Ser Name of Part Quantity Estimated Designated Rmks
Time DYD Required Shop 01 ME exhaust bellows 02 02 days SF Additional and additional fittings days may 02 Frame and foot plate 01 day P&W be required removal as all works 03 FW Cooling line 01 01 day SF are 04 Sea Water suction 01 02 day SF considered bellows and line to be done removal parallelly 05 Fuel Auto Filter 01 01 day ICE Removal 06 Lub oil line and fuel NA 01 day SF oil line removal 07 Crank shaft coupling NA 01 day ICE removal 08 Mounting Pad 08 02 days removal and addition ICE 09 Fitting back all items 05 days SF 10 Total days required 16 days