4 Pek.Pengecoran
Pek.Cor Beton Lantai 1.8 M3 1,200,000.00 2,160,000.00
Pek.Cor beton Dinding 1.92 M3 1,500,000.00 2,880,000.00
B PEK.GROUNTANK
1 Pek.Galian Tanah 4 M3 250,000.00 1,000,000.00
2 Pek.Pas.Pondasi Rolaq Bata 8 M 30,000.00 240,000.00
3 pek.Pas. Dinding bata 8 M2 45,000.00 360,000.00
4 Pek.Plesteran & acian dinding bata 16 M2 30,000.00 480,000.00
5 Pek.Pembesian Kolom praktis 4 M 50,000.00 200,000.00
6 Pek.Hamparan dak tutup grountank satu lapis 4 M2 100,000.00 400,000.00
7 Pek.Floor lantai grountank + Acian 0.4 M3 750,000.00 300,000.00
8 Pek.cor dak grountank 0.48 M3 1,200,000.00 576,000.00
9 Mal dak Grontank 4 M2 100,000.00 400,000.00
SUB TOTAL 4,996,000.00
C PEK.RUANG MESIN
1 pek.galian tanah 4 M3 250,000.00 1,000,000.00
2 Pek.Pas.Pondasi Rolaq Bata 4 M 30,000.00 120,000.00
3 pek.kolom praktis 8 M 50,000.00 400,000.00
4 pek.Pas. Dinding bata 12 M2 45,000.00 540,000.00
5 Pek.Plesteran & acian dinding bata 24 M 30,000.00 720,000.00
6 Mal Cor dak 4 M2 100,000.00 400,000.00
7 Pek.Pembesian dak 4 M2 100,000.00 400,000.00
8 pek.cor dak beton 0.48 M3 1,200,000.00 576,000.00
SUB TOTAL 5,832,000.00
D PEK.LAIN-LAIN
1 Pek.pembuangan tanah dan sampah 6 Mobil 300,000.00 1,800,000.00
SUB TOTAL 1,800,000.00