer set 280,000.00
86 Kunci slot bh 12,000.00
87 Door holder bh 23,000.00
88 Door stop bh 40,000.00
89 Rel pintu sorong set 350,000.00
90 Kunci lemari set 142,000.00
91 Kaca tebal 8 mm m2 150,000.00
92 Kaca buram 12 mm m2 360,500.00
93 Kaca cermin 5 mm m2 135,000.00
94 Kaca cermin 8 mm m2 257,700.00
95 Kaca wireglassed 5 mm m2 210,000.00
96 Kaca patri 5mm m2 2,000,000.00
97 Soda api kg 25,000.00
98 Sabun kg 11,000.00
99 Kuas bh 12,000.00
100 Pengencer kg 24,000.00
101 Teak oil ltr 30,250.00
102 Politur ltr 37,950.00
103 Politur jadi ltr 43,065.00
104 Residu atau ter ltr 27,500.00
105 Vernis ltr 34,650.00
106 Kalkarium kg 18,500.00
107 Alang-alang ikat 10,000.00
108 Cat antara kg 35,000.00
109 Wood filler kg 30,000.00
110 Woodstain kg 50,000.00
111 Sanding kg 50,000.00
112 Melamic kg 50,000.00
113 Urinoir unit 649,000.00
114 Baja tulangan kg 18,150.00
115 Kayu bekisting m2 35,000.00
116 Waterdrain bh 385,000.00
117 Floor drain unit 82,500.00

VI - 252
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
118 Pipa galvanis ½” m' 25,833.33
119 Pipa galvanis 3/4” m' 33,333.33
120 Pipa galvanis 1” m' 50,000.00
121 Pipa galvanis 1 1/2” m' 75,833.33
122 Pipa galvanis 4” m' 245,000.00
123 Sealtape bh 4,000.00
124 genteng palentong kecil bh 900.00
125 genteng kodok glazuur bh 1,400.00
126 genteng palentong besar/super bh 1,500.00
127 genteng bubung palentong besar bh 6,000.00
128 Nok genteng beton bh 4,000.00
129 Nok genteng metal bh 44,333.33
130 Pipa PVC 1/2” S.10 m' 6,150.00
131 Pipa PVC 3/4” S.10 m' 9,400.00
132 Pipa PVC 1” S.10 m' 10,600.00
133 Pipa PVC 1 1/2” S.12,5 m' 24,000.00
134 Pipa PVC 2” S.12,5 m' 30,950.00
135 Pipa PVC 3” S.12,5 m' 64,600.00
136 Pipa PVC 4” S.12,5 m' 93,750.00
137 Pipa PVC 6” S.12,5 m' 199,650.00
138 Pipa PVC 8” S.12,5 m' 312,000.00
139 Pipa PVC Ø 63 mm m' 30,600.00
140 Pipa PVC Ø 90 mm m' 64,000.00
141 Pipa PVC Ø 110 mm m' 92,980.00
142 Pipa PVC Ø 200 mm m' 308,700.00
143 Pipa PVC Ø 250 mm m' 483,750.00
144 Pipa HDPE Ø 63 mm m' 25,900.00
145 Pipa HDPE Ø 125 mm m' 101,800.00
146 Pipa HDPE Ø 200 mm m' 259,600.00
147 Pipa HDPE Ø 250 mm m' 404,300.00
148 Pipa GIP Ø 63 mm m' 85,000.00
149 Pipa GIP Ø 100 mm m' 245,000.00
150 Pipa GIP Ø 150 mm m' 355,000.00
151 Pipa GIP Ø 200 mm m' 680,000.00
152 Pipa GIP Ø 250 mm m' 875,000.00
153 Pipa tanah Ǿ 20 cm bh 173,200.00
154 pipa tanah diameter 15 cm bh 113,200.00
155 pipa beton diameter 15 – 20 cm bh 44,275.00
156 pipa beton diameter 30 – 100 cm bh 66,000.00
157 Valve Ø 150 mm bh 3,250,000.00
158 Valve Ø 200 mm bh 5,400,000.00
159 Valve Ø 250 mm bh 9,250,000.00
160 Pipa listrik 5/8” btg 5,000.00
161 Kabel 1,5 x 2 m 6,500.00
162 Kabel 1,5 x 3 m 10,000.00
163 Kabel 2,5 x 2 m 11,000.00
164 Kabel 2,5 x 3 m 13,500.00
165 T Dus bh 2,000.00
166 L Bow bh 2,000.00
167 Las Dop bh 3,000.00
168 Mongkok bh 1,000.00
169 Saklar tunggal bh 12,500.00
170 Saklar ganda bh 15,000.00
171 Fitting tempel bh 4,500.00
172 Fitting gantung bh 3,500.00
173 M C B bh 35,000.00
174 digital print m' 25,000.00
175 Lampu pijar 25 s/d 100 watt (phlips) bh 10,400.00
176 Lampu Sl philip 18 watt bh 30,000.00
177 Lampu Sl philip 25 watt bh 42,000.00
178 Downlight + SL 25 watt philip bh 77,000.00
179 Lampu taman + tiang + lampu 1 buah bh 250,000.00
180 Stop kontak broco standard bh 14,000.00
181 kawat arde m 12,000.00
182 over spaneng m 9,000.00

