You are on page 1of 17

PROJEK RUNDING TERUS SEKOLAH SECARA REKA DAN BINA

SEKOLAH MENENGAH KEBANGSAAN KOTA PUTERI 2, MASAI, JOHOR


KONTRAKTOR TURNKEY : BAKTI INSANI SDN BHD
ACADEMIC BLOCK
TENDER
REF

ELEMENT/DESCRIPTION

AMOUNT (RM)

BUDGET
TOTAL LAB.

TOTAL MATL

TOTAL

MARGIN

ACTUAL
TOTAL
TOTAL SUBTOTAL LABOUR
MATERIAL
RATE

TOTAL
AMOUNT

SUMMARY
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Piling works
Work Below Lowest Floor Level
Frame
Upper Floor Construction
Roof and roof covering
Staircases
External wall
Internal wall and partition
Door and window
Floor finishes
Wall finishes
Ceiling finishes
Sanitary appliances
Apron and perimeter drain
Internal signages
TOTAL

208,705.00
170,209.15
453,962.25
254,725.00
226,331.00
81,211.40
74,394.00
23,564.00
284,360.00
43,494.00
115,472.00
94,845.00
79,380.00
37,818.50
30,000.00

234,235.00
46,266.14
125,603.40
73,902.75
28,552.60
13,496.53
15,765.20
6,255.10
17,116.60
18,110.00
42,075.00
50,781.70
7,506.50
-

11,300.00
99,705.85
235,355.75
145,125.70
143,771.70
48,890.90
50,765.00
15,306.00
144,707.00
20,492.50
45,332.80
20,875.50
61,050.00
19,033.75
25,000.00

245,535.00
145,971.99
360,959.15
219,028.45
172,324.30
62,387.43
66,530.20
21,561.10
161,823.60
38,602.50
87,407.80
71,657.20
61,050.00
26,540.25
25,000.00

(36,830.00)
24,237.16
93,003.10
35,696.55
54,006.70
18,823.97
7,863.80
2,002.90
122,536.40
4,891.50
28,064.20
23,187.80
18,330.00
11,278.25
5,000.00

24,768.58

110,915.33

177,560.46
34,448.00

177,560.46
170,131.90
-

2,178,471.30

679,666.52

1,086,712.45

1,766,378.97

412,092.33

24,768.58

110,915.33

212,008.46

347,692.36

ACADEMIC BLOCK
PILING
TENDER
REF

ELEMENT/DESCRIPTION

1
A
B
C

PILING WORKS
Mobilisation equipments & demobilisation
Setting out,piling record & as-built drawings
Supply PC G45 250mm x 250mm piles
12m starter
12m extension
9m extension
Handle,transport and pitch for 250mm x 250mm piles
Drive only for 250mm x 250mm piles
Jointing/extension for 250mm x 250mm piles
Cut off pile head for 250mm x 250mm piles
Chainsaw
Hacking
Preliminary testing
Subsequent testing
Sub-total

D
E
F
G

H
I

UNIT QTY

LS
LS
M
No
No
No
No
M
No
No
No
No
No
No

1
1
4515

RATE

32.00

BUDGET

AMOUNT (RM)

LAB. RATE MATL. RATE

2,000.00
1,000.00
144,480.00

1,800.00
9,500.00
40.00

TOTAL LAB.

180,600.00

1,800.00
9,500.00
-

TOTAL

QTY

1,800.00 LS
9,500.00 LS
180,600.00
156
222
32

430
4515
215
215

2
2

6.00
8.00
15.00
20.00

4,500.00
3,000.00

2,580.00
36,120.00
3,225.00
4,300.00

9,000.00
6,000.00
208,705.00

9.00
6.00
20.00
25.00

3,500.00
3,000.00

3,870.00
27,090.00
4,300.00
5,375.00

7,000.00
6,000.00
234,235.00

GROSS

ACTUAL
TOTAL MATL

11,300.00

3,870.00
27,090.00 4095.5
4,300.00
201
5,375.00
42
237
7,000.00
6,000.00
245,535.00

LABOUR

MATERIAL

TOTAL RATE

AMOUNT

4,000.00
5,227.00

4,000.00
5,227.00

309.00
320.00
278.78

48,204.00
71,040.00
8,920.96
28,668.50
4,221.00
1,470.00
4,740.00
1,069.00

7.00
21.00
35.00
20.00
1,069.00

177,560.46

PROFIT
BUDGET

200.00
(8,500.00)
(36,120.00)
(1,290.00)
9,030.00
(1,075.00)
(1,075.00)
2,000.00
(36,830.00)

REMARKS
PROFIT
ACTUAL

(2,000.00)
(4,227.00)
144,480.00
(48,204.00)
(71,040.00)
(8,920.96)
2,580.00
7,451.50
(996.00)
4,300.00
(1,470.00)
(4,740.00)
7,931.00
6,000.00 rate incl. In prelim.
31,144.54 test

In prelim.

BLOK AKADEMIK
TENDER
REF

ELEMENT/DESCRIPTION

UNIT

QTY

RATE

AMOUNT (RM)

BUDGET
LAB.
RATE

MATL.
RATE

TOTAL LAB.

TOTAL MATL

ACTUAL
TOTAL

MARGIN

QTY
W/DONE

LAB. RATE

MATE.
RATE

SUB RATE

ACTUAL
TOTAL LAB.

TOTAL MATL

TOTAL SUB
RATE

TOTAL

BLOK AKADEMIK
TENDER
REF

ELEMENT/DESCRIPTION

UNIT

2
A
B
C
D
E
F
G
H
I
J

WORK BELOW LOWEST FLOOR LEVEL


Exc. oversite 250mm deep
Exc. pile caps/footing not exc. 1.50m deep
Ditto exc. 3.00m deep
Exc. for ground beam ditto
150mm thick hardcore
50mm thick lean concrete G15 beneath pile cap
50mm ditto ground beam
VRC G25 in pile cap/pad footing
Ditto Column stumps
Ditto ground beam
VRC G30 in pile cap/pad footing
Ditto Column stumps
Ditto 125mm thick in ground floor slab
Reinforcement bar in pile cap/footing
Y16
R10
Ditto in column stumps
Ditto in ground beam
Y16
Y20
Y25
BRC B6 in floor slab
BRC A10 in floor slab
Sawn formwork to sides of pile cap/footing
Ditto column stump
Ditto ground beam
0.25mm thick damp proof membrance
Prepare and apply termite treatment
Sub-total

M2
M3
M3
M3
M2
M2
M2
M3
M3
M3
M3
M3
M2
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
M2
M2
M2
M2
M2
M2
M2

K
L

M
N

O
P
Q
R
S
T

QTY

RATE

BUDGET

AMOUNT (RM)

LAB.
RATE

1586
195
2
107
1586
130
241
15
11
145

2.50
8.50
10.00
8.50
8.50
7.00
7.00
185.00
185.00
185.00

3,965.00
1,657.50
20.00
909.50
13,481.00
910.00
1,687.00
2,775.00
2,035.00
26,825.00

8.00
8.00
8.00
2.50
1.30
1.30
28.60
28.60
28.60

1586
1908

18.50
1.85

29,341.00
3,529.80

4451
8508

1.85
1.85

1586
211
107
1140
1586
1586

MATL.
RATE

2.00

TOTAL LAB.

