3812 BSBPMG430 Assessment Task 2
3812 BSBPMG430 Assessment Task 2
project work
PROJECT PORTFOLIO
STUDENT VERSION
Section 1: Project scoping and planning 4
Section 2: Project management plan 8
Section 3: Implementation activities 13
Section 4: Project finalisation 17
Date: 11/12/21
Mission
Native Bush Spices Australia is committed to providing the highest
quality product to all its clients.
Goal
Native Bush Spices Australia needs to enhance its future
arrangement of brand mindfulness and worldwide extension strategy
through the new website. The arrangement is to build up a website
that will enable our clients to purchase our items on the web.
Objective
Native Bush Spices Australia have objectives to:
o Increase sales
Operation context
Give the rationale for the Develop a new website which is include a shopping cart, so
project customers can order products directly through the website and can
access recipes and general information about the health benefits of
bush spices.
Business objectives The company’s overall business objectives for the next three years
are to increase sales and create brand awareness, develop a
Relationship of project to the
broader product range, as well as expand into overseas markets,
organisation's objectives
most likely Hong Kong, Japan and Singapore.
Stakeholders
Small Project:
Outline the project
Project Manager
stakeholders and clearly
define the project staff Project team member
Medium Project:
Project Manager
Project team member
Senior Manager
Large Project:
Project Manager
Project team member
Senior Manager
Project Steering Group
Project management tools Work Breakdown Structure, is a project management tool that helps
and system to be used visualize the scope of work by breaking a project into individual
components that can be effectively scheduled.
Outline the project
management system, tools or
methods you will use to file
documentation and share
information for this project
Background With the old design website of the current marketing plan, Native
Bush company marketing team decided to change the look of the
Provide a brief explanation of
website and logo to improve the attractive and sales of the market.
the background of the project.
The old website only contains 4 pages which is limited to customer.
They want to put more feature like shopping cart and checkout,
gallery and more payment option with language option.
Estimating and/or scheduling Probable Considerable Keep in touch with the responsible
mistakes team and support them to implement
project.
Failure to meet work health Occasional Significant Provide WSH training to provide
and safety (WHS) practical guidance to team member
requirements/other legal who have duties under the Act and
requirements Regulation on how to comply with
their duties.
Project Progress Summary There are two weeks into the project for the development of the
website and the status of the project is as follows.
Briefly describe the Project’s
progress towards meeting its The content has been developed for the website within the
target outcome during this required timeline of 1 month from the implementation of the
reporting period. Anecdotal project plan and at the specified cost.
information may be provided.
The content was written by a public relations consultancy
company, PR Pulse, for the cost specified in the project budget.
Three quotes have been received from web site developers.
The customer service officer has left the organisation
unexpectedly.
Reason for closing the project The project is now complete as the website has been developed
successfully with all the requirements. The website is live with a
Outline why this project is
positive criticism from the staffs in regards to the look and substance
over
of the site. The architects had made it very easy to use with an
imaginative touch to the illustrations and structure.
Highlights and innovations Graphics has been impacted by our flavours and item with
creative thoughts.
What were the main
highlights and innovations of Shopping truck has a drop down in the site with easy-to-use
this project? highlight.
New logo talks about the natural quality that the organization
speaks to.
Web architects are very experts in frame of mind
Summary of Training will give for administration staff to maintain the website
recommendations and ensure information content in the website is updated
regularly.
If using the case study, one of
the recommendations should Project risk areas need to be more focused on unexpected
be for the supervisor to agree factors
that the project can be
Risk contingency plan options need to be prepared for risk
deemed closed.
management plan
Risk register needs to be updated
To implement more effective team building activities
Performance against The website has been effectively conveyed by the organization with
outcomes the proper logo plan. All expected targeted outcomes were
successfully achieved within the quality assurance process. The
Describe the actual
success of this project is dependent on the production, time,
performance of the project in
expense, efficiency, group culture / environment, personnel growth,
relation to the achievement of
initiatives and developments matrix.
targeted outcomes. Were all
planned targeted outcomes
achieved, to what degree?
Performance against outputs Native Bush Spices Australia fully accepts the performance and
results of the campaign. The project is complete, website is live, and
Describe the actual
we are receiving the positive feedback from the clients. All the
performance of the project in
planned outputs were delivered except the delay in its delivery as the
relation to the delivery of the
graphics designer of the team left the project in half way. Therefore,
outputs. Were all planned
after various changes made to the actual plan, we were successful in
outputs delivered, to what
establishing the standards and expectations of the client to create the
degree? Were they all
website.
accepted? Did the quality of
the outputs meet
expectations?
Lessons learnt Setup contingency planning in case any team member leaves.
Describe the project Provide website maintenance training so that there is a person
management and quality who continuous maintains the website.
management processes that
Always keep the estimated budget below the actual initial budget
were perceived to be
allotted
inappropriate and/or
ineffective for the project, as Find the best possible cheap resources
reflected by the stakeholders Train an employee for the tasks in the activities who is in loop
and the project with the whole workings of the project.
records/documentation.
Attach:
Link to completed online file organisation and record
☐
keeping system used throughout the project.