You are on page 1of 4

SK Construction

W.O.NO:SBU-PG/TSTPP-RAMAGUNDAM/100045/22627 Dated:16-09-2021
Name of Agency: S.K.
Billing Period: 01-09-2021 to 30-09-2021
RA bill :-02

Measurement Sheet Of M/s SK Construction for the Month Of Sep-2021


S.NO Description of Works Nos Length Breadth Ht/Depth Qty Unit

1 Excavation (Manually):-
a) Excavation for Plinth Drain MCC-C 1 7.500 1.000 0.450 3.375 Cum

b) Excavation for G.slab Extended part TP-42 1 7.400 0.300 0.700 1.554 "

c) Excavation for Bitumen work CR-16 (Soil Overburden) 10 1.500 1.500 0.550 12.375 "

Excavation for Plinth Protection Soling Filing MCC-C from Staircase


d) side to transformer 1 10.090 0.750 0.210 1.589 "

e) Excavation for Plinth Drain TP43 Grid A'3-C3 1 17.500 0.910 0.350 5.574 "

Excavation Electrial Foundation Conveyor 47 A/B Segment 11 grid


8-9
f) 2 2.500 2.650 1.200 15.900 "

g) Excavation for Plinth Drain TP42 Grid C'3-E3 1 10.550 0.910 0.510 4.896 "

h) Excavation for Soling Conveyor47 A Segment 15 grid 6-13 4 7.700 2.700 0.285 23.701 "
i) 0.000
0.000

Net qty for this bill 68.964 "

2 Sludge Cleaning :-
a) G.slab Extended part TP-42 for Brickwork PCC 1 17.475 0.34 1 5.942 Sqm
b) Cable pullpit MCC-C Raft PCC MH06&07 2 2.1 2.1 1 8.820 "
c) " MH04&05 2 2.55 2.55 1 13.005 "

CR16 footing Concrete top Cleaning for Bitumen parallel to


Conveyor 45 A/B Segment GP 38-GP29
d) 23 1.5 1.5 1 51.750

Sludge Cleaning for G.slab Soling North Side of Conveyor 47A


e) Between Drain & R.Wall 1 80 1.45 1 116.000

Sludge Cleaning for G.slab Soling South Side of Conveyor 47A


f) Between Drain & R.Wall Segment 6 1 55.5 2.1 1 116.550
Net qty for this bill 312.067 "

3 Backfiling (Manually):-
a) Conveyor 47A Segment 16 Grid 1-9 9 7.7 2.7 0.35 65.489 Cum
b) "
c) "

Net qty for this bill 65.489 "


0
4 Grade Slab Soling :- 0
a) Soling in TP-42 for Extended G.Slab 1 10.075 3.700 0.275 10.251 Cum
b) Soling MCC-C Plinth Drain 1 30.000 0.750 0.100 2.250 "
c) Conveyor 47 A Segment15 grid 3 1 7.700 2.700 0.230 4.782 "
Net qty for this bill 17.283

5 Hard Barrication:-
a) Pullpit Near TP-43 2 10 1 1 20 Cum
b) " MCC-C 2 10 1 1 20 "
c) HGTUS 1 15 1 1 15
d) Pullpit TP42/CR13A 1 10 1 1 10
e) W.shop Building 1 65 1 1 65

Net qty for this bill 130 "


