12 All lighting arrangements (spark proof), Industrial DB, ventilation, blower with duct, consumables, Cables, Hand lamps to be in vendor scope
13 Cleaning of area of hot work to be done by contractor and clearance of site after work to be done by contractor
14 All work to be cleared by CSL QC
15 All material/man movement to worksite to be arranged by contractor. Only authorisation letter will be issued by CMSRU.
16 Parallel contract may be resorted by CSL in order to speed up pace of work
17 CSL safety procedures to be followed for entire period of work by contractor
18 All lifting tackles, tools and certified rigger required for shipping inside machinery spaces to be arranged by contractor
19 All lifting tackles, tools and certified rigger required for shipping inside machinery spaces to be arranged by contractor
NOTE : Rate should be qouted considering the Space and power supply issued by the CSL
i) Firms should provide previous experience of Fabrictaion heavy structure or similar activity along with offer. If the experience claimed by the bidder is of no
relevance with respect to Structure or similar activity, then such experience will not be considered for qualification. Decision taken by CSL in this regard will be
final.
Completion period