Progress Highlights

15th Floor 15th Floor ###

14th Floor 14th Floor ###

13th Floor 13th Floor ###

12th Floor 12th Floor ###

28-05-19
FLOOR 10 7/16/2019 FLOOR 10 ###
20-05-19
FLOOR 09 7/8/2019 FLOOR 09 ###
06-05-19
FLOOR 08 Slab Planned on 30/5/19 Slab Planned on 30/5/19 6/30/2019 FLOOR 08 ###

29-04-19 26-05-19
FLOOR 07 21-05-19 6/20/2019 30 FLOOR 07 ###

20-04-19 26-04-19
FLOOR 06 11-04-19 6/12/2019 26 FLOOR 06 ###

08-04-19 06-04-19
FLOOR 05 01-04-19 4/27/2019 26 FLOOR 05 ###
25-03-19 27-03-19
FLOOR 04 20-03-19 4/14/2019 25 FLOOR 04 ###

10-03-19 08-03-19
FLOOR 03 21-02-19 3/17/2019 24 FLOOR 03 ###

12-02-19 12-02-19
FLOOR 02 03-02-19 2/24/2019 21 FLOOR 02 ###

28-01-19 26-01-19
FLOOR 01 21-01-19 2/3/2019 13 FLOOR 01 ###

14-01-19 07-01-19
GROUND FLOOR 21-Dec-18 1/24/2019 GROUND FLOOR ###

Actual Dates
Baseline Dates

Ahead/Delay

07-12-18
Shear Wall Completed
Slab Completed
Core Wall Completed
Work in Progress with Planned date