TIME ESTIMATION FOR MOUNTING PAD CHANGE

(PER ENGINE)

Ser Name of Part Quantity Estimated Designated Rmks


Time DYD
Required Shop
01 ME exhaust bellows 02 02 days SF Additional
and additional fittings days may
02 Frame and foot plate 01 day P&W be required
removal as all works
03 FW Cooling line 01 01 day SF are
04 Sea Water suction 01 02 day SF considered
bellows and line to be done
removal parallelly
05 Fuel Auto Filter 01 01 day ICE
Removal
06 Lub oil line and fuel NA 01 day SF
oil line removal
07 Crank shaft coupling NA 01 day ICE
removal
08 Mounting Pad 08 02 days
removal and addition ICE
09 Fitting back all items 05 days SF
10 Total days required 16 days