Professional Documents
Culture Documents
Condensers
Test Code on
Performance
Steam Surface
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled wh
Date of Issuance: September 18, 1998
This document will be revised when the Society approves the issuance of the next
edition. There will be no addenda issued to ASMEPTC 12.2-1998.
Please Note: ASMEissues written replies to inquiries concerning interpretation of
technical aspects of this document. The interpretations are not part of the document.
PTC 12.2-1 998 is being issued with an automatic subscription service to the interpre-
tations that will be issued to it up to the publication of the next edition.
This code or standard was developed under procedures accredited as meeting the criteria for American
National Standards. The Standards Committee that approved the code or standard was balanced toassure
that individuals from competent and concerned interests have had an opportunity to participate. The
proposedcodeor standard was made available for public review and comment which provides an
opportunity for additional public input from industry, academia, regulatory agencies, and the public-
at-large.
ASME does not "approve," "rate," or "endorse" any item, construction, proprietary device, or activity.
ASME does not take any position with respect to the validity of anypatent rights asserted in connection
with any items mentioned i n this document, and does not undertake to insure anyone utilizing astandard
against liability for infringement of any applicable Letters Patent, nor assume any such liability. Users of
a code orstandard are expressly advised that determination of the validity of any such patent rights, and
the risk of infringement of such rights, is entirely their own responsibility.
Participation by.federaIagency representative(s) or person(s) affiliated with industry is not to beinterpre-
ted as government or industry endorsement of this code or standard.
ASME accepts responsibility for only those interpretations issued in accordarlce with governing ASME
procedures and policies which preclude.the issuance of interpretations by individual volunteers.
Copyright 0 1998 by
THE AMERICAN SOCIETY.OF MECHANICAL ENGINEERS
All RightsReserved
Printed in U.S.A.
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
FOREWORD
(This Foreword is not a part of ASME PTC 12.2-1998.)
When the work of revising the ASME Power Test Codes of 1915 was undertaken it was
decided to include a Committee to develop three separate test codes on Condensing
Apparatus, Feedwater Heaters, and Water Cooling Equipment. The resulting Test Code for
Steam-CondensingApparatus, after passing through the preliminary stagesin the procedure
prescribed by the Main committee, was printed in tentative form in the May 1924 issue
of Mechanical Engineering and was presented to the Society for discussion at a public
hearing held during the Spring Meeting in Cleveland in May 1924. At the December 1924
meeting of the PTC Supervisory Committee (now known as the Board on Performance
Codes), it was approved in its final revised formand on October 5, 1925, it was approved
and adopted by the Council as a standard practice of the Society.
Early in 1933 Committee No. 12 decided to completely revise the Test Code for Steam-
Condensing Apparatus. At the April 4, 1938, meeting of the PTC Supervisory committee,
this second version of the Code was approved and on July 15, 1938, it superseded the
previous one and was adopted as a standard practice of the Society by the Council.
With the reorganization ofPTC Committee No. 12 on Condensers, Feedwater Heaters,
and Deaerators in 1948, the main Power Test Codes Committee requested that the Test
Code for Steam-Condensing Apparatus be brought up to date. This third edition of the
Code wasapproved at the December 4,1953, meeting of the Power TestCodes Committee
and adopted by the Council as a standard practice of the Society on March 9, 1954.
In January 1970 the PTC Supervisory Committee requested the Test Code for Steam-
Condensing Apparatus be reviewed and updated. That fourth version of the Code was
approved by the Board on Performance Test Codes on May 7 2, 1981, and it became an
American National Standard in January 1983.
The Board on Performance Test Codes in 1988 directed the Code again be reviewed
to be certain it reflected current engineering practices. A new Code Committee was
organized in early 1989 containing members from a wide geographical area. It comprised
about equal numbers of manufacturing, user, and generalinterest members to ensure
balanced committee actions. The 1989 Committee was organized into four Subcommit-
tees - Guiding Principles, Test Procedures, Instruments and Methods, and Computation
of Results - to be sure each section of the Code revision would get attention, and the
work would be accomplished effectively.
Based on experience with the two previous versions of the Condenser Code, the reorga-
nized Committee determined to make this Code modern, accurate, practical, useful, and
cost effective. It also identified the objective of extending the Code to include performance
monitoring, because of the relatively large effectof operating condensers on plant genera-
tion and efficiency.
These ambitious 1989 goals translated into extensive revisions which triggered an almost
complete rewrite. The major areas were revised and the revision rationale of this latest
Code follow:
Instruments: To take advantage of the recent significantadvances in the field, instrumen-
tation recommendations were modernized.
Heat transfer: TO enlarge the condenser test schedule "window" while maintaining
accurate test results,the separate heat-transfer resistance method withthe latest correlations
was adopted.
Implementation: To clarify the Code rules and produce a virtually self-contained docu-
ment, techniques and instrumentation descriptions were written in an explicit and detailed
manner.
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled wh
Uncertainty determinations:To ensure proper applications of uncertainty analysis, all
the particulars of this somewhat daunting estimate (a very impofitant and now necessary
aspect of every test) are presented.
Data acquisition:To improve the condensertesteffectiveness, computerized data acqui- I
sition for the testing and data reduction is suggested; however, the Code is written so that ,
I
the BPTC on December 20, 1996. This Performance Test Code was also approved as an
American National Standard by the ANSI Board of Standards Review on February 20,
I
1998.
iv
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
PERSONNEL OF PERFORMANCE TEST COMMITTEE NO. 12.2
ON STEAM SURFACE CONDENSERS
(The following is the roster of the Committee at the time of approval of thisCode.)
OFFICERS
J. M. Burns, Chair
C. W. Almquist,Ph.D., Vice Chair
J. H. Karian, Secretary
COMMITTEEPERSONNEL
Charles W. Almquist,Ph.D., Principia ResearchCorp.
Frank S. Ambrogi, EcolaireCorp.
Larry J. Beal, PSI Energy
Robert J. Bell, HeatExchangerSystems,Inc.
John M. Burns, Stone & WebsterEngineeringCorp.
Roland L. Coit, Consultant
EugeneHernandez, Community Energy Alternatives
Jack H. Karian, ASME International
PhilipMarks, Graham Manufacturing Company,Inc.
Edward C. Saxon, Conco Systems,Inc.
James W. Thornton, Virginia Power
John L. Tsou, ElectricPower Research Institute
John G. Yost, ResourceManagementInternational,Inc.
V
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
BOARD ON PERFORMANCE TEST CODES
OFFICERS
D. R. Keyser, Chair
P. M. Gerhart, Vice Chair
W. 0. Hays, Secretary
COMMITTEE PERSONNEL
R. P. Allen R. S. Hecklinger R. R. Priestiey
C. W. Almquist R. W. Henry C. 6. Scharp
R. L. Bannister S. J. Korellis J. Siegmund
D. S. Beachler T. H. McCloskey J. A. Silvaggio
B. Bornstein J. W. Milton R. E. Sommerlad
J. M. Burns C. H. Mittendorf W. C. Steele
J. R. Friedman S. P. Nuspl J. C. Westcott
G. J. Gerber R. P. Perkins J. G. Yost
A. L. Plumley
vi
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
CONTENTS
...
Foreword . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ill
CommitteeRoster . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . V
Section
0 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1 Objectandscope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.1 Object . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.2 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.3 Uncertainty . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2 Definitions
and
Description of Terms . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.1 Symbols. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
2.2 Subscripts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.3 Superscripts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
2.4 Uncertainty Analysis Nomenclature . . . . . . . . . . . . . . . . . . . . . . . 8
3 Guiding Principles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
3.1 Purpose and Intent . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
3.2 TestPlanRequirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
3.3 Test Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
3.4 Allowable Deviations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
3.5 Method of Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
3.6 Preparation for Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
3.7 Condenser Isolation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
3.8 Non-Condensible Gas Load . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
3.9 Tubeside Blockage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
3.1 0 Tubeside Fouling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
3.11 DissolvedOxygen . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
3.1 2 Preliminary Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
3.1 3 Constancy of Test Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
3.14 Duration of Test Runs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
3.1 5 Test Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
3.1 6 Performance Test Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
4 Instrumentsand
Methods of Measurement. . . . . . . . . . . . . . . . . . . . . . 15
4.1 Purpose and Intent . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
4.2 Location of Test Points . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
4.3 Instrumentation and Methods of Measurement . . . . . . . . . . . . . . . 17
5 Computation of Results. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
5.1 Basic Heat Transfer Relations . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
5.2 Condenser Pressure Deviation Results Calculations . . . . . . . . . . . . 28
5.3 Deviation of Results Calculations for other Parameters . . . . . . . . . 32
5.4 UncertaintyAnalysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
6 Report of Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
6.1 Composition of Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
6.2 Report of Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
vii
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
Figures
Location of Condenser Test Points . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4.1 16
4.2
Basket Tip . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
4.3 Guide Plate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
4.4 Recommended Velocity Traverse Locations........................ 21
5.1 Multishell Multipressure Condenser . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
5.2 Single-Shell Multipressure Condenser . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
Tables
3.1 Allowable Deviations from Specified Test Conditions . . . . . . . . . . . . . . . . 10
3.2 Non-Condensible GasLoad (Air In-leakage) Limits . . . . . . . . . . . . . . . . . . 11
5.1 Student's t. Table for the 95% Confidence Level . . . . . . . . . . . . . . . . . . . . 33
Nonmandatory Appendices
Foreword . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
A Guideline: Flowcharts/Checklists. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
B Guideline: Automatic Data Acquisition . . . . . . . . . . . . . . . . . . . . . . . . 49
C Guideline: Performance Monitoring . . . . . . . . . . . . . . . . . . . . . . . . . . 51
D Guideline: Example Calculations ............................. 53
E Detail: Uncertainty Analysis for Condensing Pressure . . . . . . . . . . . . . 67
F Detail: Geothermal Surface Condensers ....................... 73
G Diagnostic: Air Binding. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
H Diagnostic: Non-Condensible Removal Equipment ............... 77
I Diagnostic: Tube Fouling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
1
Properties Physical of Seawater . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
K References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
I
I
viii
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAMSURFACECONDENSERS ASMEPTC 12.2-1998
CODE FOR
STEAM SURFACE CONDENSERS
SECTION 0 - INTRODUCTION
1
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAM SURFACE CONDENSERS ASMEPTC 12.2-1998
1.1 OBJECT 1.1.2 Test methods for determining the tube bundle
performance factor and degree of tube fouling, ex-
This Code provides standard directions and rules pressed as a cleanliness factor or fouling resistance,
for conductingandreportingperformancetests of are described.
water-cooled, steamsurfacecondensers,hereafter
referred to as condensers. The Code provides explicit
testprocedurestoyieldresults of the highestlevel 1.2 SCOPE
of accuracyconsistentwiththebestengineering
knowledge and practicecurrentlyavailable.The Therulesandinstructionsincluded in this Code
main purpose of this Code is toproviderulesfor areforthecondenserproper. If the scope of the
performingcondenser acceptance tests. TheCode testincludesanyorall of theauxiliaryapparatus
also provides guidelines for the routine performance associated with the condenser, it will be necessary
evaluation of condensers. torefertoother ASME PerformanceTestCodes.
