Waiting Shed Project as requirement for

e-SBM WinS Program


SCNHS
I – Bill of Materials

Qty Unit Particulars Unit Price Amount


150 pcs CHB P 20.00 P 3,000.00
30 bags Cement 270.00 8,100.00
10 pcs Rebars, 10mm 210.00 2,100.00
1 Kg Tie Wire # 16 100.00 100.00
TOTAL ------------------------------ P 13,300.00

II – Mason (Labor) -------------------------------------------- P 5,000.00

Grand Total --------------------------- P 18,300.00