PT.

JOGJASOLO MARGA MAKMUR

PEMBANGUNAN JALAN TOL SOLO-YOGYAKARTA-NYIA KULONPROGO


SEKSI I PAKET 1.2A KLATEN-PURWOMARTANI (STA 22+300 S.D STA 27+300)

NO. KONTRAK : 2601/DMT-BLS/VII/2022


TANGGAL KONTRAK : 26 Juli 2022
NO. SPMK : 009.01.12A/SPMK/Adm.DMT/VIII/2022
TANGGAL SPMK : 09 Agustus 2022

MAIN KONTRAKTOR

PT. DAYA MULIA TURANGGA

LAPORAN MINGGUAN
MINGGU KE : 9 (LIMA )
PERIODE : 30 SEPTEMBER 2022 S/D 06 OKTOBER 2022

SUBKONTRAKTOR

PT. BORNEO LINTAS SERAWAK


REKAPITULASI LAPORAN MINGGUAN

PEMBANGUNAN JALAN TOL SOLO-YOGYAKARTA-NYIA KULONPROGO


SEKSI I PAKET 1.2A KLATEN - PURWOMARTANI (STA 22+300 S.D STA 27+300)

Minggu Ke : 9 (LIMA ) Subkontraktor : PT. BORNEO LINTAS SERAWAK


Periode : 30 SEPTEMBER 2022 S/D 06 OKTOBER 2022 No. Kontrak : 2601/DMT-BLS/VII/2022
Tanggal : 06 Oktober 2022 Tanggal : 26 Juli 2022
Main Kontraktor : PT. DAYA MULIA TURAGGA

KONTRAK S/D Minggu Lalu Minggu Ini S/D Minggu Ini


No Bab Pekerjaan Keterangan
Bobot (%) Bobot (%) Bobot (%) Bobot (%)
a b c d e f=d+e g
A PEKERJAAN PELAKSANAAN

BAB 1 UMUM 0,7864 0,6344 0,0079 0,6423

BAB 2 PEMBERSIHAN TEMPAT KERJA 0,3195 0,1777 0,0016 0,1793

BAB 3 PEMBONGKARAN 0,1909 - - -

BAB 4 PEKERJAAN TANAH 32,4086 0,5970 1,3115 1,9085

BAB 5 GALIAN STRUKTUR 0,1569 - - -

BAB 6 DRAINASE 4,1112 - - -

BAB 7 SUBGRADE 0,1850 - - -

BAB 8 LAPIS PONDASI AGREGAT (SUBBASE) 2,3229 - - -

BAB 9 PERKERASAN 19,3111 - - -

BAB 10 STRUKTUR BETON 31,2762 - - -

BAB 11 PEKERJAAN STRUKTUR BAJA

BAB 12 PEKERJAAN LAIN-LAIN 8,9313 - - -

BAB 13 PENCAHAYAAN LAMPU LALU LINTAS DAN PEKERJAAN LISTRIK

BAB 14 PLAZA TOL

BAB 15 PENGALIHAN DAN PERLINDUNGAN UTILITAS YANG ADA

BAB 16 PEKERJAAN FASILITAS TOL DAN KANTOR GERBANG TOL

B PEKERJAAN PERENCANAAN

JUMLAH TOTAL 100,000 1,4091 1,3209 2,7301

Diperiksa dan Disetujui oleh : Dibuat oleh :


MAIN KONTRAKTOR SUB KONTRAKROR
PT. DAYA MULIA TURANGGA PT. BORNEO LINTAS SERAWAK

MIFTAHUL HIDAYAT DARU SURYANTORO


General Superintendent Project Manager
RINCIAN LAPORAN MINGGUAN

PEMBANGUNAN JALAN TOL SOLO-YOGYAKARTA-NYIA KULONPROGO


SEKSI I PAKET 1.2A KLATEN - PURWOMARTANI (STA 22+300 S.D STA 27+300)

Minggu Ke : 9 (LIMA ) Waktu Pelaksanaan : 540 Hari Kalender


Periode : 30 SEPTEMBER 2022 S/D 06 OKTOBER 2022 Waktu Pelaks. Terjalani : 59 Hari Kalender
Tanggal : 06 Oktober 2022 Prosen Waktu Terjalani : 10,926%
Main Kontraktor : PT. DAYA MULIA TURAGGA Sisa Waktu Pelaksanaan : 481 Hari Kalender
Sub Kontraktor : PT. BORNEO LINTAS SERAWAK

