Professional Documents
Culture Documents
Operationofureafertilizersplant 150902143845 Lva1 App6891
Operationofureafertilizersplant 150902143845 Lva1 App6891
SAIPEM PROCESS
PRESENTED BY
Prem Baboo
National fertilizers Ltd. India.
An Expert for
www.ureaknowhow.com
Fellow of Institution of Engineers
India.
R-1E-1 MV-2 Plant & Equipment's Designer
V-1 MV-3
POINTS TO DISCUSS
START UP
SHUT DOWN
TROUBLE SHOOTINGS
2
R-1E-1 MV-2 V-1 MV-3
Start Up
Initial start up
Cold start up
Hot start up
3
R-1E-1 MV-2 V-1 MV-3
Start Up
4
R-1E-1 MV-2 V-1 MV-3
START UP
5
R-1E-1 MV-2 V-1 MV-3
Start Up With Empty Reactor
General
During this phase it has been assumed that all pre-
start operations have been completed together with
Mechanical check of the unit.
6
R-1E-1 MV-2 V-1 MV-3
Sealing Tests Of All Sections
Purpose
– To eliminate leaks, if any, before charging process
fluids.
7
R-1E-1 MV-2 V-1 MV-3
Sealing Test
Fluid
– Steam condensate.
Temperature
– Ambient (cold test)
Pressure
– Operating value
8
R-1E-1 MV-2 V-1 MV-3
Sealing Test Conceptual Procedure
Admit the fluid from the lowest points and keep the
vent at highest points opened.
Slowly increase the pressure to the test value.
Check all flanges and connections in order to identify
leaks and eliminate them.
If the pressure does not fall appreciably after 4 hours
the test can be considered satisfactory, otherwise it
will be necessary to look and to eliminate them and
then repeat the test.
9
R-1E-1 MV-2 V-1 MV-3
Very Important
10
R-1E-1 MV-2 V-1 MV-3
Purging By N2 Of M.P. & L.P.Sections
Purpose
This operation must be carried out before
plant start-up in order to remove all the O2
present, avoiding any risk of explosive mixture
formation during ammonia charging.
11
R-1E-1 MV-2 V-1 MV-3
Purging By N2 - Conceptual Procedure
12
R-1E-1 MV-2 V-1 MV-3
Charging of Ammonia in MP Section
Purpose
To have a make-up of NH3 (Raw material)
Pressurize the M.P.section
Test H.P.NH3 pump
Ammoniation
13
R-1E-1 MV-2 V-1 MV-3
Ammonia Solution Preparation in V-3
Purpose
Preparation of L.P.section to receive process
fluid
The concentration of NH3 in V-3 solution is
about 30%
14
R-1E-1 MV-2 V-1 MV-3
Plant Heating Before Start Up
Purpose
Whenever start-up is to be performed with the unit empty
and at ambient temperature the equipment shall be
previously heated in order to bring them to the best
conditions to feed the process fluids to the above
equipment.
This is to avoid:
Thermal stresses on the material
Possibility of crystallization of products in cold piping and walls
15
R-1E-1 MV-2 V-1 MV-3
Plant Heating Before Start Up
16
R-1E-1 MV-2 V-1 MV-3
Conditions Before Ammoniation
17
R-1E-1 MV-2 V-1 MV-3
Conditions Before Ammoniation
18
R-1E-1 MV-2 V-1 MV-3
Ammoniation
Purpose
To reach the best conditions to start the reactions
inside the reactor.
Conceptual procedure
It consists in the pressurization of H.P.loop with
ammonia vapors up to 90 kg/cm2
The “Ammoniation” operation requires about 3 hours
and then the unit can be fed by NH3 and CO2 to Urea
Reactor.
19
R-1E-1 MV-2 V-1 MV-3
Ammoniation
21
R-1E-1 MV-2 V-1 MV-3
Ammoniation
22
R-1E-1 MV-2 V-1 MV-3
Plant Preparation for Start Up
(section by section)
26
R-1E-1 MV-2 V-1 MV-3
Plant Preparation for Start Up
(section by section)
27
R-1E-1 MV-2 V-1 MV-3
Plant Preparation for Start Up
(section by section)
28
R-1E-1 MV-2 V-1 MV-3
Initial Start Up (Feed in)
29
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
Send condensate to
– Reactor (R-1)
– Carbamate condenser (E-5)
for about 10 minutes by means of H.P. flushing pump (KW
injection points) and after that close the valves and close
HV1(CO2 to R1).
The NH3 present in the Reactor dissolves in the water
releasing heat and causing a temperature increase at the
Reactor bottom.