The acceptance testcanbeusedtodetermine 1.2.1 The determination of special data or verifica-
compliance with contractual obligations and can be tion of guaranteeswhich are outside the scope of
incorporatedintocommercialagreements.Thetest this Codeshallbemadeonlywith the written
shall be considered an ASME Code Test only if the agreement of the parties to the test, especially regard-
test procedures comply with those detailed recom- ing methods of measurementandcomputation,
mendations in this Codeandthepretest and post whichshallbecompletelydescribed in thetest
test uncertainty analysis complies with Subsections report.
1.3 and 5.4.
1.3
UNCERTAINTY
1.1.1 This Codeprovidesrulesfordeterminingthe Theuncertainty of the projecteddesignpoint
performance of a condenserwithregardtothe pressure from the acceptance test, using the recom-
following: mended procedures and instrumentation,is expected
(a) the absolute pressure maintained by the con- tobelessthan0.1 in. Hg. A posttestuncertainty
denser, orits projected design pressure with an uncer- analysis is required. Due to the variety of methods
tainty of 20.12 in. Hg; and instruments, the test uncertainty for routine heat
(b) the extent of condensate subcooling withan transferperformancetests must beestimated by a
uncertainty of 20.2"F; specific uncertainty analysis, described in Subsection
(c) the amount of dissolved oxygen in the conden- 5.4, and the resulting uncertainty shall be less than
sate, with an uncertainty of 2 1 .O ppm; and 0.12 in. Hg in order to be considered a Code Test.
(d) the tubeside pressure drop, with an uncertainty The other test objective parameter uncertainties are
of ?2%. more directly measured and defined in para. 1.1 . l .
3
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAM SURFACE CONDENSERS ASME PTC 12.2-1998
Units
us.
Symbol Term Description Customary SI
A Effective
outside Total active external area of ft2 m2
tube
surface area all tubes in condenser, in-
cluding external air cooler if
used. Active area excludes
any
tubes that may be
plugged at time of test.
Cf Cleanliness
thermal
factor
Ratio
of
transrnit-
tance of usedtubes to that
of new or cleaned (to a like-
new state)tubes operating
under identical conditions.
Acceleration of Constant
used in Nusselt ft/sec2 m/S
gravity equation.
5
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS
Units
U.S.
Symbol Term Description Customary SI
I
h Heatcoef-
transfer Rate of heat transfer perunit Btulhr-ft2- W/m2K 1
i Variable Summation
In Natural logarithm
I
m Molecular weight Formula mass Ibllb-mol kg/kg- I
mol
6
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAMSURFACECONDENSERS ASMEPTC 12.2-1998
Units
us.
Symbol Term Description Customary SI
SCFM Air in-leakage Measured rate of standard air scf m -
(at 14.7 psiaand60°F) in-
leakage into condenser as
discharged from air-removal
system
U Heat transfer coef- Rate of heat transfer per unit Btulhr-ft2- W/m2K
ficient of surface areaand tempera- "F
ture difference. This quantity
is the fundamental measure
condenser
the
of per-
formance.
7
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS
2.3 SUPERSCRIPTS
Svmbol Descriotion
*
I
Value derived from the design
reference.
+ Measured value or calculated value at the
test conditions.
Test value corrected to the design reference
I
0
conditions.
8
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
STEAMSURFACECONDENSERS ASMEPTC 12.2-1998
9
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
ASME PTC 12.2-1998 SURFACE STEAM CONDENSERS
TABLE 3.1
ALLOWABLE DEVIATIONS FROM SPECIFIEDTEST CONDITIONS
Deviation
from Constancy
Specified Test of
Testing Parameter Conditions* Conditions
inlet-water temperature 210°F 22°F
heat load 25% 22%
cooling-water flow I 25% I 22%
*Refer to Subsection 3.1 3.
all the important events of this section should be themselves withall the apparatus connected with I
included in order to help the user follow the signifi- the condenser, and all piping involved. The instru- I
cant details associated with test preparation, organi- ments to be used and the methods to be employed i
zation, and execution. (Refer to Appendix A for in calibrating and checking instrumentsshall also I
guidance.) be agreed upon in1 advance of the test. All parties 1
to the test shall certify that the condensingequipment ~
only be obtained at certain times of the year. How- drainsshall be agreed upon priorto testing. Any
ever,the acceptance test shall be conducted as pertinent circuits, including makeupwater, that can ~
soon as the desired test conditions are obtainable. jeopardize theresults of the test, shall be isolated. i
I
Performance degradation that is not inherent to the
design or the fabrication of the condenser should
I
be noted, such as normal wear, abnormal operation, 3.8 NON-CONDENSIBLE GAS LOAD I
or inadequatepreservationprocedures. I
Excessive air in-leakage oftendegrades the con- I
denser performance and increases the concentration ~
Testingshall be performed under conditions of computation of the condenser heat transfer capabil-
constant inlet-water temperature,
heat
load, and ity, it must be within the limits set in Table 3.2. This
cooling-water flowwithin the limits specified in will ensure that the performance of the condenser
Table 3.1. has not been impaired and thedissolvedoxygen
10
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
STEAMSURFACECONDENSERS ASME PTC 12.2-1998
TABLE3.2
NON-CONDENSIBLE GAS LOAD (AIRIN-LEAKAGE) LIMITS
Total
Non-condensible
Steam
Exhaust
Number of Flow to Condenser
Gas load limit
Shells Condenser (Ib/hr) (SCFM)
11
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS
(e) determining thatthevariousparameters are may be useful for diagnostic purposes, are given in
within the limits in Table 3.1 Appendices F through I.
If mutually agreed upon, the preliminary run may Before conducting a condensertest, careful consid-
be declared an acceptance run, provided that it has eration must be @veri to the specific areas covered
complied with all therequirements of this Code. in this Section. Prior to testing, the parties involved
shall agree to:
(a) a test plan as; specified in Subsection 3.2;
3.13CONSTANCY OF TEST CONDITIONS (b) the plant operating conditions, including plant
load and cooling-,water flow rate, which must be
Any condition whose variation may affect the test
steady for the duration of the test;
results shall be made as constant as possible before
(c) the necessary condenser isolations, perSubsec-
the test run begins and shall be maintained through-
tion 3.7. This is important to assure that the condenser
out the run. It is desirable to observe and record
is handling only th'e flow for which it was designed;
all readings for a briefperiod afterthe unit has
(d) the inlet cooling-water temperature at which
attained steady-state conditions but before the formal
the test is to be conducted,this factor maylimit testing
readings are taken (see Table 3.1).
to only certain times of the year;
If inconsistencies are observed for a test run, the
(e) other operating principles as specified in this
run shall be rejected in whole or in part, and shall
Section;
be repeated if necessary to attain the object of
(f) the other types of instruments to be used, their
the test.
locations, and the methods of measuring those instru-
ments. Acceptable instrumentation practices are cov-
ered in Section 4.
3.14 DURATION O F TEST
RUNS
After steady-state conditions are achieved, a 1-hr 3.1 6.2 Heat Transfer Test. The purpose of the heat
data retrieval period is sufficient for a single test run. transfer test is to determine the overall heat transfer
Readings shall be taken at intervals not exceeding 5 coefficient (OHTC) of the condenser at test, design,
min. For a 1-hr test, the minimum number of readings guarantee, or otherspecifiedconditions; from the
for a particular parameter would be thirteen. OHTC,theabsolute pressure of thecondenserat
thedesign or other conditions can be established.
It will usually be impossible to conduct the tests at
3.15 TEST
SEQUENCE the exact conditions called for in the design, guaran-
tee, or other specified conditions.
Each test run should be conducted in accordance
Provided the deviations from nominal conditions
with a predetermined test plan. Such aschedule
are within the guid,elines given in Table 3.1, a Code
should provide sufficient time for conditions to be
condenser heattransfertest can still be performed.
stabilized between runs.
In this situation, the resultsfrom the test arecorrected
to design conditions using the procedures described
in Section 5. These corrections determine the ability
3.16PERFORMANCETESTOVERVIEW
of the apparatus to condense the required amount
3.16.1Introduction. The following items provide of steam and to maintain the nominal condenser
an overview of the four types of tests prescribed by pressureatdesign,guarantee, or other specified
this Code, including the general procedures which conditions. For aCodetestthese corrections are
shall be followed in conducting aCode-typecon- required to be properly applied and so certain param-
denser test, and the measurements required for each eters shall be carefully measured. Determining any
test. Frequent reference is made to relevant Sections two of thethree following conditions - cooling-
in this Code, particularly Section 4. water flow, condensertemperature rise, and con-
There are four types of test described by this denser heat load -- allows calculation of the third.
Code: (1) heat transfer test; (2) dissolved oxygen test; This would meet the requirements necessary to per-
(3) condensate subcooling test; and (4) condenser form a complete heat balance on the apparatus and
hydraulic pressure drop test. Any or all of these ultimately serve as the foundation for calculating an
tests may comprise a condenser test under this Code. OHTC.