Kontrak Volume Kemajuan Pekerjaan Prosentase Progress (%)


Terhadap
No Item Item Pekerjaan Satuan Bobot s/d Minggu s/d Minggu s/d Minggu Minggu s/d Minggu
Volume Minggu ini Bobot Kontrak
(%) Lalu ini Lalu ini ini

A PEKERJAAN PELAKSANAAN
BAB 1 UMUM
1.19 Manajemen dan Perlindungan Lalu Lintas Ls
1.20 Mobilisasi Ls 0,21 0,537 0,179 0,002 0,181 0,4560 0,0054 0,4614 86,00%
1.26 Pekerjaaan dan Penanganan Aliran Air Yang Sudah Ada Ls 0,21 0,091 0,137 0,002 0,139 0,0594 0,0009 0,0603 66,00%
1.39 Pengamanan Lingkungan Ls 0,21 0,122 0,160 0,002 0,162 0,0926 0,0012 0,0939 77,00%
1.40 Manajemen Mutu Ls 0,21 0,037 0,151 0,002 0,153 0,0264 0,0004 0,0267 73,00%
JUMLAH BAB 1 0,786 0,6344 0,0079 0,6423 81,68%

BAB 2 PEMBERSIHAN TEMPAT KERJA


2.01 (1) Pembersihan Tempat Kerja m2 285.236,80 0,315 161.158,794 1.426,184 162.584,978 0,1777 0,0016 0,1793 57,00%
2.01 (3) Penebangan Pohon bh 105,00 0,005 - - - - - 0,00%
JUMLAH BAB 2 0,32 0,1777 0,0016 0,1793 56,11%

BAB 3 PEMBONGKARAN
3.01(1b) Pembongkaran Beton (Perkerasan) m3 1.468,85 0,075 - - - - - 0%
3.01 (5) Pembongkaran Rumah m2 11.280,00 0,116 - - - - - 0%
JUMLAH BAB 3 0,19 - - - 0,00%

BAB 4 PEKERJAAN TANAH


4.03 (1) Galian Biasa untuk Timbunan m3
4.03 (3) Galian Dibuang m3 105.604,18 1,226 40.129,588 4.224,167 44.353,756 0,4660 0,0491 0,5150 42,00%
4.05 (1) Common Borrow Material m3 475.042,00 13,791 4.512,899 43.487,101 48.000,000 0,1310 1,2624 1,3935 10,10%
4.05 (2) Selected Borrow Material (Urugan Pasir) m3 300.259,75 10,547 - - - - - 0,00%
Kontrak Volume Kemajuan Pekerjaan Prosentase Progress (%)
Terhadap
No Item Item Pekerjaan Satuan Bobot s/d Minggu s/d Minggu s/d Minggu Minggu s/d Minggu Bobot Kontrak
Volume Minggu ini
(%) Lalu ini Lalu ini ini
4.09 Urugan Material Berbutir (Granular Backfill) m3 73.641,22 3,014 - - - - - 0,00%
4,12 Geotextile Stabilisator (Kelas 1) m2 1.256.573,59 3,830 - - - - - 0,00%
JUMLAH BAB 4 32,41 0,5970 1,3115 1,9085 5,89%

BAB 5 GALIAN STRUKTUR


5.01 (1) Galian Struktur Kedalaman < 2m m3 13.000,95 0,140 - - - - 0%
5.01 (2) Galian Struktur Kedalaman 2 - 4 m m3 1.387,06 0,017 - - - - 0%

JUMLAH BAB 5 0,16 - - - 0,00%

BAB 6 DRAINASE
6.05 (7) Pipa Gorong-gorong Beton Bertulang dia 80 cm, Tipe B m' 360,22 0,413 - - - - 0%
6.06 (1) Saluran U, Tipe DS-1 m' 15.476,45 0,268 - - - - 0%

6.06 (5) Saluran U, Tipe DS-5 (Saluran Samping Pasangan Batu Terbuka) m' 2.584,38 0,724 - - - - 0%