TOTAL MATL

ACTUAL
TOTAL

MARGIN

5.70
5.50
5.50
122.10
122.10
122.10

1,560.00
16.00
856.00
3,965.00
169.00
313.30
429.00
314.60
4,147.00

3,172.00
9,040.20
715.00
1,325.50
1,831.50
1,343.10
17,704.50

3,172.00
1,560.00
16.00
856.00
13,005.20
884.00
1,638.80
2,260.50
1,657.70
21,851.50

793.00
97.50
4.00
53.50
475.80
26.00
48.20
514.50
377.30
4,973.50

3.60
0.32

15.30
1.15

5,709.60
610.56

24,265.80
2,194.20

29,975.40
2,804.76

(634.40)
725.04

8,234.35
15,739.80

0.32
0.32

1.15
1.15

1,424.32
2,722.56

5,118.65
9,784.20

6,542.97
12,506.76

1,691.38
3,233.04

12.00

19,032.00

1.10

7.20

1,744.60

11,419.20

13,163.80

5,868.20

24.00
24.00
24.00
2.00
1.20

5,064.00
2,568.00
27,360.00
3,172.00
1,903.20
170,209.15

13.00
13.00
13.00
0.50
1.60

7.00
7.00
7.00
1.00

2,743.00
1,391.00
14,820.00
793.00
2,537.60
46,266.14

1,477.00
749.00
7,980.00
1,586.00
99,705.85

4,220.00
2,140.00
22,800.00
2,379.00
2,537.60
145,971.99

844.00
428.00
4,560.00
793.00
(634.40)
24,237.16

QTY W/DONE LAB. RATE

1,586.00
195.00
2.00
107.00
1,380.00
140.00
220.00
176.00
103.59
11.00
1,672.00
3,683.00
375.00
624.00
720.00
20,884.00
1,560.00
211.00
107.00
1,218.00
1,586.00
1,586.00

2.00
2.00
2.00
23.50
23.50
23.50
2.95
0.29
0.29
0.29
0.29
0.29
1.00
0.30
-

MATE.
RATE

2.10
5.50
5.50
111.00
117.50
117.50
14.69
1.12
1.19
1.12
1.12
1.12
10.87
1.23
-

SUB RATE

2.00
6.00
8.00
8.00
18.00
18.00
18.00
1.00

TOTAL LAB.

2,760.00
280.00
440.00
4,136.00
2,434.37
258.50
4,932.40
1,049.66
106.88
177.84
205.20
5,951.94
1,560.00
475.80
24,768.58

TOTAL MATL

2,898.00
770.00
1,210.00
19,536.00
12,171.83
1,292.50
24,561.68
4,139.69
445.88
698.88
809.28
23,473.62
16,957.20
1,950.78
110,915.33

TOTAL SUB
RATE

3,172.00
1,170.00
16.00
856.00
3,798.00
1,926.00
21,924.00
1,586.00
34,448.00

TOTAL

3,172.00
1,170.00
16.00
856.00
5,658.00
1,050.00
1,650.00
23,672.00
14,606.19
1,551.00
29,494.08
5,189.35
552.75
876.72
1,014.48
29,425.56
18,517.20
3,798.00
1,926.00
21,924.00
2,426.58
1,586.00
170,131.90

BLOK AKADEMIK (B,C & D)


TENDER

BUDGET

ACTUAL
BLOK B

REF.

1
A
B
C
D
E
F
G
H
I
J

K
L

M
N

O
P
Q
R
S
T

ELEMENT/DESCRIPTION

WORK BELOW LOWEST FLOOR LEVEL


Exc. oversite 250mm deep
Exc. pile caps/footing not exc. 1.50m deep
Ditto exc. 3.00m deep
Exc. for ground beam ditto
150mm thick hardcore
50mm thick lean concrete G15 beneath pile cap
50mm ditto ground beam
VRC G25 in pile cap/pad footing
Ditto Column stumps
Ditto ground beam
VRC G30 in pile cap/pad footing
Ditto Column stumps
Ditto 125mm thick in ground floor slab
Reinforcement bar in pile cap/footing
Y16
R10
Reinforcement in column stumps
Reinforcement in ground beam
Y16
Y20
Y25
R10
BRC B6 in floor slab
BRC A10 in floor slab
Sawn formwork to sides of pile cap/footing
Ditto column stump
Ditto ground beam
0.25mm thick damp proof membrance
Prepare and apply termite treatment
Sub-total

BLOK AKADEMIK (B,C & D)

TOTAL
UNIT BLOCK BLOCK BLOCK
QTY
B
C
D

M2
M3
M3
M3
M2
M2
M2
M3
M3
M3
M3
M3
M2
Kg
kg
kg
Kg
Kg
Kg
Kg
Kg
Kg
M2
M2
M2
M2
M2
M2
M2

RATE

AMOUNT

BLOCK
B

BLOCK
C

BLOCK
D

TOTAL
QTY

LAB.
RATE

698
86
1
47
698
57
106
7
5
64

603
74
1
41
603
50
92
5
4
55

285
35
19
285
23
43
3
2
26

1,586
195
2
107
1,586
130
241
15
11
145

2.50
8.50
10.00
8.50
8.50
7.00
7.00
185.00
185.00
185.00

3,965.00
1,657.50
20.00
909.50
13,481.00
910.00
1,687.00
2,775.00
2,035.00
26,825.00

698
86
1
47
698
57
106
7
5
64

603
74
1
41
603
50
92
5
4
55

285
35
19
285
23
43
3
2
26

1,586
195
2
107
1,586
130
241
15
11
145

8.00
8.00
8.00
2.50
1.30
1.30
28.60
28.60
28.60

698
840

603
726

285
344

1,586
1,910

18.50
1.85

29,341.00
3,533.50

698
840

603
726

285
344

1,586
1,910

1,958
3,744

1,690
3,233

801
1,531

4,449
8,508

1.85
1.85

8,230.65
15,739.80

1,958
3,744

1,690
3,233

801
1,531

4,449
8,508

MATE.
RATE

2.00

TOTAL LAB

TOTAL MATT

TOTAL

MARGIN
QTY

5.70
5.50
5.50
122.10
122.10
122.10

1,560.00
16.00
856.00
3,965.00
169.00
313.30
429.00
314.60
4,147.00

3,172.00
9,040.20
715.00
1,325.50
1,831.50
1,343.10
17,704.50

3,172.00
1,560.00
16.00
856.00
13,005.20
884.00
1,638.80
2,260.50
1,657.70
21,851.50