VI - 253
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
183 arde btg 11,000.00
184 box sikring bh 40,000.00
185 box MCB bh 5,000.00
186 Holo 4/4 meni btg 12,100.00
187 Holo 2/4 meni btg 11,000.00
188 Kawat Bwg 12 kg 10,000.00
189 Paku screw 2.5 cm bh 50.00
190 Adhesive kg 6,000.00
191 Kain kasa m' 400.00
192 Cat penutup 2 kali kg 25,000.00
193 Paku beton bh 175.00
194 Kabel Listrik NYA 3 x 2,5 mm m' 6,500.00
195 Bata berongga expose bh 2,600.00
196 Atap Selulosa uk. 106 x 40 cm bh 137,000.00
197 Paku/screw atap selulosa bh 1,000.00
198 Nok/bubung untuk atap selulosa untuk uk. 106 x 40 cm bh 82,500.00
199 Atap Selulosa uk. 195 x 96 cm bh 45,000.00
200 Nok/Bubung untuk Atap Selulosa 195 x 96 cm bh 84,000.00
201 Tabung Gas kg 15,000.00

X. BAHAN JALAN LINGKUNAN


1 Pasir Beton (Kasar) M01a M3 200,000.00
2 Pasir Halus (untuk HRS) M01c M3 180,000.00
3 Agregat Kasar (5-40 mm) M03 M3 250,892.68
4 Agregat Halus (0-5 mm) M04 M3 250,892.68
5 Agregat Kasar (tertahan pada ayakan 4,75 mm) M3 250,892.68
6 Agregat Halus (lolos saringan 4,75 mm) M3 250,892.68
7 Filler M05 Kg 400.00
8 Bahan Tanah Timbunan M08 M3 125,000.00
9 Bahan Pilihan M09 M3 150,000.00
10 Aspal M10 KG 12,200.00
11 Kerosen / Minyak Tanah M11 LITER 10,225.00
12 Chipping M41 M3 245,000.00
13 Chipping (kg) M41kg Kg 129.99

X. ACCESSORIES PIPA

1 Flange socket dia. 300 mm 2,080,000.00


2 Flange socket dia. 250 mm 1,040,000.00
3 Flange socket dia. 200 mm 720,000.00
4 Flange socket dia. 160 mm 468,000.00
5 Flange socket dia. 110 mm 292,000.00
6 Flange socket dia. 90 mm 200,000.00
7 Flange Socket dia 63 mm 161,500.00
8 Flange Adaptor dia. 300 mm 1,950,000.00
9 Flange Adaptor dia. 250 mm 1,800,000.00
10 Flange Adaptor dia. 200 mm 975,000.00
11 Flange Adaptor dia. 160 mm 780,000.00
12 Flange Adaptor dia. 110 mm 420,000.00
13 Flange Adaptor dia. 90 mm 357,500.00
14 Flange Adaptor dia 63 mm 286,000.00
15 Stube Flange dia. 300 mm 1,565,800.00
16 Stube Flange dia. 250 mm 1,088,600.00
17 Stube Flange dia. 200 mm 744,800.00
18 Stube Flange dia. 150 mm 475,300.00
19 Stube Flange dia. 100 mm 269,600.00
20 Stube Flange dia. 75 mm 218,100.00
21 Stube Flange dia 50 mm 149,300.00
22 Dop OD 160 mm ( PVC ) 12,000.00
23 Dop OD 110 mm ( PVC ) 72,000.00
24 Dop OD 90 mm ( PVC ) 32,400.00
25 Dop OD 63 mm ( PVC ) 20,000.00
26 Blind Flange 250 mm 1,800,000.00

VI - 254
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
27 Blind Flange 200 mm 1,500,000.00