Otherauxiliary tests, which are not considered to The corrections described in Section 5 arebased
be a part of the Code test program butwhich on a rational analysis of the governing heat transfer
12
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
RFACE STEAM CONDENSERS ASME PTC 12.2-1998
mechanisms, using a log-meantemperature differ- specified by PTC 6. [4] In this case, the cooling-
ence (LMTD) approach to determine an overall heat water flow rate is not required for the determination
transfer coefficient. Consequently, the following of heat load.
quantities must be measured for the heat transfer test. The cooling-water flow rate is also specified in
thedesign or guarantee conditions,and must be
held within the operational guidelines specified in
3.1
6.2.1
CondenserShellside
Pressure. The con- Table3.1.
denser shellside pressure is typically the basis for
the designorguarantee point. Condenserpressure 3.16.2.4CondenserFouling. The degree of foul-
is therefore a key measurement. The shellside satura- ing on the cooling-water side of the tubes (the
tion temperature, used in determination of the fouling factor) must be determined to correct the
OHTC, is determined from the condenser shellside measured results to design or guarantee conditions.
pressure. Acceptable instrumentation for the mea- A methodof determining the fouling factor based
surement of condenser pressure is described in para. on determination of the relative heat transfer coeffi-
4.3.1. cientsofcleanandas-found tube pairs distributed
throughout the tube bundle is described in para.
4.3.12.
3.16.4CondensateSubcooling. Condensatesub-
3.1 6.2.3 Cooling-Water Flow. The cooling-water cooling (condensatedepression) is the degree to
flow is required for several phases of theanalysis. which the condensate has been cooledbelow the
Unless a turbine test per PTC 6 [4] is performed saturationtemperature corresponding to themea-
concurrently, measurement of the cooling-water flow sured condenser shellside pressure. Condensate sub-
rate, together with the inlet and outlet temperatures, cooling must be measured if it is a design or guaran-
is the preferred method of determining the heat load tee point for the condenser, or if it i s of interest for
on thecondenser, which is required to determine general performance calculations. The condensate
the OHTC. Several methods for accurately determin- temperature is determined atthesame time as the
ing the cooling-water flow ratearegiven in para. heattransfer test, usingthe method given in para.
4.3.4. Choice ofan appropriate methodcan only 4.3.1 0.
be made after considering both the requirements of
the individual methods and thecharacteristics of 3.16.5Cooling-Water Pressure Drop. Toensure
the particular installation being tested. adequate performance of thecooling-water pumping
It is extremely important that an appropriate system, the pressure drop across the condenser
'method of condenser cooling-water flow measure- should be within design values. The condenser pres-
ment is chosen.Theheat load mayalso be deter- sure drop is measured from the inlet flange to the
minedby a full steam cycle energybalance,per- outlet flange of thecondenser. It i s recommended
formed in conjunction with a full turbine testas thatthepressure drop measurements be madeat
13
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS
14
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
STEAMSURFACECONDENSERS ASME PTC 12.2-1998
SECTION 4 - INSTRUMENTSANDMETHODS
OF MEASUREMENT
4.1 PURPOSE AND INTENT required by this Code may be included for reference
purposes by mutual agreement between the parties
ThisSectiondescribestheinstruments and the
to the test.
methods for their application which are required for
the condenserperformance test described in this
4.2.2 Single-Pressure
Surface
Condenser. Figure
Code.Referenceismade to existing standards and
4.1 shows the location of the test points in the
procedures although major requirements and consid-
condenser neck that are needed to obtain the per-
erations which are of particular relevance to con-
formance data required for a single-passsingle-
denser performance testing are summarized where
appropriate. Not all instruments or techniquesde- pressure surface condenser. The final location of all
scribed in this Section are applicable to every con- test points should be determined by mutual
denser test program. Consult the procedural descrip- agreement, taking into account the internal design
tions given in Section 3 to determine which of the condenser and external piping configuration,
instruments and methods are applicable. Where this both of which may result in stratification atthe
Code refers to NlST (National Institute of Standards measurementpoints. Test points with instruments
and Technology) standards and calibrations,those internal to the condenser,such as baskettipsand
of other equivalent national standards laboratories thermowells, should be located to avoid interference
maybe usedas appropriate forthe locale of the from condenser internal structural bracing and com-
testing. ponents. All waterbox test connections should be
Before proceeding to select, construct, install, cali- shop installed if the internal surfaces the of
brate, or operate instruments, relevant Sections of waterboxes require a protective coating or lining.
the PTC 19 Series of supplements on Instruments Field-installed test connections require field repair
and Apparatus 141, ASME MFC3M (to be superceded of the coating or lining.
by ASMEPTC 19.5 when it is published) [ l l ] , or
ASME Fluid Meters 171 should beconsulted for 4.2.3 MultipressureSurfaceCondenser. The per-
detailed instructions. formance test pointsand test point locations for
Achievement of the required accuracy for each multipass and multipressure surface condensers will
parametermeasured is the single most important be similar to those illustrated in Fig. 4.1 except for
criterion in selectionof an appropriate method of the following considerations:
measurement.ThisCodeshall not be construed as Single-shell multipressure condensers require addi-
preventing the use ofadvancedtechnologies or tional condenserpressuretest points above each
methods of measurement not described herein, pro- tube bundle in each of the multipressure condensing
vided that the accuracyrequirements of Appendix zones. The performanceof each zone can be closely
D are achieved by the alternative method. estimated by measuring the final outlet temperature
It is highly recommended that provisions for con- in accordance with para. 4.3.3 and proportioning
denser testing be incorporated into thedesignof the temperature rise of each zone using procedures
the facility at which the condenser is located. Back- described in Section 5.
fitting an existing system for the required measure- Multishell multipressurecondensers require addi-
mentscan be veryexpensive and time-consuming tional pressure and temperature test points to mea-
at best, and virtually impossible atworst. sure the inlet and outlet cooling-water pressure and
temperature for each of the multipressure condenser
shells. Stratification canpersist in theshortlength
4.2 LOCATION OF TEST POINTS
of the cooling-water crossover piping between multi-
4.2.1 General. Figure 4.1 illustrates the
general pressurecondensershells.Therefore,theaverage
location of the test points. Additional test points not temperature of the inlet cooling water to the interme-
15
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS ,
Condensate
level7
I
F = Flow measurement
T = Temperature
measurement 0 Perf.connection
test
W = Water
level
measurement DO = Dissolved
oxygen
measurement 0 Supplemental
test
connection
P = Pressure
measurement S = Salinity
measurement
16
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
STEAMSURFACECONDENSERS ASME PTC 12.2-1998
17
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
ASME PTC 12.2-1998 STEAM SURFACE CONDENSERS ~
Flow
t---12 in.-
7
> 0
I I
I 1
I I
12 in.
1
t
6 in.
6 in. --+
4-
) 0
I
18
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAMSURFACECONDENSERS ASME PTC 12.2-1998
19
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS
will not provide sufficient spatial resolution to meet frequency standard shall be conducted both before
the requirements of thisparagraph. and after the testing program.
Differential pressure measuringdevices used for
4.3.4 Cooling-Water Flow. Cooling-water flow de-
Pitot-statictypemeasurements shall be calibrated
termination is required for interpretation of waterside
before and after thll test to an accuracy of atleast
pressure drop data, for computation of tubewater
50.25% of the maximum differential pressure ex-
velocity, and for determination of the heat load on
pected. Mechanical gauges, manometers, and elec-
the condenser (condenserduty) by the direct method.
tronic differential pressuretransducersareaccept-
The following methods of cooling-water flow mea-
able, so long as thestated accuracy requirements
surement in the large conduits typically found in
aremet.
a central generatingstation steamcondenserare
The velocity probe should be inspectedfor damage
acceptable for the purposes of this Codeand are
periodicallyduring testing. If anydamage to the
capable of providing an uncertainty of +1-2% when
probe is noted, all measurementsmadesincethe
properly implemented:
previous inspection shall be retaken with another
(a) velocity traverse;
calibrated probe. For this reason, it is recommended
(b) tracer dilution;
that atleast two calibrated probes be available for
(c) differential producer;
testing.
(d) ultrasonic time-of-travel;
A velocity probe may experience vibration under
(e) energy balance.
certain flow conditions. For non-LDV type probes,
Considerations concerning the application of these
if such vibration is detected,the cause of the vibration
methods to steamcondensers arecovered in this
shall be corrected. For non-LDV probes,measure-
Section. The cooling-water flow determination
ments takenunder conditions of significant probe
should be made concurrently with the heattrans-
vibration shall be considered invalid. Indicators of
fer test.
probe vibration include a sharpchange (usually a
4.3.4.1 VelocityTraverseMethods. Velocity tra- rise) in the probe differential when the probe position
verse methods are generally most applicable to the is changed slightly, physical vibration of exposed
measurement of flow in large conduits in which the part of the probe, or a relatively suddenonset of
size of the probe will not affect the measured flow. a high level of periodic pressurepulsations.
Fluid Meters, Chapter 1-7, describesthegeneral At least 10 diameters of straight,unobstructed
considerations for acceptable velocity traverse meth- piping shall exist upstream and 5 diameters down-
ods. [7] For the
purposes of PTC 12.2 [4], the stream of themeasuringstation.Traverseshall be
Fechheimer and KeiI Pitot-static type probes and the taken along at least three equally spaced diameters.
insertion-type fiber-optic laser Doppler velocimeter Thetraverse locations shall follow theChebyshef
(LDV) are explicitly recommended, although other weighing scheme described in Chapter 1-7 of Nuid
instruments which meet uncertainty requirements Meters 171, with a minimum often points along
may be used. If theFechheimer probe is used, it eachdiameter.An example of acceptable traverse
is recommended that thedirectional-sensing capabil- points is shown in Fig. 4.4.
ities of the probe beused to determine the local
flow angle, and that this flow angle be incorporated 4.3.4.2 TracerDilutionMethods. Tracer dilution
into the flow determination. If the LDV probe is methods are particularly applicable to the measure-
used, it should be oriented so that it picks up the ment of flow in large conduits. Although no formal
component of flow parallel to the pipe axis. standard on their use currently exists, the method
Pitot-static and other non-LDV type probesshall is discussed in Chapter 1-9 of Nuid Meters [7] under
be inspected and calibrated before and after the test the heading Methodof Mixtures. If this technique
by a hydraulic laboratory to an uncertainty of +1% is used, theparties to the test shall agree upon
using standards traceable to the NIST. The post-test the details of implementation, provided thatthe
calibration requirement may be waived if inspection guidelines outlined hereare followed.