30
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
When the NH3 & H2O solution reaches the saturation and
this is shown by Reactor bottom temperature that stops to
increase (After about 10 minutes), proceed to open block
valve and motorized valve on NH3 discharge line and close
Carbonate recycle valve from H.P. Separator.
Then start feeding Ammonia to the Reactor. The NH3
feeding flow rate must be about 50 rpm of P-1 ammonia
feed pump.
31
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
32
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
33
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
At reactor overflow,
start opening the motorized valve (HV-5) at
Stripper outlet line and regulate the stripper level
controller (LV-2) in Manual mode.
On manual mode adjust the opening of the MS
steam pressure control valve (PV-14) admitting
steam to shell side of Stripper, checking that the
bottom temperature never exceeds 207°C.
34
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
35
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
Temperature increase:
– The NH3/CO2 ratio is decreasing, with consequent
pressure reduction in the system, it is necessary to
increase NH3.
Temperature decrease:
– The NH3/CO2 ratio is increasing, the pressure will
tend to rise, it is necessary to decrease NH3 or
increase CO2.
36
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
37
R-1E-1 MV-2 V-1 MV-3
M.P./L.P. sections going to receive urea
solution
39
R-1E-1 MV-2 V-1 MV-3
M.P./L.P. sections going to receive urea
solution
40
R-1E-1 MV-2 V-1 MV-3
NH3 and CO2 Feed in
HIC4
MP DECOMPOSER & AMMONIA ABSORBER
46
R-1E-1 MV-2 V-1 MV-3
R-1E-1 MV-2 V-1 MV-3
48
R-1E-1 MV-2 V-1 MV-3
49
R-1E-1 MV-2 V-1 MV-3
50
R-1E-1 MV-2 V-1 MV-3
AMMONIA RECEIVER
LP SECTION
Shut Down
Flushing
Short shut down
Long shut down
Emergency shutdown
53
R-1E-1 MV-2 V-1 MV-3
Flushing system
54
R-1E-1 MV-2 V-1 MV-3
HP Flushing system
55
R-1E-1 MV-2 V-1 MV-3
HP Flushing system
56
R-1E-1 MV-2 V-1 MV-3
HP Flushing system
57
R-1E-1 MV-2 V-1 MV-3
MP Flushing system
58
R-1E-1 MV-2 V-1 MV-3
LP Flushing system
59
R-1E-1 MV-2 V-1 MV-3
Plant shutdown
60
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
61
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
62
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
63
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
64
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
65
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
66
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
67
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
68
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
69
R-1E-1 MV-2 V-1 MV-3
Short Shutdown Procedure
PLEASE REMEMBER :
Open KW only one point at a time.
Confirm KW flushing by checking reduction in KW
pressure.
Close the process isolation valve first & then the
water injection valve.
HW & LW can be opened at various point
simultaneously.
70
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
IF SHUTDOWN IS PRE-PLANNED
– CHECK R-1 DRAIN LINE PRIOR TO FEED CUT.
Checking of R-1 drain line
Check KW pressure is about 180Kg/cm2.
Inject KW through R-1 drain line injection towards HV-4.
Be careful that R-1 open drain & close drain valves are tightly closed.
Open HV-4 & let KW to flow through HV-4 & HV-5 towards MV-2.
Check KW pressure has dropped to about 50Kg/cm2 to confirm drain
line is clear.
71
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
72
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
73
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
74
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
75
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
76
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
77
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
78
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
79
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
80
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP Loop Draining)
81
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
82
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
Stop the ammonia booster pump and close the suction and
delivery valves.
Send washing water to the top of C-1 for few minutes.
Drain the liquid of the C-1 to the carbonate tank through
HV-102 when washing is finished. Shut off the water and
drain the column to the closed drain.
Isolate the NH3 tank and absorber from the other medium
pressure equipment, leaving the pressure control in
automatic position.
83
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
84
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
85
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
86
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
87
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
88
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
89
R-1E-1 MV-2 V-1 MV-3
Long Shutdown Procedure
(HP loop draining)
90
R-1E-1 MV-2 V-1 MV-3
EMERGENCY SHUT DOWN
91
R-1E-1 MV-2 V-1 MV-3
EMERGENCY SHUT DOWN
Principal causes:
1. Process reasons:
Considerable pressure and / or temperature increases
Pipe line clogging because of crystallization
2. Sudden failure of services
3. Fires, and / or ruptures with uncontrollable losses of
toxic gasses.