VI - 255
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
28 Blind Flange 150 mm 1,200,000.00
29 Blind Flange 100 mm 580,000.00
30 Loose flange dia 350 mm 784,000.00
31 Loose flange dia 300 mm 450,000.00
32 Loose flange dia 250 mm 300,000.00
33 Loose flange dia 200 mm 247,000.00
34 Loose flange dia 160 mm 180,000.00
35 Loose flange dia 110 mm 106,500.00
36 Loose flange dia 90 mm 96,000.00
37 Loose flange dia 63 mm 67,500.00
38 Gate valve dia. 350 mm 26,640,000.00
39 Gate valve dia. 300 mm 12,700,000.00
40 Gate valve dia. 250 mm 9,500,000.00
41 Gate valve dia. 200 mm 5,700,000.00
42 Gate valve dia. 160 mm 3,900,000.00
43 Gate valve dia. 110 mm 2,500,000.00
44 Gate valve dia. 90 mm 1,800,000.00
45 Gate valve dia. 63 mm 950,000.00
46 Air Valve dia. 25 mm single ball PN 10 780,000.00
47 Air Valve dia. 63 mm Double PN 10 1,950,000.00
48 Air Valve dia. 75 mm Double 2,500,000.00
49 Air Valve dia. 100 mm Double 3,500,000.00
50 Dresser joint for HDPE dia. 300 mm 1,950,000.00
51 Dresser joint for HDPE dia. 250 mm 1,560,000.00
52 Dresser joint for HDPE dia. 200 mm 975,000.00
53 Dresser joint for HDPE dia. 150 mm 780,000.00
54 Dresser joint for HDPE dia. 100 mm 552,500.00
55 Tee all flange dia 300 x 300 mm 4,368,000.00
56 Tee all flange dia 300 x 250 mm 4,032,000.00
57 Tee all flange dia 300 x 200 mm 3,696,000.00
58 Tee all flange dia 300 x 150 mm 3,528,000.00
59 Tee all flange dia 300 x 100 mm 3,444,000.00
60 Tee all flange dia 300 x 75 mm 3,276,000.00
61 Tee all flange dia 300 x 50 mm 3,192,000.00
62 Tee all flange dia 250 x 250 mm 3,780,000.00
63 Tee all flange dia 250 x 200 mm 3,696,000.00
64 Tee all flange dia 250 x 150 mm 3,528,000.00
65 Tee all flange dia 250 x 100 mm 3,276,000.00
66 Tee all flange dia 250 x 75 mm 3,108,000.00
67 Tee all flange dia 250 x 50 mm 3,024,000.00
68 Tee all flange dia 200 x 200 mm 3,108,000.00
69 Tee all flange dia 200 x 150 mm 2,772,000.00
70 Tee all flange dia 200 x 100 mm 2,688,000.00
71 Tee all flange dia 200 x 75 mm 2,520,000.00
72 Tee all flange dia 200 x 50 mm 2,184,000.00
73 Tee all flange dia 150 x 150 mm 1,638,000.00
74 Tee all flange dia 150 x 100 mm 1,470,000.00
75 Tee all flange dia 150 x 75 mm 1,428,000.00
76 Tee all flange dia 150 x 50 mm 1,386,000.00
77 Tee all flange dia 100 x 100 mm 781,000.00
78 Tee all flange dia 100 x 75 mm 756,000.00
79 Tee all flange dia 100 x 50 mm 714,000.00
80 Tee all flange dia 75 x 75 mm 688,800.00
81 Tee all flange dia 75 x 50 mm 655,000.00
82 Tee all flange dia 50 x 50 mm 646,000.00
83 Bend All Flange OD 350 x 90 4,102,500.00
84 Bend All Flange OD 300 x 90 3,091,000.00
85 Bend All Flange OD 250 x 90 2,125,200.00
86 Bend All Flange OD 200 x 90 1,789,200.00
87 Bend All Flange OD 150 x 90 1,209,600.00
88 Bend All Flange OD 100 x 90 747,000.00
89 Bend All Flange OD 75 x 90 462,000.00
90 Bend All Flange OD 50 x 90 319,200.00

VI - 256
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
91 Reducer All Flange dia 350 x 300 mm 1,645,000.00

