PEMBAGIAN JOB BASE

Tgl : 27-September-22

NO. OUTPUT MC-0 STATUS PIC KETERANGAN


1 PEMELIHARAAN RUTIN JALAN B.IKHSAN
1.MC-0 P Proses
2.Shop Drawing X Risda&zaki Data Pacing sdang d proses, Stripmap penanganan

2 PEMELIHARAAN RUTIN KONDISI B.IKHSAN


1.MC-0 P
2.Shop Drawing X Risda&zaki Data Pacing sdang d proses, Stripmap penanganan

3 PEMELIHARAAN PREVENTIF RISDA


1.MC-0 P risda OK
2.Shop Drawing X risda Data ukur Blm Ada

4 REHABILITASI MINOR JALAN B. TARMIZI


1.MC-0 P b.tarmizi OK
2.Shop Drawing X Risda&zaki Data ukur Blm Ada

5 REHABILITASI MAYOR JALAN ZAKI


1.MC-0 P zaki OK
2.Shop Drawing P Risda&zaki Data Ukur Blm Semuanya

6 PENANGANAN DRAINASE B.IKHSAN


1.MC-0 P ikhsan OK
2.Shop Drawing P risda Proses

7 BAHU DI PERKERAS RISDA


1.MC-0 P risda OK
2.Shop Drawing X risda Data ukur Blm Ada

8 PEMELIHARAAN RUTIN JEMBATAN B. TARMIZI


1.MC-0 P b.tarmizi ACC
2.Shop Drawing X Risda&zaki Data ukur Blm Ada

9 REHABILITASI JEMBATAN ZAKI


1.MC-0 P zaki ACC
2.Shop Drawing P zaki Proses

10 PEMELIHARAAN BERKALA JEMBATAN B. TARMIZI


1.MC-0 P b.tarmizi ACC
2.Shop Drawing X Risda&zaki Data ukur Blm Ada

11 PELEBARAN JEMBATAN RISDA


1.MC-0 P risda OK
2.Shop Drawing P risda Data ukur Blm Ada

LEGENDA :

BELUM DI PROSES SAMA SEKALI


SEDANG PROSES
SELESAI