Professional Documents
Culture Documents
There are some restrictions in calculating the plinth area of a building and some area have to include or exclude when calculating. Among that, areas
which can include are,
Floor area with area of walls at floor level excluding the offsets of the building, internal shafts of sanitary fittings within 2m2, lifts, air conditioning
ducts, area of porch at floor level (cantilever part can’t be included), area of barsati – a room on the terrace or roof top with veranda outside.
Areas which can’t include are,
Area of lofts, open balconies / un enclosed balconies, fascia, towers which project above terrace level, louvers & vertical sun breakers.
Documents such as line plan with complete specifications & costs for services such as water, electricity should be attached with estimate.
Types of Estimates:
Area of walls at floor level.
Internal shafts of sanitary installations not exceeding 2.0 sqm, lifts, air-conditioning ducts etc.,
Area of barsati at terrace level: Barsati means any covered space open on one side, constructed on one side, constructed on terraced roof which is
used as shelter during rainy season.
Porches of non-cantilever type.
Cubic content estimate = Volume of the building X unit cubic rate (known value)
volume of the building = plinth area (length X breadth of the proposed building) X height of the building (floor to roof top)
unit cubic rate = total cost of the previously built building / total volume of that building
3. COST PLANNING:
Cost planning as the name suggest is a system wherein in expenditure in any project is planned within the predetermined sum .
The operation of cost planning has three stages:
a) Establishing target cost
b) Cost plan
c) Cost checking.
The first stage consists of establishing a target cost before commencement of cost planning process. This is usually done by like superficial
estimation, cube area estimation or item wise estimate etc. This is the foundation of cost planning and if the estimate is un realistic , the brakes of
the cost planning will become the process of setting up of the target cost or estimated cost which represents architect/engineers expenditure and
clients financial liabilities.
The Second stage consists of Cost plan where in a definite program is set up about spending the finance on different ‘Elements” of the building or the
project. For this purpose the building is split up in number of Elements whose approximate quantities can be ascertained from the sketch plan .
The Third stage consists of cost checking which means finding out whether the expenditure set out on various elements have been a planned out
and if not, what are the reasons for deviations. This stage comes during the execution of works, the main purpose behind is to make the ultimate
amount payable on completion of project equal to the target amount.
3.UNIT MODE OF MEASUREMENTS (IS CODE AND IIA NORMS)
Table below shows units of measurement of various items of civil engineering works based on IS 1200.
Note:
•SQM = Square meter
•CUM = Cubic meter
•RM = Running meter
Units of
Sl. No. Particulars of item Units of payment
measurement
1 Earthwork
1. Earthwork in
CUM Per CUM
excavation
2. Earthwork in
filling in foundation CUM Per CUM
trenches
3. Earth work in
CUM Per CUM
filling in plinth
2 Concrete
4 Brick work
1. Lime concrete in
CUM Per CUM
foundation
1. Brickwork in
CUM Per CUM
2. Cement concrete in foundation
CUM Per CUM
lintels
6. Cement concrete
CUM Per CUM
bed 5. Brickwork in
CUM Per SQM
arches
7. Reinforced concrete
sunshade (specified CUM Per CUM 6. Reinforced
CUM Per CUM
width and height) brickwork
1. Stone masonry CUM Per CUM 1. Steel reinforcement bars etc. in RCC
Quintal Per Quintal
and reinforced brick work
6 Wood work
1. Doors and
windows frames or 2. Bending, binding of steel
CUM Per CUM Quintal Per quintal
chaukhats, rafters, reinforcement
beams
3.provide their associates with suitable working environment, compensate them fairly and facilitate their professional
development,
6. Be Inspired
(co-ordination)
(co-ordination)
(co-ordination)
(co-ordination)
ARCHITECTS ROLE:
1 Taking Client's instructions and preparation of design brief.
2 Site evaluation, analysis and impact of existing and / or proposed development on its immediate environs.
3 Design and site development.
4 Structural design.
5 Sanitary, plumbing, drainage, water supply and sewerage design.
6 Electrical, electronic, communication systems and design.
7 Heating, ventilation and air conditioning design (HVAC) and other mechanical systems.
8 Elevators, escalators, etc.
9 Fire detection, Fire protection and Security systems etc.
10 Periodic inspection and evaluation of Construction works.
. SCHEDULE OF SERVICES :
The Architect shall, after taking instructions from the Client, render the following services:
2.09 Invite, receive and analyse tenders; advise Client on appointment of contractors.
CONSTRUCTION [STAGE 6] :
2.10 Prepare and issue working drawings and details for proper execution of works during construction.
2.11 Approve samples of various elements and components.
2.12 Check and approve shop drawings submitted by the contractor/ vendors.
2.13 Visit the site of work, at intervals mutually agreed upon, to inspect and evaluate the Construction Works and where necessary clarify any
decision, offer interpretation of the drawings/specifications, attend conferences and meetings to ensure that the project proceeds generally in
accordance with the conditions of contract and keep the Client informed and render advice on actions, if required.
2.14 In order to ensure that the work at site proceeds in accordance with the contract documents/ drawings and to exercise time and quality
controls, the day-to-day supervision will be carried out by a Construction Manager (Clerk of Works/ Site Supervisor or Construction Management
Agency in case of a large and complex project), who shall work under the guidance and direction of the Architect and shall be appointed and paid by
the Client.