793.00
97.50
4.00
53.50
475.80
26.00
48.20
514.50
377.30
4,973.50

3.60
0.32

15.30
1.15

5,709.60
611.20

24,265.80
2,196.50

29,975.40
2,807.70

(634.40)
725.80

0.32
0.32

1.15
1.15

1,423.68
2,722.56

5,116.35
9,784.20

6,540.03
12,506.76

1,690.62
3,233.04

698

603

285

1,586

12.00

19,032.00

698

603

285

1,586

1.10

7.20

1,744.60

11,419.20

13,163.80

5,868.20

93
47
502
698
698

80
41
433
603
603

38
19
205
285
285

211
107
1,140
1,586
1,586

24.00
24.00
24.00
2.00
1.20

5,064.00
2,568.00
27,360.00
3,172.00
1,903.20
170,209.15

93
47
502
698
698

80
41
433
603
603

38
19
205
285
285

211
107
1,140
1,586
1,586

13.00
13.00
13.00
0.50
1.60

7.00
7.00
7.00
1.00

2,743.00
1,391.00
14,820.00
793.00
2,537.60
46,266.14

1,477.00
749.00
7,980.00
1,586.00
99,705.85

4,220.00
2,140.00
22,800.00
2,379.00
2,537.60
145,971.99

844.00
428.00
4,560.00
793.00
(634.40)
24,237.16

%
W/DONE

698.00
86.00
1.00
47.00
620.00
60.00
100.00
108.00
43.24
5.00
928.00

100%
100%
100%
100%
100%
100%
100%

BLOK C
QTY
W/DONE

QTY

%
W/DON
E

BLOK D
QTY
W/DONE

QTY

%
W/DON
E

QUANTITY
%x
W/DONE

100%
100%
100%
100%

698.00
86.00
1.00
47.00
620.00
60.00
100.00
- - 108.00
43.24
5.00
928.00

603.00
74.00
1.00
41.00
510.00
60.00
80.00
48.00
41.35
4.00
512.00

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

603.00
74.00
1.00
41.00
510.00
60.00
80.00
48.00
41.35
4.00
512.00

285.00
35.00
19.00
250.00
20.00
40.00
20.00
19.00
2.00
232.00

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

285.00
35.00
19.00
250.00
20.00
40.00
20.00
19.00
2.00
232.00

1,645.00
165.00

100%
100%

1,645.00
165.00

1,228.00
124.00

100%
100%

1,228.00
124.00

810.00
86.00

100%
100%

810.00
86.00

720.00
10,355.00
2,727.00

100%
100%
100%

720.00
10,355.00
2,727.00

249.00
7,995.00
1,855.00

100%
100%
100%
100%

249.00
7,995.00
1,855.00

375.00
2,534.00
441.00

100%
100%
100%
100%

375.00
2,534.00
441.00

813.00
93.00
47.00
580.00
698.00
698.00

100%
100%
100%
100%
100%
100%

813.00
93.00
47.00
580.00
698.00
698.00

513.00
80.00
41.00
433.00
603.00
603.00

100%
100%
100%
100%
100%
100%

513.00
80.00
41.00
433.00
603.00
603.00

234.00
38.00
19.00
205.00
285.00
285.00

100%
100%
100%
100%
100%
100%

234.00
38.00
19.00
205.00
285.00
285.00

TOTAL QTY

1,586.00
195.00
2.00
107.00
1,380.00
140.00
220.00
176.00
103.59
11.00
1,672.00
3,683.00
375.00
624.00
720.00
20,884.00
5,023.00
1,560.00
211.00
107.00
1,218.00
1,586.00
1,586.00

W/DONE

1,586.00
195.00
2.00
107.00
1,380.00
140.00
220.00
176.00
103.59
11.00
1,672.00
3,683.00
375.00
624.00
720.00
20,884.00
5,023.00
1,560.00
211.00
107.00
1,218.00
1,586.00
1,586.00

LAB.
RATE

2.00
2.00
2.00
23.50
23.50
23.50
2.95
0.29
0.29
0.29
0.29
0.29
0.29
1.00
0.30
-

MATE.
RATE

2.10
5.50
5.50
111.00
117.50
117.50
14.69
1.12
1.19
1.12
1.12
1.12
1.19
10.87
1.23
-

SUB
RATE

TOTAL LAB.
RATE

TOTAL MATE.
RATE

TOTAL SUB.
RATE

2.00
6.00
8.00
8.00
18.00
18.00
18.00
1.00

2,760.00
280.00
440.00
4,136.00
2,434.37
258.50
4,932.40
1,049.66
106.88
177.84
205.20
5,951.94
1,456.67
1,560.00
475.80
26,225.25

2,898.00
770.00
1,210.00
19,536.00
12,171.83
1,292.50
24,561.68
4,139.69
445.88
698.88
809.28
23,473.62
5,977.37
16,957.20
1,950.78
116,892.70

3,172.00
1,170.00
16.00
856.00
3,798.00
1,926.00
21,924.00
1,586.00
34,448.00

TOTAL
AMOUNT

3,172.00
1,170.00
16.00
856.00
5,658.00
1,050.00
1,650.00
23,672.00
14,606.19
1,551.00
29,494.08
5,189.35
552.75
876.72
1,014.48
29,425.56
7,434.04
18,517.20
3,798.00
1,926.00
21,924.00
2,426.58
1,586.00
177,565.94

GROSS
PROFIT
PROFIT
BUDGET
ACTUAL

793.00
97.50
4.00
53.50
475.80
26.00
48.20
514.50
377.30
4,973.50
(634.40)
725.80
1,690.62
3,233.04
5,868.20
844.00
428.00
4,560.00
793.00
(634.40)
24,237.16

793.00
487.50
4.00
53.50
7,823.00
(140.00)
37.00
2,775.00
2,035.00
3,153.00
(14,606.19)
(1,551.00)
(153.08)
3,533.50
(5,189.35)
(552.75)
8,230.65
15,739.80
(876.72)
(1,014.48)
(29,425.56)
(7,434.04)
19,032.00
(18,517.20)
1,266.00
642.00
5,436.00
745.42
317.20
(7,356.79)

REMARKS

TENDER

BUDGET

ACTUAL
BLOK B

REF.

ELEMENT/DESCRIPTION

UNIT BLOCK BLOCK BLOCK


B
C
D

6
A
B
C
D
E
F
G
H
I
J
K
L

STAIRCASES AND FINISHES


VRC G25 in staircase
M3
Ditto in landing beam
M3
Ditto in landing slab
M3
Reinforcement in staircase
KG
Ditto in landing beam
KG
Ditto in landing slab
KG
Sawn formwork to sloping soffit of staircase
M2
Ditto of landing beam
M2
Ditto of landing slab
M2
Ditto to undercut of riser
M
Ditto to raking open string
M
Staircases finishes and railing
Flight
Sub-total

7
A
B
C
D
E

EXTERNAL WALLS
115mm thick common brickwall
Damp proof course
6mm bonding ties
Mild steel railing
50mm Upvc spout pipe 250mm long

TOTAL
QTY

RATE

INTERNAL WALLS
115mm thick common brickwall
Damp proof course
6mm bonding ties

BLOCK
B

BLOCK
C

BLOCK
D

TOTAL
QTY

LAB.
RATE

MATE.
RATE

TOTAL LAB

TOTAL MATT

TOTAL

MARGIN
QTY

8
2
71
1,513
911
3,245
46
29
71
158
26
4

7
2
61
1,307
787
2,802
40
25
61
136
24
3

3
1
29
619
373
1,327
19
12
29
64
13
1

18
5
161
3,439
2,071
7,374
105
66
161
358
63
8

185.00
185.00
185.00
1.85
1.85
1.85
24.00
24.00
24.00
8.00
8.00
1,500.00

3,330.00
925.00
29,785.00
6,362.15
3,831.35
13,641.90
2,520.00
1,584.00
3,864.00
2,864.00
504.00
12,000.00
81,211.40