92
R-1E-1 MV-2 V-1 MV-3
EMERGENCY SHUT DOWN
Safety interlocks
93
R-1E-1 MV-2 V-1 MV-3
EMERGENCY SHUT DOWN
Safety interlocks
94
R-1E-1 MV-2 V-1 MV-3
EMERGENCY SHUT DOWN
95
R-1E-1 MV-2 V-1 MV-3
EMERGENCY SHUT DOWN
96
R-1E-1 MV-2 V-1 MV-3
Electric Failure
97
R-1E-1 MV-2 V-1 MV-3
Electric Failure
98
R-1E-1 MV-2 V-1 MV-3
Electric Failure
99
R-1E-1 MV-2 V-1 MV-3
Electric Failure
100
R-1E-1 MV-2 V-1 MV-3
Electric Failure
101
R-1E-1 MV-2 V-1 MV-3
Steam Failure
102
R-1E-1 MV-2 V-1 MV-3
Steam Failure
103
R-1E-1 MV-2 V-1 MV-3
Steam Failure
104
R-1E-1 MV-2 V-1 MV-3
Steam Failure
105
R-1E-1 MV-2 V-1 MV-3
Steam Failure
106
R-1E-1 MV-2 V-1 MV-3
Cooling Water Failure
107
R-1E-1 MV-2 V-1 MV-3
Cooling Water Failure
Proceed as follows :
– Open E-41,E-9,E-7 top cooling water vents
– Stop feeding to the reactor. Trip compressor,
P-1,P-2 and all the pumps except for the washing
pumps must be stopped.
– Close LV-2,HV-5 and closing the steam valve
(PV-14) to the stripper
108
R-1E-1 MV-2 V-1 MV-3
Cooling Water Failure
109
R-1E-1 MV-2 V-1 MV-3
Instrument Air Failure
110
R-1E-1 MV-2 V-1 MV-3
Instrument Air Failure
111
R-1E-1 MV-2 V-1 MV-3
Instrument Air Failure
112
R-1E-1 MV-2 V-1 MV-3
Important Checks
113
R-1E-1 MV-2 V-1 MV-3
Important Checks
114
R-1E-1 MV-2 V-1 MV-3
Important Checks
115
R-1E-1 MV-2 V-1 MV-3
Important Checks
116
R-1E-1 MV-2 V-1 MV-3
Important Checks
117
R-1E-1 MV-2 V-1 MV-3
MP Loop Hand Over
Depressurize MP loop
– E-9 should be kept isolated from V-1.
– MV-2, E-7, C-1 & E-9 through 2” BD header on
C-1.
– HP loop should be kept isolated from MP loop.
– Steam / MP steam condensate should be cut to
E-2.
118
R-1E-1 MV-2 V-1 MV-3
MP Loop Hand Over
119
R-1E-1 MV-2 V-1 MV-3
MP Loop Hand Over
120
R-1E-1 MV-2 V-1 MV-3
V-1 Handing Over
121
R-1E-1 MV-2 V-1 MV-3
V-1 Handing Over
122
R-1E-1 MV-2 V-1 MV-3
V-1 Handing Over
123
R-1E-1 MV-2 V-1 MV-3
L P Loop Handing Over
124
R-1E-1 MV-2 V-1 MV-3
E-1 Handing Over
125
R-1E-1 MV-2 V-1 MV-3
E-1 Handing Over
126
R-1E-1 MV-2 V-1 MV-3
E-1 Handing Over
127
R-1E-1 MV-2 V-1 MV-3
E-1 Handing Over
128
R-1E-1 MV-2 V-1 MV-3
E-5 Handing Over
129
R-1E-1 MV-2 V-1 MV-3
E-5 Handing Over
130
R-1E-1 MV-2 V-1 MV-3
E-5 Handing Over
4. Line from
1. MV-4 –6”
2. Steam outlet flange 2 no.-20”
5. PSV flanges
1. 2 no. –6”.
2. E-5 shell side drain one no. 3”
Total 8 blinds. LT tapping 2no.
131
R-1E-1 MV-2 V-1 MV-3
E-5 Handing Over
132
R-1E-1 MV-2 V-1 MV-3
R-1 Handing Over
133
R-1E-1 MV-2 V-1 MV-3
R-1 Handing Over
Check –
1. R-1 open drains are in open condition.
2. R-1 CD are in closed position HV-4 close.
3. MV-8 is depressurized condition.
4. Confirm all the injections are closed.
5. Confirm P-11 is not running.
6. No water is coming out of HV-2 up stream
drain. Check HV-3 is removed
134
R-1E-1 MV-2 V-1 MV-3
R-1 Handing Over
135
R-1E-1 MV-2 V-1 MV-3
R-1 Handing Over
136
R-1E-1 MV-2 V-1 MV-3
For any type of queries
Please contact to
Prem Baboo
Mob-+919425735974
+918718870316
Prem.baboo@nfl.co.in
pbaboo@hotmail.com
137
R-1E-1 MV-2 V-1 MV-3