reveals no damage to the probe. A deviation of A key requirement of the tracer is that it exhibit
more than 1% betweenthepretest and post-test minimal tendency to adsorb onto organic and inor-
calibrations shall be cause for investigation. Calibra- ganic surfaces. Recent applications of this technique
tions shall cover therangeofReynoldsnumbers havemostoftenused Rhodamine WT fluorescing
(based on probe diameter) expected in the velocity dye as the tracer,;althoughany dye which can be
measurements. For an LDV probe, calibration of the shown to be conservative (not subject to adsorption
LDV processingelectronics against an NIST-traceable or other loss mechanisms) is acceptable.The dye
20
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAMSURFACECONDENSERS ASMEPTC 12.2-1 998
I
Chebyshef
Distribution
I Relative radius I
I (a)0.2891 I
I (b) 0.5592 I
I (c) 0.7071
I
I (d) 0.8290
I
I (e) 0.9572
I
All points weighed equally
concentration is measured using a calibrated preci- into the flow before the sampling point should be
sion fluorometer. General considerations relating to shut off before the test. In the case of a closed-
the application of Rhodamine WT or similar tracers cycle system, a prolonged period of no treatment
may be found in Flow Measurements in Sanitary may be required to purge the cooling system of
Sewers. [8]In addition to the general considerations treatmentchemicals.Chlorine, in particular, may
outlined in Fluid Meters 171 and Flow Measurements affect Rhodamine dyes.
in Sanitary Sewers [8]the precautions discussed Complete mixing of the tracer with the flow must
below should beobserved. be achieved for an accurate flow measurement. As
The flow should be free of any chemicals or silt a general guideline, atleast 100 diameters of pipe
concentrations which may affect the detectability of shouldexist between the injection and sampling
the tracer. Chemical treatment which is introduced points, although this distance may be substantially
21
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS
reduced by the presence of flow disturbances such pling temperatures and correcting the readings to a
as pumps, elbows, valves, or orifices. The presence common temperature. For Rhodamine WT dye, the
of complete mixing atthe sampling cross-section temperaturecorrectionsmay be found from the
shall be determined by traverse before testing by following equation (Smart and Laidlaw [9]):
withdrawing samplesat nine equally spaced points
along 1 diameter at the sampling cross-section and c$, = , C ~ - O . O Z ~ ( T ~T- )
verifying that the concentrations at all points agree
to within 21Y0.This verification shall be conducted
within 225% of the flow at which the condenser where f, = fluorescenceatstandardtemperature
tests are to be run. T , and FB is the measured fluorescence at tempera-
Injection ofdyemaybe through a manifold or ture T.
at a single point in the flow, so long as complete The tracer injection apparatus shall be calibrated
mixing of the dye at the sampling point is verified for injection flow tlefore and after the test program.
as describedabove. The uncertainty of the injection rate shall be 20.5%
The dye concentration must reach steady state at or better.
the sampling point before data to be used in the The fluorometer (or other concentration measure-
flow determination aretaken. This determination ment instrument) shall be calibrated before and after
shall be made by continuously monitoring the tracer the test program. Calibrations shall be performed at
concentration at the sampling cross-section. a minimum ofthree concentrations bracketing the
Caremust be taken to ensure that no flow is expected dye concentration. Instrument uncertainty
introduced or removed between the injection and shall be no more than 2 1 Yo.
sampling stations. It is not sufficient to simply ac- Periodic field calibration of the tracer injection
count for these flows, since a small inflow or outflow apparatus and thefluorometer during testing is highly
can lead to a large measurement error. An exception recommended to ensuredata integrity.
is that any outflows between the section at which 4.3.4.3 DifferentialProducers. Differential pro-
complete mixing has been verified and the sampling ducers which are accepted by this Code include
station will not affect the measured flow. the orifice plate,the flow nozzle, and the venturi
Precautions must be taken if the possibility exists meter.Thesedevices will be most applicable to
that the injected dye may recirculate to the injection smaller condensers, i.e., those with inlet piping less
site. In the case of a time-varying flow, such as a than about 3 ft in diameter.
tidally influenced estuary, it is necessary to demon- The installation ofthe differential producer shall
strate, by measurement before the start of the test, follow the requirements of fluid Meters [7] or ASME
that no dye recirculation exists. In the case of MFC-3M [ l l ] particularly with regard to the length
a closed-cycle cooling system, it is necessary to of upstreamanddownstream piping, construction
demonstrate, by measurement, that any previously and finish ofthe flow element, and location and
injected dye is thoroughly mixed throughout the finish of thepiezometer taps. The flow element
cooling-water system before a testcan begin. As a together with any flow conditioning devices immedi-
rule, about five cycle-recirculation times are required ately upstreamofthe element shall be calibrated
for complete mixingto be achieved (the cycle- as a unit before and after the testingby an hydraulic
recirculation time is the total volume of water in laboratory to an uncertainty of 5 1YO or better using
the cooling-water system divided by the cooling- NIST-traceablemethods.Thepost-test calibration
water flow). requirement may be waived if a post-test inspection
It is desirable for bothtracer injection and sampling reveals no damage or deposits that would affect
to be on either the inlet-water or the outlet-water flow meter accuracy. A deviation of more than 1%
side of the condenser. In this case, either continuous between the pretest and post-test calibrations shall
sampling or grab samples are acceptable. If injection be cause for investigation.
and sampling occur on opposite sides of the con-
denser, extreme care must be taken to account for 4.3.4.4 Ultrasonic Time-of-Travel. Inall con-
temperature effects. Grab samplesmay be brought duits, particularly large ones, flow may be measured
to a common temperature before analysis.This is using the multiple-path, time-of-travel type ultrasonic
the preferred method. In the case of a continuous flow measurement method. The provisions given in
sampling system, temperature compensation can be PTC 18 141 underthe heading Acoustic Method
accomplished by measuring the injection and sam- shall govern the application of this method. Several
22
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAM SURFACE CONDENSERS ASME PTC 12.2-1998
significant features are summarized here. A minimum suregauge is of the proper diameter and is sloped
of four parallel chordal paths shall be provided, continuously downward from the gauge to the ori-
regardless of the size of the conduit. The metering fice, to avoid accumulation of water. Gaugepressure
sectionshall be preceded by atleast 10 diameters and temperature of the discharge shall be measured
and followed by atleast 3 diametersofstraight either upstream or downstream of the orifice plate.
pipe. The time-of-travel instrumentation shall be The differential pressure instrument, static pressure
tested at zero flow before and after thetest to ensure gauge, and the temperature measuring device shall
proper and accurate operation. be calibrated before and after the tests. The differen-
Because this method may be adverselyaffected tial pressure instrument attached to the orifice shall
by the presence of silt and other particulates or air be calibrated to an uncertainty of +1% of the
bubbles in the flow, it should be verified thatthe expected orifice differential. The static pressure de-
sourcewater is suitably clean before the metering vice shall be calibrated to an uncertainty of 2 1 psi.
system is installed. The temperature measuring device shall becalibrated
Since ultrasonic time-of-travel systemsare rela- to an uncertainty of 2 1 OF.
tively difficult and expensive to install, it is recom- The flow shall be determined according to the
mended that provision for its installation in the equations for gas flow through an orifice as given
cooling-water piping be made during designand in Part 11-111 of PTC 19.5 [4] or ASME MFC-3M.
construction of the cooling system. [l 11 Gas properties,such as theexpansionfactor,
density, and viscosity, shall be determined assuming
4.3.4.5EnergyBalanceMethods. In the energy
thatthe orifice flow consists of saturated air. For
balance method, an energy balance on the turbine-
convenience, simplified equations yielding sufficient
generator cycle is performed in order to determine
accuracy for purposes of thisparagraph are given
the rate at which heat is rejected to the condenser
in Appendix H.
(condenser duty) in the low-pressure exhaust steam.
As described in para. 3.16.2, cooling-water flow 4.3.6 Hotwell Level. Thecondenser hotwell shall
can then be determined from the condenserduty be provided with a sight glass, graduated in at least
and thedifferencebetween the inlet and outlet 1-in. increments. The level of water in the hotwell
waterbox temperatures. One advantage of this shall be monitored and remain within design limits
method is thatthecondenser duty is determined for the duration of the test.
directly.
Determination of the condenser duty by the energy 4.3.7 Waterbox Level. Waterbox level shallbe-
balance methodshallbe performed according the monitored throughoutthe tests to ensure that all
applicable sections of PTC 6 [41 for thetesting of waterboxes are kept full. A means for verifying that
steamturbines.Because of the complexity of this the condenser waterboxes are full of water should
test, it i s recommended that the condenser be tested be used during thetest period.
at the same time as the steam turbine. The overall 4.3.8Waterbox Differential Pressures. Differential
uncertainty of the condenser duty measurement will pressuregaugesshall be provided to measurethe
have to be determined for eachcasebased on the pressure drop between the inlet and outlet waterbox
cycles,procedures, and instrumentation used. nozzles. There shall beat least one differential gauge
4.3.5
Non-condensible Flow. Non-condensible for each parallel water circuit in the condenser. The
flow shall be measured by methods that have been gauges shall be calibrated before and after the test
shown to be accurate.This Code recommendsthe to +1% of the maximum expected differential. Me-
use of an orifice plate located ator near the discharge chanical gaugesor electronic differential pressure
of the evacuating apparatus. The orifice plate shall gauges are acceptable. Mercury manometers are not
meet the specifications described in ASME-MFC3M recommended due to the operational and environ-
[ l l ] (see alsoSubsection4.1) or PTC 19.5. [4] mental hazards posed should the mercury be inad-
Provided that all specified installation criteria are vertently blown from themanometer.
followed, no calibration of the orifice meter is re-
4.3.9
Dissolved
Oxygen
quired. Particular attention should be paid to ensur-
ing that adequate lengths of straight pipe upstream 4.3.9.1General. This method describesthemea-
and downstream of the orifice areavailable,that surement of the dissolved oxygen(DO)concentration
the pressure taps are properly located and finished, of the condensate. Prior to conducting the measure-
and that the pressure piping to the differential pres- ments described in this Section, the conditions for
23
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS
testing in accordance with Subsection3.1 1 ofthis 4.3.1 0 Condensate Temperature. Condensate tem-
Code must be achieved. perature measurements shall be made in accordance
with the general procedures described in para. 4.3.2.
