RENCANA ANGGARAN BIAYA

PROGRAM : PENINGAKATAN SARANA PRASARANA KESEHATAN


KEGIATAN : PENGADAAN REHABILITASI RUANG OPERASI
PEKERJAAN : PERENCANAAN TEKNIS REHABILITASI RUANG OPERASI
LOKASI : RSUD PANDAN - TAPANULI TENGAH
T.A : 2022

SATUAN JUMLAH
NO NAMA BARANG SAT QTY
RUPIAH RUPIAH
1 PANEL DINDING GALVANIZED M2 52.56 7,672,500.00 403,266,600.00
2 PINTU GESER OTOMATIS KEDAP UDARA SET 1.00 260,400,000.00 260,400,000.00
3 PINTU AYUN MANUAL KEDAP UDARA SET 1.00 49,245,000.00 49,245,000.00
4 PANEL KONTROL UNIT 1.00 129,412,500.00 129,412,500.00
5 LEMARI ALAT/INSTRUMENT UNIT 1.00 71,412,500.00 71,412,500.00
6 LEMARI OBAT UNIT 1.00 87,725,000.00 87,725,000.00
7 WRITING TABLE UNIT 1.00 19,140,000.00 19,140,000.00
8 PEREDAM TEKANAN BUAH 1.00 37,065,000.00 37,065,000.00
9 BOX TERMINAL GAS OUTLET SET 1.00 23,475,000.00 23,475,000.00
10 X-RAY VIEWER LED BUAH 1.00 61,845,000.00 61,845,000.00
11 BOX STOP KONTAK SET 4.00 6,090,000.00 24,360,000.00
12 RETURN AIR GRILL SET 4.00 19,635,000.00 78,540,000.00
1 PANEL PLAFON M2 27.61 7,672,500.00 211,837,725.00
2 LAMINAR AIR FLOW SET 1.00 297,362,500.00 297,362,500.00
3 LAMPU PERIPHERAL LED BUAH 12.00 5,775,000.00 69,300,000.00
4 SURGICAL PENDANT SET 1.00 240,625,000.00 240,625,000.00
5 ANESTHESIA PENDANT SET 1.00 253,310,000.00 253,310,000.00
1 VINYL M2 34.62 1,562,500.00 54,093,750.00
2 SCRUB UP STATION UNIT 1.00 215,586,250.00 215,586,250.00
3 TRAFO ISOLASI MEDIK SET 1.00 232,500,000.00 232,500,000.00
1 TATA UDARA RUANG OK SET 1.00 1,471,112,500.00 1,471,112,500.00
SUBTOTAL 4,291,614,325.00
PPN 10% 429,161,432.50
TOTAL 4,720,775,757.50