BINTAN ISLAND
KEPULAUAN RIAU
INDONESIA
712
TECHNICAL SPECIFICATION
MECHANICAL & ELECTRICAL SYSTEM (M&E)
HOLIDAY INN HOTEL INDIGO HOTEL
Prepared for:
23 August 2021
HOLIDAY INN & INDIGO HOTEL, BINTAN
BINTAN ISLAND
KEPULAUAN RIAU
INDONESIA
712
TECHNICAL SPECIFICATION
Prepared for:
Prepared by:
23 August 2021
HOLIDAY INN & INDIGO HOTEL, BINTAN PT. SIGMATECH TATAKARSA
CONTENTS
1. PROJECT TEAM
2. GENERAL INFORMATION
5. SCOPE OF WORKS
6. TECHNICAL SPECIFICATION
APPENDICES:
PROJECT TEAM
GENERAL INFORMATION
1. INTRODUCTION
PT. Graha Agung Indahsentosa, will develop a new resort hotel 4 - Star hotel located in Bintan
Island Bintan is a one island of Kepulauan Riau (Riau Archipelgo). Bintan island is approximately
45 km to southeast of Singapore. This hotel project located in the Bintan Beach International
Resort (BBIR) area.
2. BUILDING DATA
- Power House, Ground Water Tank and Pump Room for both Hotel located in 1 storey Building
A;
• Air conditioning system with Variable Refrigerant Volume (VRV) system split duct type and
ventilation system for M&E Plant Room, toilets and pressurized fan.
• Plumbing/hydraulic (cold water, hot water, waste water, soil water and rain water).
• Fire fighting system (hydrant, sprinkler and portable fire extinguisher).
• Vertical Transportation System (Lift).
• Electrical system that the source is from PLN and diesel generating set as emergency power,
distribution system, general lighting, emergency lighting, general purpose outlets, lightning
protection.
• Communication and Control (Fire Alarm, Sound System, Telephone, Data, CATV, Electronic
Security, Hotel Management System).
3. DEFINITION
1. Owner : The party, that engages the main-contractor to deliver all of the scope of
works.
2. Main-Contractor : The party engaged to carry out all of construction works contract.
3. Sub-Contractor : The party engaged to carry out a part of the main-contractor works and
under the Main-Contractor. The Sub-Contractor has no relation with the
Owner.
4. Specialist : The party who supply and install a special equipment to the Main-
Contractor. The specialist has no relation with the Owner.
5. Superintendent : The person(s) appointed by the Main-Contractor to perform inspect of
works being carried out under a contract between the Specialist/Sub-
Contractor and the Main-Contractor for the construction of a facility.
All equipment installed and work carried out shall comply with the requirements and regulations of
all authorities having jurisdiction over this contract, current building regulations and the referenced
documents specified.
Hydraulic
1. Standar Nasional Indonesia No. SNI 03-7065-2005 tentang Tata Cara Perencanaan Sistem
Plambing (Plumbing system design).
2. Standar Nasional Indonesia No. SNI 03-6481-2000 Sistem Plambing 2000 (Plumbing System).
3. Standar Nasional Indonesia No. SNI 03-3424-1994 tentang Tata Cara Perencanaan Drainase
Permukaan Jalan (Drainage – System design)
4. Standar Nasional Indonesia No. SNI 03-6373-2000 tentang Tata Cara Pemilihan dan
Pemasangan Ven pada Sistem Plambing (ven selection on plumbing system).
5. Perencanaan dan Pemeliharaan Sistem Plambing (Soufyan Moh. Noerbambang & Takeo
Morimura).
6. Standar Nasional Indonesia No. SNI 03-2453-2002 tentang Tata Cara Perencanaan Sumur
Resapan Air Hujan untuk Lahan Pekarangan (Soakway system design).
7. Intercontinental Hotel Grup Design Guidelines for Bintan Resort.
Fire Fighting
1. Standar Nasional Indonesia No. SNI 03-1745-2000 tentang Tata Cara Perencanaan dan
Pemasangan Sistem Pipa Tegak dan Slang Untuk Pencegahan Bahaya Kebakaran Pada
Bangunan Gedung (Stand Pipe and Hose for Fire Prevention in Buildings – System design and
installation).
2. Standar Nasional Indonesia No. SNI 03-3989-2000 tentang Tata Cara Perencanaan dan
Pemasangan Sistem Sprinkler Otomatik Untuk Pencegahan Bahaya Kebakaran Pada
Bangunan Gedung (Automatic Sprinkler System for Fire Prevention in Buildings – System
design and installation).
3. Standar Nasional Indonesia No. SNI 03-6570-2001 tentang Instalasi Pompa Yang Dipasang
Tetap Untuk Proteksi Kebakaran (Fixed type pump for fire protection).
4. National Fire Protection Association (NFPA) 10 : Standard for Fire Extinguisher Systems
5. National Fire Protection Association (NFPA) 13 : Standard for the Installation of Sprinkler
Systems.
6. National Fire Protection Association (NFPA) 14 : Standard for the Installation of Standpipe
Systems
7. National Fire Protection Association (NFPA) 20 : Standard for the Installation of Fire Pumps.
8. Intercontinental Hotel Grup Design Guidelines for Bintan Resort.
Electrical
1. Standar Nasional Indonesia No. SNI 0225:2011 tentang Persyaratan Umum Instalasi Listrik
2011 (PUIL 2011) (Indonesia Electric Code).
2. Standar Nasional Indonesia No. SNI 03-6652-2002 tentang Tata Cara Perencanaan Proteksi
Bangunan dan Peralatan Terhadap Sambaran Petir (Lightning Protection System for Buildings
and Equipment – System design).