VI - 257
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
92 Reducer All Flange dia 350 x 250 mm 1,428,000.00
93 Reducer All Flange dia 350 x 200 mm 1,316,000.00
94 Reducer All Flange dia 350 x 150 mm 1,239,000.00
95 Reducer All Flange dia 300 x 250 mm 1,141,000.00
96 Reducer All Flange dia 300 x 200 mm 1,064,000.00
97 Reducer All Flange dia 300 x 150 mm 1,001,000.00
98 Reducer All Flange dia 300 x 100 mm 896,000.00
99 Reducer All Flange dia 250 x 200 mm 966,000.00
100 Reducer All Flange dia 250 x 150 mm 868,000.00
101 Reducer All Flange dia 250 x 100 mm 567,000.00
102 Reducer All Flange dia 250 x 75 mm 637,000.00
103 Reducer All Flange dia 200 x 150 mm 749,000.00
104 Reducer All Flange dia 200 x 100 mm 679,000.00
105 Reducer All Flange dia 200 x 75 mm 595,000.00
106 Reducer All Flange dia 150 x 100 mm 511,000.00
107 Reducer All Flange dia 150 x 75 mm 441,000.00
108 Reducer All Flange dia 150 x 50 mm 343,000.00
109 Reducer All Flange dia 100 x 75 mm 224,000.00
110 Reducer All Flange dia 100 x 50 mm 168,000.00
111 Reducer All Flange dia 75 x 50 mm 133,000.00
112 Water Meter Induk dia 300 mm 44,850,000.00
113 Water Meter Induk dia 250 mm 32,300,000.00
114 Water Meter Induk dia 200 mm 19,800,000.00
115 Water Meter Induk dia 150 mm 15,300,000.00
116 Water Meter Induk dia 100 mm 8,950,000.00
117 Water Meter Induk dia 75 mm 7,350,000.00
118 Water Meter Induk dia 50 mm 6,050,000.00
119 Reducer equal HDPE dia 100 x 75 mm 475,000.00
120 Reducer equal HDPE dia 75 x 50 mm 325,000.00
121 Pressure Reducing Valve 250 mm 98,475,000.00
122 Pressure Reducing Valve 200 mm 78,325,000.00
123 Tee equal coupling dia 100 x 100 mm 515,000.00
124 Tee equal coupling dia 100 x 75 mm 512,000.00
125 Tee equal coupling dia 100 x 50 mm 509,000.00
126 Tee equal coupling dia 75 x 75 mm 450,000.00
127 Tee equal coupling dia 75 x 50 mm 431,400.00
128 Tee equal coupling dia 50 x 50 mm 367,000.00
129 Bend HDPE dia 250 x 90 1,800,400.00
130 Bend HDPE dia 200 x 90 1,131,000.00
131 Bend HDPE dia 150 x 90 927,700.00
132 Bend HDPE dia 100 x 90 456,400.00
133 Bend HDPE dia 75 x 90 371,400.00
134 Bend HDPE dia 50 x 90 222,200.00

B. UPAH
1 Mandor /hari 110,000.00 15,714.29
2 Kepala tukang /hari 105,000.00 15,000.00
3 Tukang kayu / besi /hari 100,000.00 14,285.71
4 Tukang batu /hari 100,000.00 14,285.71
5 Tukang bor /hari 100,000.00 14,285.71
6 Tukang Las /hari 110,000.00 15,714.29
7 Pembantu tukang/Pekerja /hari 80,000.00 11,428.57
8 Pembantu operator /hari 80,000.00 11,428.57
9 Supir truk /hari 85,000.00 12,142.86
10 Pembantu supir /hari 80,000.00 11,428.57
11 Mekanik /hari 90,000.00 12,857.14
12 Pembantu mekanik /hari 80,000.00 11,428.57
13 Buruh lapangan terlatih /hari 100,000.00 14,285.71
14 Buruh lapangan kurang terlatih /hari 80,000.00 11,428.57
15 Buruh lapangan tak terlatih / pekerja /hari 80,000.00 11,428.57

VI - 258
HARGA
SATUAN
NO URAIAN BAHAN/UPAH/ALAT KODE SAT. KET.
Rp
C. ALAT
1 Sewa crane (10 Ton) unit/hari 3,900,000.00
2 Sewa pipe support buah/hari 297,000.00
3 Sewa scaffolding unit/hari 297,000.00
4 Sewa Tripot/Tackel & handle crane 2 T unit/hari 3,500,000.00
5 Sewa excavator type 225 kapasitas 0,5 - 1,0 m3 unit/hari 1,596,000.00
6 Peralatan potong pipa T1/manual (gergaji) /saw unit/hari 50,000.00
7 Peralatan potong pipa T2/manual (gergaji) /saw unit/hari 50,000.00
8 Mobile crane £ 3 ton unit/hari 1,450,000.00
9 Sewa Genset 1500 watt unit/hari 1,234,800.00
10 Sewa Pompa Submersible 3 m3/h unit/hari 330,000.00
11 Sewa crane (3 Ton) Jam 115,000.00
12 Compressor Jam 68,310.00
13 Driling rig + perlengkapan (daerah berbatu/keras) m 700,000.00 87,500.00
14 Driling rig + perlengkapan (daerah Lunak/Lempung) m 525,000.00
15 Mesin Las Jam 200,000.00
Mesin Blower Jam 300,000.00