6.06 (11) Saluran U, Tipe DS-11 (U 80 Median Drain) m' 4.700,00 2,394 - - - - 0%
6.08 Saluran U, Tipe DS-8 (Gutter) m' 4.453,00 0,312 - - - - 0%
JUMLAH BAB 6 4,11 - - - 0,00%

BAB 7 SUBGRADE
7.01 Persiapan Tanah Dasar m2 186.851,55 0,185 - - - - 0%
JUMLAH BAB 7 0,19 - - - -

BAB 8 LAPIS PONDASI AGREGAT (SUB BASE)


8.01.(3) Lapis drainase m3 22.718,97 2,323 - - - - 0%
JUMLAH BAB 8 2,32 - - - 0,00%

BAB 9 PERKERASAN
9.04 Bitumen Lapis Resap Pengikat (Prime Coat) ltr
9.05 Bitumen Lapis Perekat (Tack Coat) ltr
9.07(3) Asphalt Concrete Wearing Course (ACWC) ton
9.07(4) Ashpalt Cement ton
9.08(1)a Perkerasan Beton Semen m3 38.965,00 16,108 - - - - 0%
9.08(2a) Perkerasan Beton Semen Double Wiremesh m3 262,50 0,139 - - - - 0%
9.09 Wet Lean Concrete (t=10cm) m2 132.090,16 3,064 - - - - 0%
JUMLAH BAB 9 19,31 - - - 0,00%

BAB 10 STRUKTUR BETON


10.01(4a) Beton Kelas B-1-1a (Lantai Beton Bertulang dari Gelagar Beton Pratekan U/I) m3 1.044,11 0,422 - - - - 0%
10.01(4a). Beton Kelas B-1-1a (Struktur Lantai Elevated) m3
Kontrak Volume Kemajuan Pekerjaan Prosentase Progress (%)
Terhadap
No Item Item Pekerjaan Satuan Bobot s/d Minggu s/d Minggu s/d Minggu Minggu s/d Minggu
Volume Minggu ini Bobot Kontrak
(%) Lalu ini Lalu ini ini
10.01(3c) Beton Kelas B-1-3 (Kepala Pier Beton Bertulang) m3
10.01(3c). Beton Kelas B-1-3 (Struktur Pierhead Elevated) m3
10.01(7f) Beton Kelas B-1-4f (Kolom Beton Bertulang dari Pier) m3
10.01(7f). Beton Kelas B-1-4f (Kolom Beton Bertulang dari Pier,Elevated) m3
SS. 10.01(7f1) Fasade Elevated Pilar
10.01(10) Beton Kelas C-1 (Abutment, Telapak Pier, Box, Wingwall) m3 23.334,55 9,342 - - - - 0%
10.01(10). Beton Kelas C-1 (Struktur Telapak Pier Elevated) m3
10.01(11) Beton Kelas C-2 (Box Culvert, Plat Injak) m3 9.793,57 5,058 - - - - 0%
10.01(14) Beton Kelas E m3 2.499,45 0,702 - - - - 0%
10.02 (3) Batang Baja Tulangan Sirip BjTS 420A kg 7.427.688,93 4,897 - - - - 0%
10.03 (13c1) Gelagar PCI bentang nominal 15,10m to 17m H=1,4m, penyediaan unit
10.03 (13c2) Gelagar PCI bentang nominal 15,10m to 17m H=1,4m, pemasangan unit
10.03 (14a) Gelagar PCI bentang nominal 25,0m to 27m H=1,6m, penyediaan unit 15,00 0,668 - - - - 0%
10.03 (14b) Gelagar PCI bentang nominal 25,0m to 27m H=1,6m, pemasangan unit 15,00 0,162 - - - - 0%
10.03 (15a) Gelagar PCI bentang nominal 30,0m to 32m H=1,7m, penyediaan unit 30,00 1,998 - - - - 0%
10.03 (15b) Gelagar PCI bentang nominal 30,0m to 32m H=1,7m, pemasangan unit 30,00 0,345 - - - - 0%
10.03 (16a1) Gelagar PCI bentang nominal 20,0m to 22m H=2,1m, penyediaan unit
10.03 (16a2) Gelagar PCI bentang nominal 20,0m to 22m H=2,1m, pemasangan unit
10.03 (16b1) Gelagar PCI bentang nominal 39,0m to 41m H=2,1m, penyediaan unit 15,00 1,348 - - - - 0%
10.03 (16b2) Gelagar PCI bentang nominal 39,0m to 41m H=2,1m, pemasangan unit 15,00 0,220 - - - - 0%
10.03 (16b1). Gelagar PCI bentang nominal 39,0m to 41m H=2,1m, penyediaan (Elevated) unit
10.03 (16b2). Gelagar PCI bentang nominal 39,0m to 41m H=2,1m, pemasangan (Elevated) unit
SS.10.03 (17b1) Gelagar PCI bentang nominal 50m H=2,3m, penyediaan unit
SS.10.03 (17b2) Gelagar PCI bentang nominal 50m H=2,3m, pemasangan unit
SS.10.03 (17b7) Precast Diafragma Girder unit 462,00 0,402 - - - - 0%
Ss 10.03.(19) Galvanized Metal Formwork (Bondek) m2 5.028,17 0,255 - - - - 0%
SS. 10.05 (4a) Penyediaan Minipile Triangel 32 x 32 m'
SS.10.05 (4b) Pemancangan Minipile Triangel 32 x 32 m'
10.07 (1a) Tiang Cor Beton Cast-in-Place D=100cm dengan pemantauan ultrasonik m' 4.598,00 4,701 - - - - 0%
SS.10.07 (4 b) Tiang Cor Beton Cast-in-Place D=200cm m'
10.10 (2) Sambungan Siar Muai Tipe B (Adhesive Sealant Joint) m' 444,50 0,388 - - - - 0%
SS 10.11 (7A) Elastomeric Bearing Pad 500 x 400 bh 122,00 0,115 - - - - 0%
SS 10.11 (7B) Elastomeric Bearing Pad 500 x 400 (Lead Rubber Bearing) bh
SS.10.11 (27a) Angkur dan Aksesoris (Fix/Move) unit 244,00 0,032 - - - - 0%
10.12 (1) Pipa Drainase D=20cm dengan fitting dan penompang m' 1.720,00 0,174 - - - - 0%
10.12 (3) Deck Drain Tipe 1 dengan pelengkapan unit 160,00 0,047 - - - - 0%
JUMLAH BAB 10 31,28 - - - 0,00%