2.15 Issue Certificate of Virtual Completion of works.
COMPLETION [STAGE 7] :
2.16 Prepare and submit completion reports and drawings for the project as required and assist the Client in obtaining "Completion/ Occupancy
Certificate" from statutory authorities, wherever required.
2.17 Issue two sets of as built drawings including services and structures.
CLIENT'S ROLE AND RESPONSIBILITIES :
The Client shall discharge all his obligations connected with the project and engagement of the Architect as follows:
8.01 To provide detailed requirements of the project.
8.02 To provide property lease/ ownership documents.
8.03 To provide a site plan, to a suitable scale, showing boundaries, contours at suitable intervals, existing physical features including any existing
roads, paths, trees, existing structures, existing service and utility lines and such lines to which the proposed service can be connected. In case such
information is not readily available, the Client shall arrange for the survey/ collection of necessary information and pay for the same.
8.04 To furnish reports on soil conditions and test as required by the Architect or pay for the preparation of the same.
8.05 To furnish specific conditions/ Statutory stipulations/ Codes of Practice/Schedule of rates, etc., desired to be followed.
8.06 To pay all the fees, levies, security deposits and expenses in respect of statutory sanction.
8.07 To give effect to the professional advice of the Architect and cause no changes in the drawings and documents without the consent of the
Architect.
8.08 To honour Architect's bills within one month of its submission.
8.09 To appoint a Construction Manager (Clerk of Works/ Site Supervisor or Construction Management Agency in case of a large and complex project)
as per the Architect's advice.
QUANTUM MERUIT
“QUANTUM MERUIT” is a Latin word , the Essence of which is the reasonable remuneration in proportion to the benefits received by the defending
party. It comes in to operation as soon as the oral contract between the two parties come to an end and is also applicable in case of partial services.
a) Evaluation of the architectural inspiration for finding a solution to a particular problem
b) Experience and standing of the architect
c) Nature of work done , drawing, interviews , correspondence etc.
After taking in to consideration all the above facts , the remuneration payable to the architect in such cases as decided by the court is said to be fees
on quantum meruit basis. It is the right whereby a reasonable remuneration is required to be paid for the work done, where there is no contract or
no price has been fixed for the work. It will be applicable when the contract becomes void due to mistake, fraud and for other resaons.
5. Legal Aspects-Arbitration
Contents:
1.Concept
2.Advantages
3.Qualification criteria for arbitrators appointment
4. Application of arbitration procedure/obligations u/IIA form of building contracts.
5.Types of arbitration.
THE ARBITRATION AND CONCILIATION ACT, 1996
An Act to consolidate and amend the law relating to domestic arbitration, international commercial arbitration and enforcement of foreign arbitral
awards as also to define the law relating to conciliation and for matters connected therewith or incidental thereto.
ARBITRATION:
It is a method of Settling the disputes and differences between two or more parties whereby they appoint one or more persons to adjudicate upon the
said disputes and differences hat have arisen or that may hereafter arise and agree to abide by the decision of the said one or more persons
nominated for the purpose of adjudication.
ARBITRATOR:
He is the person to whom the disputes and differences are referred as necessary adjudication. If there are more than one arbitrator, they are known
as “Joint arbitrator” and if there is only one arbitrator appointed for the purpose , he is known as sole arbitrator. Unless a specific provision is made for
two or more arbitrator, the reference will ne to sole arbitrator.
2. If the appointed arbitrator is lacking in some qualification as per agreement.(like cl.56 of the IIA form of contract puts a condition on the arbitrator
to be a Fellow Member of IIA, and appointed person is not) , the parties must be informed about it.
3. To conduct arbitration proceedings with equal treatment to both the parties, giving full opportunities, sufficient advance notice of hearings, order
on inspection of document , goods or other property as also not disregarding the principles of natural justice.
4. Can call for deposit amount towards the case of Arbitral Tribunal from both the parties in equal parts.
5. To decide its own jurisdiction and seeks reports of experts on issues pertaining to specialized discipline,
7.To hear the parties patiently on all issues at dispute till termination without exceeding the scope of authority setout.
9.Not to give any decision according to what the tribunal thinks just or reasonable. It has to decide according to law expert when the parties have
expressly authorized to do so.
10. Make, Declare as publish interim award , final award without undue delay, showing the outcome including the burden of cost of arbitration and
incidental cost and in what proportion to be borne by the parties.
TYPES OF ARBITRATION:.
A) Arbitration : based on arbitration clause in the contract:
It arises in case if arbitration of the contract whereby present or future disputes are referred to the adjudication if the tribunal disputes. No suit is filed
in this case and the arbitral award takes the form of the decree of the court.
C) Arbitration in suits:
In case of suit pending in court, all the interested parties at any time before the judgment is pronounced , agree that the disputes
and differences be settled by arbitration and the judicial authority will refer the parties to arbitration.
Essentials:
a) The award must be made without undue delay as otherwise the arbitrators mandate can be terminated.
b) The award as a rule must be in writing and to be signed by the members of the arbitral tribunal and signatures attested.
c) The award must be self explanatory with any ambiguity and must show nature of adjudication whether unanimous or by majority. The decision by
majority will form a binding force in case unanimous decision is not possible.
d) The award to be made on a stamp paper of Rs 100 value.
e) After the tribunal award is made , a signed copy to be supplied to each of the party.
f) The arbitral award is to state its date and place of arbitration, claim adjudication in terms of money contents, interest on amount awarded or part
thereof at such rate as it deems reasonable for the period or part of period from the date on which cause of action arose to the date of making of
the award.
g) The award must provide interest on the awarded amount from the date of award to the date of payment.
h) The arbitral award must provide for legal cost , cost of arbitration ad other incidental expenses and the manner in which the cost to be shard and
paid.
i) The arbitral award has to be reasoned one unless both the parties agree for non reasoned award.