3. Australian Standards (AS) 3000/2007 – SAA Wiring Rules
4. Intercontinental Hotel Grup Design Guidelines for Bintan Resort.
Communication & Control (Electronic)
1. Standar Nasional Indonesia No. SNI 03-3985-2000 tentang Tata Cara Perencanaan,
Pemasangan dan Pengujian Sistem Deteksi dan Alarm Kebakaran Untuk Pencegahan
Bahaya Kebakaran Pada Bangunan Gedung (Fire Detection and Alarm System – System
design, installation and commissioning)
2. Standar Nasional Indonesia No. SNI 0225:2011 tentang Persyaratan Umum Instalasi Listrik
2011 (PUIL 2011) (Indonesia Electric Code).
3. Intercontinental Hotel Grup Design Guidelines for Bintan Resort.
2. AUTHORITIES APPROVALS
Arrange for all inspections required by the relevant authorities at various stages and at completion
of the whole installation.
Original documents evidencing approval by the authorities or self-certification by the M&E Sub-
Contractor shall be submitted to the Owner’s representative and copies included in the operating
and maintenance manuals.
4. QUALITY ASSURANCE
The Emergency Power Supply M&E Sub-Contractor shall be responsible for planning and
developing a program, which assures that all of the Contractor’s management, design and
technical responsibilities for quality are integrated and executed effectively. Hence the Contractor
shall plan, establish, implement and maintain a quality assurance program.
The M&E Sub-Contractor shall prepare and submit for acceptance to the Owner’s representative
before the Contract is let, a quality assurance manual approved and signed by a senior
management official.
Manufacturer
Firm regularly engaged in manufacture of services equipment, materials and accessories of types
and size required, whose products have been in satisfactory use in similar service for not less than
5 years.
Installer
Firm with at least 5 years of successful installation experience on services system projects similar
to this project.
5. SUBMITTALS
The M&E Sub-Contractor shall submit the following prior to commencing work. Any work
commenced prior to receiving approval of these will be at the M&E Sub-contractors risk; and any
abortive work will be at his own expense.
1. Product Data
2. Shop Drawings
The arrangement of equipment and plant shown on the “tender” and “for construction” drawings is
typical only and shall be varied to suit the equipment and plant accepted and coordinated with the
structure and other services.
Workshop and installation of all systems and services shall be submitted progressively and signed
by the M&E Sub-Contractor. All drawings (3 sets) shall be forwarded to the Owner’s representative
for approval. Approval of shop drawings, however does not relieve the M&E Sub-Contractor for
coordination of all services and structure.
All connections indicated on the shop drawings submitted either by Site Personnel or Corporate
Design shall be adhered to and final connected shop drawing resubmitted. This applies to drawings
approved with comments or rejected.
• Arrangements (drawing) showing size, location and height or depth of equipment, all piped
services, electrical cables and ductwork, complete with clearances shown. Particularly show
the size and location of all penetrations, fully dimensioned.
• Where packaged equipment is supplied, include the manufacturer’s standard circuit diagram,
modified to comply with the specified system and control requirements. Should the modification
require the provision of an additional control board or cabinet, a dimensioned arrangement,
including equipment lay out, of such board or cabinet shall be include.
• Details showing any modifications proposed to the plans and specification.
• Any other plans the Owner’s representative may require showing how the equipment is
proposed to be installed; giving sizes and position of apparatus.
All the M&E Sub-Contractor drawings shall only use reduction scales 1:20, 1:50, 1:100 or multiples
of 10 of these scales. All lettering shall be a minimum 3.5 mm high.
The Owner’s representative examination of shop drawings shall not remove from the M&E Sub-
Contractor responsibility for the correctness of the dimensions of such drawings nor conforming
strictly with the requirements of this specification nor compliance with Statutory Regulations.
Allow not less than seven (7) working days after receipt of the drawings by the Owner’s
representative for perusal and return.
The fabrication and installation of the work shown on each plant shall proceed as soon as
permission has been given by the Owner’s representative to use the drawing for the purpose of the
Construction.
The M&E Sub-Contractor shall keep all shop drawings on site and continuously mark any
deviations from the shop drawings; as actually installed.
Within two weeks after Practical Completion supply five (5) bound sets of the ‘as installed’ drawings
and diagrams together with concise operating and maintenance instructions, schedules and
commissioning records specified below.
Prepare and supply a draft operation and maintenance manual to the Owner’s representative for
approval for all services installed in this Contract before Practical Completion.
The manual shall give a clear, comprehensive description of all the equipment, components and
sub-components, principle of operation, method of operation and maintenance procedures. The
descriptions shall be accompanied by flow diagrams, line diagrams and any other illustrations
necessary to achieve the required objective.
Operation and maintenance manuals and associated drawings shall be supplied as a quality
publication and shall be as follows:
Submit at the same time five (5) bound sets of as installed diagrams bound as follows:
AS-BUILT DRAWINGS
MECHANICAL & ELECTRICAL WORKS
FOR
HOLIDAY INN & INDIGIO HOTEL, BINTAN
KEPULAUAN RIAU, INDONESIA
All material contained in the manual shall be printed by an approved process on approved quality
paper. This requirement includes all illustrative material.
Present these items of maintenance pertaining to fire safety matters and things as a separate
section of the operation and maintenance manual to facilitate the completion of the relevant log
sheets.
The items of maintenance included in this section shall not be repeated elsewhere in the operating
and maintenance manual but shall be supplemented elsewhere as necessary to ensure that all
systems are comprehensively serviced and maintained.
6. COORDINATION
The Contractor shall coordinate the work with all trades and with all appropriate sections of these
specifications to ensure proper execution of work.