8
2
71
1,513
911
3,245
46
29
71
158
26
4

7
2
61
1,307
787
2,802
40
25
61
136
24
3

3
1
29
619
373
1,327
19
12
29
64
13
1

18
5
161
3,439
2,071
7,374
105
66
161
358
63
8

26.00
26.00
26.00
0.32
0.32
0.32
13.00
13.00
13.00
0.65
0.65

111.00
111.00
111.00
1.15
1.15
1.15
7.00
7.00
7.00
0.30
0.30
1,400.00

468.00
130.00
4,186.00
1,100.48
662.72
2,359.68
1,365.00
858.00
2,093.00
232.70
40.95
13,496.53

1,998.00
555.00
17,871.00
3,954.85
2,381.65
8,480.10
735.00
462.00
1,127.00
107.40
18.90
11,200.00
48,890.90

2,466.00
685.00
22,057.00
5,055.33
3,044.37
10,839.78
2,100.00
1,320.00
3,220.00
340.10
59.85
11,200.00
62,387.43

864.00
240.00
7,728.00
1,306.82
786.98
2,802.12
420.00
264.00
644.00
2,523.90
444.15
800.00
18,823.97

M2
M
No
M
No

973
388
528
44
53

841
335
456
38
46

398
158
216
18
21

2,212
881
1,200
100
120

26.00
2.00
0.60
120.00
20.00

57,512.00
1,762.00
720.00
12,000.00
2,400.00
74,394.00

973
388
528
44
53

841
335
456
38
46

398
158
216
18
21

2,212
881
1,200
100
120

7.10

17.00
1.00
0.30
118.00
1.00

15,705.20
60.00
15,765.20

37,604.00
881.00
360.00
11,800.00
120.00
50,765.00

53,309.20
881.00
360.00
11,800.00
180.00
66,530.20

4,202.80
881.00
360.00
200.00
2,220.00
7,863.80

M2
M
No

388
105
132

335
91
114

158
43
54

881
239
300

26.00
2.00
0.60

22,906.00
478.00
180.00
23,564.00

388
105
132

335
91
114

158
43
54

881
239
300

7.10

17.00
1.00
0.30

6,255.10
6,255.10

14,977.00
239.00
90.00
15,306.00

21,232.10
239.00
90.00
21,561.10

1,673.90
239.00
90.00
2,002.90

Sub-total
8
A
B
C

AMOUNT

Sub-total

QUOTATION FOR SUPPLY LABOUR ONLY


SEKOLAH MENENGAH KEBANGSAAN KOTA PUTERI 2, MASAI, JOHOR

0.50

%
W/DONE

BLOK C
QTY
W/DONE

QTY

%
W/DON
E

BLOK D
QTY
W/DONE

QTY

%
W/DON
E

QUANTITY
%x
W/DONE

TOTAL QTY

W/DONE

LAB.
RATE

MATE.
RATE

SUB
RATE

TOTAL LAB.
RATE

TOTAL MATE.
RATE

TOTAL SUB.
RATE

TOTAL
AMOUNT

GROSS
PROFIT
PROFIT
BUDGET
ACTUAL

864.00
240.00
7,728.00
1,306.82
786.98
2,802.12
420.00
264.00
644.00
2,523.90
444.15
800.00
18,823.97

3,330.00
925.00
29,785.00
6,362.15
3,831.35
13,641.90
2,520.00
1,584.00
3,864.00
2,864.00
504.00
12,000.00
81,211.40

4,202.80
881.00
360.00
200.00
2,220.00
7,863.80

57,512.00
1,762.00
720.00
12,000.00
2,400.00
74,394.00

1,673.90
239.00
90.00
2,002.90

22,906.00
478.00
180.00
23,564.00

57,381.34

358,338.80

REMARKS

ACADEMIC BLOCK
TENDER
REF.

9
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
W
X
Y
Z

TOTAL
UNIT BLOCK BLOCK BLOCK
QTY
B
C
D

ELEMENT/DESCRIPTION

DOOR AND WINDOWS


One hour fire-rated door c/w framing size 900 x 2100
No
Single flush door c/w framing size 900 x 2550
No
Ditto c/w glass panel & framing size 900 x 2100 No
Double flush door c/w framing size 1800x 2550
No
Ditto c/w glass panel & framing size 1800 x 2100 No
PVC door size 750 x 2100
No
Sliding door size 1800 x 2550
No
Aluminium framed casement window size 1800 x 1800
No
Ditto size 3600 x 1800
No
Ditto size 4800 x 1800
No
Ditto size 1800 x 1200
No
Ditto size 3600 x 1200
No
Ditto size 4800 x 1200
No
Ditto size 5550 x 2500
No
Aluminium framed top hung size 1800 x 600
No
Ditto size 3600 x 600
No
Ditto size 4800 x 600
No
Timber frame top hung size 1800 x 600
No
Ditto size 3600 x 600
No
Ditto size 4800 x 600
No
Adjustable louvres window size 600 x 1200
No
Ditto size 1200 x 1200
No
Ditto size 1200 x 1800
No
Ditto size 1800 x 1800
No
Ditto size 3600 x 1800
No
Ditto size 4800 x 1800
No
Sub-total

5
7
2
36

4
4
-

26

30
10

45
8

6
3

14
-

3
30

22
-

53
2
16

9
11
2
72

10
-

75
22

4
-

12

20
3
3
64

12
2
5

102
9
32

37
5
11

BUDGET
RATE

AMOUNT

550.00
780.00
500.00
1,600.00
340.00
120.00
800.00
900.00
1,800.00
2,400.00
600.00
1,200.00
1,600.00
3,850.00
300.00
600.00
800.00
130.00
260.00
350.00
150.00
250.00
380.00
550.00
1,100.00
1,500.00

4,950.00
8,580.00
1,000.00
115,200.00
9,000.00
17,600.00
2,600.00
780.00
1,050.00
9,600.00
56,100.00
9,900.00
48,000.00
284,360.00

BLOCK
B

5
7
2
36
-

BLOCK
C

4
4
-

45
8
-

6
3

14
-

3
30

22
-

TOTAL
QTY

26
-

30
10
-

BLOCK
D

9
11
2
72

10
-

75
22

4
-

LABOUR MATERIAL TOTAL LAB

28.00
23.00
23.00
50.00
23.00
20.00

252.00
253.00
46.00
3,600.00
1,500.00
745.60
5,304.00
936.00
4,480.00
17,116.60

5,445.00
2,948.00
540.00
38,592.00
9,600.00
17,380.00
2,320.00
696.00
930.00
4,288.00
30,804.00
5,436.00
25,728.00
144,707.00

LABOUR MATERIAL TOTAL LAB

TOTAL MATT

12

20
3
3
64
102
9
32

53
2
16

37
5
11

12
2
5

BLOCK
B

BLOCK
C

BLOCK
D

11.65
23.30
35.00
52.00
104.00
140.00

605.00
268.00
270.00
536.00
270.00
128.00
790.00
560.00
1,120.00
1,490.00
372.00
745.00
1,000.00
2,400.00
200.00
400.00
500.00
116.00
232.00
310.00
67.00
134.00
201.00
302.00
604.00
804.00

TOTAL MATT

RATE

5,697.00
3,201.00
586.00
42,192.00
11,100.00
17,380.00
2,320.00
696.00
930.00
5,033.60
36,108.00
6,372.00
30,208.00
161,823.60

MARGIN

(747.00)
5,379.00
414.00
73,008.00
(2,100.00)
220.00
280.00
84.00
120.00
4,566.40
19,992.00
3,528.00
17,792.00
122,536.40

QUOTATION FOR SUPPLY LABOUR ONLY


SEKOLAH MENENGAH KEBANGSAAN KOTA PUTERI 2, MASAI, JOHOR

ACADEMIC BLOCK
TENDER
REF.

