NCR LOG

ISSUE / RECEIVED CLOSED /


SL. NCR NO. REV. NO. BRIEF DESCRIPTION STATUS REMARKS
DATE APPROVED DATE

1 NCR-001 R0 PERMANENT BARRICATION WORK 07-03-2022 25-03-2022 CLOSED

1. CONCRETE PEDESTAL FOR CANOPY FRAMING IN MODULE NO 8 NORTH SIDE, IS NOT AS PER DETAILS GIVEN
IN GFC.
2 NCR-002 R0 24-05-2022 26-05-2022 CLOSED
2. ALIGNMENT AND LINE NOT ENSURED.
3. PRIOR APPROVAL NOT BEEN TAKEN.

3 NCR-003 R0 105, 106 & 107 7 DAYS CUBE RESULTS FOUND BELOW 70% 22-08-2022 23-09-2022 CLOSED

4 NCR-004 R0 CUBE ID 108CC_C19 & C26 28 DAYS CUBE FAILURE 10-09-2022 23-09-2022 CLOSED

5 NCR-005 R0 KLL TO JLL NCR 10-09-2022 03-10-2022 CLOSED

6 NCR-006 R0 WATER LEAKAGE IN UB-P1 SLAB 06-10-2022 - OPEN Will be closed on before 16/11/2022

7 NCR-007 R0 FOUND CRACKS ON POUR 3 UPPERBASEMENT SLAB BETWEEN GRID D-E/6-7 24-10-2022 - OPEN Will be closed on 07/11/2022

8 NCR-008 R0 FOUND BEAM BULGED 30-50MM AT UPPER BASEMENT POUR-2 SLAB GRID E'/4-5 28-10-2022 - OPEN Will be closed on before 20/11/2022

9 NCR-009 R0 NON PT SLAB GF DEFECTS 29-10-2022 - OPEN Will be closed on before 20/11/2022