7. GUARANTEE
All equipment, material and workmanship shall be guaranteed by the M&E Sub-Contractor for a
period of one year from the date of final acceptances certified by the Owner’s representative. Upon
receipt of notice from the Owner’s representative of any failure during the warranty period, the
affected part of work shall be replaced promptly by the M&E Sub-Contractor at his own expense.
The guarantee shall not extend to damage incurred through improper operation and/or
maintenance by the Owner. The Owner shall assume full responsibility for proper operation after
final acceptance.
• Requirement: For each required test, submit a report or certificate for inclusion in an operation
and maintenance manual, signed and dated, legibly typed or printed, recording:
• Manufacturers’ certificates: For each factory or type test provide a certificate from the
manufacturer stating that the relevant item has been tested and meets the specified
requirements. Certify that each type-tested item is identical with the specified production item.
Imported items: Manufacturers’ certificates of tests performed in the country of origin may be
accepted items.
8.2. Commissioning
The M&E Sub-Contractor shall commission all services and equipment to ensure satisfactory
operation.
Prior to carrying out testing and commissioning, the M&E Sub-Contractor shall prepare a
PROPOSED Commissioning procedure; detailed schedule of the proposed methods, instruments
and materials, program etc. and submit the schedules to the Owner’s representative for approval.
The Owner’s representative will randomly inspect the testing and commissioning and report on any
deficiencies of these random inspections or on examination of the M&E Sub-Contractor’s
commissioning results. The M&E Sub-Contractor shall rectify any defects until the Owner’s
representative is satisfied with the performance and operation of all systems.
The M&E Sub-Contractor be responsible for the initial start up and operation of both the complete
system and of each item of equipment until the time that the whole installation is operating under
commercial load to the satisfaction of the Owner’s representative. Make all adjustments and
alterations during the commissioning period which are required to establish safe, reliable and
automatic operation and to the achieve the specified condition of service, operation and
performance. Particularly adjust loading of all sections of the system, Calibrate and adjust all
automatic controls and instrument, verify correct operation of all safety and protective elements and
select and fit fuse links and relays for accurate electrical control, protection and discrimination.
Be fully responsible for keeping isolated all electrical circuits connected to equipment installed by
others and shall only connect these circuits when authorized to do so in writing by the equipment
installer. Similarly isolate electricity supplies to each switchboard until it is fully complete, safe and
locked up.
Undertake a full-load trial of the installed equipment prior to Practical Completion. The full load trial
will be required to demonstrate stable, safe, reliable operation of the installed equipment through
the whole range of plant operation. Supply all labor and test equipment required for the trial and it
necessary co-ordinate with M&E Contractor to attend after normal working hours to carry out the
trial. If the trial proves unsatisfactory, rectify all faulty work and repeat the trial without variation to
the Contract Sum.
Demonstrate to the Owner’s representative that the system is satisfactorily commissioned and fully
operational for a minimum continuous period is seven days before Practical Completion is given.
Provided that reliability is satisfactorily demonstrated in this way, the Defects Liability Period will
commence on that date in accordance with the Contract Conditions. Operating responsibility for the
system will pass to the Principal subject to any other conditions of the Contract.
At the time of submission of as installed circuit diagrams, also submit log sheets, sequence and
program setting out the commissioning procedure to be adopted and nominate the person who will
be responsible for commissioning. All circuit diagrams shall be countersigned by that person. The
log sheets shall be kept on site in a folder during commissioning and shall record all test results,
name plate details, operating and protective instrument and relay settings. Log sheets shall include
a detailed checklist of all systems and equipment specified and shall also incorporate checklists for
start-up of equipment as published by Manufacturers. The person responsible for commissioning
shall personally ensure that arrangements are made in advance for attendance of technicians and
also those of Contractors and suppliers as required and to keep the Owner’s representative fully
informed of progress.
It is solely the M&E Sub-Contractor’s responsibility to carry out maintenance from initial start up in
accordance with Manufacturer’s recommendations.
Before Practical Completion, submit for approval a proforma service report made specially for this
Contract for use each month during the Defects Liability Period.
Instruct persons nominated by the Principal in the correct practice of operation, routine adjustment
and maintenance of the installation before it has reached Practical Completion. Instructions shall
continue as required during the period of operation preceding the date of Practical Completion
during which time Contractor shall be responsible for operation, supervision and correcting faults.
During the Defects Liability Period, the Principal will operate all diesel generating sets. The M&E
Sub-Contractor shall continue the maintenance log specified above throughout the Defects Liability
Period.
The Sub-Contractor shall carry out all scheduled and preventive maintenance work during this
period in strict accordance with the recommendations of the Manufacturers and as detailed in the
Operation and Maintenance Manuals.
Send experienced and qualified technicians to side at regular monthly intervals or as required for
testing. They shall carry out all preventative maintenance; service, routine adjustments,
replacements, cleaning and lubrication needed to keep the whole installation operating in a first
class condition. They shall report to the Principal’s nominated representative on arrival, receive any
instructions about the work and issue a written report on their activity and the condition of the
installation to the Principal within five days.
The M&E Sub-Contractor may, if so desired, seal operational controls to prevent adjustment
beyond defined limit if maladjustment and/or mal-operation could result in a malfunction which
could give rise to a plant defect, the correction of which would be a contractual responsibility in
terms of Defects Liability.
As provided in the General Conditions of Contract, maintain the installation and make good any
defect in workmanship or materials with all possible speed during the Defects Liability Period. Be
prepared to send a suitable technician promptly to site at one hour’s notice throughout the Defects
Liability Period to meet emergency calls for service at any time. Work continuously during of hours
of any day as required to affect the fastest possible restoration of normal system operation in the
event of breakdown. Employ M&E Sub-Contractor and airfreight or otherwise transport
replacement equipment if directed by the Owner’s representative.