TOTAL
UNIT BLOCK BLOCK BLOCK
QTY
B
C
D

ELEMENT/DESCRIPTION

10
A
B
C
D
E

FLOOR FINISHES
20mm Thick cement paving
Homogeneous tiles with screed
Carpet
Ceramic tiles ditto
Cementitious water proofing system

11
A
B
C
D
E

BUDGET
RATE

AMOUNT

TOTAL
QTY

M2
M2
M2
M2
M2

1,084
134
134

936
116
116

443
55
55

2,463
305
305

8.00
65.00
35.00
60.00
18.00

19,704.00
18,300.00
5,490.00
43,494.00

1,084
134
134

936
116
116

443
55
55

2,463
305
305

WALL FINISHES
20mm Thick c.s. plaster to wall & column
Emulsion paint to internally plastered wall
Weather sheild paint to externally ditto
Ceramic wall tiles with screed
Acoustic treatment
Sub-total

M2
M2
M2
M2
M2

2,722
1,749
973
115
119

2,351
1,510
841
99
103

1,113
715
398
47
49

6,186
3,974
2,212
261
271

8.00
4.50
5.50
65.00
70.00

49,488.00
17,883.00
12,166.00
16,965.00
18,970.00
115,472.00

2,722
1,749
973
115
119

2,351
1,510
841
99
103

1,113
715
398
47
49

6,186
3,974
2,212
261
271

12
A
B
C
D

CEILING FINISHES
20mm Thick c.s. plaster to soffit of slab
Asbestos free ceiling sheet
Emulsion paint to plastered surfaces
Ditto to asbestos ceiling
Sub-total

M2
M2
M2
M2

1,884
559
1,884
559

1,628
483
1,628
483

771
229
771
229

4,283
1,271
4,283
1,271

8.00
28.00
4.50
4.50

34,264.00
35,588.00
19,273.50
5,719.50
94,845.00

1,884
559
1,884
559

1,628
483
1,628
483

771
229
771
229

4,283
1,271
4,283
1,271

13
A
B
C
D
E
F
G
H
I

PLUMBING AND SANITARY FITTINGS


Cold water plumbing ( under M & E)
Soil and waste plumbing ( under M & E)
Water tank ( under M & E)
Squatting WC complete with stool
Pedestal WC
Mirror
Wash hand basin with counter top
Kitchen sink
Dentist vanity basin
Sub-total

LS
LS
LS
No
No
No
No
No
No

1
1
1
16
25
5
34

6
10
2
14

1
1
1
36
57
12
78

Sub-total

10,000.00
12,000.00
2,000.00
14
22
5
30
-

6
10
2
14
-

36
57
12
78
-

350.00
300.00
60.00
320.00
250.00
1,700.00

12,600.00
17,100.00
720.00
24,960.00
79,380.00

16
25
5
34
-

14
22
5
30
-

RATE

MARGIN

5.00
21.00
5.00
19.00

2.50
46.25
20.00
19.00
28.00

12,315.00
5,795.00
18,110.00

6,157.50
5,795.00
8,540.00
20,492.50

18,472.50
11,590.00
8,540.00
38,602.50

1,231.50
6,710.00
(3,050.00)
4,891.50

6.00

2.50
2.80
2.80
19.00
28.00

37,116.00
4,959.00
42,075.00

15,465.00
11,127.20
6,193.60
4,959.00
7,588.00
45,332.80

52,581.00
11,127.20
6,193.60
9,918.00
7,588.00
87,407.80

(3,093.00)
6,755.80
5,972.40
7,047.00
11,382.00
28,064.20

2.50
8.00

25,698.00
9,532.50
11,992.40
3,558.80
50,781.70

10,707.50
10,168.00
20,875.50

36,405.50
19,700.50
11,992.40
3,558.80
71,657.20

(2,141.50)
15,887.50
7,281.10
2,160.70
23,187.80

8,000.00
10,000.00
1,800.00
8,100.00
19,380.00
900.00
12,870.00
61,050.00

8,000.00
10,000.00
1,800.00
8,100.00
19,380.00
900.00
12,870.00
61,050.00

2,000.00
2,000.00
200.00
4,500.00
(2,280.00)
(180.00)
12,090.00
18,330.00

19.00

6.00
7.50
2.80
2.80

8,000.00
10,000.00
1,800.00
225.00
340.00
75.00
165
200
1650

QUOTATION FOR SUPPLY LABOUR ONLY


SEKOLAH MENENGAH KEBANGSAAN KOTA PUTERI 2, MASAI, JOHOR

ACADEMIC BLOCK
TENDER
REF.

ELEMENT/DESCRIPTION

14
A
B
C
D
E

APRON AND PERIMETER DRAIN


Exc. oversite 250mm deep
150mm Thick hardcore
100mm Thick VRC G25 apron slab
One layer fabric reinforcement
230mm half round perimeter drain

15
A

INTERNAL SIGNAGES
Internal signages/lettering

UNIT BLOCK BLOCK BLOCK


B
C
D

M2
M2
M2
M2
M

310
310
310
310
101

268
268
268
268
87

127
127
127
127
41

TOTAL
QTY

705
705
705
705
229

BUDGET
RATE

2.50
8.30
18.50
12.00
38.00

AMOUNT

1,762.50
5,851.50
13,042.50
8,460.00
8,702.00
37,818.50

BLOCK
B

BLOCK
C

BLOCK
D

310
310
310
310
101

268
268
268
268
87

127
127
127
127
41

TOTAL
QTY

LABOUR MATERIAL TOTAL LAB

705
705
705
705
229

2.50
2.60
1.00
14.00

2.15
6.50
11.10
4.00
10.00

1,762.50
1,833.00
705.00
3,206.00
7,506.50

TOTAL MATT

RATE

MARGIN

1,515.75
4,582.50
7,825.50
2,820.00
2,290.00
19,033.75

1,515.75
6,345.00
9,658.50
3,525.00
5,496.00
26,540.25

246.75
(493.50)
3,384.00
4,935.00
3,206.00
11,278.25

25,000.00

25,000.00

5,000.00

25,000.00

25,000.00

5,000.00

Sub-total

Ls

30,000.00

25,000.00

30,000.00

QUOTATION FOR SUPPLY LABOUR ONLY


SEKOLAH MENENGAH KEBANGSAAN KOTA PUTERI 2, MASAI, JOHOR

ACADEMIC BLOCK
TENDER
REF.

