Professional Documents
Culture Documents
11 Eva
11 Eva
EVA
EVA Example
Schedule Variance
= EV – PV = $5,000 – $7,500 = - $2,500
Schedule Performance Index (SPI)
= EV/PV = $5,000 / $7,500 = .66
Cost Variance
= EV – AC = $5,000 - $9,000 = - $4,000
Cost Performance Index (CPI)
= EV/AC = $5,000 / $9,000 = .55
• Method #4
• EAC = BAC / CPI
• = $100,000 / 0.875
• = $114,285
• (Change Management for $14,285 funds request)
Problem 1
• You are a project manager of a project to develop a new
wireless feature. The feature is made up of the phases in the
table below. Each phase is planned to be completed one after
the other. Today is the end of Month 5
Task Duration Budget
Requirements 1 month $10,000
Architecture 1 month $10,000
Design 1 month $10,000
Code 2 months $ 20,000
Testing 1 month $10,000
Using the Project status chart below, calculate PV, EV, AC,
BAC, CV, SV, CPI, SPI, EAC, ETC, VAC.
PV 10,000+10,000+10,000+10,000+10,00 50,000
0
EV 10,000+10,000+10,000+5,000 35,000
AC 10,000+12,000+,12,500+7,000 41,500
BAC 10,000+10,000+10,000+20,000+10,00 60,000
0
CV 35,000-41,500 -6,500
CPI 35,000 / 41,500 0.84
SV 35,000 – 50,000 -15,000
SPI 35,000 / 50,000 0.70
EAC 29762+41500 71,262
ETC (60000-35000)/.84 29,762
VAC 60,000 – 71,262 -11,262
Problem 2
Hardware
Design
1 2 3 4 5
Requirements Architecture Chip Design Circuit Pack Testing
Design
Assume the following rates:
1. System Engineer: $20,000/month 1 Oscilloscope at $20,000
2. Architect: $20,000/month
3. Chip Designer: $ 30,000/month
4. Circuit Pack Designer: $ 30,000/month
5. Tester: $20,000/month
EAC (if the both SPI and CPI influence the project work) =
AC + [(BAC – EV) / (CPI x SPI)]
1.Schedule Performance Index (SPI) = EV/PV =
$13,000/$14,000 = 0.93 Since SPI is less than 1, this
indicates that the project is behind schedule
2.Cost Performance Index (CPI) = EV/AC =
$13,000/$15,000 = 0.87 Since CPI is less than 1, this
indicates that the project is over budget.
3.EAC = $15000 + [($22,000 – $13,000)/(0.93 X 0.87)] =
$26,123
4.VAC = BAC – EAC = $22,000 – $26,123 = -$4,123 The
project is experiencing a budget overrun of -$4,123.
Problem 2