Attachment 3.

Bar Chart of Investigation Schedule


Items Plan 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180
Preparation for plan 10 days
(1)Review and Comment by CAAB 5 days
(2)Review and Submission 4 days
(3)Obtain Approval from CAAB 1 days
Geological Survey Work 120 days
(1)Main Equipment Ready 20 days
(2)Verification and Calibration 15 days
(3)Setting Out and Measurement 5 days
(4)Drilling and Testing Outside 70 days
(5)Indoor Testing 80 days
Confirmation of Report 45 days
(1)Preparation and Submission 21 days
(2)Review and Comment by CAAB 7 days
(3)Revision and Submission 14 days
(6)Obtain Approval from CAAB 3 days