4.3.9.2SampleExtraction. Sampling of the con- The thermowells slhould be located upstream of the
densate for DO shall be performed by extracting condensatepump.
condensate from thecondensate outlet piping as
close as possible to the hotwellbut prior to the 4.3.1 1 Saline/Bra!ckish Water Concentration. Sa-
condensatepump, and priorto addition of any linity measurements shall be made by using Method !
oxygen scavenging chemicals (see Fig. 4.1). Extrac- 2520 for “Salinity” from Standard Methods for the I
tion shall be made using a pump. Caremust be Examination of Water and Wastewater. [61
I
taken to avoid any airingress in thesample line
Tube
4.3.1
Bundle
2 Fouling
(Cleanliness) I
from the hotwell outlet piping to the pump. Samples
shall be measured in each hotwell outlet which is 4.3.12.1Introdluction. ThisCoderequiresade- I
The sample nozzle should extend into the conden- Themeasurement is necessary in order to adjust
sate outletpiping 4 in. or 25% of the pipe diameter, thecondenser overall heattransfer coefficient test ,
whichever is less. Metal tubing shallbe used to results to design or guarantee conditions. The fouling
connect the sample nozzle to the DO probe, and test consists of a measurement of the outlet tempera- ~
to connect the DO probe to thesampling pump. tures of sets of two adjacent tubes. One of the tubes
The pump effluent may be routed back to the of each set remain!; in the as-found fouled condition
condenser under vacuum, in order to reducethe while the neighboring tube has either been cleaned
pump head pressure. orreplaced with a new tube. As required, the
condenserhas justhadageneral cleaning. Other-
4.3.9.3SampleConditioning. Samples for con- wise, the tube pair experience identical heat transfer
tinuous flow oxygen analyzersshould be at flow rates
conditions, i.e.,steampressures, cooling-water flow
and temperatures recommended by theinstrument rates, and velocities. The outlet temperature measure-
manufacturers. Flow and temperature shall be held ments provide a comparison of the heat transfer
constant during the tests.
rates of the tube pairs, and, consequently, the bundle
If sample tubing is used to transport the sample fouling resistance.
to aremote location, the tubing shall be sized to I
24
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAMSURFACECONDENSERS ASMEPTC 12.2-1998
4.3.1 2.4 Outlet Temperature Installation. A tem- (c) Attachment of asuitable minimal blockage fix-
perature sensorshall be installed attheoutletsof ture into the tube interior that holds the sensor is also
each of the tubes in a mannerthatensures tube permitted if it can be demonstrated the total added
blockage is minimized and an accuratedischarge blockage is less than 5% of theinternal tube flow area.
temperature is measured.The installation shall be 4.3.1 2.5 Tube Temperature Rises. Tube tempera-
sufficiently rugged and suitably waterproofed to with- ture rises for the fouling tests shall be measured in
stand the hydraulic forces and temperatures of the general accordance with theproceduresdescribed
discharged cooling water.Thetemperaturesensor in this section. RTDs or thermocouples may be used,
lead wirefrom thesampledtubesshallberouted provided that the uncertainty of thetemperature
and secured between thetubeholes on the outlet measurement systemis at most 50.1 O F . If thermocou-
tube sheet.Theyshall be bundled andfed out plesare
used, it is recommended thata direct
through a new or existing waterbox penetration to differential temperature measurementsetup be used.
thereadout. If RTDsareused, it is highly recommendedthat
In the case of two-pass or multipressure condensers the pairs of RTDs which will be used on the moni-
in separateshells, tube pairs located in the bundle tored tubes be calibrated together, in order to mini-
subsequent to the first shall have an inlet temperature mize the effect of any bias errors in the calibration
on the determination of the temperature difference
measurement similar to that described for the outlet
between thepaired RTDs. Provision shall be made for
sensor.
calibration of the temperature measurement devices
Since the variety of installation situations will be
before and after the fouling test, over the expected
numerous, only generalguidanceon affixing the range of temperature differences and within 5°F of
sensor to the tube sheet can be provided, as follows. the expected inlet-water temperature. Following the
(a) If an outlet tube stub exists, plastic collars can fouling test, all instrumented tubes shall be inspected
be utilized as shown in Appendix G. to ensure that theyare clear and have not been
(b) Direct attachment to the tubesheet is permissi- influenced by blockageorany other factor (other
ble as long as the sensor extends into the flow. thantube fouling) which mayaffectthe results.
25
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
STEAM SURFACE .CONDENSERS ASMEPTC 12.2-1998
5.1
BASIC
HEAT
TRANSFER RELATIONS 5.1.3
Tubewall
Resistance.
This Section defines all the computations required
to obtain results from the various types of condenser (5.1.4)
testsaddressed in theCode. For both single-pass
and two-passcondensers,these include the heat
transfercoefficients,adjustments to design condi- and
tions, fouling resistance, subcooling, condensate dis-
solved oxygen, tubeside pressure drop, non-conden-
(5.1.5)
sible gas flow, and measurementuncertainty. Though
thebasicequationsare the same, multipressure
condenser performance assessments are slightly dif- for metric units.
ferent as is described in para. 5.2.8. Note that when
5.1.4TubesideResistance. The tubesidethermal
the complete equationsare given, U.S. Customary
resistance calculation is taken from Rabas and
Units areassumed.
Crane. [ I ]
5.1.1 Condenser Heat Load. Thecondenserheat
load shall be computed according to the following
equation: [
R; = .0158
k+
-'
- (Re+).835(Pr+).462
D;
] (5.1.6)
5.1.2 Overall Heat Transfer Coefficient. The over- R' = 0.0451 ( k + 0.538
p+ 0.373
* ,,+0.835 * c+0.482
P
) (5.1.7)
u+ = Q+ (5.1.2) where
A, * LMTD+
W+
v+ = (5.1.8)
where
27
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
ASMEPTC 12.2-1998 STEAMSURFACECONDENSERS
RT = (5.2.3)
1 1
p~ 0.373
0.045 1 p0.538 * p* 0.835 * 'c+P 0.482
where
5.1.6 ShellsideResistance. The shellside resistance
at the test conditions is determined by difference
as follows:
1
R: = -- R;- R;($) - R; (5.1.1 2) Circulating water fluid propertiesareevaluatedat ,
U+
the bulk water temperature, TB, which is defined as
28
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAMSURFACECONDENSERS ASMEPTC 12.2-1998
(5)+
1
value to the design condition, some formulation is uo = (5.2.15)
necessary to correct for the difference in condensate R& + R: RF + RP
film temperature between design condition and test
condition. Because this requires an adjustment over
a limited range of conditions, rather thana prediction 5.2.6
Adjusted
Test
CondenserSteamPressure.
of an absolute value of the shellside resistance, very The test condenser steam pressure, which is adjusted
precise predictions are not required.TheNusselt to thedesignreference conditions, i s determined
equation used herein provides for film condensation using the following procedure:
on the outside of horizontal tube bundles,and i s
expressed as follows:
Uo * A*
NTUO = -
c,: * w*
(5.2.1 6)
I ,113
(5.2.9)
N
(5.2.1 7)
Noting that
Theadjustedsteampressure, f'z,
corresponding to
the saturation steam temperature, Tg, as calculated
fromthe above, is deteimined from ASME Steam
(5.2.1 0 )
Tables. [ 2 ]
5.2.7Evaluation of Results/Acceptance Criterion.
then The difference between the test adjusted and design
referencesteampressures is evaluated as follows:
h*
RP = R - j * L (5.2.1 1)
h:
Ifthe pressure difference is greater than or equal
to zero, the condenser performance is satisfactory
Combining equations 5.2.9 and 5.2.1 1, and considered acceptable. If the pressure difference
29
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
ASME PTC 12.2-1998 STEAMSURFACECONDENSERS
Tz2 TY 1
Turbine
- --(&
l-x1
i s less than zero,thecondenser performance is pump turbine, then thatestimated value shallbe I
worse than design and is considered unacceptable. added to the compartment heat load. I
For multipressure condensers the cooling-water I
5.2.8 Multipressure
Condensers. Multipressure
temperature between compartments cannot be mea- I
condenser performance is assessed separately for
sureddue to temperature stratification or inaccessi- !
each pressure compartment. There are two types of
bility. The temperature canbe estimated by assuming ;
multipressure condensers: the multishell multipres-
sure condenser (Fig. 5.1) and the single-shell multi-
that the temperature rise is proportional to the heat i
load in eachcompartment.The calculation proce-
pressurecondenser(Fig. 5.2).
~
dure is as follows: I
I
30
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
STEAM SURFACE CONDENSERS ASME PTC 12.2-1998
where Q = 0%+ Qy + Qz
AT, = (At)(%);
Atti (measured) = ATtx,; + ATtY,; + ATt,,,;
= (At,,;)(%)
31
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
ASME PTC 12.2-1998 STEAMSURFACECONDENSERS
Rr,x,i = -
( Ts,x - Tl
Ts,x - %2,i
1
) - In ( Ts,x-T1
T,X - Tc,2,i
j If the calculated coindensate subcooling at test condi- 1
tion is less than or equal to design value, this aspect i
of the condenser performance is satisfactoryand 1
considered acceptable. If it is greater than the design I
value, the condenser performance is worsethan
designand is consideredunacceptable.
Rf,y,i (
(A)[ (
= wcp In TS,Y - Tt2,;)-1 In TS,” - T c , 2 , j j 5.3.3 DissolvedOxygenCalculationsAcceptance
Criterion. The dissolved oxygen test result shall be
T,, - %3,i T,, - TC,3,i determined by averaging the measureddissolved I
oxygenresultsat the specified time intervalsfor
eachcondenser outlet pipe. If the averagedresult
is greater than the design value for any condensate
outlet dissolved oxygen measurement, the condenser ,
performance i s worse than design and is considered ,
unacceptable.
