hisham gawish Project Management Professional

(PMP)
Question : 1 of 27
Q - ID : Q0000225
Selected Choice : 0

Q. You are a construction project manager working on a residential compound construction project in the UK. The project is
complex with lots of outputs, phases, and activities outsourced to vendors and suppliers. You want to structure your project, so
that each project team member has a discrete work package to perform. Which WBS structure would be suitable?

1  Use phases of the project life cycle as the second level of decomposition on your WBS, with the product and
project deliverables inserted at the third level.
2  Use major deliverables as the second level of decomposition only. No need to include project phases at this
level.
3  Incorporate subcomponents that may be developed by organizations outside the project team into the WBS.
4  Use phases of the project life cycle as the second level of decomposition, with the product and project
deliverables inserted at the third level, or include major deliverables at the second level of decomposition, or
incorporate supplier subcomponents.