BOLLETTINO I-I-0125-09/06/03

BULLETIN GB-I-0125-09/06/03

O.M.T. Officina Meccanica Tartarini S.p.A.

TARTARINI
Via P. Fabbri, 1 I - 40013 Castel Maggiore (Bologna) Italy
Tel. : +39 - 51 - 4190611 Fax: +39 - 51 - 4190715

MN and MF Series Spring-Loaded Regulators


1. Description When carrying out routine maintenance, all rubber parts should
The M... Series are spring-loaded regulators featuring a balanced be replaced. For this purpose, use only the parts included in
valve. They are available in diameters from DN 25 to DN 150, in Tartarini's spare parts kit.
the following versions: Note: Servicing does not require removal of valve from the line.
MN/ - MF/: without internal slam-shut valve 6.2 Replacing seal pad
MBN/ - MBF/: with internal slam-shut valve
a ) Loosen adjusting screw (1); unscrew bush (2) and slide out
The slam-shut valve is controlled by the OS/66 pilot (see Bulletin spring (4); remove bottom (39). Note: for the Monitor versions
0092 for pilot use and maintenance).
remove completely the counterbalance system included stem (35).
The procedures described herein are applicable to the MB... b) Lock stem (35) by inserting a suitable wrench in the appropriate slots (T).
version. As for the M... version, please disregard the sections
c ) Hold stem locked and unscrew pad-holder (36). This operation
concerning the slam-shut valve.
must be carried out with extreme care in order to avoid
2. Instructions for Installation damage to the balancing assembly.
d ) Replace pad (34) and reassemble parts by carrying out the
a ) Make sure that specifications on the regulator plate are
above steps in reverse order.
compatible with actual working conditions.
Note: During this procedure, seat (42) and O-ring (43) can be
b ) In regulators with diameters of DN25 to DN65, insert impulse
checked and replaced, if required. In order to do this, open
pipe (33) into coupling (32) from the grooved end. In DN80
slam-shut valve sleeve and keep it open while unscrewing the
and DN100 regulators, mount impulse connection downstream
seat with the appropriate wrench. With the slam-shut valve
by means of coupling (107).
sleeve still kept open, mount a new seat.
c ) Check that gas flows through valve body in the direction
indicated by the arrow. 6.3 General Maintenance
a ) Remove both seal pad (see steps described in 6.2 above) and
3. Instructions for Start-Up reset assembly (screws 86 and 91).
a ) Slightly open outlet shut-off valve so that a minimum amount b ) Loosen and remove screws (15) to take off cover (5).
of gas is allowed to flow through. c ) Lock stem (35) by inserting a suitable wrench in the
b) Slightly and very slowly open inlet shut-off valve. appropriate slots (T) and unscrew nut (6). Remove and check
c ) Remove cap nut (C), screw it onto stem and pull outwards. diaphragm (12) and replace where required.
d ) By means of the appropriate wrench, hold stem pulled and Note: During general maintenance of the AP and APA (high-
slowly turn shaft (B) counterclockwise until balls (90 and 91) pressure) versions, O-ring (67) and bush (68) can be checked
are felt to be clearly engaged, after which release wrench. by sliding out balancing piston (66) and stem (35). In the
e ) Wait for outlet pressure to stabilize. following steps, therefore, the procedure for these versions will
f ) Release cap nut and remount in original position. have to be modified accordingly.
g ) Very slowly open inlet and outlet valves fully. d ) Loosen and remove the two screws (52) and slide out plate
(58) and bush (20).
4. Troubleshooting e ) Remove the balancing stem/diaphragm assembly and then
4.1 Gas not flowing downstream of regulator can be due to: unscrew spacer (18) and disassemble the various parts.
Check shaped diaphragm (50) and O-rings (17 and 23).
a ) Insufficient inlet gas flow. f ) Replace the two screws (19) with longer screws and loosen
b ) Clogged inlet filter. and remove the remaining screws which hold cover (61) and
c ) Tripped pilot. cup (21) in place. Progressively unload spring of slam-shut
4.2 A decrease in regulator outlet pressure can be due to: (22) and remove assembly. Check O-ring (51) and antifriction
rings (24).
a) Insufficient inlet gas flow.
Note: In case of cup (21) being clogged due to oxidation or dust,
b) Gas demand being higher than regulator capacity. remove by inserting a puller in the appropriate threaded holes.
c) Clogged inlet filter. g ) Remove snap ring (31) and disassemble the various parts.
d) Broken spring. Then check pad (30), O-ring (44) and antifriction ring (48).
4.3 An increase in regulator outlet pressure can be due to: Replace where required.
a ) Worn seal pad (34) or seat (42). h ) By using the appropriate wrench, unscrew seat (42) and check
b ) Dirt being deposited on the seal pad, thus preventing regular O-ring (43).
sleeve positioning. i ) Clean the various parts with petrol and dry with compressed
c ) Damaged or broken diaphragm (12). air. Replace worn parts.
6.4 Reassembling
5. Periodic Checks
Reassemble the various parts by reversing the steps laid out
Periodic regulator efficiency checks are highly recommended. above. Attention should be made that each reassembled part
5.1 Regulator Checking Procedures moves freely and without friction. In addition, care should be
First slowly close the outlet shut-off valve and then check the taken with regards to:
pressure in the pipe length between the regulator and the valve. a ) Lubricating all moving parts and seals with MOLYKOTE 55
Before outlet pressure stabilizes, a slight increase in pressure will M grease and making sure that parts are not damaged during
occur due to shut-off overload. In case of faulty sleeve seal, reassembly.
outlet pressure will continue to increase. In this event, the inlet b ) Progressively and uniformly tightening all the screws so as to
valve must be closed and maintenance effected. guarantee maximum seal.
c ) Setting the slam-shut valve and checking reset mode at end of
5.2. Pilot Checking Procedures reassembly.
See instructions in Bulletin 0092. d ) Checking for any leaks by using soapy water.

