You are on page 1of 1

PEMBANGUNAN PIPA TRANSMISI GAS BUMI CIREBON-

SEMARANG TAHAP I (RUAS SEMARANG - BATANG)

WORK INSPECTION REQUEST (WIR)


KSO PP – ELNUSA
(SHIFT MALAM)

To : ESDM/PPK/MK Request Number : KSO-PPEN-EPC-00-WIR-0087


Date : 24 Oktober 2022

Attn : KSO PP - ELNUSA : Asep Sutisna Daryatmo


Cc : Project Manager PPK/ESDM/MK Contact Number : 0813 8038 4011

Date of Inspection : 24 Oktober 2022


Detail of Activities:

Type of Type of
No. Activities Time Jts Location PIC
Report Inspect

Kontinyu cleanpass 19.00- KP 6 Witness Ilham Roy S


1. Report
HDD-8 KP 6 Selesai 082243759696

Kontinyu cleanpass 19.00- KP 4 Witness Ilham Roy S


2. Report
HDD-6 KP 4 Selesai 082243759696

Preaparation HDD-21 19.00- KP 20 Witness Ilham Roy S


3. Report
KP 20 Selesai 082243759696

Preaparation HDD-1 19.00- KP 1 Witness Ilham Roy S


4. Report
KP 1 Selesai 082243759696

Insert pipa product 19.00- KP 14 Witness Ilham Roy S


5. Report
Auger boring KP 14 Selesai 082243759696

Acknowledge
MK / Tim Pendukuk PPK
Prepared By,
KSO PP – ELNUSA

Name : AS Daryatmo
Name :

You might also like