Ch08'-Scheduling - Review and Homework
Ch08'-Scheduling - Review and Homework
SCHEDULING
Review & Homework
Review: Construction the Network AON-AOA
Practice 1: Construction the Network AON-AOA
Assignment 1: Construction the Network AON-AOA
Assigment 2
8-5
Assignment 3
ACTIVITY IMMEDIATE TIME (DAYS)
PREDECESSOR(S)
A _ 3
B A 4
C A 6
D B 6
E B 4
F C 4
G D 6
H E,F 8
Earliest Earliest
Start
ES Activity EF Finish
8-7
What the Critical Path Calculates
Earliest Start (ES) = the earliest time at which an activity can start
Calculated by a forward pass through the network diagram,
Calculated on the basis of the project’s start time and the duration the
preceding activity. If If an activity has multiple immediate predecessors:
ES= Max {EF of all immediate predecessors}
Earliest Finish (EF) = the earliest time by which an activity can be finished
Calculated by adding the activity’s duration estimate to the earliest start
time.
EF= ES + Duration estimate
8-8
What the Critical Path Calculates
Latest Finish (LF) = the latest time at which an activity has to finish and still allow
the project to be completed on time.
Calculated by a backward pass through the network diagram
Calculated on the basis of the project’s completion time and the duration for the
succeeding activities. If an activity is an immediate predecessor to more than one
activity
LF = Min {LS of all immediate following activities}
Latest Start (LS) = the latest time by which an activity can start and still allow the
project to be completed on time.
Calculated by subtracting the activity’s duration from the activity’s latest finish time
LS= LF – Duration estimate
8-9
Assignment 4
𝟐
𝟐
8-11
Calculating Uncertain Activity Times:
PERT Method
Assignment 5:
8-12
Calculating Uncertaint Activity Times:
PERT Method
Assignment 6:
8-13
Calculating PERT Method
Assignment 7:
8-14