Supply and install replacement electric lamps and other consumable items, which fail in normal
service during the Defect Liability Period. Supply complete lists of spare parts normally held in
Manufacturers stock with sufficient detail to permit accurate ordering by facsimile. Supply additional
spare part if specified and deliver them into store on site, properly packed and preserved.
Supply at the time of commissioning all special tools and equipment which may be required for
routine operation, maintenance, adjustment or cleaning of the installation as recommended by the
equipment Manufacturers.
No work or operation shall be carried out by the M&E Sub-Contractor at any time in the building
once commercial operation has commenced without the full knowledge and prior approval in the
Principal.
Notify the Owner’s representative four weeks before the expiration of the Defects Liability period so
that the Principal can notify the relevant insurers.
After completion of the Defects Liability Period the operation and preventive maintenance of all
plant, equipment and services will become the responsibility of the Principal.
Submit a proposal to the Owner’s representative for an annual maintenance Contract four weeks
before the end of the Defects Liability Period.
Organize and conduct a seminar to instruct the Owner and his representatives in the operation of
all diesel generating sets provided at the completion of the project.
Submit agenda schedule and list of representatives to the Owner’s representative for approval
thirty (30) days prior to seminar.
Instruct Owner’s operating personnel in proper starting sequences, operation, shutdown and
maintenance procedures, including normal and emergency procedures.
PROJECT DEVELOPMENT
HOLIDAY INN HOTEL – BINTAN
ICT (INFORMATION COMMUNICATION TECHNOLOGY) WORKS
SCOPE OF WORKS
1. GENERAL
The services will include the supply, installation, and testing, commissioning, guarantee and certify
the installation, service and maintenance of the specified systems, to provide as built drawing,
operating procedure and maintenance and training installation for building maintenance.
In case some of the material and equipment used are different from the specifications listed below,
the Sub-Contractor is responsible for changing the equipment and/or materials to ones that comply
with the technical specifications or general standard codes without any additional fee and approved
by Board/Site Supervisor/Construction Management.
2. SCOPE OF WORKS
The electronics services will include the supply, fabrication, delivery, off loading, installation,
connection, testing, commissioning, guarantee and certify the installation, service and maintenance
of the specified systems.
The electronics ICT services will include, but not be limited to the following:
A. Telephone
1. Procurement, installation and testing of IP PABX, complete with all specified facilities located in
the 1st floor server room, Building P.
2. Procurement, installation and testing of telephone outlets and their hand sets.
3. Conducting training for maintenance crew.
4. Provision of operation and maintenance manual books.
5. Provision of as built drawings.
6. Testing installation from both Sub-Contractor and Authority.
7. Testing and commissioning of all systems.
8. The Sub-Contractor shall give a training including operation, maintenance and troubleshooting
to some personnel appointed by owner until they can operate, maintain by them self before
handing over.
1. Procurement, installation and testing of network system data, including complete servers with
switching equipment and firewalls placed in the 1st floor server room, Building P..
2. Procurement, installation and testing of data outlets.
3. Procurement, installation and testing includes Switch, Patch Panel, data cable, data outlet and
installation.
4. Conducting training for maintenance crew.
5. Provision of operation and maintenance manual books.
6. Provision of as built drawings.
7. Testing installation from both Sub-Contractor and Authority.
8. Testing and commissioning of all systems.
9. The Sub-Contractor shall give a training including operation, maintenance and troubleshooting
to some personnel appointed by owner until they can operate, maintain by them self before
handing over.
The above work shall be carried out by specialists experienced in the electrical services trades.
All Participants Tender shall arrange with the Principal or Main Contractor to inspect the site and be
aware of all design details, operation and site conditions.
3. TERMINATION POINTS
The work covered by this section of the specification shall be fully complete and independent within
the limits of the following section termination points at which it shall connect to existing systems or
work carried out by others or other trades.
It is responsibility of the Sub Contractor to ensure the installation is complete within the contract
termination points and that interdisciplinary termination’s between trades are fully coordinated. The
following list of section termination points is included to allow quotations to be assessed on an
equal basis.
• Connect cables to the telecommunication provider and ISP (PT. Telkom telephone box)
• Interconnection to other M/E equipments
4. ASSOCIATED WORK
4.1. Scope
Carry out civil, structural and building required for access, construction, installation, operation and
maintenance of the installation covered by this specification unless otherwise specified or shown
on the accompanying drawings to be carried out by others.
Ensure that the strength and rigidity of structures and fastenings are adequate to prevent failure,
significant movement or deflection during operation, traffic or maintenance during the life of the
installation.
Submit shop drawings or other details of frames, structures and building work for inspection by the
Superintendent before fabrication or installation.
Ensure that overall dimensions do not exceed those specified and other wise conform generally to
the dimensions shown on the drawings.
State at the time of tendering any changes that are required to these provisions and be fully
responsible for the cost of any subsequent alterations or reselection of equipment necessary to
complete the work as specified.
Form necessary openings and recesses, make good and perform any other incidental work
required for the installation of the electrical services.
Summary of work directly associated with the installation covered by this section of the
specification which will be carried out by the Owner is as follows.
• None
Summary of work directly associated with the installation covered by this section of the
specification which will be carried out by the construction management is as follows.
Summary of work directly associated with the installation covered by this section of the
specification which will not include in this phase is as follows.
• None
PROJECT DEVELOPMENT
HOLIDAY INN – BINTAN
ICT (INFORMATION COMMUNICATION TECHNOLOGY) WORKS
The IP PABX system in this building is used to fulfill the voice communication needs of operational
management, building maintenance and hotel occupants (which are connected with system billing).
