PEMBANGUNAN PIPA TRANSMISI GAS BUMI CIREBON-

SEMARANG TAHAP I (RUAS SEMARANG - BATANG)

WORK INSPECTION REQUEST (WIR)


KSO PP – ELNUSA
(SHIFT MALAM)

To : ESDM/PPK/MK Request Number : KSO-PPEN-EPC-00-WIR-0080


Date : 17 Oktober 2022

Attn : KSO PP - ELNUSA : Asep Sutisna Daryatmo


Cc : Project Manager PPK/ESDM/MK Contact Number : 0813 8038 4011

Date of Inspection : 17 Oktober 2022


Detail of Activities:

Type of Type of
No. Activities Time Jts Location PIC
Report Inspect

Kontinyu 2nd Reaming 19.00- KP 6 Witness Ilham Roy S


1. Report
HDD-8 KP 6 Selesai 082243759696

1st Reaming HDD-6 19.00- KP 4 Witness Ilham Roy S


2. Report
KP4 Selesai 082243759696

Acknowledge
MK / Tim Pendukuk PPK
Prepared By,
KSO PP – ELNUSA

Name : AS Daryatmo
Name :