6. Legal Aspects-Easement
Content:
1. Concept- Acquisition/ modes of acquiring Easement.
2. Extinction of Easement-Revised of Easement
3. Different types of Easement for property (with illustrations)
EASEMENTS:
As easement is right which the owner or occupier of certain land possesses , as such , for the beneficial enjoyment of the land:
1.To do and continue to do something: or
2. To Prevent and to continue to prevent something from being done; in or upon, or in respect of certain other land not his own.
CHARACTERISTICS OF EASEMENT.
1. Owner or Occupier of Land is necessary.
2. The Right to do and continue to do something, or prevent and continue to prevent something being done, in or upon or in
respect of certain other land not his own must be vested in the owner or occupier.
3. The Right should be for the beneficial enjoyment of the Dominant heritage(Owner)Since it is attached to land and as such
it is transferred automatically with the sale of land and separate agreement is not necessary.
A-sells to ‘C”
A=owner &
sells to ‘c’
The Right of passing over the land of ‘B” R S
Is automatically transferred to ‘C’ provided
Right of way has been enjoyed by ‘A’ as an
easement, it is the easement of necessity. B=owner
T V
4.Servient heritage in or upon which the right of Dominant Heritage has to be exercised must belong to Dominant owner that is
both lands must have different owners. This is the right over somebody else’s land and the owner can not enjoy easement over
hos own land.
7. Legal Aspects-Land Acquisition
Content:
1. Concept-
2. Principles Underlying Procedure of Acquisition
LAND ACQUISITION:
Land acquisition is India refers to the process by which union or a State Government in India acquires a Private Land for the purpose of
Industrialization, development of infrastructural facilities or Urbanization of the private land , and Provides compensation to the affected land owners
and their rehabilitation and resettlement.
2) After hearing from parties , the collector will submit report to govt. with his observations and if all fine the govt. will declare land for acquisition , on
other hand , if the objection from owners are upheld (part property taken), the govt an cancel the notification.
3) After the publication of the notification, land Acquisition officer is appointed. (LAO).
The LAO will issue notices to all parties interested in acquisition, including the occupants, to file their claim reports. He will conduct the necessary
inquiries which are not judicial ones ,and his reward is merely an offer unless the parties accept the same.
The claim filed before LAO must contain;
a) Names of the claimants and co sharer if any, with their shares, a written declaration, is required to that affect.
b) Documents of profits
c) Rents or profits of last 3 years
d) Valuation report of an architect or engineer together with the documentary evidence in support of the same.
e) Whether area given in notice issued by collector is acceptable or not.
The market value of the land can be determined by one of the following methods:
a) The actual price of actual property under acquisition provided that there is no material time lag between the date of transaction and date of
notification . Rise and fall in the value of land during that period will have to be accounted for.
b) By comparing land under acquisition with instances of sale in the neighborhood of comparable properties after making due allowances for all
relevant factors which affect the value.
c) Development method of valuation depending upon circumstances of case.
8. Legal Aspects-Valuation
Content:
1. Concept-
2. Purpose of Valuation
3. Factors affecting valuation
4. Different “values “ defined for property
5. Methods of valuation
VALUATION: BASIC TERMINOLOGY
COST • The term cost is used to indicate the actual amount incurred in
producing a commodity. • Cost means the original cost of construction and
can be known after accounting all day-to-day expenditure from the very
planning stage till the construction is completed. • The expenditures or
charges represented directly in the commodity produced are called the
prime costs. • Other expenditures or charges like rent, management,
services, salaries, depreciation, etc. represented indirectly in the production
of the commodity are called the supplementary costs.
Value • Value means its worth or utility. • Value varies from time to time and
depends largely on the supply of that particular type of property and the
extent of the demand for it • The cost of the construction of a building may
have no relation to the value of the same if sold in the open market. • The
value of the property within a short time may be more like double than
construction when there are more buyers . • The value depends upon ->It’s
utility -> scarcity -> events
Price • The term price is used to indicate the cost of the commodity plus
profit of the manufacturer. Price = Cost + Profit • As labour and capital are
required to produce a commodity, • The manufacturer is entitled to have
some reward over and above the cost of commodity. • The price of a
commodity is determined by the supply and demand conditions prevailing in
the market for that particular commodity and as such , a commodity may be
sold above or below its cost of production
PURPOSE OF VALUATION:
1) Purpose for investment or for Occupation
2) Sale
3) Mortgage
4) Rent Fixation
5) Land Acquisition
6) Betterment charges
7) Auction bids
8) Probate
9) Speculation
10) Insurance
11) Capital gains
12) Wealth tax
13) Stamp duty
14) Gift Tax
15) General court purpose in order to determine the amount of Court Fee, Stamp in a suit etc.
The purpose of valuation plays a big part in determining the Market value of the property. Hence it is most essential that the purpose of valuation
should be known in advance as the values will defer with different purposes for which they are acquired.
DIFFERENT VALUES DEFINED FOR PROPERTY:
1) Assessed value: The value of the property which is recorded in the register of the local authority and used for the purpose
of determining the amount of property taxes to be collected from the owner of property.