The IP PABX system is required to be integrated with the hotel PMS server and able to fulfill the
basic features needed for hotel operations such as mess waiting waiting, wakeup call, call billing
and others.
Materials and equipment to be used must meet or approach the technical requirements as follows:
A. The intended PABX is an IP PABX system that has the following configuration capabilities:
• 30 trunk SIP to the central PT. Telkom consists of 20 used analog trunks and 10 analog
trunk spare parts.
• 400 IP extensions
• 200 DIOD Lines
• 1 (one) port interface for Music-on-Hold
• 1 (one) port interface for the paging system
• set PC console for Operators.
• Auto attendance, at least able to receive 15 simultaneous calls.
• OA & M system (Operation, Administration & Maintenance) PABX that is GUI based and
runs on Linux / Unix / Equivalent systems to provide operational and maintenance
convenience for all PABX users.
• 1 (one) set of terminals for OA & M (operation, administration & maintenance) GUI.
With the following specifications:
- Processor: Core i7
- Chipset Processor: Intel P55
- Memory RAM: Min. 4GB
- Graphic Memory: Min 2GB
- HDD: Min. 1000GB
- Acc: Keyboard, USB Optical Mouse, DVD-RW
- Screen: Min 18.5 "LCD
- Operation System: Windows 7 32-Bit version
- Sound Card & Speaker
- Riva TNT 1GB / Equivalent VGA Card
- ASUS Mother Boards
- OA & M software (operation, administration & maintenance)
• 1 (one) set of Billing System to meet the needs of all telephone users with
ability to charge between tenants.
With the following specifications:
- Processor: Core i7
- Chipset Processor: Intel P55
- Memory RAM: Min. 4GB
- Graphic Memory: Min 2GB
- HDD: Min. 1000GB
- Acc: Keyboard, USB Optical Mouse, DVD-RW
C. The design must be modular, so that it provides convenience in capacity building in line with
increasing communication needs from time to time.
D. PABX offered must be able to provide the right solution to the needs of capacity and function /
facilities, in addition to the requirements including:
Ease of hardware (hardware):
• It must be easy and economical if it is necessary to develop and upgrade the equipment,
provided that what is installed is not wasted.
• Must be easy and efficient in carrying out service and maintenance, as well as ease in
providing spare parts, so that the speed and accuracy of service and maintenance can be
achieved at a lower cost.
A. Is an internet protocol exchange or IP-PBX not IP Enable PBX that can function to convert voice
signals into data packets so that voice, data and images can be combined in one channel /
media via LAN / WAN and in accordance with existing Protocol standards, but also follow TDM
standards.
B. Based on Open OS (Operating System) like Linux, and must be hardened on the system, not
vulnerable to viruses and other interference (not the Windows operating system).
D. The design of PABX is modular in the sense that it can be easily developed from the initial
capacity to the desired capacity, Addition to the number of extension planes, Trunk lines and
features can be developed without disrupting the system.
E. The slots in the PABX cabinet are universal which do not limit certain types of modules in certain
places.
G. Can be connected with analog aircraft telephone, digital telephone, IP telephone. If the
telephone IP is connected to an existing LAN / WAN network, then the telephone IP must be the
PABX extension number.
H. The equipment and materials to be used must have the characteristics, capacity and capabilities
in accordance with the required specifications, and have a license in accordance with their use.
I. It has an Auto Attendance that is integrated with an IP PBX system and is able to accept a
minimum of 80 simultaneous calls. Greeting can be changed via LAN (WAV).
J. All devices / modules must follow the standard / can enter the 19 "rack.
L. The modules have lightning protection circuits and shock voltages, 220 V rms voltage, over
voltage protection and heat protection.
M. TELKOM channels can automatically move to a predetermined branch channel, if the flow of
electricity or battery does not work / die.
N. Has the ability to be connected with an external alarm either in the form of a lamp or bell /
buzzer to notify if there is a system failure or night answering.
O. Can be connected with analog extensions of LD type and / or DTMF, digital extensions with
ISDN standards (2B + D) or IP enhanced hardware telephones that run on LANs with Ethernet
topologies. Digital extension and IP have the ability to voice and data communication
simultaneously (full duplex).
P. Can be connected with analog TELKOM channels or digital TELKOM channels (ISDN) in
accordance with the CCITT standard (Consultative Committee on International Telegraph and
Telephony) for primary access (30 B + D).
Q. Has functions and facilities needed for voice communication, data communication (data
switching), and has the ability to be connected as a network (networking) either on a star mesh
or a combination of both.
R. Has an interface that can be connected with transmission media that specifically uses satellite
services.
A. Adhering to a distributed architecture system with a multi processing system that can manage
all gateways / cabinets in each location with high levels of reliability and availability and not a
collection of standalone IP PBXs.
B. Using a redundant processor where the processor used must be more than one and able to act
as a running processor and stand by processor.
C. The relationship between the processor and the gateway must be duplicated to support high
reliability.
D. Relationships between Network Ports must be able to use: Direct Connect that uses Fiber Optic,
IP Connect and ATM
E. The system must support Networking Features such as: DCS, Qsig and Private Networking
Feature
F. The system must support the signaling method: H.323, SIP, SBC, R2MFC, ISDN-PRI, ISDN-BRI
and Q.SIG
G. Can be expanded to 36,000 thousand extensions consisting of: IP, analog and digital extension
by only adding cards and / or modules according to the required capacity
K. Able to compress and uncompress Voice Conversation (Codecs) and fax transmissions through
IP Infrastructure (VoIP and FoIP) that are in accordance with existing standards, so as to reduce
Bandwidth requirements.