6. Maintenance 7. Setting
Mount a pressure gauge downstream of the regulator so as to
6.1 Important measure outlet pressure. Turn adjusting screw (1) clockwise to
Servicing should be carried out by qualified, skilled increase pressure or anticlockwise to diminish it, as the case
personnel. For further information, please contact our requires. Wherever great pressure variation is required with
Technical Assistance Department or our authorized dealers. respect to the original set-point, spring (4) may have to be
Before servicing, make sure there is no gas under pressure in the replaced with a more suitable one.
regulator body by first cutting off inlet and outlet gas in the line Check pilot setting in case of pilot-fitted regulator (see Bulletin
being serviced and then letting it out via the appropriate bleed 0092).
cock.

The manufacturer reserves the right to make modifications in the technical data reported in this Bulletin for continual improvement of its products.
DETTAGLIO VALIDO
SOLO PER DN 25
DETAIL APPLICABLE
DETTAGLIO CONTROBILANCIAMENTO A PISTONE
ONLY TO DN 25
VALIDO PER VERSIONI ALTA PRESSIONE
(MB.../...AP o APA o PST, M.../...AP o APA o PST)
DETAIL OF PISTON BALANCING ASSEMBLY
APPLICABLE TO HIGH-PRESSURE VERSIONS ONLY
(MB.../...AP or APA or PST, M.../...AP or APA or PST)

PRESA DI IMPULSO DA
COLLEGARE A VALLE
DEL REGOLATORE,
VALIDO SOLO PER MN/
MBN/ DN 80 E DN 100 E
TUTTI I DN MF/ - MBF/

IMPULSE PIPE FOR


CONNECTION
DOWNSTREAM OF
REGULATOR,
APPLICABLE TO MN/
MBN/ DN 80 - 100 AND
FOR MF/ - MBF/ ALL SIZES

NELLE VERSIONI SENZA VALVOLA DI BLOCCO I PARTICOLARI 22, 30, 31, 44, 45, 46, 47, 48, 49, 71, 72, 73, 74 NON ESISTONO
PARTS 22, 30, 31, 44, 45, 46, 47, 48, 49, 71, 72, 73, 74 ARE NOT INCORPORATED IN THE VERSION WITHOUT SLAM-SHUT VALVE