2) Book Value: It is also known as book cost which shows original investment of the company on its assets, including
properties and machineries less depreciation for the period passed.
3) Salvage value: Value of machinery realized on sale when its useful span of life is over but it has not become useless.
4) Scrap value or Junk value: Value of machinery realized when it becomes absolutely useless except form sale as junk. It also
applies to built properties which have outlived their useful life span and in such cases the value of old materials of such
buildings less cost of demolition will represent the scrap value .It is also known as Demolition value.
5) Replacement value: It indicates the value of building or portions thereof if these to be replaced in the form of acceptable
substitutes , at the current market rates.
6) Earning value: it is the Present value of the property which will start yielding an income in future.
7) Potential value: The land has got an inherent value which may go on increasing due to passage of time or due to some
alternative use fetching more return. The inherent value is known as “Potential value”.
It includes the following:
1) Beneficial present use of land
2) Future usefulness
3) Special suitability for a definite purpose.
4) Better layout.
8) Distress value: When a property is sold over lower price than that which can be obtained for it in an open market , it is said
to have “Distress value”.
It may be due to following reasons:
1) Financial difficulties of vendor.
2) Indirect profit to vendor or purchaser.
3) Part consideration paid otherwise.
4) Panic due to war and riots.
9) Speculative value: When the property is purchased so as to sell the same at a profit after a short duration, the price paid is
known as Speculative value and the chief aim behind the purchase is not that of development so as to earn rent but that of
speculation.
10) Monopoly value: Following the law of supply and demand as the number of available plots in a locality goes on decreasing,
the value of the land goes on increasing and a time comes when very few plots remain in the market. The fancy price demanded
by the vendor for those few remaining plots will be known as “Monopoly Value”.
11) Sentimental value: The fancy price which is demanded by the vendor when he attaches sentimental value to his property is
known as “Sentimental value” having no relationship with Market value.
12) Accommodation Land and Accommodation value: The land on the outskirts of the land for the purpose of playgrounds,
gardens etc. is known as Accommodation land. It has greater value than that of agricultural land and less than that of building
land.
At times small strips of land cannot be developed independently and as such the same will not find prudent purchasers in the
open market. The owners of the adjoining land are the only people who can benefit from it as the value of the land will be less
than market value. Such price offered is known as Accommodation value.
FACTORS AFFECTING VALUATION:
1) SUPPLY AND DEMAND: Rise in population due to influx or by multiplication will result in heavy demand for Housing and to
satisfy the said demand more land is required. If sufficient land is not available to satisfy the demand fully, the same may
result in the increase in the value of land.
2) COST OF REPLACEMENT: When a built up property is available for sale with vacant possession for the beneficial occupation
of purchaser, he will always consider the cost of replacement of the same building at present.
3) OCCUPATIONAL VALUE: When a property is required for the purpose of residential occupation, the price paid is generally
more than its market value arrived at by rental method. It has been observed that a built up property, part vacant , will
fetch a good price even if the premium for the vacant portion is taken in to consideration. In the purchase of such a
property , the returns forms a secondary consideration.
4) INTEREST & SECURITY OF CAPITAL: Every person expects some reward in return if he allows the use of his capital. This
reward is known as Interest.
5) RENT RESTRICTION ACT: The Value of Property depends upon its annual rental and in case of an old let out prior to 1940
the same is not allowed to be increased under the Rent Act except for permitted increases.
6) ABNORMAL CONDITIONS: The value of the properties may go down due to abnormal conditions like war, riots, or due to
insecure conditions.
7) TOWN PLANNING ACT: Due to declaration of Town planning scheme in a particular area whereby the said area is proposed
to be provided with all civic amenities like roads, gardens,, drainage, etc the value of open plots in that locality will go up.
METHODS OF VALUATION:
9. TENDER
CONTENTS:
1.Procedure –Criteria's for different kind of tenders
2. Duties/ Obligation of architect for procedure of tender
3. Concepts of Tender Documents- EMD, SD, RMD, Mobilization fund
1. Concept:
A “Tender” is nothing but an offer made by one party to another for execution of specified work at a specified cost
In keeping with all the terms and conditions set there in the tender document including the extent of the work
shown in the plans. IT remains floating till the time it receives a seal of acceptance either by the employer and /or his
architect/engineer and thereafter forms a binding contract.
1.2. Tender Documents:
The tender documents occupy important position not only from the view point of contractors and employers, but
also to the architects. They find their place in the contract documents with required modifications if any. The tender
documents are to comprise the following.
1. Tender Notice
2. Special Notice
3. Letter of order
4. Special conditions
5. Form of contract with conditions
6. General specifications
7. One set of building plans
8. One set of R.C.C plans
9. Bill of quantities (BOQ)
1.2.1 TENDER NOTICE
a) Tender Notice must mention the name of the owner, the place , the nature of work , extent of work and the estimated cost.
b) It must mention amount of Earnest Money and Tender Fees.
c) Minimum time of returning the tender by the contractor should be at least 15-20 days from the date of issue of tender.
d) The place of Delivery of tenders by the contactors should be specified.
e) The contractors should be requested to inspect the site prior to filling of the tender , so that they ascertain well in advance the working
conditions of the nature of soil.
f) Lastly the architec.t/Engineer have to be very careful in inviting the tenders in time, as the delay in the sum may prove to be dangerous
both for clients as well as for architects.