L. The system can be integrated with Mobile Operator Network (GSM & CDMA) so that brigde is
possible between extensions with Mobile Phone, for internal transfers or conferences.
M. Voice applications can be loaded / installed on mobile phones for internal, external, conference,
transfer calls
N. System IP-telephony must be equipped with encryption facilities both on the system processor,
gateway (cabinet) and end-point (telephone set).
O. The existing Encryption System must be integrated and already existing features of the IP-
Telephony System, and includes both conversations and signaling encryption, and refers to the
AES (Advanced Encryption Standard) 128 bit and H. standards. 248 Encryption links, including
SSL-SSH for telnet.
1.3.1. Feature
A. Dialing, with numbers abbreviated from several digits being easily memorized codes.
B. Call Forwarding. Calls can be diverted to other terminals if they are not answered, busy or
absent from the group.
C. When more than one data call then the calls will be queued (call queue).
D. Compatibility check. For data communication, correct checking is needed, whether terminal A
can be compatible with terminal B.
E. Hunting Group.
F. For data communication out of the system (to Telkom) a polling modem is needed to save the
number of modems that are used enough with several modems that can be made in sharing by
turning the desired modem number or simply the modem group number.
H. The system offered must be able to be connected with a telephone that uses simultaneous voice
and data in one pair cable (2B + D).
J. To meet the security needs of transferring data from unwanted access (criminal actions) to
access terminals from other terminals, the system must be able to provide capabilities so that
with or without additional tools needed:
• Direct access with a password
• Access + password with the procedure of calling back to a predetermined point.
• Access + password is accompanied by calling procedure back to a certain point by the
system and followed by the second password by the accessor.
K. Distinctive Ringing:
Telephone ringing must be different for internal or external calls.
Q. Instantenous Ringing:
Direct dial tone is given once the last digit is rotated / pressed.
T. Traffic Measurement:
Each conversation can be measured the length of the conversation, where, how many pulses,
etc. through the operator plane.
U. Traffic Classes:
The classification of extensions can be arranged according to the hierarchy, with more than 5
levels of hierarchy starting from only accepting them, to the level of the operator hierarchy.
1. General
The operator is equipped with a minimum of 500 MB hard drive, 1.44 flexible disk, indicators and a
number of displays that function on the color monitor screen, with adjustable viewing angles.
A. Button:
To handle calls and to help carry out relationships.
B. Indicator:
To provide call information, the results of number, status and alarm playback.
C. Directory Dialing System: (on screen name directory) makes it easier and faster for the
operator to connect to the communication connection with just the push of a button.
D. Display:
To show the trunk group extension number, as well as connecting the channel number, number
of meters and pulses during the conversation and the actual length of the conversation.
2. Facilities
Operators can directly transfer calls to an extension without notice. When the operator is still
connected by calling, the operator can directly dial the destination number.
If the number that is rotated is idle (free), the call will automatically connect to the number
without needing to talk to the caller.
If all trunk lines in the group trunk are busy, the operator can mediate the conversation and
notify the party that is talking that the channel is needed for an emergency and that he can
disconnect the two parties.
With this facility the operator can carry out the relationship by rotating the abbreviated number.
If some extensions want to talk to the same external telephone, the operator will press the
Series button. Call and notify the telephone outside that there are several serial calls. The
operator will connect the first extension, and when the relationship is finished and the operator
will connect with the next extension and so on until the last extension without breaking the
connection with the outer plane.
If the operator cannot immediately connect the call to the intended extension, the operator can
place a call on hold position.
The caller will receive back-ground music (music on hold).
G. Individual Monitoring:
Operators can mark calls one by one so they can give immediate attention to the call, if the call
is returned to the operator for further handling.
H. Display Number:
I. Pilot Buzzer:
When operator assistance is needed and the operator is not handling the call, the buzzer will
sound with a predetermined rhythm.
If the operator continues the call to the extension, but the extension is diverted / transferred to
another extension (call forwarding, follow me, etc.) the operator will know by looking at the
indicator. The indicator will remain on as long as the operator is associated with the call.
If the operator is asked by an extension to connect to an extension that is not allowed, the
operator will be able to see through
"Indicator". This indicator will remain lit as long as the operator is associated with the extension.
L. Congestion Indicator:
The indicator will show that the connection cannot be entered or all channels are used.
Operators can find out the identity or division of the last party contacted by an outside number,
in a series-call, so that if needed the operator's redial can be more efficient.
The system can determine whether the outside party is released or returned to the operator
when the internal PABX presses the enquery and puts down the handle of the aircraft. If several
times an outside party returns to the operator, the connection will be released.
The console operator can turn on the buzzer sound automatically if the outside caller does not
wait longer than a certain period of time, even though the buzzer has been turned off.
With this feature, the operator can pay attention to the amount of traffic load on each call queue,
so that the operator can intentionally adjust the speed of handling calls to shorten the waiting
time for outside callers.
Q. On Hold Delay:
After the operator has finished answering an external call, the system is given 5 seconds to the
caller before the operator can terminate the connection.
This can prevent the use of calls that are too fast by the opera
1. Day service
2. Night service (night service)
During day Service all incoming / outgoing calls are carried out by 1 operator. If the last operator
on duty activates the night service from the operator console, the "night service" facility will
function automatically.
This situation usually occurs at the end of working hours, when the number of incoming /
outgoing calls does not really require an operator. In the "Night Service" incoming calls are
received by one of several possibilities that can, namely:
A. Music On Hold:
Music sounds can be played either to the trunk line plane or to the extension, if the relationship
is being processed or waiting.
B. Call forwarding:
If there is a call to one extension and is not picked up, then after a certain interval the call is
immediately transferred to another specified extension.