BAB 11 PEKERJAAN STRUKTUR BAJA


JUMLAH BAB 11 - - - - -
Kontrak Volume Kemajuan Pekerjaan Prosentase Progress (%)
Terhadap
No Item Item Pekerjaan Satuan Bobot s/d Minggu s/d Minggu s/d Minggu Minggu s/d Minggu
Volume Minggu ini Bobot Kontrak
(%) Lalu ini Lalu ini ini

BAB 12 PEKERJAAN LAIN-LAIN


12.01 Solid Sodding m2 205.164,21 0,541 - - - - 0%
12.02(3) Pasangan Batu Kali Tipe C m3 70,00 0,013 - - - - 0%
12.03(3) Perlindungan Lereng dengan Blok Beton m2 28,00 0,003 - - - - 0%
12.06(1) Guardrail Kendaraan Tipe A m' 15.481,95 3,124 - - - - 0%
12.06(11) Bagian Ujung Guardrail bh 110,00 0,013 - - - - 0%
12.07.(1) Rambu Pengaturan dan Peringatan, Tipe A-1 Buah
12.07.(2) Rambu Pengaturan dan Peringatan, Tipe A-2 Buah
12.07 (3) Rambu Pengaturan dan Peringatan, Tipe B-1 Buah
12.07 (5) Rambu Pengaturan dan Peringatan, Tipe C-1 Buah
12.08.(2) Rambu Petunjuk Tipe A-2 Buah
12.08.(4) Rambu Petunjuk Tipe A-4 Buah
12.08.(8) Rambu Petunjuk Tipe B-1 Buah
12.08.(9) Rambu Petunjuk Tipe B-2 Buah
12.08.(10) Rambu Petunjuk Tipe C1 Buah
12.08.(12) Rambu Petunjuk Tipe D1 Buah
12.09 (1) Marka Jalan, Tipe A m2 6.843,39 0,295 - - - - 0%
12.10 (2) Delineator Tipe B bh 25,00 0,001 - - - - 0%
12.12 (1) Kerb Beton Tipe A m' 1.503,69 0,078 - - - - 0%
12.15 (1) Concrete Barrier, Tipe A (2 Muka) termasuk pekerjaan ducting PVC Tipe AW m' 1.420,18 0,585 - - - - 0%
12.15 (2) Concrete Barrier, Tipe B (1 Muka) termasuk pekerjaan ducting PVC Tipe AW m' 8.993,44 2,918 - - - - 0%
12.19(5) Patok Kilometer bh 1.316,94 0,411 - - - - 0%
12.20(1) Pagar ROW, Tipe 1 (Panel Beton) m' 2.820,00 0,467 - - - - 0%
12.20(2) Pagar ROW, Tipe 2 (Kawat Berduri) m' 8.245,08 0,483 - - - - 0%
JUMLAH BAB 12 8,93 - - - 0,00%