6 Pouring Of Concrete
Manually:-
a) MCC-C Plinth PCC 1 30.000 0.980 0.100 2.940 Cum
b) Conveyor 47 A/B Segment13 Grid 2-5 4 2.700 7.100 0.100 7.668 "
c) TP-42 extended G.Slab PCC for b/work 1 10.075 0.300 0.075 0.227 "
" 1 7.400 0.300 0.075 0.167
d) Cable Pullpit Near CR14 MH04 Raft PCC 1 2.150 2.150 0.075 0.347 "
" Duct Bank Mh04 to MH05 1 15.000 1.650 0.075 1.856 "
Cable Pullpit TP43 MH05 Raft PCC 1 2.150 2.150 0.075 0.347
e) Cable Pullpit MCC-C MH06&MH07 Raft PCC 2 2.050 2.050 0.075 0.630 "
" Duct Bank Mh06 to MH07 1 15.000 1.600 0.075 1.800
f) Excavation for Plinth Drain TP43 Grid A'3-C3 1 17.500 0.910 0.075 1.194 "
g) TP-42 Deck Slab +25.00 mtr T.padestals RCC 0 2.700 7.700 0.075 0.000 "
Padestal mark 06 4 0.250 0.150 0.150 0.023 "
Padestal mark 08 8 0.260 0.220 0.200 0.092 "
Padestal mark 09 4 0.120 0.120 0.200 0.012 "
TP-42 Deck Slab +22.500 mtr T.padestals RCC 0 2.700 7.700 0.075 0.000 "
Padestal mark 06 4 0.250 0.150 0.150 0.023 "
Padestal mark 05 8 0.260 0.220 0.200 0.092 "
h) MCC-C Plinth Drain PCC 1 7.500 0.910 0.075 0.512

Net qty for this bill 17.927 "

7 Scaffolding:-
a) HGTUS for Concreting 4 2 2 2 32.000 Cum
b) Switchgear Room MCC-C 1 17 1 5 85.000
c) Control Room For Ceiling Paint 1 5 2.5 4.5 56.250
d) External Side of MCC-C for Plaster repair 3 4 1.5 5 90.000

Net qty for this bill 263.250 "

8 Shifting of Steel

a) Steel Shifting from yard to Workplace for Conveyor 47 A & Cable


Pullpit /W.shop 5.000 MT

Net qty for this bill 5.000 "


ABSTRACT SHEET
SK Construction
W.O.NO:SBU-PG/TSTPP-RAMAGUNDAM/100045/22627 Dated:16-09-2021
RA Bill No:02
Billing period : 01-09-2021 to 30-09-2021 Date:-31-08-2021

Item code Description of item Unit BOQ qty Rate Amount Quantity Amount
Previous bill This bill Up to date Previous bill This bill Up to date
Excavation (manual) in all kind of soils up to depth of 2mts from ground level
LA0299540614 Cum 250.00 450.00 112,500.00 171.07 68.96 240.03 76,980.15 31,032.00 108,012.15
including labour,tools,lead and lifts etc.complete
OA09999852138 Labour Charges for removal of slush including dressing for PCC preparation Sqm 750.00 140.00 105,000.00 740.00 0.00 740.00 103,600.00 - 103,600.00

Laying approved dry stone rubble soling 230 mm thick below grade slabs,
plinth protection, and at other locations, set in regular lines, interstices
LB0499540054 thoroughly filled with small chips and compacted by hand rollers after Cum 900.00 250.00 225,000.00 68.00 192.00 260.00 16,999.00 48,000.00 64,999.00
spreading 12mm layer of grit on top, etc., complete, as indicated in
drawings, specification and as directed by the ENGINEER

OA0999850484 Labour Charges for hard barricading fixing rm 500.00 45.00 22,500.00 145.00 130.00 275.00 6,525.00 5,850.00 12,375.00

Placing in position design mix reinforced cement concrete or plain concrete


(with Boom Placer) with 20mm downgraded coarse aggregates for works
at all levels to all shapes as shown in the drawings, including scaffolding,
OA0999850721 mixing, placing vibrating, curing, dewatering wherever necessary, providing Cum 0.00 275 0.00 0.00 0.00 - - -
construction joints, leaving cut-outs/ pockets, etc., complete, but excluding
the cost of providing shuttering, cement and reinforcement all as per
specifications and as directed by the ENGINEER (Nothing extra shall be
paid for water retaining structures, all the measurement shall be as per
approved drawings)