C. Group Hunting:
A number of extensions, generally included in one department / section, can be combined into
one group for hunting. Individual numbers for each extension function as usual. If the group
number is played, the plane that is free of the group will ring either cyclically or a regular routine.
Each extension can take calls for other extensions that are still in the pick-up group, by playing
certain code.
1. Follow Me:
A call to one programmed A extension follows me to extension B, the B extension will
automatically be called.
3. Emergency Alarm:
Extension alarms can be rotated by extensions with certain Traffic Classes by turning the
alarm code. If you rotate the handset, before the call is answered the call is still active. Then
the emergency alarm extension is lifted, the Automatic Ring Bank procedure works and the
extension originator (which starts ringing).
5. Break-In:
Extensions with Break-in facilities can mediate ongoing conversations. Break-in initiatives are
carried out by the extension by playing the Break-In code. Break In will be followed by a
warning tone that is heard by all those who speak.
6. Inquiry:
An extension that is in talks can call a third party by pressing the inquiry button. The initiator
will receive a dial tone and can call a third party. The second party will wait and hear musical
tones. After finishing with the third party the conversation can be continued with the second
party again.
7. Shuttle:
During the inquiry, the initiator can help third parties to wait and talks with the second and
third parties can be alternated by pressing the inquiry again.
8. Transfer:
In a state of inquiry, the initiator can connect the second party with a third party by placing
the telephone receiver. The extension originator will be idle and the second and third parties
will be related.
9. Add-on Conference:
With this facility, the extension can talk to three, by pressing the Add-On conference code
before dialing the third party number.
A. IP Phone Set
• Mid-sized multi-gray scale graphic display
• WML browsers use XML standards
• LDAP directory access via a browser
• Integrated switch for connection with PC
• 10/100 BaseT with separate auto negotiation for each port
• Minimum 14 fixed feature buttons
B. SoftConsole Operators
• Able to display information on the number of callers on the display up to 6 phones
simultaneously.
• Able to search internal and external directories
• Lookup and dialing directories
• Integrated with directory management and supports up to 100 directory databases
• Records per call and permanent
• Integrated iClarity for IP Audio
2.1. Cable
This terminal is installed at an altitude of 300 cm from the floor or determined by the architect.
2.4. Conduit
Conduits must be clamped to building structures with sadle clamps. All installation pipes on the
ceiling, on the ceiling and on the shafts must be marked every distance of 10 m in red (fire
alarm), black (sound / fitting), blue (telephone), green (data), yellow (security) , brown (BAS).
3. Testing
This installation must get a good test certificate from PT. TELKOM and the manufacturer.
4. Product Reference
A. Equipment, materials and materials used must meet specifications. It is possible for the
contractor to submit a similar alternative and the Contractor can only replace it if there is
official and written approval from the Directors / Field Supervisor / Construction Management.
B. Reference Products that can be used are as follows: see list of equipment & materials.
The Data Network System in this building will use a data cable network that is distributed to
each building and terminated to each data panel path (ST-DT) in the panel room. Backbone
Network Installation Data from FO server patch panel to ST-DT FO patch panel per floor using
Multi Mode FO 24 core.
Materials and equipment to be used must meet or approach the technical requirements as
follows :
2. Mode of Operation
a. Transparent Mode (bridging)
b. Routing Mode
c. NAT (DNAT/SNAT, Masquerading)
d. Support source-based routing
e. Support time-based policy
f. Support generic Proxy
3. Firewall
a. Support stateful packet inspection
b. Support time-based policy
c. Support protocol handling
4. VPN Gateway
a. VPN Throughput 1.06 GB
b. Support L2TP and PPTP protocol
c. Support IPSec NAT transversal and virtual IP
d. Support L2TP over IPSec
e. Support multiple architecture including Net-to-Net, Host-to-Net, and Host-to-Host
f. 3rd party user authentication including Local user, Radius server, Novel eDirectory,
Microsoft Active Directory, LDAP.
g. Support multiple encryption including DES, 3DES, AES etc.
h. Support Authentication method including PSK, X.509, RSA,CHAP, MSCHAP,
MSCHAPv2, PAP, RADIUS (for L2TP, IPSec and PPTP).
6. Web Security
a. Support URL filtering / surf protection
b. Support time base policy
c. Support transparent and user authentication proxy with active directory service and
Novell e-Directory
d. Support database of categorized web sites currently includes more than 60 million
entries
e. Dual virus scanning engine
f. Support spyware protection (filtering flash, java script, VB script also)
g. Support regular expression
h. Support File extension blocking
i. Support URL white list and black list
7. Email Security
a. Support POP3 and SMTP Proxy transparent
b. Support Phishing protection
c. Support Spam protection
d. Dual virus scanning engine
e. Multiple detection methods and a database of over 170,000 virus signatures
f. Spam quarantine supported
g. Support method greylisting, Sender Policy Framework (SPF), BATV signatures,
Sender and Recipient verify, USE SBL/RBL, Deny recipient hack, Sender black
list.
h. SMTP Authentication supported
i. Support SSL/TLS
8. Reporting
a. Graphical view
b. Daily Executive Report
c. Detailed Real time logging
d. Network Accounting logging
1.2. Switch
1.6. Cable
The size and number of cores (contents) in the cable are as shown in the picture & all cables are
installed in a conduit
4.1. Equipment
a. Cable trunking and cable ladder must be installed horizontally and one vertical line.
b. The cable ladder is attached to the wall of the shaft using 3 dynabolt pieces measuring 1/2
"x 2" at a distance of 75 cm.
c. Trunking cables are hung on the floor of the building with dynabolt measuring 1/2 "x 2"
5. Testing
Testing of equipment working systems must be carried out by the equipment sales agent and the
party must prepare letters guaranteeing good installation.
