Slide Sub Grade Prepareation

The document discusses bill subgrade preparation, with objectives to identify methods for subgrade work implementation, quantification calculations, and on-site quality control methods. It provides details on subgrade definition, measurement, layout areas, and a comparison of bill of quantities versus actual quantities, showing discrepancies between estimated and actual amounts of earthworks.

Uploaded by

Kamal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
145 views13 pages

Slide Sub Grade Prepareation

The document discusses bill subgrade preparation, with objectives to identify methods for subgrade work implementation, quantification calculations, and on-site quality control methods. It provides details on subgrade definition, measurement, layout areas, and a comparison of bill of quantities versus actual quantities, showing discrepancies between estimated and actual amounts of earthworks.

Uploaded by

Kamal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

BILL SUBGRADE PREPARATION

OBJEKTIF:
1) PENGENALPASTIAN KAEDAH PERLAKSANAAN KERJA-KERJA SUB GRADE
2) PENGENALPASTIAN KAEDAH PENGIRAAN MELALUI BQ, SPESIFIKASI DAN MYCESMM
3) PENGENALPASTIAN KUANTITI DI DALAM BQ BERBANDING KUANTITI SEBENAR DIANGGARKAN
4) KAEDAH PERLAKSANAAN KERJA-KERJA DI TAPAK QC DAN LAB (METHOD OF STATEMENT)
5) SOAL JAWAB
BILL SUBGRADE PREPARATION
BILL NO. 3 - EARTHWORKS

ITEM CODE RATE AMOUNT


DESCRIPTION UNIT QTY.
NO. NO. (RM) (RM)

High Energy Impact Compaction General Filling

J F371 To scarify, blend with the stabilizer, compact and m³ 33,500 30.00 1,005,000.00
shape 300mm thick subgrade to achieve minimum
CBR 12.1% as per specification

ITEM CODE RATE AMOUNT


DESCRIPTION UNIT QTY.
NO. NO. (RM) (RM)

NEW PAVEMENT

R100 SUBGRADE PREPARATION

A R110 Earth material to receive road pavement. m² 368,300 4.00 1,473,200.00

B F131 Earth material, commencing from top subgrade to max m³ 4,530 8.00 36,240.00
depth 0.30m below formation (due to none
compliance of CBR criteria) in cuttings.

C F332 Imported material from Contractor's own source with m³ 4,530 40.00 181,200.00
grading limits as per Specification to form
embankment including formation of benches.

D R140 Proof rolling test at formation level as specified in the m² 368,300 2.00 736,600.00
Specifications or as directed by the S.O. for receiving
road pavement.
SUBGRADE DEFINITION – JKR S2-16
SUBGRADE DEFINITION – JKR S2-16
MYCESMM2 - SUBGRADE
MYCESMM2 - SUBGRADE
SUBGRADE MEASUREMENT
SUBGRADE DETAILS

23m
SUBGRADE DETAILS
LAYOUT KAWASAN CADANGAN KERJA

CH 44+661.984 – CH 44+300.00
LAYOUT KAWASAN CADANGAN KERJA

CH 44+300 – CH 43+600.00
PERINCIAN KUANTITI KESELURUHAN
CUTTING AREA FILLING AREA 37060 37130 70.00
CHAINAGE CHAINAGE 37130 37450 320.00
LENGTH (m) LENGTH (m) 37450 37750 300.00
FROM TO FROM TO
31000 31520 520.00 37750 39100 1,350.00
31520 31690 170.00 39100 39650 550.00
39650 39760 110.00
31690 31845 155.00
39760 40150 390.00
31845 32125 280.00
40150 40700 550.00
32125 32435 310.00
40700 40900 200.00
32435 33000 565.00
40900 41280 380.00
33000 33985 985.00 41280 41480 200.00
33985 34255 270.00 41480 41625 145.00
34255 34285 30.00 41625 41800 175.00
34285 34370 85.00 41800 42575 775.00
34370 34425 55.00 42575 42725 150.00
34425 34590 165.00 42725 42750 25.00
34590 34835 245.00 42800 43275 475.00
34835 34930 95.00 43275 43650 375.00
34930 35125 195.00 43650 44050 400.00
35125 35475 350.00 44050 44250 200.00
35475 35700 225.00 44250 44661.98 411.98
35700 35825 125.00 TOTAL (m) 5,390.00 TOTAL (m) 8,221.98
35825 36200 375.00
36200 36550 350.00
36550 36600 50.00 TOTAL LENGTH
13,611.98
(m)
36600 36650 50.00
36650 36750 100.00
36750 37025 275.00
37025 37060 35.00
PERBANDINGAN KUANTITI BQ &
ANGGARAN SEBENAR

Quantity Amount (RM)


Bill No. Item No. Code No. Description Unit Rate (RM) Remark
BQ Actual Def BQ Actual Def
To scarify, blend with the stabilizer,
compact and shape 300mm thick
3 A F371 m3 33,500 93,923 60,423 30.00 1,005,000.00 2,817,680.69 1,812,680.69
subgrade to achieve minimum CBR
12.1% as per specification
Earth material, commencing from
top subgrade to max depth 0.30m
5 B F131 below formation (due to the non m3 4,530 37,191 32,661 8.00 36,240.00 297,528.00 261,288.00
compliance of CBR criteria) in
cuttings
Imported material from contractor's
own source with the grading limits as
5 C F332 per specification to form m3 4,530 37,191 32,661 40.00 181,200.00 1,487,640.00 1,306,440.00
embankment including formation of
benches