1.2. Tender Documents:
1.3. methods of calling tender:
1.4. Tender Scrutiny:
3. NATURE OF TENDER CAN BE CLASSIFIED AS UNDER:
1) a) Item rate tender:
The contractor is paid in the measurement of the work executed at the rates quoted by him in the tender. In act
the rates of the item are the part of the contract and the approximate quantities are not.
Its a balanced method of execution and not risky for contractor and hence quality of workmanship will be assured.
Reasonable variations can be made in the plans and also in the quantities. Its suitable to all types of work like
buildings, bridges, culverts, sewer lines roads, etc.
Essential characteristics:
1.Plans with all details and elevations to be clear for which the work is to be carried out.
2. Work to be described in details in the specifications with special conditions, if any.
3.Time for completion of work should be specified.
4.If contractor id not given part payments it should be specified in advance .
5. Site shall be accessible to contractors so that he can ascertain the nature of soil, cost of foundation & other relevant
work conditions.
6.No serious variations are contemplated.
7. Contract amount is not decided on the basis of measurement except for additions and omissions.
Advantages:
1.Total cost of construction is known in advance .
2. The contractor will try to complete work as early as possible so as to have good margin of profit.
3. Work load of the engineer and architect is reduced, as no detailed measurements are required to be taken for each
Item of the work executed.
Disadvantages:
1.More and more of extra works
2.Design is likely to be adversely affected with variations.
3. Quality of work is not guaranteed.
4. Contains more element of speculation and risky form of tender.
Suitable for additions and alternations to an existing building , works of repair to a building, works under water like
foundations for bridges culverts etc and not suitable for All building works, laying of main services, General drainage
and plumbing, Road works.
4) Labor tender
In this the contractor agrees to carry out the complete labor work of all the items of the work at the rates quoted by
him. The contractor has to supply the tools plants, scaffolding, centering materials, and the owner supply only the
material required for the construction work. The labor tender generally includes the labor work for the construction of
water tank for storage of water required for construction purpose as well as labor work for putting up temporary shed
for office and cement godown of reasonable size.
The labor tenders are invited sometimes on the basis of rate per square meter or cubic meter of the construction
work. Its suitable for all kinds of work like buildings, roads, culverts, repairing etc.
2. Duties/ Obligation of architect for procedure of tender:
1) Earnest Money: (EMD)
It as defined as an initial deposit which is sent along with the tender order to show genuineness of the contractor. The
amount or earnest money varies from 1-2 % of the estimated cost of the project. This amount remains in the safe
custody of the architect or the engineer till the work is allotted to the particular contractor who will be asked to
deposit further sum towards the security deposit. The main purpose of the Earnest money is to see that a fair
competition takes place for the work. The Earnest money is forfeited in favor of the owner in case the contractor
refuses to enter in to contract after his tender has been accepted. It is accepted in cash or cheque at times in the form
of Negotiable government securities.
Main purpose:
1. To make good the defect before the final certificate has been issued.
2. To meet the claim, damages, compensations, if any by the adjoining owner or any of the workmen for any reason
whatsoever.
3. To make the necessary payments to the nominated sub contractors in case the contractor fails in the same.
4. To meet the compensation which may become due from the contractor for the delay in completion.
5. It can be utilized for the necessary adjustments in the final bill, over payment, and in the make up of the bills for
extra work.
6. Any work left out by the contractor before virtual completion can be executed by this amount.
7. Disposal of material wrongly supplied.
4) Mobilization fund:
Before executing works of larger magnitude, the actual work and receipt if payments on account, the contractor is
required to incur initial expenditure for preparatory works, such as recruitment of labor , travel of staff, erection if
temporary structures on site, purchase of centering materials, insurance premium, etc. Such preparatory works involve
financial outlay at the beginning for which liquid finance is essential and this is fund is called mobilization fund.
a) Maximum amount of Mobilization fund is limited to 10% of the contract amount.
b) It is paid in full in one installment within in one month of the award of the work and after signing the contract
against the bank guarantee for the full mobilization fund advanced or paid in two or three stages.
Stage:1
50% of the mobilization fund as agreed is paid within one month of the award of the work and signing of the contract
against bank guarantee
Stage:2
Part released on completion of preparatory works depending upon their value.
Stage:3
Part released on bringing plants and machineries on site again depending upon their value.
It s recovered from each of interim bill at f und specified percentage of interim payment and entire mobilization fund
is recovered on completion of 80% of the work.
It can interest free fund or carrying a specified rate of interest. It is rightly said that Mobilization fund is the backbone
of successful implementation of big scale construction projects.
4) Tender for demolition work.
These tenders are called for demolition of the existing buildings up to ground level or up to road level and removal
all he materials of the same including carting away the debris.
Essentials:
1)The highest and the lowest tender should be approved
2) The tender should be accompanied with certain specified deposit so that work can be carried out
3) The Whole of the tender amount should be taken in advance before the possession of the building is given for
demolition.
4) The Contractor should be asked to take an insurance for accident.
ENTIRE PROCESS OF TENDERING:
10. CONTRACT
CONTENTS:
1) Concept
2) Building contract document
3) Time limit completion of work
4) Different categories of CERTIFICATES to be issued by an architect
5) Determination of contract by CLIENT/CONTRACTOR –impact of it & obligation of architect u/determination
6) Assessment of damage u/determination –various factors and evaluation of damage etc.
CONCEPT OF BUILDING CONTRACT:
A BUILDING OR Engineering contract may be defined as an agreement under which a person (builder or
contractor)undertakes for reward to carry out for other person (owner or employer) works of building or civil
engineering character.