TOTAL
UNIT BLOCK BLOCK BLOCK
QTY
B
C
D

ELEMENT/DESCRIPTION

BUDGET
RATE

AMOUNT

BLOCK
B

BLOCK
C

BLOCK
D

TOTAL
QTY

LABOUR MATERIAL TOTAL LAB

TOTAL MATT

RATE

MARGIN

170,209.15
453,962.25
254,725.00
226,331.00
81,211.40
74,394.00
23,564.00
284,360.00
43,494.00
115,472.00
94,845.00
79,380.00
37,818.50
30,000.00

46,266.14
125,603.40
73,902.75
28,552.60
13,496.53
15,765.20
6,255.10
17,116.60
18,110.00
42,075.00
50,781.70
7,506.50
-

99,705.85
235,355.75
145,125.70
143,771.70
48,890.90
50,765.00
15,306.00
144,707.00
20,492.50
45,332.80
20,875.50
61,050.00
19,033.75
25,000.00

145,971.99
360,959.15
219,028.45
172,324.30
62,387.43
66,530.20
21,561.10
161,823.60
38,602.50
87,407.80
71,657.20
61,050.00
26,540.25
25,000.00

24,237.16
93,003.10
35,696.55
54,006.70
18,823.97
7,863.80
2,002.90
122,536.40
4,891.50
28,064.20
23,187.80
18,330.00
11,278.25
5,000.00

1,969,766.30

445,431.52

1,075,412.45

1,520,843.97

448,922.33

ACTUAL

SUMMARY
1
2
3
4
5
6
7
8
9
10
11
12
13
14

Work Below Lowest Floor Level


Frame
Upper Floor Construction
Roof and roof covering
Staircases
External wall
Internal wall and partition
Door and window
Floor finishes
Wall finishes
Ceiling finishes
Sanitary appliances
Apron and perimeter drain
Internal signages
TOTAL

#REF!

REF

ELEMENT/DESCRIPTION

UNIT

3
A
B
C
D
E
F
G
H
I

FRAME
VRC G25 in column/stiffener
Ditto in suspended floor beam
Ditto in roof beam
Reinforcement bar in column/stiffener
Ditto in floor beam
Ditto in roof beam
Sawn formwork to sides of column/stiffener
Ditto suspended floor beam
Ditto roof beam
Sub-total

M3
M3
M3
Kg
Kg
Kg
M2
M2
M2

124
290
88
23103
76345
22297
1229
3368
1064

185.00
185.00
185.00
1.85
1.85
1.85
24.00
24.00
24.00

22,940.00
53,650.00
16,280.00
42,740.55
141,238.25
41,249.45
29,496.00
80,832.00
25,536.00
453,962.25

26.00
26.00
26.00
0.32
0.32
0.32
13.00
13.00
13.00

111.00
111.00
111.00
1.15
1.15
1.15
7.00
7.00
7.00

3,224.00
7,540.00
2,288.00
7,392.96
24,430.40
7,135.04
15,977.00
43,784.00
13,832.00
125,603.40

13,764.00
32,190.00
9,768.00
26,568.45
87,796.75
25,641.55
8,603.00
23,576.00
7,448.00
235,355.75

16,988.00
39,730.00
12,056.00
33,961.41
112,227.15
32,776.59
24,580.00
67,360.00
21,280.00
360,959.15

5,952.00
13,920.00
4,224.00
8,779.14
29,011.10
8,472.86
4,916.00
13,472.00
4,256.00
93,003.10

4
A
B
C
D

UPPER FLOOR CONSTRUCTION


125mm thick suspended floor slab
BRC A10 ditto
BMC A6 ditto
Sawn formwork to soffit suspended floor slab
Sub-total

M2
M2
M2
M2

4271
4403
96
4271

23.00
12.00
12.00
24.00

98,233.00
52,836.00
1,152.00
102,504.00
254,725.00

3.25
1.00
1.00
13.00

13.90
12.60
4.00
7.00

13,880.75
4,403.00
96.00
55,523.00
73,902.75

59,366.90
55,477.80
384.00
29,897.00
145,125.70

73,247.65
59,880.80
480.00
85,420.00
219,028.45

24,985.35
(7,044.80)
672.00
17,084.00
35,696.55

ROOF STRUCTURE AND COVERING


Roof Structure (prefabricated roof trusses)
M2
125mm thick VRC G25 in roof slab
M2
Concrete roof covering, sisalation, wiremesh and etc M2
Fascia board and painting
M
Gutter and rainwater downpipe
M
Sub-total

2466
95
2466
413
413

38.00
19.00
43.00
15.00
45.00

93,708.00
1,805.00
106,038.00
6,195.00
18,585.00
226,331.00

5.80
3.60
4.30
6.00
2.00

32.00
15.30
23.20
5.00
10.00

14,302.80
342.00
10,603.80
2,478.00
826.00
28,552.60

78,912.00
1,453.50
57,211.20
2,065.00
4,130.00
143,771.70

93,214.80
1,795.50
67,815.00
4,543.00
4,956.00
172,324.30

493.20
9.50
38,223.00
1,652.00
13,629.00
54,006.70

5
A
B
C
**D
E

QTY

RATE

AMOUNT (RM)

LAB. RATE

MATL. RATE

TOTAL LAB.

TOTAL MATL

TOTAL

MARGIN

BLOK AKADEMIK (B,C & D)


TENDER

BUDGET

ACTUAL
BLOK B

REF.

ELEMENT/DESCRIPTION

UNIT

BLOCK B

BLOCK C

BLOCK D

TOTAL QTY

RATE

AMOUNT

BLOCK B

BLOCK C

BLOCK D

TOTAL QTY

LAB. RATE

MATE. RATE

TOTAL LAB

TOTAL MATT

TOTAL

MARGIN
QTY

FRAME

A
B
C
D

M3
M3
M3
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg

55
128
39
10,165

47
110
33
8,779

22
52
16
4,159

124
290
88
23,103

185.00
185.00
185.00
1.85

22,940.00
53,650.00
16,280.00
42,740.55

55
128
39
10,165

47
110
33
8,779

22
52
16
4,159

124
290
88
23,103

26.00
26.00
26.00
0.32

111.00
111.00
111.00
1.15

3,224.00
7,540.00
2,288.00
7,392.96

13,764.00
32,190.00
9,768.00
26,568.45

16,988.00
39,730.00
12,056.00
33,961.41

5,952.00
13,920.00
4,224.00
8,779.14

33,592

29,011

13,742

76,345

1.85

141,238.25

33,592

29,011

13,742

76,345

0.32

1.15

24,430.40

87,796.75

112,227.15

29,011.10

VRC G25 in column/stiffener


Ditto in suspended floor beam
Ditto in roof beam
Reinforcement bar in column/stiffener
Y25
R8
Ditto in floor beam
Y20
Y25
R10
Ditto in roof beam

9,811

8,473

4,013

22,297

1.85

41,249.45

9,811

8,473

4,013

22,297

0.32

1.15

7,135.04

25,641.55

32,776.59

8,472.86

G
H
I

Sawn formwork to sides of column/stiffener


Ditto suspended floor beam
Ditto roof beam

M2
M2
M2

541
1,482
468

467
1,280
404

221
606
192

1,229
3,368
1,064

24.00
24.00
24.00

29,496.00
80,832.00
25,536.00

541
1,482
468

467
1,280
404

221
606
192

1,229
3,368
1,064

13.00
13.00
13.00

7.00
7.00
7.00

15,977.00
43,784.00
13,832.00

8,603.00
23,576.00
7,448.00

24,580.00
67,360.00
21,280.00

4,916.00
13,472.00
4,256.00

125,603.40

235,355.75

360,959.15

93,003.10

UPPER FLOOR CONSTRUCTION

A
B
C
D

125mm thick suspended floor slab


BRC A10 ditto
BMC A6 ditto
Sawn formwork to soffit suspended floor slab

13,880.75
4,403.00
96.00
55,523.00

59,366.90
55,477.80
384.00
29,897.00

73,247.65
59,880.80
480.00
85,420.00

24,985.35
(7,044.80)
672.00
17,084.00

73,902.75

145,125.70

219,028.45

35,696.55

ROOF STRUCTURE AND COVERING

A
B
C
D
E

Roof Structure (prefabricated roof trusses)