ALAT JALAN
1 EXCAVATOR 80-140 HP E10 Jam 530,505.76
2 DUMP TRUCK 3.5 TON E08 Jam 272,784.44
3 WHEEL LOADER 1.0-1.6 M3 E15 Jam 353,363.06
4 MOTOR GRADER >100 HP E13 Jam 466,154.35
5 VIBRATORY ROLLER 5-8 T. E19 Jam 344,765.59
6 WATER TANKER 3000-4500 L. E23 Jam 258,774.99
7 TANDEM ROLLER 6-8 T. E17 Jam 443,067.01
8 ASPHALT DISTRIBUTOR E41 Jam 374,495.18
9 COMPRESSOR 4000-6500 L\M E05 Jam 179,166.49
10 TIRE ROLLER 8-10 T. E18 Jam 442,515.74
11 ASPHALT MIXING PLANT E01 Jam 6,233,983.42
12 GENERATOR SET E12 Jam 449,852.17
13 ASPHALT FINISHER E02 Jam 969,852.05
14 DUMP TRUCK 5 TON E09 Jam 458,230.39
15 THREE WHEEL ROLLER 6-8 T E16 Jam 222,018.09
16 ASPHALT SPRAYER E03 Jam 111,731.09

Sumber, 2018

Kepala Dinas Perumahan, Kawasan


Permukiman Dan Pertanahan Kabupaten
Cirebon

H. SUKMA NUGRAHA, SH.,MM.


NIP. 19610301 198603 1 012

VI - 259
HARGA PERKIRAAN SENDIRI (HPS)
RENCANA BIAYA : PEMBANGUNAN / REHABILITASI
TAHUN : 2018
DESA :
KECAMATAN :
KABUPATEN : C I R E B O N
HARGA
JUMLAH
NO JENIS PEKERJAAN ANALISA VOLUME SATUAN
Rp Rp
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 (K3) Pembuatan 1 m2 gudang semen dan peralatan A. 2.2.1.7. m2 -
2 Pengukuran dan pemasangan 1 m’ Bouwplank A. 2.2.1.4. m' -
3 (K3) Pembuatan 1 m2 steger/perancah dari bambu A. 2.2.1.10. m2 -
4 Papan nama proyek SNI.100.03 bh -
-

II PEKERJAAN BONGKARAN
1 Pembongkaran 1 m3 beton bertulang A. 2.2.1.13. m3 -
2 Pembongkaran 1 m3 dinding tembok bata A. 2.2.1.14. m3 -
-

III PEKERJAAN GALIAN/URUGAN


1 Penggalian 1 m3 tanah biasa sedalam 1 m A.2.3.1.1. m3 -
2 Pengurugan kembali 1 m3 galian tanah A.2.3.1.9. m3 -
3 (K3) Pemadatan tanah 1 m3 tanah ( per 20 cm) A.2.3.1.10. m3 -
4 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 -
-

IV PEKERJAAN PONDASI
1 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 -
2 (K3) Pemasangan 1 m3 batu kosong (anstamping) A.3.2.1.9. m3 -
3 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP A.3.2.1.3 m3 -
-

V PEKERJAAN BETON/PEMBESIAN
1 Pembesian 10 kg dengan besi polos atau besi ulir A.4.1.1.17 kg -
2 (K3) Pemasangan 1 m2 bekisting untuk pondasi A.4.1.1.20 m2 -
3 (K3) Pemasangan 1 m2 bekisting untuk sloof A.4.1.1.21 m2 -
4 (K3) Pemasangan 1 m2 bekisting untuk kolom A.4.1.1.22 m2 -
5 (K3) Pemasangan 1 m2 bekisting untuk balok A.4.1.1.23 m2 -
6 (K3) Pemasangan 1 m2 bekisting untuk lantai A.4.1.1.24 m2 -
7 (K3) Pemasangan 1 m2 bekisting untuk dinding A.4.1.1.25 m2 -
8 (K3) Pemasangan 1 m2 bekisting untuk tangga A.4.1.1.26 m2 -
Membuat 1 m3 beton mutu f’c = 7,4 Mpa (sama dengan K
9 A.4.1.1.1 m3
100), setara dengan beton rabat -
Membuat 1 m3 beton mutu f’c = 9,8 Mpa (sama dengan K-
10 A.4.1.1.2 m3
125) -
Membuat 1 m3 beton mutu f’c = 12,2 Mpa (sama denga K
11 A.4.1.1.3 m3
150) -
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump
12 A.4.1.1.4 m3
(3-6) cm, w/c = 0,87 -
Membuat 1 m3 beton mutu f’c = 14,5 MPa, slump (120 ± 20)
13 A.4.1.1.5. m3
mm (sama dengan K 175) -
Membuat 1 m3 beton mutu f’c = 16,9 Mpa (sama dengan K
14 A.4.1.1.6 m3
220) -
Membuat 1 m3 beton mutu f’c = 19,3 Mpa (sama dengan K
15 A.4.1.1.7. m3
225) -
Membuat 1 m3 beton mutu f’c = 21,7 Mpa (sama dengan K
16 A.4.1.1.8. m3
250) -
Membuat 1 m3 beton mutu f’c = 24,0 Mpa (sama dengan K
17 A.4.1.1.9. m3
325) -