The Indian contract act of 1872 , defines contract as agreement enforceable at law. An “agreement” is defined as
ever promise or every set of promises forming consideration for each other and enforceability must have been
made by
a) Free consent b) Parties competent to contract c) Lawful consideration and object d) Agreement must not be
expressly declared to be void.
EXTENSION OF TIME AND LIQUIDATED DAMAGES:
Condition no 40 of IIA form of contract deals with extension of time and condition no 41 deals with damages for
non completion known as Liquidated and ascertained damages”. If the Contractor finds that he will not be able to
complete the work in time or within the extended time limit , it is compulsory for him to give “forthwith” a notice to
the causes of delay and apply for extension of time.The causes for delay have to fall within an one or more of the
ten compartments:
1) Force Majeure which means if there is strike, breakdown, pandemic , fire etc.
2) Exceptionally inclement weather
3) Loss or damage due to fire , storm, tempest etc as given in insurance clause
4) By reason of civil commotion, local combination of workmen, strike or lock outs this affecting the supply of
labor, materials or goods needed for work.
5) By reason of architect’s instructions in general or instructions pertaining to variations or instructions as to
postponement of work.
6) Not receiving in due time necessary instructions, drawing details or level in spite of written application to that
effect.
7) Delay on the part of nominated sub contractor or nominated supplier.
8) Delay on the part of agencies appointed and employed by the owner.
9) By reasons of opening up for inspection of any work covered up or of testing of any work, material or goods to
ascertain weather the same are as per contract or otherwise.
10) Unable to secure labor, goods and materials for works for reason beyond the contractors control and which he
could not have foreseen at the time of execution of contract.
ARCHITECT’S DUTIES AND LIABILITIES UNDER THE CONTRACT:
1) AGENT OF THE OWNER:
a) To act as owners representative during construction period.
b) Periodically visit the site to find out the progress and quality of the work.
c) To keep informed he owner about the progress of the work.
d) Too guard the owner against defects and deficiencies in the work
e) To Condemn the work which is not as per the contract document.
f) To act within the contract as expressly provided and not to exceed his authority.
g) To stop the work as may be necessary.
3) AS QUASI-ARBITRATOR:
To make decisions on all claims of either party as also on all other matters relating to execution and progress of the
work or interpretation of the contract.
There can be many legal problems associated with construction completion times. This is a fertile field for lawyers
involved in construction-related practices. Therefore, astute construction people should make every effort to
protect themselves and thus avoid problems, attorney’s fees and related expenses.
It is extremely rare to find a construction contract that provides for a fixed or a determinable completion time
without a companion clause excusing the contractor from delays occasioned through circumstances beyond his
control. The contractor should insist upon such an excuse clause. The contract clauses which excuse contractor’s
delays because of circumstances beyond his control are called “force majeure” clauses; force majeure meaning a
superior or irresistible force.
Typical delay excuse clauses provide that the contractor is excused for periods of delay occasioned because of
delaying activities of the owner or his representative, strikes, shortages or unavailability of workers or materials,
fires, floods, tornadoes, unforeseen casualties, unanticipated adverse weather conditions, other acts of God, riots,
civil unrest, wars, transportation delays and other conditions beyond the reasonable control of the contractor.
LIQUIDATED DAMAGES:
In order to bring home the importance of time for completion of the work known as “time being the essence of
contract” as also to compensate the owner for the loss that may have to undergo to some extent, some provision is
essential making it obligatory on contractor to pay pre –estimated damages in case he fails in due performance of hs
contractual obligations.
Conditions no 41 of IIA Form of contract provides for the above aspect under the head of “ Damages for non-
completion” .
1) Failure of the contractor to complete the work within the specified or extended time limit.
2) Certificate from the architect that the contractor reasonably ought to have completed within the specified or
extended time limit.
3) For such failure contractor to pay or allow to the owner a sum calculated at the rate stated in the Appendix as
agreed “Liquidated damages” for delay period.
4) The owner may deduct such damages from the moneys due under the contract.
DEFECT LIABILITY PERIOD
A defects liability period is a period of time following practical completion during which a contractor remains liable
under the building contract for dealing with any defects which become apparent. Depending on the form of
contract you are reading, it may also be referred to as a rectification period or defects correction period.
A defects liability period is usually a period of around six or 12 months but it can vary depending on the contract
used. Any defects or faults which arise during this period (for example - due to defective materials or workmanship)
must be put right by the contractor at its own expense.
The inclusion of a defects liability period in a contract arguably benefits both the contractor and the employer. For
the employer, it provides an opportunity to request that the contractor return to site and remedy a defect, while for
the contractor it is usually cheaper to return and remedy a defect itself than to be asked to pay for the employer's
losses in arranging for someone else to remedy that defect. Having a practical contractual remedy can therefore
save the parties' time and cost compared to adjudication or litigation.
It should be noted, however, that defects liability periods will only arise if they are included in the contract.
Contractors therefore need to be aware that they do not have an automatic right to return to site to rectify a defect.
Employers, on the other hand, need to carefully consider the wording and requirements of defects rectification
provisions if they are considering hiring another contractor to fix the original contractor's mistakes, or else they risk
being found to have failed in their duty to mitigate their losses.
It is also worth noting that a defect which is not discovered until after the defects liability period has expired is still a
breach of contract for which the contractor is liable (subject to limitation arguments). In this circumstance, the
contractor has no right to return to the site to repair the defect but is liable to the employer for damages.
