3TE.Example.22.MoH.

Bakeries:

MoH, Ministry of Health, is planning a new project to reuse hospital bakeries surplus
products to Kuwaiti farms due to lack of regional wheat/grain production.

Project is planned to start with 4 hospital central bakeries as follows: As-Sabah Hospital
Bakeries, AHB(2,3,5mo, KWD1000); Banid-ul-Gar Hospital Bakeries, BHB(3,4,6mo,
KWD2000); Jahra Hospital Bakeries, JHB(4,5,11mo, KWD3000); and Mubarak Hospital
Bakeries, MHB(1,3,6mo, KWD4000), ~ simultaneously … All 4 bakery centers will deliver
surplus to Salmiya Warehouse, SWH(1,2,6mo, KWD5000). SWH will inspect and sort
deliverables, then send them to 2 Kuwaiti farms same day: Wafra Farms, WF(1,2,4mo,
KWD6000); and Abdelli Farms, AF(1,2,8mo, KWD7000). … Node(optimistic, most-Likely,
pessimistic time/N; KWD … )

T/N = (a+4*m+b)/6 … weighted average to convert 3TE to STE

MoH needs your consulting firm to calculate:

- Project Estimated Time, PET

- Project Estimated Cost, PEC

- Probability to finish after PET

- Probability to finish before PET