VII - 260
Membuat 1 m3 beton mutu f’c = 26,4 Mpa (sama dengan K
18 A.4.1.1.10. m3
350) -
Membuat 1 m3 beton mutu f’c = 28,8 Mpa (sama dengan K
19 A.4.1.1.11. m3
375) -
Membuat 1 m3 beton mutu f’c = 31,2 MPa, slump (120 ± 20)
20 A.4.1.1.12. m3
mm (sama dengan K 425) -
21 Membuat 1 m3 beton kedap air dengan strorox – 100 A.4.1.1.13 m3 -
22 Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm A.4.1.1.35 m' -
23 Membuat 1 m’ ring balok beton bertulang (10 x 15) cm A.4.1.1.36 m' -
-

VI PEKERJAAN PASANGAN DINDING BATA


Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1
1 A. 4.4.1.4. m2
batu campuran 1SP : 5PP -
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½
2 A. 4.4.1.10 m2
batu campuran 1SP :5PP -
Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½
3 A. 4.4.1.15 m2
batu campuran 1SM : 1KP :2PP -
4 Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm A.4.4.2.5. m2 -
5 Pemasangan 1 m2 acian A.4.4.2.27. m2 -
6 Pemasangan 1 m2 plesteran granit 1SP : 2 granit tebal 1cm A.4.4.2.21. m2 -
7 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP A.4.4.2.23. m2 -
8 Pemasangan 1 m2 finishing siar pasangan conblock ekspose A.4.4.2.25. m2 -
Pemasangan 1 m2 finishing siar pasangan batu kali,
9 A.4.4.2.26. m2
campuran 1SP : 2PP -
10 Pemasangan 1 m2 dinding keramik 20 cm x 20 cm A.4.4.3.54. m2 -
-
-
VII PEKERJAAN KUSEN,PINTU DAN JENDELA
Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen
1 A.4.6.1.1. m3
jendela, kayu kelas I -
Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen
2 A.4.6.1.2. m3
jendela, kayu kelas II atau III -
Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca,
3 A.4.6.1.6. m2
kayu kelas I atau II -
Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi
4 A.4.6.1.7. m2
kayu kelas I atau II -
Pemasangan 1 m2 teakwood rangkap, rangka expose kayu
5 A.4.6.1.11. m2
kelas I -
Pemasangan 1 m2 teakwood rangkap lapis formika, rangka
6 A.4.6.1.12. m2
expose kayu kelas II -
7 Pemasangan 1 m kusen pintu alluminium A.4.2.1.11. m' -
8 Pemasangan 1 m2 pintu alluminium strip lebar 8 cm A.4.2.1.12. m2 -
Pemasangan 1 m2 langit-langit gypsum board ukuran
9 A.4.5.1.7. m2
(120x240x9) mm, tebal 9 mm -
10 Pemasangan 1 m’ list langit-langit kayu profil A.4.5.1.9. m' -
11 Pemasangan 1 m2 kaca tebal 3 mm A.4.6.2.16. m2 -
12 Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17. m2 -
13 Pemasangan 1 m2 kaca tebal 8 mm A.4.6.2.18. m2 -
14 Pemasangan 1 m2 kaca buram tebal 12 mm A.4.6.2.19. m2 -
15 Pemasangan 1 m2 kaca cermin tebal 5 mm A.4.6.2.20. m2 -
-

VIII PEKERJAAN KUDA-KUDA / ATAP


- Atap Baja Ringan Pelana Bentang < 9 m Zinc-Alumunium
1 - m2
G.550 -
Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas
2 A.4.6.1.16. m2
II -

3 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II A.4.6.1.17. m2


-
4 Pemasangan 1 m2 rangka atap sirap, kayu kelas II A.4.6.1.18. m2 -
Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu
5 A.4.6.1.19. m2
kelas II atau III -
Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu
6 A.4.6.1.20. m2
kelas II atau III -
Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I
7 A.4.6.1.21. m'
atau kelas II -