Mannually placing in position design mix reinforced cement concrete or


plain concrete with 20mm downgraded coarse aggregates for works at all
levels to all shapes as shown in the drawings, including scaffolding, mixing,
OA0999851439 placing vibrating, curing, dewatering wherever necessary, providing
Cum 100.00 450 45,000.00 62.76 19.927 82.68 28,239.75 8,967.15 37,206.90
construction joints, leaving cut-outs/ pockets, etc., complete, but excluding
the cost of providing shuttering, cement and reinforcement all as per
specifications and as directed by the ENGINEER (Nothing extra shall be
paid for water retaining structures, all the measurement shall be as per
approved drawings)
Labour Charges for fixing and removal staging work for building
OA0999851997 Cum 600.00 35 21,000.00 331.50 263.25 594.75 11,602.50 9,213.75 20,816.25
slabs,beams,columns,tanks and retaining walls above 3m height.
Providing and laying brick work in cement mortar of 1:4 mix using burnt clay
bricks of class designation 50 or above or fly ash bricks, including curing 0.00 0.00 0.00 0.00 - - -
etc. complete at all levels and heights including staging & scafolding
(Bricks,cement, sand and scafolding materials free issue)
LB0199540138 (i) 230 mm brick wall Cum - 1,200 0.00 0.00 0.00 - - -

Providing 12mm thick plain faced cement plaster in cement mortar 1:3 for
RCC, brick work/block work sides and undersides of slabs, canopies,chajjas
HP0099541635 with drip moulding,etc. including scafolding ,curing ,hacking of concrete Sqm - 210 0.00 0.00 0.00 - - -
surfaces where required etc, complete per specification (Bricks,
cement,sand and scafolding aterials free issue)

Providing 20 mm thick exterior sand faced cement plaster in two layers


( First layer of 12 mm in cement mortar 1:3 and second layer of 8 mm
HP0099541620 thickness in cement ortar 1:2)using sand faced for RCC, masonry including Sqm - 290 0.00 0.00 0.00 - - -
scafolding, curing,hacking of concrete surfaces where required etc.,
complete per specifications.. (Bricks,Cement, sand and scaffolding materials
free issue)
OA1699850028 Shifting of TMT steel from barbending yard to work location manually MT 20 2,500 50000 8.75 5.00 13.75 21875 12500 34375
LA0399540011 Back filling soil , as per projects specification Cum 500 55 27500 42.35 65.48 107.83 2329.25 3601.4 5930.65
608,500.00 268,150.65 119,164.30 381,384.30
Ref no : SK/TPL/STACKER/RA-02/ 2021 Date:-30-10-2021
SK Construction
CHP Package, 2x800 MW stage-1NTPC Ramagundam ,Telangana-505215
Telephone: 6374005624
E-Mail : sk7809383@gmail.com
GOODS & SERVICE TAX INVOICE
PAN No. HAFPK1325C GSTIN/UIN 10HAFPK1325C1ZI
Billing & Shipping Address: RA Bill.:- 02 DATE:- 30-09-2021
INVOICE NO SK/CHP/RA-02
TATA PROJECTS LIMITED, LOI NO.:
TSTPP-1,NTPC RAMAGUNDAM , WO NO.: 22627 DATE :- 16-09-2021
(TELANGANA STATE). GST
NO: 36AAACT4119L1Z9 Work Period :-01-09-2021 to 30-09-2021

AMOUNT in INR
Sr. No. DESCRIPTION SAC Code
Civil Works for WTP 2x800 MW Previous Bill This Bill Cummulative Bill
A Telangana Super Thermal Power 995426 119,164.30 119,164.30
Project of NTPC RAMAGUNDAM
Sub Total (A)= - 119,164.30 119,164.30
B Goods & Service Tax (GST)
i IGST @ 18% on (A) - 21,450.00 21,450.00
Sub Total (B)= - 21,450.00 21,450.00
Total (A+B)= 0 140,614.30 140,614.30
Rupees One Lakh Fourty Thousand Six Hundred And Fourteen Paise Thirty Only
Service Category : Work Contract Services

For

(site-in- Incharge)