TYPES OF CERTIFICATE:
1) VIRTUAL COMPLETION CERTIFICATE:
The Architect gives Virtual completion certificate under the following circumstances:
a) When the contractor gives a notice to that effect
b) When the drainage completion certificate has been obtained.
c) When the architect applies for occupation certificate from local authority.’
d) When the local authority grants the occupation certificate.
e) When certificate under sec 270-A of BMC has been granted for adequacy of water supply.
f) When the architect applies fro completion certificate.
g) When the local authority grants completion certificate.
h) When the building is being occupied after water connection has been obtained.
2) INTERIM CERTIFICATES:
1) These certificates are simply statements of facts which show approximate value of the work done or the contract
price of the materials delivered on site. It is merely a ministerial work which does not call for the final opinion
requiring exercise of judgment and skill.
2) They show that the owner is quiet safe in making such payments to the contractor equivalent to work or
materials that value on the owner plot.
3) These are issued during the progress of the works strictly in compliance with conditions of the contract specially
period of honoring certificates, stages of payments, maximum limit of retention fund.
4) Architect cannot be sued for certifying less amount than due to the contractor.
5) These are not binding or conclusive certificates and that the issue of interim certificates does not guarantee that
the works executed are proper.
6) These cannot be cited in court of law or before arbitrators in the event of claim for the breach of contract or
claim on Quantum Meruit.
7) Payment made under these certificates are provisional and are subject to adjustments at the end of contract.
8) Final certificate can be with held even though interim certificate have been issued and the same cannot be made
a ground for the issue of the final certificate.
9) After issue of the interim certificate, the materials cannot be removed form site.
10) Issue of Interim certificates waives the rights of the owner to claim damages on account of delay from the
contractors.
11) These are usually issued at certain stages of work like plinthl vl, firs t slab etc or monthwise or based on the value
of works executed.
12) Interim certificates can be revised by subsequent certificates.
13) Retention fund is required to be considered while issuing the interim certificate.
3) FINAL CERTIFICATE:
As per condition 31 the architect is bound to issue the final certificate for which he has been give three parameters
and out of the three the latest can be adopted like:
a) Fro m the end of the defect liability period which is printed as 12 months from the date of virtual completion
certificate.
b) In case the defects the contractor is required to be issued with the schedule of defects not later than 14 days
from the end of defect liability period., after contractor ha made goods to the defects.
c) The contractor must submit all the documents pertaining to measurements and valuation either before or within
a reasonable time fro issue of Virtual completion. Here the delay will be at the cost of the contractor if he fails to
comply with the same in time.
WHAT IS BREACH OF CONTRACT?
When a Party repudiates or fails to perform one or more of the obligations imposed upon on him by the contract ,
breach of contract occurs which gives immediate cause of action and a right to damages for loss flowing from the
breach.
There are two parties to the contract , namely the owner and the contractor and as such any of them may fail to fulfill
hos obligations under the contract , resulting in the breach of contract , leading to its determination.
2) BANKRUPTCY:
a) When the contractor becomes bankrupt
• Competitions
intended for smaller
projects of charitable
trust in which 4-6
local firms compete
for project.
• No premium are given
and the winner shall
be appointed to
carryout the project.
COPYRIGHTS AND RIGHTS OF OWNERSHIP IN COMPETITION.
From Architects point of view:
1. Drawings of the design winning prize will be retained by the promoter as hos property. All other drawings to be returned by the promoter at the end
of competition.
2. Design awarded for firs prize will be used by promoter with the author winning design being retained as architect for the project unless there are pre
declared reservations or valid objections to the same. The right to make use of the design is limited to one execution only and repetition if needed
will be subject to agreed terms and conditions either specified in advance or agreed thereto subsequently including fees aspects.
3. No other design whether permitted or not shall be used wholly or partly by the promoter.
12. Dilapidation-Law related to repairs
Content:
1. Repair-Guidelines for repairs
2. Modality of repair work to be undertaken u/BMC Act +provisions for CGDCR-2017 (updated nov’2019) for related activity
WHAT IS DILAPIDATION:
1) The word “Dilapidation” means wasteful destroying or letting a building run to ruin and decay for want of reparation. This conveys the idea that
meaning of dilapidation is confined to buildings and is either a)an act of destruction, b)an omission to repair.
2) Dilapidation is the injury accrued to the houses, buildings, or erections, during temporary possession of one party whereby a successor or
reversionary sustains damage and for which the law and custom of this realm have provided and pointed a remedy.
So dilapidation is
a) State of disrepair of the building
b) Defective condition of the building
c) Worn out or ruinous condition of the building.
REPAIRING CLAUSE:
a) It makes it obligatory to keep the premise in a good tenantable repair having regard to the age, character, and situation of the house such that it
is fit for Occupation thereafter by reasonable class of tenants. The repairing clause sets out in detail the responsibilities of the lessee so far as the
repairs of the building are concerned.it is the clause which is introduced in the lease document can be worked in a suitable manner depending
upon;
1) the share of the lessee in the repairs
2) the type of repairs like structural repairs leading to improvement, tenantable repairs etc.
3) the liabilities of monthly tenants seldom arise in dilapidation resulting in from failure to carry out the repairs as several statues make landlord
liable for tenantable as well as for structural repairs
4) The law of property provides that the tenant shall not pull down or damage the building belonging to the landlord(lessor) or commit any other
act which is destructive or permanently injurious to the premises. In other words the tenant is prohibited from any act of injury whereby the
building becomes dilapidated. Such act is known as “act of waste” and in India this is governed by The Rent Control Legislations.