VII - 261
Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I
8 A.4.6.1.22. m'
atau kelas II -
Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm
9 A.4.6.1.23. m2
kayu kelas II atau III -
Pemasangan 1 m2 dinding lambrisering dari papan kayu
10 A.4.6.1.26. m2
kelas I -
11 Pemasangan 1 m2 atap genteng palentong kecil A.4.5.2.1. m2 -
12 Pemasangan 1 m2 atap genteng palentong besar/super A.4.5.2.3. m2 -
13 Pemasangan 1 m’ bubung genteng palentong A.4.5.2.4. m' -
14 Pemasangan 1 m’ bubung genteng palentong besar A.4.5.2.6. m' -
Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I
15 A.4.6.1.21. m'
atau kelas II -
Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I
16 A.4.6.1.22. m'
atau kelas II -
Pemasangan 1 m2 atap asbes gelombang 0,92 m x 2 ,5 m x
17 A.4.5.2.8. m2
5 mm -
18 Pemasangan 1 m’ bubung stel gelombang 0,92 m A.4.5.2.22. m' -
19 Pemasangan 1 m’ nok paten 0,92 m A.4.5.2.22. m' -
-

IX PEKERJAAN LANTAI
1 Pengurugan 1 m3 dengan pasir urug A.2.3.1.11. m3 -

Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40cm x


2 A.4.4.3.1. m2
40 cm
-

3 Pemasangan 1 m2 lantai ubin warna ukuran 40 cm x 40 cm A.4.4.3.4. m2


-

4 Pemasangan 1 m2 lantai ubin granit ukuran 40 cm x 40 cm A.4.4.3.9. m2


-
Pemasangan 1 m2 lantai ubin teralux marmer ukuran 40
5 A.4.4.3.14. m2
cm x 40 cm -
6 Pemasangan 1 m2 lantai keramik ukuran 33 cm x 33 cm A.4.4.3.34. m2 -
7 Pemasangan 1m2 lantai keramik ukuran 30 cm x 30 cm A.4.4.3.35. m2 -
8 Pemasangan 1m2 lantai keramik ukuran 20 cm x 20 cm A.4.4.3.36. m2 -
9 Pemasangan 1 m2 dinding keramik 20 cm x 20 cm A.4.4.3.54. m2 -
Pemasangan 1 m’ plint ubin Pc abu-abu ukuran 10cm x
10 A.4.4.3.18. m'
40cm -
11 Pemasangan 1 m’ plint ubin warna ukuran 10 cm x 40 cm A.4.4.3.21. m' -
12 Pemasangan 1 m’ plint ubin granit ukuran 10 cm x 40 cm A.4.4.3.24. m' -
13 Pemasangan 1 m’ plint keramik ukuran 10 cm x 20 cm A.4.4.3.39. m' -
14 Pemasangan 1 m2 paving block natural tebal 6 cm A.4.4.3.64. m2 -
15 Pemasangan 1 m2 paving block berwarna tebal 6 cm A.4.4.3.66. m2 -
-

X PEKERJAAN BESI / LAIN-LAIN


1 Pemasangan 1 buah kunci tanam biasa A.4.6.2.2. bh -
2 Pemasangan 1 buah engsel pintu A.4.6.2.5. bh -
3 Pemasangan 1 buah kait angin A.4.6.2.9. bh -
4 Pemasangan 1 buah engsel jendela kupu-kupu A.4.6.2.6. bh -
5 Pemasangan 1 buah door closer A.4.6.2.10. bh -
6 Pemasangan 1 buah kunci slot (grendel) A.4.6.2.11. bh -
7 (K3) Pemasangan 1 buah closet duduk/monoblock A.5.1.1.1. bh -
8 Pemasangan 1 buah closet jongkok porselen A.5.1.1 2. bh -
9 (K3) Pemasangan 1 buah urinoir A.5.1.1 4. bh -
10 (K3) Pemasangan 1 buah wastafel A.5.1.1 5. bh -
11 Pemasangan 1 buah bak cuci piring stainlessteel A.5.1.1 12. bh -
12 Pemasangan 1 buah floor drain A.5.1.1 14. bh -
Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi
13 A.5.1.1 15. bh
35 cm -
14 Pemasangan 1 m’ pipa galvanis diameter ½” A.5.1.1 18. m' -
15 Pemasangan 1 m’ pipa PVC tipe AW diameter ½ ” A.5.1.1 25. m' -
16 (K3) Pemasangan 1 buah titik lampu (Instalasi) A.8.4.6.1 bh -

17 (K3) Pemasangan 1 buah MCB (Penyambungan Daya ke PLN) A.8.4.6.1 bh


-
-

VII - 262
XI PEKERJAAN MENGECAT
1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis
1 A.4.7.1.4. m2
cat dasar, 2 lapis cat penutup) -
Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat
2 A.4.7.1.10. m2
dasar, 2 lapis cat penutup) -
3 Pengecatan 1 m2 permukaan baja dengan menie besi A.4.7.1.16. m2 -
Pengecatan 1 m2 permukaan baja galvanis secara manual 4
4 A.4.7.1.18. m2
lapis -
5 Plituran 10 m2 dengan plitur melamic A.4.7.1.22. m2 -
6 Pemasangan 1 m2 wallpaper A.4.7.1.15. m2 -
7 1 m2 Pengikisan/pengerokan permukaan cat lama A.4.7.1.1. m2 -
-