125mm thick VRC G25 in roof slab
Concrete roof covering, sisalation, wiremesh and etc
Fascia board and painting
Gutter and rainwater downpipe

14,302.80
342.00
10,603.80
2,478.00
826.00

78,912.00
1,453.50
57,211.20
2,065.00
4,130.00

93,214.80
1,795.50
67,815.00
4,543.00
4,956.00

493.20
9.50
38,223.00
1,652.00
13,629.00

28,552.60

143,771.70

172,324.30

54,006.70

10992
1984

453,962.25

1,879
1,937
42
1,879

1,623
1,673
37
1,623

769
793
17
769

4,271
4,403
96
4,271

23.00
12.00
12.00
24.00

Sub-total

Sub-total

98,233.00
52,836.00
1,152.00
102,504.00

1,879
1,937
42
1,879

1,623
1,673
37
1,623

769
793
17
769

4,271
4,403
96
4,271

3.25
1.00
1.00
13.00

13.90
12.60
4.00
7.00

254,725.00

M2
M2
M2
M
M

QTY
W/DONE

QTY

0
0
0
0
0
0
0

47
144
38

% W/DONE

BLOK D

QUANTITY
LAB. RATE

QTY
W/DONE

QTY

0
0
0
0

% W/DONE

22
40
14

MATE. RATE

SUB RATE

W/DONE

TOTAL LAB.
RATE

% x W/DONE

TOTAL QTY

0
0
0
0

0
0
0
0

0
0
0
0

0
0
0
0

124
351
86
0
10992
1984
0

0
0
0
0

0
3531
1279

0
0
0

0
0
0

0
0
0
0

1813
28809

Sub-total

M2
M2
M2
M2

55
167
34

% W/DONE

BLOK C

1,085
42
1,085
182
182

937
36
937
157
157

444
17
444
74
74

2,466
95
2,466
413
413

38.00
19.00
43.00
15.00
45.00

93,708.00
1,805.00
106,038.00
6,195.00
18,585.00
226,331.00

1,085
42
1,085
182
182

937
36
937
157
157

444
17
444
74
74

2,466
95
2,466
413
413

5.80
3.60
4.30
6.00
2.00

32.00
15.30
23.20
5.00
10.00

1315
584

0
0
0
0

1644
485

0
0
0
0

572
210

0
0
0
0
0

0
0
0
0
0

0
0
0
0
0

0
0
0
0

0
0
0
0

0
0
0
0

0
0
0
0
0

0
0
0
0
0
0

0
0
0
0
0
0

0
0
0
0
0
0

0
0
0
0
0

0
0
0
0
0

0
0
0
0
0

0
0
0
0
0
0

TOTAL
TOTAL SUB.
MATE. RATE
RATE

TOTAL
AMOUNT

GROSS
PROFIT
PROFIT
BUDGET
ACTUAL

REMARKS

REF

ELEMENT/DESCRIPTION

UNIT

QTY

RATE

6
A
B
C
D
E
F
G
H
I
J
K
L

STAIRCASES AND FINISHES


VRC G25 in staircase
Ditto in landing beam
Ditto in landing slab
Reinforcement in staircase
Ditto in landing beam
Ditto in landing slab
Sawn formwork to sloping soffit of staircase
Ditto of landing beam
Ditto of landing slab
Ditto to undercut of riser
Ditto to raking open string
Staircases finishes and railing
Sub-total

M3
M3
M3
KG
KG
KG
M2
M2
M2
M
M
Flight

18
5
161
3439
2071
7374
105
66
161
358
63
8

185.00
185.00
185.00
1.85
1.85
1.85
24.00
24.00
24.00
8.00
8.00
1,500.00

3,330.00
925.00
29,785.00
6,362.15
3,831.35
13,641.90
2,520.00
1,584.00
3,864.00
2,864.00
504.00
12,000.00
81,211.40

26.00
26.00
26.00
0.32
0.32
0.32
13.00
13.00
13.00
0.65
0.65

111.00
111.00
111.00
1.15
1.15
1.15
7.00
7.00
7.00
0.30
0.30
1,400.00

468.00
130.00
4,186.00
1,100.48
662.72
2,359.68
1,365.00
858.00
2,093.00
232.70
40.95
13,496.53

1,998.00
555.00
17,871.00
3,954.85
2,381.65
8,480.10
735.00
462.00
1,127.00
107.40
18.90
11,200.00
48,890.90

2,466.00
685.00
22,057.00
5,055.33
3,044.37
10,839.78
2,100.00
1,320.00
3,220.00
340.10
59.85
11,200.00
62,387.43

864.00
240.00
7,728.00
1,306.82
786.98
2,802.12
420.00
264.00
644.00
2,523.90
444.15
800.00
18,823.97

7
A
B
C
D
E

EXTERNAL WALLS
115mm thick common brickwall
Damp proof course
6mm bonding ties
Mild steel railing
50mm Upvc spout pipe 250mm long

M2
M
No
M
No

2212
881
1200
100
120

26.00
2.00
0.60
120.00
20.00

57,512.00
1,762.00
720.00
12,000.00
2,400.00
74,394.00

7.10

17.00
1.00
0.30
118.00
1.00

15,705.20
60.00
15,765.20

37,604.00
881.00
360.00
11,800.00
120.00
50,765.00

53,309.20
881.00
360.00
11,800.00
180.00
66,530.20

4,202.80
881.00
360.00
200.00
2,220.00
7,863.80

26.00
2.00
0.60

22,906.00
478.00
180.00
23,564.00

7.10

17.00
1.00
0.30

6,255.10
6,255.10

14,977.00
239.00
90.00
15,306.00

21,232.10
239.00
90.00
21,561.10

1,673.90
239.00
90.00
2,002.90

Sub-total
8
A
B
C

INTERNAL WALLS
115mm thick common brickwall
Damp proof course 114mm Wide
6mm bonding ties

M2 881
M 239
No 300
Sub-total

AMOUNT (RM)

LAB. RATE

0.50

MATL. RATE

TOTAL LAB.