REPAIR:
Repairs is a term of wildest connotation whose range arises from upkeep to maintain the property as far as possible in its original condition and
efficiency without the renewal and also include restoration, reconstruction or even renewal of any existing part of the building and at times renewal
of the complete building.
“Any labor or materials provided to restore, reconstruct, or renew any existing part of the building, it fixture or appurtenances.
GUIDELINES FOR REPAIR
1) Statuary provisions for repairs are found in the Acts of Local authorities , Rent Control Legislation as well as in the state acts. These provide for
Obligations both for the tenantable as well as for structural repairs and on failure to fulfill such obligations , alternative modes- are also provided
to prevent the building from reaching a dilapidated stage.
In Mumbai the liabilities of repair are imposed on landlords as per section 354, 381 &257 of the Mumbai Municipal corporation act 1888. Section
354 provides for structural repairs , 381 AND 257 provide for tenantable repairs .
a) Section 354 provides that if any building, wall or other structure is in ruinous condition, or likely to fall in any way dangerous , the commissioner
may , by written notice require the owner or occupier of such a structure to pull down, secure or repair such structure
b) Section 381 provides that the state of the building or premises is such as to constitute a nuisance by reasons of broken plaster of walls, broken
flooring, broken staircase, and leakages through the wall and/or floors causing damages , the land lord is required to make suitable action by
rectifying the above items so as to abate nuisance.
c) Section 257 provides for repairs to drainage works including replacement of broken drain pipes by new ones.
MODALITY ON FAILURE OF LANDLORD TO EXECUTE REPAIRS AS PER MUNCIPAL NOTICES( BMC ACT 1888)
If the landlord has failed to execute the repairs as per Municipal notices he will be prosecuted in court and thereafter necessary authority will be
granted to tenants under section 499 of BMC act 1888 which provides for grant of such authority to the occupiers with rights to recover reasonable
expenses incurred by them on repairs that may become due from time to time It should be noted that recovery procedure starts after the authority
has issued completion certificate as to the satisfactory execution of repairs, strictly as per Municipal notices and landlord has not moved to court
against then notice, authority, certificate as against the reasonable cost.
PROCEDURE AND TERMS AND CONDITIONS FOR AUTHORITY UNDER SECTION 499:
1) Appointment of architect/Engineer to prepare the plans and estimates of repairs as per Municipal notices as well as for other works of incidental
thereto.
2) Application duly signed by the Occupiers for issue of authority to be submitted to the Dy. Municipal commissioner along with plans and estimate
as well as supervision memo of architect and engineer agreeing to supervise the works of repairs.
3) An undertaking on Rs20/- stamp paper duly signed by occupiers to the effect that if the cost of repair exceeds the amount of five years of gross
rent, such excess will be borne by occupiers.
4) Undertaking on Rs 100/- stamp paper indemnifying BMC that any dispute arising between tenants and owner or any other person due to granting
of such repair permission.
5) After issue of authority necessary tenders be invited for the repair work and granted to well experienced contractor.
6) The date of commencement of repair s be communicated to the authority with in the week form starting of the work.
7) No additions, alterations, or change of user is permitted for the structure for which the authority has been granted for repairs.
8.Complaince to any other terms and conditions as may be laid down in the authority.
9. Application by the architect or engineer for issue of Completion certificate after the repairs area complete.
10. Notice to the landlord about the completion of repairs and deduction of the cost of repairs incurred from the rents that may be due thereafter.
13. Important Acts
ELLABORATIONS:
AUTHORITIES/BODIES:
MOEF: MINISTRY OF ENVIRONMENT & FORESTS
GSDMA: GUJARAT STATE DISASTER MANAGEMENT AUTHORITY
BMRDA: BANGALORE METROPOLITAN REGIONAL DEVELOPMENT AUTHORITY
DDA: DELHI DEVELOPMENT AUTHORITY
GEDA: GUJARAT ENERGY DEVELOPMENT AGENCY
EMD: EARNEST MONEY DEPOSIT
RMD : RETENTION MONEY DEPOSIT
ACT:
BPMC :BOMBAY PROVINCIAL MUNICIPAL CORPORATIONS ACT, 1949
GTP& UD: GUJARAT TOWN PLANNING & URBAN DEVELOPMENT ACT
BMC: BOMBAY MUNICIPAL CORPORATION ACT,1888
NBC:NATIONAL BUILDING CODE
ULC: THE URBAN LAND(CEILING AREGULATION) ACT,1976
LAQ: LAND ACQUISITION ACT
COA: COUNCIL OF ARCHITECTURE ACT
LEGAL ENTITIES:
LAO: LAND AQUISITION OFFICER
TPO: TOWN PLANNING OFFICER
TDO: TALUKA DEVELOPMENT OFFICER
CEA: CHIEF ECONOMIC ADVISOR
COW: CLERKS OF WORK
APPROVAL PROCESS:
BUC:BUILDING UTILITY CERTIFICATE
FSI: FLOOR SPACE INDEX
VCF: VIRTUAL COMPLETION CERTIFICATE
GDCR: GENERAL DEVELOPMENT CONTROL REGULATIONS
DP: DEVELOPMENT PLAN
TPS: TOWN PLANNING SCHEME
CRZ: COASTAL REGULATION ZONE
RERA: REAL ESTATE REGULATION AUTHORITY
15. RERA 2016