Skilled Labour Front

1 3 Carpenters 6 Helpers 7.9 Sqm Work retaining wall 1 Mtr Ht


for 9 Carpenters 18 Helpers 23.7 Sqm Work retaining wall Need fronage

2 0.75 Carpenters 1.5 Helpers 10.8 Sqm Work Footing 1 Mtr Ht


for 6 Carpenters 12 Helpers 86.4 Sqm Work retaining wall Need fronage

3 1 Carpenters 2 Helpers 4.5 Sqm Work Columns 2.5 Mtr Ht


for 2 Carpenters 4 Helpers 9 Sqm Work retaining wall Need fronage

4 1 Bar binders 1 Helpers 100 Kgs Work Below Plinth


for 20 Bar binders 20 Helpers 2000 Kgs Work retaining wall Need fronage

Work Front Details as on 8th Nov 2022


1 Total number of footing PCC 56 Nos Part A
2 Available front for footing PCC 20 Nos
Required front 36 Nos

1 Total Length of retaining wall PCC 215 Mtrs Part A


2 Available front for footing PCC 91 Mtrs
Required front 124 Mtrs

Pour 1 14 Nos Footings 3 Casted PCC


Pour 2 21 Nos Footings 3 Casted PCC
Pour 3 14 Nos Footings 12 Casted PCC
Pour 4 7 Nos Footings 2 Casted PCC
56