ID Task Task Name Duration Start Finish Sep '22 Oct '22 Nov '22 Dec '22 Jan

Oct '22 Nov '22 Dec '22 Jan '23 Feb '23
Mode 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19
1 PEKERJAAN 100 Mon 19/09/22 Mon
GEDUNG INDUK days 06/02/23
2 Pekerjaan Persiapan 10 days Mon 19/09/22 Fri 30/09/22
3 Penyelenggaraan 5 days Mon 19/09/22 Fri 23/09/22
SMKK
4 Pekerjaan Struktur67 days Mon 26/09/22 Tue 27/12/22
5 Pekerjaan Galian 18 days Mon 26/09/22 Wed
dan Urugan 19/10/22
6 Pekerjaan Pondasi 29 days Mon 26/09/22 Thu 03/11/22
7 Pekerjaan 25 days Wed 12/10/22 Tue 15/11/22
Struktur Elevasi
8 Pekerjaan 28 days Thu 20/10/22 Mon
Struktur Beton 28/11/22
9 Pekerjaan 39 days Sun 23/10/22 Wed
Struktur Baja 14/12/22
10 Pekerjaan Atap 38 days Fri 04/11/22 Tue 27/12/22
11 Pekerjaan 64 Tue 08/11/22 Mon
Arsitektur days 06/02/23
12 Pekerjaan 25 days Tue 08/11/22 Mon
Pasangan dan 12/12/22
13 Pekerjaan 14 days Tue 13/12/22 Fri 30/12/22
Pasangan Plafond
Interior (modif)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS Proj
Summary Manual Summary Rollup Critical
Date: Thu 15/09/22
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1
ID Task Task Name Duration Start Finish Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23
Mode 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19
14 Pekerjaan 24 days Tue 13/12/22 Mon
Pasangan Keramik 16/01/23
Lantai dan
15 Pekerjaan 32 days Wed 14/12/22 Fri 27/01/23
Pengecatan
16 Pekerjaan Kusen 28 days Wed 28/12/22 Mon
Pintu dan Jendela 06/02/23
Allumunium
Powder Coating
17 Pekerjaan Sanitair 11 days Mon 26/12/22 Tue 10/01/23
Fixture
18 Pekerjaan Fasade 35 days Mon 12/12/22 Mon 30/01/23
19 SUB JUMLAH 61 Wed 16/11/22 Thu 09/02/23
PEKERJAAN days
STRUKTUR &
ARSITEKTUR
20
21 PEKERJAAN
MEKANIKAL
22 Pekerjaan Plambing 32 days Wed 16/11/22 Thu 29/12/22
23 Pekerjaan Instalasi 21 days Tue 03/01/23 Tue 31/01/23
Tata Udara AC

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS Proj
Summary Manual Summary Rollup Critical
Date: Thu 15/09/22
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 2
ID Task Task Name Duration Start Finish Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23
Mode 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19
24 Pekerjaan 3 days Mon 09/01/23 Wed
Pengadaan Alat 11/01/23
Pemadam Api
25 PEKERJAAN
ELEKTRIKAL
26 Pekerjaan Panel daya11 days Mon 26/12/22 Tue 10/01/23
27 Pekerjaan Kabel Daya18 days Tue 17/01/23 Thu 09/02/23
28 Pekerjaan Rak Kabel 12 days Tue 13/12/22 Wed 28/12/22
29 Pekerjaan System 4 days Wed 14/12/22 Mon
Grounding ( 19/12/22
Pentanahan )
30 Pekerjaan Instalasi 25 days Tue 06/12/22 Tue 10/01/23
Penerangan dan
Stop Kontak
31 Pengadaan & 8 days Thu 01/12/22 Mon
Pemasangan 12/12/22
Instalasi Genset
32 Pengadaan & 10 days Tue 13/12/22 Mon
Pemasangan 26/12/22
Transformator
33 Pekerjaan CCTV 19 days Wed 11/01/23 Mon 06/02/23
34 Pekerjaan 8 days Tue 27/12/22 Fri 06/01/23
Penangkal Petir

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS Proj
Summary Manual Summary Rollup Critical
Date: Thu 15/09/22
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 3
ID Task Task Name Duration Start Finish Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23
Mode 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19
35 SUB JUMLAH
PEKERJAAN
MEKANIKAL &
ELEKTRIKAL
36
37 PEKERJAAN 49 Fri 16/09/22 Wed
SARANA days 23/11/22
38 Pekerjaan Sarana
dan Prasarana
39 Pekerjaan Pondasi 3 days Fri 16/09/22 Tue 20/09/22
IPAL
40 Pekerjaan Struktur 5 days Wed 21/09/22 Tue 27/09/22
Septictank
41 Pekerjaan Pos Jaga 18 days Wed 21/09/22 Fri 14/10/22
(2 unit)
42 Pekerjaan Power 17 days Wed 28/09/22 Thu 20/10/22
House ( Ruang
Panel dan Gardu
43 Pekerjaan Rumah 14 days Mon 17/10/22 Thu 03/11/22
Pompa dan GWT
44 Pekerjaan Halaman 28 days Mon 17/10/22 Wed 23/11/22
45 Pekerjaan Saluran 28 days Mon 17/10/22 Wed
Keliling Bangunan 23/11/22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS Proj
Summary Manual Summary Rollup Critical
Date: Thu 15/09/22
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 4
ID Task Task Name Duration Start Finish Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23
Mode 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19
46 Pekerjaan 14 days Fri 04/11/22 Wed
Halaman Parkir 23/11/22
47 SUB JUMLAH (B)
PEKERJAAN
SARANA
48
49 PEKERJAAN MESIN 34 days Fri 16/09/22 Wed
REFRIGERASI & 02/11/22
INSULATED
50
51 PENGADAAN 32 days Wed 16/11/22 Thu 29/12/22
PERLENGKAPAN
COLD STORAGE

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS Proj
Summary Manual Summary Rollup Critical
Date: Thu 15/09/22
Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress