Sol: A. Partially PO will be short closed by changing the PO qty based on GR qty happened prior and
enabling the Delivery check box in delivery tab of PO line item and save
B Partially W/O will be short closed by changing the PO qty based on SES qty happened Prior and
save.
C. Fully PO/WO will be short closed by deleted the line item and save,ONLY AFTER 180 DAYS
2. What will there be impact on quantity of order after short closure of POs/WOs.
Soln : The PR Qty is open again for which we can created another PO and budget is released
Soln: the Budget consumed while creation of PO/WO, it will be deallocated once it is short closed
Soln: The mail will trigger to vendor and Purchasing head, after confirmation by vendor user will run
the report and close/cancel the PO’s manually.
For PO/WOs cancellation:
Soln: PO Line items will be deleted, if all line items are deleted it is fully PO is cancelled, if it is
partially line items are deleted; it is partially PO is cancelled
Soln: The PR Qty is open again for which we can created another PO and budget is released
The mail will trigger to vendor and Purchasing head, when the user deleted the line item.