I
Calculation. The condenserpressure deviation results in Subsection 1.3,an estimate of the uncertainty ~
calculation for each compartment is the same as in the testresults attributable to testmeasurement j
the single pressure condenser,as outlined in Subsec- uncertainties must be performed as part of the test i
tion 5.2. The cooling-water temperaturebetween calculations. Thisluncertaintyanalysis shall beper- !
compartments shall be estimatedusing the same formed in accordance with ASME PTC 19.1. [41
method as outlined in para.5.2.8.1. The purpose of this Subsection is to provide the
procedures to be used in propagating the individual
test measurement uncertainty terms into a test result I
FOR OTHERPARAMETERS
5.4.1 Uncertainty in TestAdjustedSteamPressure.
5.3.1TubesidePressure Drop DeviationCalcula- An estimate of the uncertainty in the teststeam
tions Acceptance Criterion. The test measured tube- pressure, adjusted to the design reference conditions,
side pressuredrop is adjusted for differences between is calculated as follows:
the test and designreference water-flow rates as
follows:
1 .a
A e = APT($) (5.3.1)
and
32
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
RFACE STEAM 12.2-1998
TABLE 5.1
STUDENT’S f, TABLE FOR THE 95% CONFIDENCE LEVEL
Degrees Degrees Degrees
of of of
Freedom f Freedom f Freedom t
1 12.706 11 2.201 21 2.080
4.303 2 12 2.1 79 22 2.074
3.1 3 82 13 2.1 60 23 2.069
4 2.776 14 45 2.1 24 2.064
2.571 5 15 2.131 25 2.060
2.447 6 16 2.1 20 26 2.056
2.365 7 17 2.1 10 27 2.052
2.306 8 18 2.1 01 28 2.048
2.262 9 19 2.093 29 2.045
10 2.228 20 2.086 30 or 2.000
more
GENERAL NOTE:
Table gives values of t such that from -t to + t the area included is 95%.
SF$ = (OqSq:)’ + (0&L+)’ + ( 0 q S q Y input test parameters. The final result referred to in
the preceding sentence is the Codetest objective
being considered, i.e., the designreference steam
+ (@TtsJ$)2
+ (@J;sT;)2 + (@J;,&;,r)’ (5.4.3) pressure, subcooling, dissolved oxygen, or tubeside
pressure drop. The ratio of the change in the per-
+ (@rt,SJQ2 + (@T;,cSr~,c)2
+ (@r~,,Sr~,,)’ turbed parameter to the change in the output is the
sensitivity factor for that particular parameter.
The methodology and procedures for estimating the Sensitivity factors can also be obtainedanalytically
bias limits and calculating the precision indices for by partial differentiation of theequations used in
each of the independent measurementparameters computing the results. The equations to be used in
are provided in ASME PTC 19.1 [41 and are therefore the computation of each of thesensitivityfactors
not repeatedhere.Alsonote that correlated bias follow. In deriving these sensitivity factor equations,
analysis is beyondthe scope of thecurrentCode. it is assumed thatthe error in the calculated fluid
Student’s t factor, t,,, is defined in PTC 19.1 141 and steam properties (heat capacity, density, viscos-
and i s a function of the degrees offreedom (i.e., ity, etc.) due to errors in the measurement parameters
one less than the number of observations taken for aresmall, when compared to theeffect of these
a given measuredparameter). A table of t factors measurement parameters on the overall test uncer-
is given in Table 5.1. If the number of observations tainty. Accordingly, these sensitivity factors neglect
is greater than 30, the t factor can be taken as 2.0. fluid property erroreffects.
The t factor is used to convert standard deviations Sensitivity Factor for Steam Flow Rate:
to 95% confidence intervals.
5.4.2 Sensitivity Factors. The sensitivity factors (01,
used in the above, can be determined by either of
the following techniques.
The central difference method can be employed
with separate perturbations of the individual instru- (5.4.4)
ment uncertainties. That is, using the data reduction
proceduresandequationsgiven previously in this
Section, compute the averagetestresult from the
averagetestdata.Then,usingthesameequations,
systematically compute the change in the final test
resultcaused by a smallchange in each of the where
33
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
ASMEPTC 12.2-1998 STEAMSURFACE CONDENSERS
xi LMTDt; - xi
LMTD;,;
* i= 1 i = l
where
(5.4.8)
(5.4.9) *i
i = l
34
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
STEAMSURFACECONDENSERS ASMEPTC 12.2-1998
A DO
(5.4.1 9)
(5.4.20)
35
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAMSURFACECONDENSERS ASME PTC 12.2-1998
37
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
ASME PTC 12.2-1998 STEAMSURFACECONDENSERS
(b) List of Instrumentation. This list shall include ments made ateach point in each circulating-water j
all instruments used in the tests, and shall include: conduit.
(7) manufacturer
(2) model number 6.2.6CondensateTemperature. Temperaturemea- i
(3) serial number surements made at eachpoint in each active conden-
(4) operating settings sate outlet conduit.
(5) claimed accuracy 6.2.7
Cooling-Walter Flow
(6) calibration coefficients
(a) Velocity traverse I
(c) List of personnel. All personnel who substan-
Velocities measured at each point in the velocity tra-
tively participated in the planning, execution, analy- verse. I
sis, or reporting of the test shall be listed along with (b) Acoustic I
their organizational affiliations and functionin the Individual path velocities 1
testing. Average flow velocity I
(d) Uncertainty analysis sample computation. This (c) Dye dilution I
sample calculation should be included for one run,
water
sample Temperature
of 1
and shall be presented in sufficient detail thatthe Background fluorescence
reader can repeat the calculations for the other test Fluorescence of standard
runs. Fluorescence of circulating water
6.1.11Distribution of Data. The following infor- (d) Differential producer
mation shall be made available to all parties to the Differential pressurle across meter I
,
I
I
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
STEAM SURFACE CONDENSERS ASMEPTC 12.2-1998
39
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
STEAM SURFACE CONDENSERS ASMEPTC 12.2-1 998
41
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
NONMANDATORY APPENDIX A - GUIDELINE:
FLOWCHARTSKHECKLISTS
(This Appendix is not apart of PTC 12.2 and is included for information purposesonly.)
43
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
44
FIG. A.l
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
TEST PLAN CHECKLIST (PTC 12.2)
Determine the overall scope of the test. Evaluate the specific parameters that need to be tested.
Select the most cost-effective instruments and/or methodsto measure all of the necessary param-
eters.
Perform a pretest uncertainty analysis regarding the parametersto be measured.
Install instruments in a sensible order. Begin with the pressureinstruments.Thesemust all be
calibrated at their respective locations to compensate for environmental changes.
All temperature instruments mustbe calibrated prior to installation, including any extension cable
associated with energized or voltage-producing sensors.
Install all temperature instruments in a logical order. Run extension wire or cable back to data-
logging device (where appropriate).
Check logging device for operation, including a continuity check on all the test parameters.
inspect installation and assure that no open circuits and/or faulty ground loops exist.
When all channels are properly working (data logger use only) begin pressure calibration.
At this point check all local instruments for proper operation;calibrate where appropriate (thermo-
couples, gages, transducers, etc.).
Make certain that all calibrations are clearly recorded and traceable to an accepted standard.
After calibrating, check for measurementfeasibilityby loggingall pressures, flows, and temperatures
at the operational conditions.
Correct any problems with instruments, loggers, and associated hardware.
Conduct a preliminary test as close to the agreed-upon operational requirements as possible. (1
hr max) Check all average values for feasibility.
If all equipment functions correctly prepare forthe performance test. Coordinate all efforts through
the operating department and the designated parties.
Make certain that any cycle isolation that needs doing is taken care of prior to starting.
If a separate cooling-water flow test is to be conducted simultaneously, coordinate with all testing
parties.
Consider any special cycle isolation necessary to conduct concurrent tests.
Prepare a test schedulewith alltestindoperating parties. Include start/stop times,unit load or steam
flow, operating requirements, and any other pertinent information regarding the operation of the
condenser. Incorporate these into a logical and achievable test schedule.
Follow the test schedule and begin testing.
Make any schedule changes necessary to meet the scope and objectives of the test. Keep a test
log to document any deviations from the test plan or the original testing schedule.
45
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
Evaluate the
apparatus being Meet with Agree on a
tested (review responsible site-specific
size, location, and parties; begin scope and
ease of instrument to prepare a ok.jective to
est conduct plan test installation)
I
I
I
Discuss and Determine the Investigate the
determine all test specific possibility of
used criteria operational using station
final the requirements
in instruments
evaluation
Calibrate and
instruments plant use site-specific
instrumentation checklistorder in the
given where in the for the test
appropriate test plan
Check all
Calibrate all Compose a instruments prior
instruments to the actual test
mutually
and field b by conducting a
agreed-upon
check all test schedule preliminary test
t
connections (1 hr ma).
"Afkr unit has
reached stability"
7
I
L
46
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
Condenser cooling
water flow
determination
(instrumentshethods
of recommended
f
accuracy)
I
c
>
Is the
distance pipe size
from the pump
a long straight
v
to the waterbox
section of \ more than
r-
period only
section (measuring pipe diameters
t
section length should
be at least
10 pipe diameters)
1
Expertise is usually
be necessary reliability
usually found
required
within the
organization
I
into a process
instrument?
No
The proper number
of sampling points Permanent when installed
must be determined access to installation in smaller pipe
(choose the condenser may require
appropriate waterbox or calibration
distribution for inlet pipe
.
sampling)
f (Differential
producer) square
Dilution Black box root extractionand
calculations computation direct reading linearization
i
must be needed forfinal device (certain needed for final
performed to determination inputs are interpretation in
determine flow engineering units
f
The appropriate
m e appropriate The appropriate
The appropriate choice forthis
choice for this choice for this
choice for this application is the
application is the
application is a permanent or application is the
dye dilution flow orifice or nozzle;
pitot tube traverse; portable ultrasonic
determination;
overall accuracy 'flow meter'; 'overall accuracy'
overall accuracy
"5% (of flow) overall accuracy +2% (of flow)
+3% (of flow)
t5% (of flow)
47
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
--
Condenser
pressure
instrumentation
~
A A
v
4
Recommended
accuracy
with local
Local indication
common, high-speed
I"
and remote data collection contained
indicators or difficult or not
loggers applicable power source) I
i
No
acquisition indication indication
only?
lNo
Adaptable to
process Can be
instrumentation
external power into a process
needed
/
CYB.
No extensive
experience is
Data collection
during testcan
\ available for
needed for only be done on
installation a manualbasis
c
Durable under
Is cost a contained
governing power source environmental
factor? not necessary test conditions
The appropriate
The appropriate choice for this
choice forthis application is
application is capillary fluid
transducerhransmitter; mechanical gauges;
vacuum gauges;
overall accuracy overall accuracy
overall accuracy
20.1% (range)
+0.25% (range)
48
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
NONMANDATORYAPPENDIX B - GUIDELINE:
AUTOMATICDATAACQUISITION
(This Appendix is notapart of PTC 12.2 and is included for information purposesonly.)
This Appendix is a guide for the implementation (b) Flexible network which can analyze sensor and
of an automatic Data Acquisition System (DAS). The acquisition faults.