VALIDO PER DN 25 ÷ DN 80 VERSIONE AP VALIDO PER DN 100 VALIDO PER DN 100 VERSIONI AP e APA
APPLICABLE TO DN 25 TO DN 80 AP VERSION APPLICABLE TO DN 100 APPLICABLE TO DN 100 AP and APA VERSIONS
Dettaglio kit "SR" Dettaglio versione silenziata SR
"SR" Kit Detail
SR silenced version detail

109

108

Dettagli versioni Monitor - Monitor versions details

Versione -Version Versione -Version


Monitor DN 40 ¸ 100 Monitor "AP" "APA"

36 48

119 59
118

48 17
120

118 60
17

40 7 38 113

117 50 111 112

116 6 110 6 7

20 117 Tubo di valle Æ 10


Tubo di valle Æ 10
Outlet pipe Æ 10
115 Outlet pipe Æ 10 115

114 114

Versione -Version
Monitor DN 25

113

Tubo di valle Æ 10
Outlet pipe Æ 10
Manutenzione gruppo di riarmo Maintenance of reset assembly
a ) Fare scattare l’organo di sgancio e rimuovere la presa di a ) Trip pilot and remove impulse connection. Then loosen
controllo; svitare le viti (86 e 91) e smontare l’insieme gruppo di and remove screws (86 and 91) and take off the combined
riarmo-organo di sgancio. reset and pilot assembly.
b) Allentare i grani (G) e sfilare l’organo di sgancio dal gruppo di b ) Loosen dowels (G) and slide out the pilot from the reset
riarmo. assembly.
c ) Svitare il dado (D). c ) Unscrew nut (D).
d) Svitare lo stelo (78) e scomporre l’albero (82), la molla (79), il d ) Unscrew stem (78) and remove shaft (82), spring (79),
reggi-molla (84) e l’O-Ring (83) spring holder (84) and O-Ring (83).
e ) Svitare il tappo (89) e rimuovere la molla (87) e le sfere (90 e 92). e ) Unscrew plug (89) and remove spring (87) and balls (90 and 92).
f ) Togliere la spina (96), svitare il grano (105) e sfilare l’albero f ) Remove pin (96), unscrew dowel (105) and then slide out
(103); controllare gli anelli antifrizione (94 e 98) e l’O-Ring (97), shaft (103). Check antifriction rings (94 and 98) and O-ring
sostituire se necessario. (97); replace if required.
g) Pulire e controllare tutti i particolari, sostituire quelli usurati. g ) Clean and check all components and replace if worn.
h) Lubrificare le parti in movimento e rimontare i particolari h ) Lubricate moving parts and reassemble by reversing the
procedendo in senso inverso alle operazioni sopra descritte. Nel steps set out above. When reassembling reset assembly,
rimontare il gruppo di riarmo assicurarsi che la camma (93) sia make sure that cam (93) is to the right of the operator.
sulla destra dell’operatore. A operazione ultimata controllare che Upon completion of maintenance procedure, check opening
ruotando in senso antiorario l’albero (103) la pastiglia del blocco (30) apra. of slam-shut pad (30) by rotating shaft (103) anticlockwise.

DATI DA FORNIRE PER LA RICHIESTA DI PARTI DI RICAMBIO DATA TO BE SUPPLIED WHEN SPARE PARTS ARE REQUIRED
TIPO .................................................... MATR. N. ........................... TYPE .......................................... SERIAL No ....................................
ATTACCO ENTRATA DN ................... USCITA DN.......................... INLET CONNECTION .............. OUTLET CONNECTION ................
N° PARTICOLARE ............................................................................ PART No ..............................................................................................
DENOMINAZIONE ............................................................................ NAME ...................................................................................................
ELENCO PARTICOLARI (riferito al Bollettino I-I-0125-09/06/03) PARTS LIST (referred to Bulletin GB-I-0125-09/06/03)