REKAPITULASI
I PEKERJAAN PERSIAPAN Rp -
II PEKERJAAN BONGKARAN Rp -
III PEKERJAAN GALIAN/URUGAN Rp -
IV PEKERJAAN PONDASI Rp -
V PEKERJAAN BETON/PEMBESIAN Rp -
VI PEKERJAAN PASANGAN DINDING BATA Rp -
VII PEKERJAAN KUSEN,PINTU DAN JENDELA Rp -
VIII PEKERJAAN KUDA-KUDA / ATAP Rp -
IX PEKERJAAN LANTAI Rp -
X PEKERJAAN BESI / LAIN-LAIN Rp -
XI PEKERJAAN MENGECAT Rp -
JUMLAH -

PPN 10 % Rp -
JUMLAH TOTAL Rp -

DIBULATKAN Rp -

TERBILANG : ( ………………………………………….. )

Sumber, 2018

Kepala Dinas Perumahan, Kawasan Permukiman


Dan Pertanahan Kabupaten Cirebon

H. SUKMA NUGRAHA, SH.,MM.


NIP. 19610301 198603 1 012

VII - 263
Paraf
Tim Teknis Penyusun
Disiapkan
Analisa

Diperiksa Kasie Perencanaan

Mengetahui Kabid Bina Teknik


RISALAH ANALISA
Pemasangan 1 m2 dinding bata berongga ekspose 5 x 10,5 x 21
-
campuran 1SP :3PP (Pemasangan Tanpa Spasi)
dibuat 16 Mei 2017 pengganti analisa A. 4.4.1.24.rob
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.300 80,000.00 24,000.00
Tukang batu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.015 105,000.00 1,575.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 42,225.00
B BAHAN
Bata Berongga ekspose buah 83.000 2,600.00 215,800.00
Semen Portland Kg 19.000 1,400.00 26,600.00
Pasir pasang m3 0.032 207,900.00 6,652.80
JUMLAH HARGA BAHAN 249,052.80
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 291,277.80


E Overhead & Profit 15.00% 43,691.67
F Harga Satuan Pekerjaan (D+E) 334,969.47
- ATAP BITUMEN SELULOSA MONOLAYER UK.106 X 40 CM
dibuat 13 Juni 2017
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 27,160.00
B BAHAN
Atap Selulosa 0.650 137,000.00 89,050.00
Paku/Screw 12.060 1,000.00 12,060.00
JUMLAH HARGA BAHAN 101,110.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 128,270.00


E Overhead & Profit 15.00% 19,240.50
F Harga Satuan Pekerjaan (D+E) 147,510.50

NOK/BUBUNGAN UNTUK ATAP SELULOSA MONOLAYER


- UK. 106 X 40 CM

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang batu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 38,200.00
B BAHAN
Nok Selulosa 1.300 82,500.00 107,250.00
Paku/Screw 10.400 1,000.00 10,400.00
JUMLAH HARGA BAHAN 117,650.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 155,850.00


E Overhead & Profit 15.00% 23,377.50
F Harga Satuan Pekerjaan (D+E) 179,227.50
- ATAP BITUMEN SELULOSA MONOLAYER UK. 195 X 96 CM

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 80,000.00 16,000.00
Tukang batu L.02 OH 0.100 100,000.00 10,000.00
Kepala tukang L.03 OH 0.010 105,000.00 1,050.00
Mandor L.04 OH 0.001 110,000.00 110.00
JUMLAH TENAGA KERJA 27,160.00
B BAHAN
Atap Selulosa 3.230 45,000.00 145,350.00
Paku/Screw 16.150 1,000.00 16,150.00
JUMLAH HARGA BAHAN 161,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 188,660.00


E Overhead & Profit 15.00% 28,299.00
F Harga Satuan Pekerjaan (D+E) 216,959.00

NOK/BUBUNG UNTUK ATAP SELULOSA MONOLAYER UK.


- 195 X 96 CM

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.250 80,000.00 20,000.00
Tukang batu L.02 OH 0.150 100,000.00 15,000.00
Kepala tukang L.03 OH 0.020 105,000.00 2,100.00
Mandor L.04 OH 0.010 110,000.00 1,100.00
JUMLAH TENAGA KERJA 38,200.00
B BAHAN
Nok Selulosa 1.300 84,000.00 109,200.00
Paku/Screw 10.400 1,000.00 10,400.00
JUMLAH HARGA BAHAN 119,600.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 157,800.00


E Overhead & Profit 15.00% 23,670.00
F Harga Satuan Pekerjaan (D+E) 181,470.00