DAS can enhance data collection and analysis. The (c) Flags and alarms for out-of-range values.
DAScan accomplish the following: (dl Graphics for data trending and results presen-
(a) Simultaneous reading and recording of all data tation.
points. (e) Mass data storage and ease of data retrieval.
(b) Provide data collection frequencyexceeding (0 Ease ofcalculation development and export data
that described in Section 3. for third-party thermodynamic model analysis.
(c) Provide data collection time measurements/ TheDAScan provide certain enhancements that
synchronization as described in Section 3. manual data collection cannot offer,such as:
(d) Provide data accuracy exceeding that described (a) Real time data at very high sampling frequency.
in Subsection 4.3. (b) Reduction in manual datacollection personnel.
A portable,computer-based DAS together with (c) Reduction in data recording errors.
state-of-art sensor technology and analog-to-digital (d) Quick test condition/results validation which
converter reliability can accomplish the aboveobjec- leads to prevention of retest and associated costs.
tives.ThisDAS could also fulfill the following: ASMEPTC 19.22 [4] deals with this subject in
(a) Portability and ease of configuration. detail.
49
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
NONMANDATORYAPPENDIX C - GUIDELINE:
PERFORMANCE MONITORING
(This Appendix is not apart of PTC 12.2, and is included for information purposesonly.)
51
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
Performance Monitoring Thisincludes circulating-water flow devices,feed-
Measurement Code Requirement Methods water flow device;, and plant stream venturis. A
Cooling- Dye Dilution, Pump CurvedTDH calibration of plant devices during an accuratetest is
Water Flow Traverse,
etc. correlations, heat necessary to monitor the flow properly. For example, II
balance, calibrated
flow instrument, outlet correlate pump TDH outlet waterbox pressure drop, I
waterbox DP or a Pitot-statictype center reading during a previous I
dye-dilution test. With regard to pressure and temper- i
Cooling-Water Traverse, full rake Thermowells, partial ature instruments, refer to the Sections in this Code !
Outlet rake, thermowells which address the choices for instrumentation. Some I
Temp. correlated to one time new instrumentatioln is likely required for a successful I
temperature traverse program. In addition, an automated quick purge of
the pressure measurement lines before reading and
Tube Adjacent Tube Differential waterbox some added temperature hardware at the outlet to
Measurements
Cleanliness and waterbox outlet
reflect the temperature profile more adequately than
pressures, expected
backpressure, outlet a few shallow existing thermowells will significantly
temperature profile, enhancethe monitoring results.
terminal temperature
difference
C.3 CA1CULATIC)NS
Pressure NlST Calibrated Existing locations near
Electronic bundle; calibration of Refer to Section 5, for the details of the computation I
Transducer at sensors required of parameters for trending. All variables are recom- !
installed plant flow devices are not sufficiently accu- approximationscan be made depending on the
rate to serve as a primary flow measurement device. experienceofthepersonneland program goals.
I
i
52
i
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
NONMANDATORYAPPENDIX D - GUIDELINE:
EXAMPLE CALCULATIONS
(This Appendix is not a part of PTC 12.2, and is included for information purposes only.)
D.l BASICHEATTRANSFERRELATIONS
D.l.l Condenser Heat Load. The condenserheatloadatthetestconditions is computedasfollows:
where
= 1.4687E + 08 lb/hr
u+ = 0
'
A, * LMTD+
- 2.31 61 E + 09
=Btu/hr-ft2-"F
564.1 3 (D.1.2)
239,476 * 17.14
53
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
TABLE D.l
CONDENSER DESIGN DATA
Condenser Description
Design Conditions
Inlet CS temp ("F) 65
CW Outlet temp ("F) 80.6
CW flow (gpm) 280000
CW flow (Ib/hr)
1.3989E + 08
Cleanliness factor (%) 85
Condenser
pressure (in. . HgA) 1 .50
0.74 (psia) pressure Condenser
Heat load
2.1(Btu/hr) 760E + 09
pressure
Tubeside drop14.5
(ft water)
222:2185 flow (Ib/hr)
Condensing
-
where
(D.1.3) '
I
and
T j = f {Pj} = 101.14"F
RL = - 0.875
(D.1.4)
I
24 * k; 24 * 26.00
I
D.1.4 Tubeside Resistance. The tubeside heat transfer coefficient calculation is taken from Rabas and Cane. I1 I 1
54
I
I
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
TABLE D.2
TEST DATA
Measurement Average
Standard Number
Value Point Test Measurement Deviation
Inlet CW temp (OF) 1 75.0 60 0.1 50
74.9 2 4360 0.1
Average 74.9
0.373 dY.165
R: = 0.0451 k+0.538 * p+ 0.835 * c+0.462 v+0.835
P )*-
= 0.0451
where
W+
v+ =
3600 * p+ * A;
- 1.4687 E + 08
= 7.50 ftlsec (D.1.6)
3600 * 62.19 * 87.42
55
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
TABLED.3
STEAM AND WATERPROPERTIES
Design Test
CONDENSER STEAM PROPERTIES
Condenser Pressure (in. Hga) 1.5 22.0
Condenser Sat. Temp. ( O F ) 91.72 101.14
Density (Ib/ft3)* 0.0022 0.0029
TABLE D.4
FOULING RESISTANCE DETERMINATION TEST
Tube Tl JZ Tf Tc RI
Set "F "F "F 'F hr . f t 2 . "FIBtu
______~ ~~ ~ ~ ~~~~~~ ~~ ~~~ ~ ~ ~~~~
1 74.9 101.14
93.1 91.9 0.0001 83
74.9 2 93.7
101.14 92.3 0.000205
3 74.9 101.14
93.8 92.3 0.00021 8
74.9 4 93.4
101.14 91.9 0.000226
74.9 5 93.2
101.14 91.6 0.000247
.14 74.9 6 0.000266
74.9 7 101.14
93.9 92.6 0.0001 86
8101.14 74.9 92.8 94.0 0.0001 69
74.9 9 93.9
101.14 92.3 0.000232
10 74.9 101.14 92 .O 93.8 0.000266
11 74.9 101.14
93.2 91.5 0.000264
12 74.9 101.14
93.0 91.4 0.000252
13 74.9 101.14
93.2 91.5 0.000264
14 74.9 101.14
93.1 91.3 0.000283
Avg. 0.000233
56
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
D.1.5 FoulingResistance. The fouling resistance calculations, performed in accordance with para. 5.1.5,
are provided in Table D.4. The resulting fouling resistancewas:
1
Rt = -
l4
2 Rif; = 0.000233 hr-ft2-"F/Btu (D.1.7)
14 i = 1
Rf = -1-
U+
R+, - R: (%) - R?
=-- I
564.1 3
0.0001 6656 - 0.00057987 (i:;;;)
-- 0.0002330
( *
2.275°.373 0.777°.'65
= 0.0451
0.3489°.538* 62.28°.835* 0.999°.462) 7.14°.835
where
W*
v* =
3600 * p* * Ai
(D.2.3)
D.2.3 FoulingResistance. Thedesign fouling factor is determined from the design cleanliness factor as
follows:
57
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
R f = - - (' - )' - (' - 0'85) = 0.00029379 hr-ft*-"F/Btu (D.2.4)
U* 51 0.56
where
(J* = Q*
A, * LMTD*
2.1 760E + 09
- (D.2.5)
239,476 * 17.80
= 51 0.56 Btu/hr-ft2-"F
= f { p S ) = 91.72"F
= - 0.2 * LMTD*
I
= 88.16"F
T t = T: - 0.2 * LMTD+
= 97.72"F
3. Solve for theadjusted shellside resistance, where p, K, and p arethe physical properties atthedesign
and testtemperaturestaken from Appendix J.
58
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
= 0.00072 * (24083 14 )"*
22221 85
1.6956
(-)'I3*
1.8923
(-)
0.35908
0.36309
* (-)
62.138
62.026
2/3
- 1
UO*A,
NTUO =
$*w*
~
- 530.87 * 234,476
- = 0.89106 (D.2.13)
0.9986 * 1.3989E + 08
- 80.6
- - 65.0 e-0.89106 = 91.45"F (D.2.14)
1 - e-0.89106
59
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
P'j = f (Q} = 0.73 psia
D.2.7 Evaluation of Results. The difference between the test adjusted and design reference steampressures
are evaluated as follows:
APs = pf -e
= 0.74 - 0.73 = 0.01 (D.2.15)
Thus, the condenser is operating slightly better than thedesign level of performance.
Thus, the condensertubesidepressure drop is 0.1 ft. water less thanthe design value.
I
(D.4.1)
where
F1 = 0.001 690e0.02736@
I
60
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
(D.4.3)
= -1.2662E - 09 -
psia
(D.4.4)
I b/hr
1
Tt - T;
61
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled wh
where
1
F3 =
0.001 690 ?'