N° DENOMINAZIONE NAME N° DENOMINAZIONE NAME N° DENOMINAZIONE NAME

1 Vite registro Adjusting screw 41 Ferma-pastiglia Pad retainer *81 O-Ring O-Ring
2 Cannotto Bush 42 Sede Seat 82 Albero Shaft
3 Reggi-molla Spring carrier *43 O-Ring O-Ring *83 O-Ring O-Ring
4 Molla Spring *44 O-Ring O-Ring 84 Reggi-molla Spring carrier
5 Coperchio Cover 45 Cannotto Bush *85 O-Ring O-Ring
6 Dado Nut 46 Molla Spring 86 Vite Screw
7 Rondella Washer 47 Reggi-molla blocco Spring carrier 87 Molla conica Tapered spring
8 Piattello Plate *48 Fascia Antifriction ring *88 Guarnizione Seal
9 Piattello Plate 49 Seeger Snap ring 89 Tappo Plug
10 Gruppo sfiato Vent *50 Membrana Diaphragm 90 Sfera Ball
11 Piattello Plate *51 O-Ring O-Ring 91 Vite Screw
*12 Membrana Diaphragm 52 Vite Screw 92 Sfera Ball
13 Golfare Eyebolt *53 O-Ring O-Ring 93 Camma Cam
14 Rondella Washer *54 O-Ring O-Ring 94 Anello atifrizione Antifriction ring
15 Vite Screw 55 Tappo Plug 95 Boccola Bushing
16 Piattello Plate *56 O-Ring O-Ring 96 Spina elastica Spring pin
*17 O-Ring O-Ring 57 Tappo Plug *97 O-Ring O-Ring
18 Distanziale Spacer 58 Piastra Plate 98 Anello antifrizione Antifriction ring
19 Vite Screw 59 Piattello Plate *99 O-Ring O-Ring
20 Cannotto Bush 60 Mozzo Hub 100 Tappo Plug
21 Gruppo tazza Cup assembly 61 Coperchio inferiore Bottom cover *101 O-Ring O-Ring
22 Molla Spring 62 Dado Nut 102 Seeger Snap ring
*23 O-Ring O-Ring *63 Guarnizione Seal 103 Albero Shaft
*24 Fascia Antifriction ring 64 Targhetta Data plate 104 Mozzo Hub
*25 O-Ring O-Ring 65 Gruppo indicatore Indicator assembly 105 Vite Screw
*26 O-Ring O-Ring 66 Pistone Piston 106 Dado Nut
27 Colonnetta Stud bolt *67 O-Ring O-Ring 107 Raccordo Connection
28 Raccordo Connection 68 Cannotto Bush 108 Disco Disc
29 Prolunga pescante Impulse drawer *69 O-Ring O-Ring 109 Silenziatore Silencer
*30 Pastiglia blocco Slam-shut pad 70 Rondella Washer *110 O-Ring O-Ring
31 Seeger Snap ring *71 O-Ring O-Ring 111 Boccola Bushing
32 Gomito Elbow 72 Cannotto Bush 112 Pistone Piston
33 Prolunga Exstension 73 Ferma-pastiglia Pad retainer *113 O-Ring O-Ring
*34 Pastiglia Pad *74 O-Ring O-Ring 114 Raccordo Connection
35 Stelo Stem 75 Anello Ring 115 Fondello Cap
36 Porta-pastiglia Pad holder 76 Anello Ring 116 Anella monitor Monitor ring
37 Corpo Body 77 Vite speciale Special screw *117 O-Ring O-Ring
38 Vite Screw 78 Stelo Stem 118 Tazza monitor Monitor cup
39 Fondello Bottom 79 Molla Spring 119 Stelo monitor Monitor stem
*40 O-Ring O-Ring 80 Tappo Plug 120 Rondella Washer
LE PARTI IN GOMMA INDICATE CON ASTERISCO (*) VENGONO FORNITE RUBBER PARTS MARKED WITH (*) ARE SUPPLIED IN THE " SPARE PART
NEL "KIT RICAMBI" CONSIGLIATO COME NORMALE SCORTA MAGAZZINO. KIT", RECOMMENDED AS STOCK.