MULTAN ELECTRIC POWER COMPANY .

LTD(MEPCO)
MONTHLY STATEMENT SHOWING EXTRA MAXIMUM LOAD RECORDED OF POWER TRANSFORMER
I.R.O 132 KV GRID STATION INDUSTRIAL ESTATE RAHIM YAR KHAN. FOR THE MONTH OF ___/20____
ST-11
COPY.2

MAXIMUM LOAD RECORDED RUNNING 11KV FEEDERS UNDER THE


NAME OF SCHEDULE
GRID CODE EXTRA
FORCE SHEDING BREAK DOWN PTW REMARKS
NO. OF SHEDING
STATION MAXIMUM DATE TIME LOAD
FDR,S
LOAD NO. OF NO. OF NO. OF NO. OF
LOAD LOAD LOAD LOAD
FDR,S FDR,S FDR,S FDR,S
INDUSTRIAL ESTATE RAHIM YAR
132 KV GRID STATION

TR-1
31.5/40
MVA
KHAN

FULL
DEMAND

No: Date:
Incharge
132 KV G/S Industrial Estate
Forward to A.M (T) SS&T Sub Division Rahim Yar Khan Rahim Yar Khan