(D.4.8)
= 37.1824 "F/psia
R:
F1
*
*
W+
F2
*
*
C;
Rf * A, * -1*
* (Tt - Tt) j
x
;=
j
@T+2,f
FI * F? * R: * A, * -1*
i
i
i =1
R: * W+ * C+P * ( T t - T t )
62
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
(41 The values in Table D.5 are provided for example purposes only. Although these values are typical for
a test conducted in accordance withthis Code, actual values must be determined for a specific testand
will depend on the condenser design, the instrumentation used, and the operating conditions at the time
of the test. For this example, the biaslimits and precision indices are as follows:
D.4.1.3 Uncertainty in Result. An estimate of the uncertainty in the test steam pressure, adjusted to the
design reference conditions, is calculated as follows:
Bias f h i t :
(D.4.13)
and
Precision Index:
(D.4.14)
= 4.914605 psia’
and
63
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
S p = 20.0070 psia
Combined Uncertainty:
Based on the number of readings for each measurement parameter, as provided in Table D.2 for this sample
calculation, the pooled degrees of freedom was determined to be greater than 30; therefore,theStudent's
t-value from Table 5.1 is 2.00. The combined uncertainty is then determined as follows:
= 20.044 psia
D.4.2 Uncertainty in Tubeside Pressure Drop. An estimate of the uncertainty in the test tubesidepressure I
=-
APp = -
14.2
- 0.90446 (D.4.16)
APT 15.7
ft Water
= 1.7403E-07 -
Ib/hr
In accordance with theWelsh-Satterthwite formula from ASME PTC 19.1 [4] and using 11 degrees of
freedom for both the circulating water flow rate and thetubeside pressure drop,the pooled degrees of
freedom for determining the Student's t-value is:
64
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
Parameter x s ( Xs)* ( x 34/11
Press Drop .9045 x .042 .0014 1.893E - 07
Flow 1.74E - 07 X 556,106 .0094 8.090E - 06
.0108 8.279E-06
TheStudent’s t-valueat 95% coverage and 14 degreesof freedom is 2.145. The combined uncertainty is
then computed as follows:
65
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
TABLE D.5
EXAMPLE OF BIAS LIMIT AND PRECISION INIDICES
Precision ,
Measured Parameter Sensitivity Factor Bias Limit Index
Flow Steam
w (22.5%) (20.21%)
w Water CW 1.2662E-09 psidlb/hr 2558,106 Ib/hr25,140,450 Ib/hr
W+ (23.5%) (20.38%)
Inlet CW Temp 0.01 14 psid"F 20.20"F 20.021 "F
T;
Outlet CW Temp
20.065"F 20.50"F 0.0330 psid0F
Tt
901 Pressure Condenser psia
PS+
psiaPF 3.9915E-06
CF Fouled Tubes OF
Inlet Temp
Ttl
Tubes CF Fouled psid°F 20.090"F 20.75"F
Outlet Temp
Tl2
I
~~~~ ~ ~~ ~~ ~~ ~~~~ ~
6.1345E-06
CF Clean Tubes psid'f 20.021 20.20"F "F I
Inlet Temp
T; 1 I
66
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
NONMANDATORYAPPENDIX E - DETAIL:
UNCERTAINTYANALYSISFORCONDENSINGPRESSURE
(This Appendix is not apart of PTC 12.2 and is included for information purposesonly.)
67
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
P: = f { T z )
(E.1.3)
U0* A,
NTUO = - (E.1.4)
c; * w*
LMTD;,; =:
v:,,; - Tt,,;) (E.1.12)
* (E)[E]
(5)’”. * (P*) 213 dP,”= (-)dT:
ap:
8 T:
and
I
I
(E.1.13) ,
(aa T:
dT,” = -)dNTUo
)
NTU’
P+ 0.373
R: = 0.04” ( p0.538 * c+P 0.462 (E.1.9)
where
fouled or clean test tubes divided by its heat pick-up (Note that and : 7 areexactdesignvalues;there-
I
~
is considered to approximately equal fore, their partial derivatives are equal to zero.) From
AJQ, then, Eq. E.1.4: I
68 I
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
dNTUO = (=)duo
N TU0a (E.1.16)
where
(dub)= u o
aNTUo NTUO /hr-ft*-OF\
(E.1.17)
Iblhr
(Note that Ao,c;, and w* areexactdesignvalues;
therefore, their partial derivatives are equal to zero.) The design steam flow rate is an exact design value;
FromEq.E.1.5: therefore, the partial derivative is equal to zero. The
error in thecirculatingwaterandsteamproperties
atthedesign-adjustedandtestconditions is not
a uo
dUo = (-)dR;
exact; however, the magnitude of the partial deriva-
aR;
tives of these properties will have a negligible effect
on the resulting sensitivity factors for the measured
where
parameters. As a result,theuncertaintyanalysis
hasbeensimplified by assumingthatthesepartial
derivativesareequaltozero.
The derivation of the sensitivity factor for the test
measured steam flow rate is completed at this point,
(Note that R,, R,, and Rf are exactdesignvalues; since:
therefore, their partial derivatives are equal to zero.)
Theseterms are thencombinedusing the chain B q and Sw: = dW:
rule as follows:
Thus,combining Eqs.E.1.13,E.1.14,andE.1.17:
= (S) (-) = *
a
* (%)
(dub)
NTUO
@q = (3)
(3) * aR; (3)
* aw: (E.l.18)
or
P-1
'
hr-ft2-"F
Btu '
Thederivation of thesensitivityfactorsforthere-
maining parametersfollows,
beginning with Eq.
E.1.7.
From Eq. E.1.6:
where
69
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
Evaluation of the partial derivative terms of Eq.
E.1.19 first requires substitution of EquationsE.1.11
and E.1.12 into Eq.E.1.10, and then substitution of
Eq.E.1.8,E.1.9, and E.l.10 into Equation E.1.7. The
resulting equationcan then be solvedfor each of (!E$)
the partial derivatives. These derivativesand the
resulting sensitivity factors follow.
Sensitivity Factor for Circulating Water Flow: Sensitivity Factor for Outlet Water Temperature:
r 1
- - - ($+ 0.835R: (2)+ R;)
aR:
ad d
(E.1.20)
which is equal to
(E$) (E.1.23)
d \Ib/hr/
*I- I
70
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
Then applying Eq. E.1.20 and combining Eqs. E.1.13,
E.1.14, and E.1.16:
- F, * F2 * R,O * A,
(E.1.24)
F3 * R: * w+ * c; * ( T ; - T;)
Then applying Eq. E.1.20 and combining Eqs. E.1.13, Then applying Eq. E.1.20 and combining Eqs. E.1.13,
E.1.14, and E.1.16:
E.1.14, and E.1.16:
Sensitivity Factor for Cleanliness Factor Fouled Tube Sensitivity Factor for Cleanliness Factor Clean Tube
OutletTemperature: OutletTemperature:
71
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
w # 1.8
AP; = APL( 7 )
(E.2.2)
E.2 SENSITIVITYFACTORSFORTUBESIDE
PRESSURE D R O P
The adjusted tubeside pressure drop is calculated ow+= -dAPE, - 1.8 * APL psi )
(- (E.2.3)
as follows: aW+ k Ib/hr
72
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
NONMANDATORYAPPENDIX F - DETAIL:
GEOTHERMALSURFACECONDENSERS
(This Appendix is not a mandatory part of PTC12.2,SteamSurfaceCondensers; and is included for information purposesonly.)
73
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
NONMANDATORYAPPENDIX G - DIAGNOSTIC:
AIR BINDING
(This Appendix is not apart of PTC 12.2 and is included for information purposesonly.)
75
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
TUBEOUTLETTEMPERATUREMEASUREMENT
76
bellmouth
FIG. G.l
Plastic
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
NONMANDATORYAPPENDIX H - DIAGNOSTIC:
NON-CONDENSIBLE REMOVAL EQUIPMENT
(This Appendix is not a pan of PTC 12.2 and is included for information purposes only.)
77
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
H.3.2 Critical Measurements. The critical measure- mV= molecular weight of vaporatcondenser
ments needed to assess vacuum pump performance vent.
are as follows: mG= molecular weight of non-condensible gas
(a) Suction pressure and temperature at condenservent.
(b) Seal-water flow and temperature PT= absolute total pressure at the condenser
(c) Cooling-water flow and temperature vent.
(d) Air-vapor flow rate P,= absolute 'vaporpressure corresponding to
the temperature at the condenser vent.
78
.
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w
NONMANDATORYAPPENDIX I - DIAGNOSTIC:
TUBEFOULING
(This Appendix is not a part of PTC 12.2 and is included for information purposesonly.)
79
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolle
NONMANDATORY APPENDIX j - PHYSICAL
81
(This Appendix is not a part of PTC12.2
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
chart has34.483 g of solids per 1000 g seawater.
The normal seawater concentrationused in this
140
120
DENSITY
OF
O F
100
Temperature,
82
80
GENERAL NOTE
60
32 40
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
83
FIG. j.2
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolle
i
CONDUCTIVITY
chart has 34.483 g of solids per 1000 g seawater.
The normal seawater concentration usedin this
Temperature, "F
84
GENERAL NOTE:
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
"F
Temperature,
85
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled wh
This page intentionally left blank.
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled
N O N M A N D A T O R Y APPENDIX K - REFERENCES
[ l l Rabas,T.J.,Oane, D., “An Update of lntube PTC19.5, Instruments and Apparatus: Part I/
Forced Convection Heat Transfer Coefficient with of Fluid Meters [1972]
Variable Physical Properties,” Advances in Heat PTC 19.22, Digital Systems Techniques [1986]
Transfer, Vol. 6, pp. 503-564, 1970. PTC24, Ejectors [1976]
[2] Meyer,C.A.etal, ASMESteamTables. Third [5] HeatExchange Institute Standards for Steam
Edition, The American Society of Mechanical Engi- SurfaceCondensers, 9th Edition, 1995.
neers, New York,NY, 1993. [6] Standard Methods for the Examinationof Water
[3] Taborek, J., Design Methods For Heat Transfer and Wastewater, 17th Edition, 1985.
Equipment, in Heat Exchangers: Design and Theory [71 H.S. Bean (editor), Fluid Meters: Their Theory
Sourcebook, ed. by Afgan, .N. and Schiunder, E., and Application, sixth edition, The American Society
Hemisphere Publishing Company, 1974. of Mechanical Engineers, New York, NY 1971.
[4] PerformanceTest Codes, The American Society
[81 FlowMeasurements in Sanitary Sewers by
of Mechanical Engineers, New York, NY:
Dye Dilution, Monograph, SS 7-80, Turner Designs,
PTC2, Definitions and Values [1980]
Sunnyvale, CA, 1980.
PTC6, Steam Turbines [1996]
PTC9, Displacement Compressors, Vacuum [91Smart, P.L., and I.M.S. Laidlaw, An Evaluation
Pumps, and Blowers [1970] of FluorescentDyes for Water Tracing, Water Re-
PTC12.3, Deaerators [1997] sourcesResearch, Vol. 13, No. 1, February 1977.
PTC18, Hydraulic Turbines [1992] [lo] Test Methods for Dissolved Oxygen in Water,
PTC 19.1, Measurement Uncertainty [1985] ASTM Standard D888-87.
PTC 19.2, Instruments and Apparatus: Pressure [l 11 MFC-3M-1989, Measurement of Fluid Flow
Measurement [ 19871 in Pipes Using Orifice, Nozzle and Venturi, The
PTC 19.3, Instruments and Apparatus: Ternper- AmericanSocietyof Mechanical Engineers, New
ature Measurement [1974] York, NY, 1990.
87
Copyrighted material licensed to Stanford University by Thomson Scientific (www.techstreet.com), downloaded on Oct-05-2010 by Stanford University User. No further reproduction or distribution is permitted. Uncontrolled w