BAB 13 PENCAHAYAAN, LAMPU LALU LINTAS, DAN PEKERJAAN LISTRIK


13.01(1).1 Lampu PJU, Tinggi 13 m Tipe A (1x 120 Watt), Jenis LED Dimming System Unit
13.01(1).2 Lampu PJU, Tinggi 13 m Tipe B (2x 120 Watt), Jenis LED Dimming System unit
13.01.(1).8 Lampu Menara (High Mast), Tinggi 40 m unit
13.01(1).13 Lampu Kedip (Flashing Light), 2x100w unit
13.01.(1).14 Penangkal Petir Lampu Menara (termasuk Box Grounding dan Grounding) Buah
Ss 13.01.(1)14a Grounding Lampu Unit
Ss 13.01.(1)14b Penyediaan Sparring Underpass Unit
13.01(1).20 Kabel NYFGBY 4C - 16 mm2 m'
13.01 (2). Panel PJU Termasuk Pondasi unit
13.01 (3).1 Box dan Pondasi Panel Meter PLN Unit
13.01(4).8 Lampu LPL (Lampu Pengatur LaluLintas) Tipe -1 Unit
SS 13.05 Sparing ME Elevated Pilar
JUMLAH BAB 13 - - - -
Kontrak Volume Kemajuan Pekerjaan Prosentase Progress (%)
Terhadap
No Item Item Pekerjaan Satuan Bobot s/d Minggu s/d Minggu s/d Minggu Minggu s/d Minggu
Volume Minggu ini Bobot Kontrak
(%) Lalu ini Lalu ini ini

BAB 14 PLAZA TOL


14.01.(1) Pulau Tol Tipe A (Standar) Unit
14.01.(3) Pulau Tol Tipe C ( Long Booth) Unit
14.03. (4) Atap Gerbang Tol untuk 5 Pulau Unit
14.04. (3) Genset Bergerak 30 Kva Unit
JUMLAH BAB 14 - - - -

BAB 15 PENGALIHAN DAN PERLINDUNGAN UTILITAS YANG ADA


15.1 Relokasi Utilitas dan Layanan Yang Ada PS
JUMLAH BAB 15 - - - -

BAB 16 PEKERJAAN FASILITAS TOL DAN KANTOR GERBANG


Jalan, Lapangan Parkir, Drainase, Pembuangan Air Kotor, Pagar dan Lansekap untuk
16.01 (1) Ls
Plaza dan Kantor Tol
16.01 (2a) Pos Tol Unit
16.01 (3b) Highway Patrol Office Unit
16.01 (5) Masjid Unit
16.01(7) Rumah Generator Unit
16.01 (8) Menara Air dan Pasokan Tipe A (8000 Liter) Unit
16.01 (9) Resevoir Air Bawah Tanah Unit
16.01 (10) Instalansi Listrik Ls
16.01 (11) Sistem Perpipaan dan Pemadam Kebakaran Unit
16.01(12) Sistem Alarm Pemadam Fire Unit
16.01(13) Air Condition Unit
SS 16.5 Penyiapan Lahan Rest Area PS
JUMLAH BAB 16 - - - - -
TOTAL (A) 100,00 1,4091 1,3209 2,7301 2,7301%

B PEKERJAAN PERENCANAAN Ls

TOTAL (B) - - - - -
TOTAL 100,00 1,4091 1,3209 2,7301 2,7301%
REALISASI PEKERJAAN 1,4091 1,3209 2,7301
RENCANA PEKERJAAN
DEVIASI 1,4091 1,3209 2,7301