6. Product Reference
a. Equipment, materials and materials used must meet specifications. It is possible for the
contractor to submit a similar alternative and the Contractor can only replace it if there is
official and written approval from the Directors / Field Supervisor / Construction
Management.
b. Reference Products that can be used are as follows: see equipment & material list
c. All data cabling system installations must be certified with a guarantee of 10-15 years for
the application.
LAMPIRAN :
TABLE OF COMPLIENCE (TOC) / MINIMAL SPESIFIKASI
PEKERJAAN ICT (INFORMATION COMMUNICATION TECHNOLOGY ) HOTEL HOLIDAY INN - BINTAN
No Jenis Pekerjaan Type / Spesifikasi yang dipersyaratkan Merk yang direkomendasikan Merk yang diajukan Kontraktor
I PEKERJAAN ICT
3 Access Switch PoE - Merupakan manageable switch dengan dimensi Rack-mounted 19 ". HP, Cisco, Alcatel Lucent
- Kapasitas switch 24 port gigabit 10/100/1000 Mbps Ethernet IEEE 802.3at PoE.
- Memiliki kemampuan stack dengan menggunakan port khusus baik untuk data dan power supply.
- Mendukung fitur-fitur layer 2 sebagai berikut : Konfigurasi VLAN dinamis, 802.1x, 802.1q, VLAN
berdasarkan port, private VLAN, 802.1d STp, 802.1s MSTP (Multiple Spanning Tree Protocol)
4 Access Switch PoE - Merupakan manageable switch dengan dimensi Rack-mounted 19 ". HP, Cisco, Alcatel Lucent
- Kapasitas switch 24 port gigabit 10/100/1000 Mbps Ethernet
- Memiliki kemampuan stack dengan menggunakan port khusus baik untuk data dan power supply.
- Mendukung fitur-fitur layer 2 sebagai berikut : Konfigurasi VLAN dinamis, 802.1x, 802.1q, VLAN
berdasarkan port, private VLAN, 802.1d STp, 802.1s MSTP (Multiple Spanning Tree Protocol)
5 Fire Wall - Memiliki minimal 8 port gigabit ethernet & 2 port 10G SFP+ HP, Cisco, Alcatel Lucent,
- Memiliki kemampuan sebagai VPN gateway Fortinet
- Mendukung VLAN minimal hingga 250 VLAN
- Mendukung minimal Routing protokol statik dan OSPF
5 Network Management Server - Merupakan perangkat LAN Management System yang mampu mengkontrol dan HP, Cisco, Alcatel Lucent
mem-visualisasikan semua perangkat jaringan yang disediakan hingga 1500
perangkat LAN
- Dapat memberikan gambaran performa jaringan dengan real-time dan historical reports
- Real-time fault detection pada setiap perangkat yang dimonitor
- Memiliki kemampuan untuk mengkonfigur, memonitor, dan troubleshoot implementasi VRFLite
- Support pada virtualisasi Server
6 Fiber Optic - Merupakan jenis kabel fiber single mode OS2 (ITU-T G652d), indoor cable. LS, DTC, AMP
- Core diameter 9 micron dan diameter cladding 125 micron.
- Mempunyai fire rating Low Smoke Zero Halogen (LSZH).
- Standard compliance TIA568, ISO11801, ICEA, EN50173.
- Fiber Attenuation (dB/Km) ≤ 0.22 dengan panjang gelombang 1550 nm.
No Jenis Pekerjaan Type / Spesifikasi yang dipersyaratkan Merk yang direkomendasikan Merk yang diajukan Kontraktor
B IP Telephone
1 IP PABX IP PABX yang dimaksudkan adalah merupakan IP PABX system yang memiliki kemampuan untuk Panasonic, NEC, Alcatel, Siemens,
dikembangkan menjadi 15.000 extension IP serta memiliki konfigurasi sebagai berikut : Transtel
- Kebutuhan extension yang dibutuhkan sebanyak 350 IP extension.
- 30 Port SIP Trunk
- Memiliki kemampuan redundant power untuk setiap kabinet dan jika dibutuhkan dapat juga memiliki
redundant prosesor untuk setiap kabinet.
- Bersifat modular, dalam arti dapat dikembangkan dengan mudah,dari kapasitas maupun fasilitas yang
diinginkan tanpa harus mengganggu kerja sistem yang sudah ada.
- Memiliki kemampuan untuk diintegrasikan dengan Billing System software guna merekam data - data
pemakain telepon. Data - data yang akan disedia- kan oleh sistem PABX yang ditawarkan minimal :
Lamanya pembicaraan, Nomor yang dipanggil, Nomor pesawat cabang pemanggil, Identifikasi Nomor
Trunk PTT. Waktu pembicaraan terjadi, dan biaya yang dibutuhkan .
- Memiliki kemampuan untuk memenuhi fitur fitur komunikasi perhotelan dan bisa di integrasikan dengan
sistem management hotel.
3 IP Telephone Handset - Memiliki port ethernet untuk PC 10/100 Panasonic, NEC, Alcatel,
- Mendukung 802.3af PoE. Siemens, Transtel
- Memiliki dual line access sehingga memungkinkan dapat menerima call yang kedua jika sedang on-line.
- Memiliki tampilan LCD, minimal 3 line dengan masing - masing line dapat mencakup sampai 40
karakter.
To :
Dear Sir/Madam,
We hereby state that our company is committed to deliver this project in a professional
and ethical way, and free of any corruption, conspiracy, and/or collusion practices.
We are fully aware of the consequence of any offence or breach of this Integrity Pact
which may result in any sanction, penalty, termination of Contract, or criminal charge.
Jakarta,................
PT. ......................
........................
Director