TOTAL MATL

TOTAL

MARGIN

REF

ELEMENT/DESCRIPTION

UNIT

9
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
W
X
Y
Z

DOOR AND WINDOWS


One hour fire-rated door c/w framing size 900 x 2100
Single flush door c/w framing size 900 x 2550
Ditto c/w glass panel & framing size 900 x 2100
Double flush door c/w framing size 1800x 2550
Ditto c/w glass panel & framing size 1800 x 2100
PVC door size 750 x 2100
Sliding door size 1800 x 2550
Aluminium framed casement window size 1800 x 1800
Ditto size 3600 x 1800
Ditto size 4800 x 1800
Ditto size 1800 x 1200
Ditto size 3600 x 1200
Ditto size 4800 x 1200
Ditto size 5550 x 2500
Aluminium framed top hung size 1800 x 600
Ditto size 3600 x 600
Ditto size 4800 x 600
Timber frame top hung size 1800 x 600
Ditto size 3600 x 600
Ditto size 4800 x 600
Adjustable louvres window size 600 x 1200
Ditto size 1200 x 1200
Ditto size 1200 x 1800
Ditto size 1800 x 1800
Ditto size 3600 x 1800
Ditto size 4800 x 1800
Sub-total

No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No

QTY

9
11
2
72
0
75
22
0
0
0
0
0
0
0
0
0
0
20
3
3
64
0
0
102
9
32

RATE

550.00
780.00
500.00
1,600.00
340.00
120.00
800.00
900.00
1,800.00
2,400.00
600.00
1,200.00
1,600.00
3,850.00
300.00
600.00
800.00
130.00
260.00
350.00
150.00
250.00
380.00
550.00
1,100.00
1,500.00

AMOUNT (RM)

4,950.00
8,580.00
1,000.00
115,200.00
9,000.00
17,600.00
2,600.00
780.00
1,050.00
9,600.00
56,100.00
9,900.00
48,000.00
284,360.00

LAB. RATE

28.00
23.00
23.00
50.00
23.00
20.00

11.65
23.30
35.00
52.00
104.00
140.00

MATL. RATE

605.00
268.00
270.00
536.00
270.00
128.00
790.00
560.00
1,120.00
1,490.00
372.00
745.00
1,000.00
2,400.00
200.00
400.00
500.00
116.00
232.00
310.00
67.00
134.00
201.00
302.00
604.00
804.00

TOTAL LAB.

252.00
253.00
46.00
3,600.00
1,500.00
745.60
5,304.00
936.00
4,480.00
17,116.60

TOTAL MATL

5,445.00
2,948.00
540.00
38,592.00
9,600.00
17,380.00
2,320.00
696.00
930.00
4,288.00
30,804.00
5,436.00
25,728.00
144,707.00

TOTAL

5,697.00
3,201.00
586.00
42,192.00
11,100.00
17,380.00
2,320.00
696.00
930.00
5,033.60
36,108.00
6,372.00
30,208.00
161,823.60

MARGIN

(747.00)
5,379.00
414.00
73,008.00
(2,100.00)
220.00
280.00
84.00
120.00
4,566.40
19,992.00
3,528.00
17,792.00
122,536.40

REF

ELEMENT/DESCRIPTION

UNIT

QTY

RATE

AMOUNT (RM)

LAB. RATE

MATL. RATE

TOTAL LAB.

TOTAL MATL

TOTAL

MARGIN

10
A
B
C
D
E

FLOOR FINISHES
20mm Thick cement paving
Homogeneous tiles with screed
Carpet
Ceramic tiles ditto
Cementitious water proofing system
Sub-total

M2
M2
M2
M2
M2

2463
0
0
305
305

8.00
65.00
35.00
60.00
18.00

19,704.00
18,300.00
5,490.00
43,494.00

5.00
21.00
5.00
19.00

2.50
46.25
20.00
19.00
28.00

12,315.00
5,795.00
18,110.00

6,157.50
5,795.00
8,540.00
20,492.50

18,472.50
11,590.00
8,540.00
38,602.50

1,231.50
6,710.00
(3,050.00)
4,891.50

11
A
B
C
D
E

WALL FINISHES
20mm Thick c.s. plaster to wall & column
Emulsion paint to internally plastered wall
Weather sheild paint to externally ditto
Ceramic wall tiles with screed
Acoustic treatment
Sub-total

M2
M2
M2
M2
M2

6186
3974
2212
261
271

8.00
4.50
5.50
65.00
70.00

49,488.00
17,883.00
12,166.00
16,965.00
18,970.00
115,472.00

6.00

2.50
2.80
2.80
19.00
28.00

37,116.00
4,959.00
42,075.00

15,465.00
11,127.20
6,193.60
4,959.00
7,588.00
45,332.80

52,581.00
11,127.20
6,193.60
9,918.00
7,588.00
87,407.80

(3,093.00)
6,755.80
5,972.40
7,047.00
11,382.00
28,064.20

12
A
B
C
D

CEILING FINISHES
20mm Thick c.s. plaster to soffit of slab
Asbestos free ceiling sheet
Emulsion paint to plastered surfaces
Ditto to asbestos ceiling
Sub-total
PLUMBING AND SANITARY FITTINGS
Cold water plumbing ( under M & E)
Soil and waste plumbing ( under M & E)
Water tank ( under M & E)
Squatting WC complete with stool
Pedestal WC
Mirror
Wash hand basin with counter top
Kitchen sink
Dentist vanity basin
Sub-total

M2
M2
M2
M2

4283
1271
4283
1271

8.00
28.00
4.50
4.50

34,264.00
35,588.00
19,273.50
5,719.50
94,845.00

2.50
8.00

25,698.00
9,532.50
11,992.40
3,558.80
50,781.70

10,707.50
10,168.00
20,875.50

36,405.50
19,700.50
11,992.40
3,558.80
71,657.20

(2,141.50)
15,887.50
7,281.10
2,160.70
23,187.80

LS
LS
LS
No
No
No
No
No
No

1
1
1
36
57
12
78
0
0

8,000.00
10,000.00
1,800.00
8,100.00
19,380.00
900.00
12,870.00
61,050.00

8,000.00
10,000.00
1,800.00
8,100.00
19,380.00
900.00
12,870.00
61,050.00

2,000.00
2,000.00
200.00
4,500.00
(2,280.00)
(180.00)
12,090.00
18,330.00

13
A
B
C
D
E
F
G
H
I

350.00
300.00
60.00
320.00
250.00
1,700.00

10,000.00
12,000.00
2,000.00
12,600.00
17,100.00
720.00
24,960.00
79,380.00

19.00

6.00
7.50
2.80
2.80

8,000.00
10,000.00
1,800.00
225.00
340.00
75.00
165
200
1650

REF
14
A
B
C
D
E

ELEMENT/DESCRIPTION

UNIT QTY

APRON AND PERIMETER DRAIN


Exc. oversite 250mm deep
150mm Thick hardcore
100mm Thick VRC G25 apron slab
One layer fabric reinforcement
230mm half round perimeter drain

M2
M2
M2
M2
M

705
705
705
705
229

Ls

RATE

2.50
8.30
18.50
12.00
38.00

AMOUNT (RM)

1,762.50
5,851.50
13,042.50
8,460.00
8,702.00
37,818.50

LAB. RATE

2.50
2.60
1.00
14.00

MATL. RATE

2.15
6.50
11.10
4.00
10.00

TOTAL LAB.

1,762.50
1,833.00
705.00
3,206.00
7,506.50

TOTAL MATL

TOTAL

MARGIN

1,515.75
4,582.50
7,825.50
2,820.00
2,290.00
19,033.75

1,515.75
6,345.00
9,658.50
3,525.00
5,496.00
26,540.25

246.75
(493.50)
3,384.00
4,935.00
3,206.00
11,278.25

25,000.00

25,000.00

5,000.00

25,000.00

25,000.00

5,000.00

Sub-total
15 INTERNAL SIGNAGES
A Internal signages/lettering

30,000.00

30,000.00

25,000.00

You might also like